The document is an examination paper for a B.E. (Civil) course on Operations Research, consisting of 8 questions from which candidates must choose pairs to answer. It covers topics such as the Hungarian Method, transportation problems, the Simplex method, and optimization techniques. The exam has a total duration of 2.5 hours and is worth 70 marks.

Uploaded by

j98583969
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
7 views4 pages

Or Apr23

The document is an examination paper for a B.E. (Civil) course on Operations Research, consisting of 8 questions from which candidates must choose pairs to answer. It covers topics such as the Hungarian Method, transportation problems, the Simplex method, and optimization techniques. The exam has a total duration of 2.5 hours and is worth 70 marks.

Uploaded by

j98583969
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Total No. of Questions: 8] SEAT No.

:
P537 [6004]-459
[Total No. of Pages :4

B.E. (Civil)
OPERATIONS RESEARCH
(2019 Pattern) (Semester-VII) (Elective-III) (401003-F)
Time : 2½ Hours] [Max. Marks : 70
Instructions to the candidates:
1) Solve Q1 or Q2, Q3 or Q4, Q5 or Q6, Q7 or Q8.
2) Figures to the righte side indicate full marks.
3) Use of Calculator is allowed.
4) Assume suitable data if necessary.

Q1) a) Explain the following in the context of assignment problem [6]


i) The Hungarian Method
ii) Infesible assignment
b) Unit cost of transporting precast blocks from four factories to three sites
is given along with availability at each factory and the requirement on
each site. Obtain optimal solution to minimize cost of transportation
using VAM method. [12]
1 2 3 4 supply
A 2 7 4 6 5
B 3 3 7 2 8
C 5 4 1 3 7
D 1 6 2 5 14
Demand 7 9 18 6

OR
Q2) a) Six different jobs J1,J2, J3, J4 J5 and J6 are to be worked on a machine
tool with setting times as given in the following matrix. It is necessary that
a job once undertaken will not be handled again till all other jobs are
finished. Decide the sequence of jobs which gives minimum elapsed time.
[12]

P.T.O.
Next jobs
J1 J2 J3 J4 J5 J6
J1 - 17 20 22 6 8
J2 21 - 18 23 17 16
J3 23 22 - 19 22 19
Jobs J4 27 19 21 - 20 21
Before J5 16 18 17 23 - 17
J6 18 16 20 24 19 -
b) What are the applications of transportation problem in Construction
industry? [6]

Q3) a) In Simplex problem, explain the two phase method and its applications
[8]

b) What are the advantages of Linear programming problems? [4]


c) Define the following terms and indicate their significance of decision making
with linear programming and simplex method: [6]
i) Key cloumn
ii) Key row
OR
Q4) a) Solve using Simplex method [8]
Maximize Z=2x1–4x2+5x3–6x4
Subject to

x1  4 x2  2 x3  8 x4  2
 x1  2 x2  3 x3  4 x4  1
x1 , x2 , x3 , x4  0

b) Under which circumstances, Big M method is used? [4]


c) Explain the significance of surplus and slack variables. [6]

[6004]-459 2
Q5) a) Optimize Z   x12  x22  4 x1  9 x2 [10]
Subject to

4 x1  3x2  15
3x1  5 x2  14
x1 , x2  0

Use Lagrangian Multiplier technique.


b) Give the steps involved in steepest ascent/descent method. [7]
OR
Q6) a) Explain the following [7]
i) Hessian matrix
ii) Gradient vector
b) A company sells two types of items, A and B. On item A, three is no
discount and is sold at a fixed of price of Rs. 250 per unit. The sales
revenue for item B is given as (40–0.40x2)x2 where x2 is the number of
units sold. The marketing department has only 1,500 hours available for
selling these items in the next year. Further the company estimates the
sales time function as sales time  x1  0.3 x12  3 x2  0.5 x22 . The company
can procure a maximum of 6,000 units of the two products combined.
Formulate the mathematical model of the problem to maximize the
revenue. [10]

Q7) a) Solve the following 3 X 5 game using dominance property [8]


Opponent 2
1 2 3 4 5
A 6 15 30 21 16
Opponent 1 B 3 3 6 6 4
C 12 12 24 35 3
Give optimum strategy for both the opponents and find value of games

[6004]-459 3
b) In an investment project, Seven salesmen are to be appointed for three
areas to maximize the sales. the sale in each zone w.r.t the number of
salesman is as given under. Find the optimum allocation. [9]
N. of salesmen 0 1 2 3 4 5 6 7
Zone 1 2 4 7 12 16 19 21 22
Zone 2 3 6 10 17 22 25 27 27
Zone 3 2 3 6 10 15 19 22 23

OR
Q8) a) Why is replacement of items required? what is the strategy used for
replacement of any machine? What are the types of costs to be
considered for calculating the replacement year? [9]
b) Write the applications of following OR techniqus in the filed of Civil
Engineering. [8]
i) Non linear Programming
ii) Dynamic programming



[6004]-459 4