Renewable Energy Sources Integration and
Renewable Energy Sources Integration and
fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TIA.2018.2878143, IEEE
Transactions on Industry Applications
0093-9994 (c) 2018 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TIA.2018.2878143, IEEE
Transactions on Industry Applications
Substation
Wind power
controller
WTG
PV power
controller
PVG
Battery
DC BUS
Tracking/Braking
0093-9994 (c) 2018 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TIA.2018.2878143, IEEE
Transactions on Industry Applications
the event of peak or acceleration phases. Finally, the penalty by assigning the current reference Irefdc calculated during the
cost related to the subscribed power exceeding is covered voltage control.
simultaneously by the RES and the battery. The 'battery agent' may also refuse the 'line manager agent'
The proposed railway microgrid control by MAS is quoted proposal if its SOC is not correlated. The DC bus current
in section II. Section III shows the reliability of the proposed control is then supported by other agents. The case where the
microgrid, by detailing the simulation results. Section IV SOC is not correlated with the proposal of the 'line manager
concludes the paper. agent' is not taken into account.
The battery is current-controlled in order to regulate the
II. RAILWAY CONTROL BY MAS bus voltage and balance the energy flow in the DC bus. The
The control of the railway microgrid follows the same current reference Irefdc is the current to be assigned to the
principle of a power flow control in a DC bus [14]. The converters and becomes Ibattdc in order to regulate the bus
current flowing in the line reveals different possible scenarios; voltage as it was previously pointed out. The calculation of the
a train or several trains brake, or a train brakes while others DC bus voltage is given by (3) which Cdc is the DC bus
accelerate. Therefore, the average current represents the capacitor. Irefdc is calculated via the bus voltage vdc during
outcome of the various possible scenarios that may occur. It is voltage control. The difference between the line current
viewed by the DC bus as reversible load. The positive (substation ISubstation and trains consumption Itrains) and the
resultant current expresses the acceleration phase and the RES current IRES is seen by the DC bus as a bidirectional load;
negative resultant current represents the deceleration phase. consumes energy in the event of acceleration and provides
The intelligence of the proposed control by MAS allows energy in case of deceleration. The difference between these
the battery to be charged from the RES generated power while currents is the current to be controlled by the battery via Irefdc.
trains are stopped and during deceleration periods, to reuse the
stored energy during acceleration periods. It also allows the vdc
1
Cdc
I Battery dc I RES I substation Itrains dt
(3)
RES to reduce the subscribed power while the trains speed is
constant.
Using the MacsimJX tool [15] [16], there are three agents
that receive three Simulink signals. All the necessary Moreover, when the trains speed on the line is equal to
calculations are carried out by Simulink while the decision zero (at the start or the stop), the current to be controlled by
making is performed by the agents in the Jade environment the battery is the current generated by the RES, for this reason,
[17]. the battery consumes the RES current when the trains are
The resulting current signal which informs about the stopped on the line or during the start.
various scenarios that may occur on the line is the input signal When the trains’ speed running on the line is constant, the
of the 'line manager agent'. The processing of this data by the objective will be to reduce the subscribed power thanks to the
agent indicates whether a request for energy supply is RES generation. Consequently, the RES will supply the line
required, due to an acceleration in order to suppress the directly in order to reduce the subscribed power. On the other
voltage drop on the line, or a consumption demand in order to hand, if the difference between the resulting current on the line
remove the voltage increase due to deceleration is necessary. (from the different circulating, accelerating and decelerating
The 'line manager agent' then sends this information to trains) and the RES generated current is always considered as
agents interested by this information and who can provide the the current to be controlled by the battery, there will be an
supply or consumption of energy service to meet the excess of energy on the line when trains’ speed is constant
acceleration and deceleration phases requirements. Actually, because the RES production will exceeds the trains
these agents are 'battery agent' and 'RES manager agent'. consumption moving at fixed speed. Then the battery will
On the other side, the 'battery agent' receives from consume this excess of energy of renewable origin instead of
Simulink the signal indicating its state of charge SOC. If the integrating it in the line in order to reduce the subscribed
proposal of the 'line manager agent' is correlated with the power as it is desired.
SOC, the 'battery agent' accepts the proposal and begins to In order to achieve this objective, the proposed smart
supply the energy needed during the acceleration which is not control by MAS assumed in this case that on the DC bus the
recovered by the RES, that also participate in the supply of power flows are balanced, that means, the RES generated
energy during acceleration. The battery consumes the total power will not be integrated into the DC bus. ie there will be a
excess of energy on the line due to deceleration and also due zero reference current, Irefdc = 0 and the converter associated to
to the RES generation which is not consumed at deceleration the battery receives a set-point equal to zero IBref = 0. This is
time. the role of the 'RES manager agent'.
The 'battery agent' sends its decision of acceptance to the
converter associated to the battery in Simulink environment,
0093-9994 (c) 2018 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TIA.2018.2878143, IEEE
Transactions on Industry Applications
iTrains
iTS
iT I RES Vdc
S
SpeedTrains
Line manager Agent
RES manager Agent
Ye No
s IR 0
Processing Data
Send Send
controller proposal to proposal to
Decision Making agents able agents able
to provide to provide
Wind power supply consume
controller service service
IRES
Wind Turbines Agent Send request
PV power
controller
PVs
Battery Agent
Voltage
Controller Processing Data
Vref
PI
controller
Decision Making
Irefdc
Battery converter
Irefdc Agent
IB
IBref
0 PI dc
ILB
The 'RES manager agent' receives from Simulink the line power exceeding. On the other hand if a deceleration occurs
circulation cycle signal, which informs about the trains speed the battery consumes the total of the braking energy that is not
on the line, and receives in parallel from Jade the 'line recovered by other trains and the energy produced by the RES
manager agent' proposal. If there is a demand to supply energy considered in excess in the event of deceleration.
supply, it means that the resulting current in the line is If the traffic speed is constant, the 'RES manager agent'
positive. On the other hand, the processing of the information will integrate a zero current on the DC bus, which means that
coming from Simulink which provides information about the the bidirectional load current in the DC bus is considered to be
trains speed through the line will allow the 'RES manager equal to zero, in order to have IrefDC = IBref = 0. This lets to
agent' to take the decision to accept or to reject the 'RES consider a DC bus where the power flows are balanced. On
manager agent' proposal. the other hand, the generation of the RES in the case where the
If the circulation speed is non-constant and a supply circulation speed is constant supplies the line directly in order
request is suggested, the 'RES manager agent' will integrate to reduce the subscribed power. The demonstration is given
into the DC bus the resulting current which is the resulting later by analyzing the simulation results. The proposed railway
traction and braking current on the line and the RES current as microgrid control principle is illustrated in Fig.2. It is shown
a bi-directional load as explained above. Therefore, the current that each agent depending on received signals and messages; it
to be monitored by the battery is the difference current, i.e., if controls autonomously the corresponding elements. It gathers
acceleration is produced the battery supplies the energy that is the needed data to determine the set-points following the
not covered by the RES in order to eliminate the subscribed
0093-9994 (c) 2018 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TIA.2018.2878143, IEEE
Transactions on Industry Applications
PS=2,5 MW
A B C D E
Fig. 3. The available power in the railway line (P S=2.5 MW)
PS=2.5 MW
3,51MW 3,51MW
3MW
A B A B
3MW 3MW
DG
Fig. 5.a . The peak load demand near to Fig. 5.b . The peak load demand near to
substation consumption with a DG substation consumption without a DG
3MW D
A DG 2.4MW A 2.4MW
D
Fig. 6.a . The crossing point peak load Fig. 6.b . The crossing point peak load
demand consumption with a DG demand consumption without a DG
decision-making. Therefore, the agents are autonomous and DG here depicts the RES which their maximum power is
self-adaptive. about 0.5 MW.
The RES do not always generate the maximum power.
III. RESULTS AND DISCUSSION However the objective here is not to activate the battery to let
the RES reach their maximum power. The battery is turned on
Two configurations are studied. The first one illustrates the to remove the rise voltage and aiming solving the peak load
railway line when a DG is integrated, and aims to show the demand causing the drop voltage occurring for example near
reaction of the hybrid system tied to the DC bus which is to substation as shown in Fig.5.a and Fig.5.b.
viewed as a DG, in the different cases. The second The maximum power that can be delivered by the hybrid
configuration validates the strategy of energy management by system tied to the DC bus is about 3 MW. It is shown in
MAS proposed in the previous section, by taking full Fig.5.a that the peak load demand is supplied by the hybrid
advantages of the capacity, characteristics and limitations of system and therefore the subscribed power is not exceeded.
each element in the HS following a driving cycle scenario. Contrarily to Fig.5.b the peak load demand is provided by the
The objective is to improve the energy quality of the whole substation and exceeds the subscribed power by 1.512 MW in
system by the energy flow distributed and intelligent control. order to meet the peak load demand occurring near to
Fig.3 shows the available power in the line. The subscribed substations.
power is equal to 2.5 MW. The distance between each point in The crossing point between two trains is considered as the
the line is about 5 Km. Due to the losses in the line, the second peak load. Fig.6.a and Fig.6.b illustrate a crossing
available power decreases while going away from the point occurring at point D that consumes 2.4 MW. It is shown
substation. When a DG is integrated as illustrated in Fig.4, the in Fig.6.a that the hybrid system which is viewed as a DG
subscribed power is reduced, also the power coming from the provides its maximum power to meet the peak load demand
substation. The subscribed power can be reduced by 0.5MW. without exceeding the subscribed power. It is shown in Fig.6.b
Therefore, voltage drop across the catenary system due to the that the peak load demand is covered by the substation letting
long distance between two substations is also reduced. The
0093-9994 (c) 2018 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TIA.2018.2878143, IEEE
Transactions on Industry Applications
0093-9994 (c) 2018 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TIA.2018.2878143, IEEE
Transactions on Industry Applications
Fig. 10. Battery DC-DC converter output current Fig. 13. Subscribed power gain
Fig. 11. The line current Fig. 14. Subscribed power exceeding removal
0093-9994 (c) 2018 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TIA.2018.2878143, IEEE
Transactions on Industry Applications
References
[1] R.R.Pecharroman and al, “Riding the Rails to DC Power Efficiency:
Energy efficiency in dc-electrified metropolitan railways”, IEEE
Electrification Magazine, vol. 2, No.3, pp. 32 – 38 , 2014.
[2] Boudoudouh Soukaina, and Mohammed Maâroufi. "Smart control in a
DC railway by Multi Agent System (MAS)." In Electrical Systems for
Aircraft, Railway, Ship Propulsion and Road Vehicles & International
Transportation Electrification Conference (ESARS-ITEC), International
Conference on, pp. 1-6. IEEE, 2016.
[3] Hajizadeh, A., Golkar, M. A., "Intelligent power management strategy
Fig. 16. DC bus voltage evolution of hybrid distributed generation system", Elsevier, electrical Power and
Energy systems, pp. 783-795, 2007
[4] H.Ibrahim and al “Integration of Wind Energy into Electricity Systems:
advantage of both, the regenerated energy due to the braking Technical Challenges and Actual Solutions”, Energy proceedia, vol. 6,
process and also consume the total energy from the RES, pp. 815_824, 2011.
which enable the battery to charge, in order to be discharged [5] B. Robyns and al, “Electricity production from renewables energies”,
during critical periods. ISTE Wiley 2012.
During the last phase, the trains are stopped. Consequently, [6] M. Alvarez-Herault, “Architectures of the distribution futir networks in
their speed is equal to zero. The battery consumes the current the presence of decentralized production”, Phd thesis, University of
coming from the RES which supply during this phase the DC Grenoble, 2009.
bus following the 'RES manager agent' decision in order to [7] R.Faranda.;S. Leva “ Energetic Sustainable.developement of railway
stations”;. IEEE Power engeneering society general meeting pp 1-6,
achieve the DEM objectives in the proposed railway Tampa, FL, 2007.
microgrid. [8] H. Hayashiya and al, “Necessity and possibility of smart grid technology
Fig.14 shows the remove of the subscribed power application on railway power supply system”, proceeding of 14th
exceeding, by the battery and the RES during the acceleration European conference onpower electronics and applications (EPE 2011),
phases. Fig.15 shows the suppression of the penalty cost pp 1-10, Bermingham, 2011.
related to the acceleration and the subscribed power overrun [9] Khamphanchai, W.;Pipattanasomporn, M., and Rahman, S., “A Multi-
by the battery and the RES. Also the removal of penalty cost Agent System for Restoration of an Electric Power Distribution Network
with Local Generation,” IEEE Power and Energy Society General
related to the deceleration and the energy excess coming from Meeting, 2012.
the RES exhaustively via the battery. Fig.16 illustrates the
[10] W. Khamphanchai, M. Kuzlu and M. Pipattanasomporn, “A Smart
evolution of the DC bus voltage during the simulation. It is Distribution Transformer Management with Multi Agent Technologies,”
constant equal to the reference voltage throughout the IEEE PES Innovative Smart Grid Technologies, 2013
simulation time, which proves the success of the control by [11] D. E. Olivares, C. A. Canizares, and M. A. Kazerani, “Acentralized
MAS of the proposed railway microgrid. optimal energy management system for microgrids,” in Proc. IEEE
Power Energy Soc. Gen. Meet., Jul. 2011, pp. 1–6.
IV. CONCLUSION [12] A. H. Etemadi, E. J. Davison, and R. Iravani, “Adecentralized robust
control strategy for multi-DER microgrids—Part I: Fundamental
This paper deals the DEM by MAS in the railway concepts,” IEEE Trans. Power Del., vol. 27, no. 4, pp. 1843–1853, Oct.
microgrid with HSS based on HPGS to meet the limitations of 2012.
rail transportation systems in terms of energy saving. The [13] AL. Kulasekera, RARC. Gopura, KTMU. Hemapala, et al (2011), “A
HPGS consists of a multi-source system with decentralized Review on Multi-Agent Systems in Microgrid Applications,” In:
Proceedingsof IEEE PES Conference on Innovative Smart Grid
energy sources with different capacities and a different Technologies India (ISGT 2011), Kollam, Kerala, India, December 1-3,
generation, therefore, judicious use and integration of each 2011.
element were respected. Reducing the subscribed power, [14] S.Boudoudouh; M.Ouassaid; M. Maâroufi, ‘Multi Agent system in a
eliminating the voltage drop in the line due to the acceleration distributed energy management of a multi sources system with a hybrid
and leading to the subscribed power exceeding and avoiding storage’ 3th renewable and sustainable energy conference (IRSEC,
2015), IEEE conference
the voltage rise due to the deceleration by consuming the total
of the regenerative energy not recovered by the other trains in [15] S. Boudoudouh et M. Maâroufi, ‘Real Time Battery State Of Charge
Estimation In Smart Grid Application by Multi Agent System’ Journal
the line, remain the main issues that should be taking into of Hydrogen Energy, 2017.
account while hybridizing the substation without modifying [16] S.Boudoudouh, M. Maâroufi (2017), Real Time Distributed Systems
the existing architecture. Thereby, this paper meets the Modeling and Control: Application to Photovoltaic Fuel Cell
mentioned limitations and constraints by designing reversible, Electrolyser System, journal of Engineering Science and. Technology
active, intelligent, self-adaptive, and autonomous DG Review (jestr), Vol 10, issue 1
connected to the catenary thanks to the distributed DC bus [17] Fabio Bell feminine, Telecom Italy, “Giovanni Caire, telecom
voltage control by MAS. It was shown the ability of the Italy”Developing Multi Agent Systems with JADE “John Wiley& sons
2007”.
proposed control to reduce the subscribed power and to omit
the subscribed power overrun by the RES generation and the
storage system which is represented by the battery. The
0093-9994 (c) 2018 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.