Implementation Plan
Implementation Plan
Implementation Plan
California Department of Water Resources
December 2009
Draft
FloodSAFE
Implementation Plan
December 2009
0901D2
Table of Contents
Table of Contents i
1 Introduction 1
1.1 Purpose and Scope 1
1.2 Geographic Areas 2
1.3 Background 5
2 FloodSAFE Initiative 8
2.1 FloodSAFE Definition 8
2.2 Vision 9
2.3 Goals 9
2.4 Foundational Objectives 10
2.5 Guiding Principles 11
FloodSAFE i DRAFT
Implementation Plan December 2009
0901D2
6 Investment Strategy 74
6.1 Investment Need 74
6.2 State General Fund 76
6.3 State Bond Funds 76
6.4 Cost Sharing 77
6.5 Investment Status 78
6.6 Near-Term Investment Plan 79
6.6.1 Investment Strategy 79
6.6.2 Summary of Planned Investments 80
7 FloodSAFE Governance 82
7.1 Overview of Roles and Responsibilities within DWR 82
7.2 DWR Internal Teams and Coordination Groups 84
7.2.1 FloodSAFE Deputy Director Team 86
7.2.2 FloodSAFE Integrated Water Management Team 86
7.2.3 FloodSAFE Environmental Conservation Team 87
7.2.4 FloodSAFE Management Services Coordination Team 88
7.2.5 Functional Area Management Team 88
7.2.6 Technical Coordination Groups 89
7.3 Partnerships 89
7.4 Local Agencies 91
7.5 Management by Functional Area 94
FloodSAFE ii DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE iv DRAFT
Implementation Plan December 2009
0901D2
G.2.1 Goal 2
G.2.2 Objectives 2
G.3 Elements and Components 2
G.3.1 Communication and Briefing Materials 3
G.3.2 Funding Advocacy and Agencies’ Alignment 5
G.3.3 Legislative Liaison and Legal Issues 5
G.3.4 Program Management, Budget and Fiscal Services 6
G.3.5 FloodSAFE Program Administrative and Coordination
Services 7
G.4 Geographic Focus 8
G.5 Major Deliverables 8
G.6 Performance Measures 10
G.7 Projected Budget, Resources, and Schedule 11
Table of Figures
FloodSAFE v DRAFT
Implementation Plan December 2009
0901D2
Table of Tables
FloodSAFE vi DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE ix DRAFT
Implementation Plan December 2009
0901D2
1 Introduction
FloodSAFE 1 DRAFT
Implementation Plan December 2009
0901D2
The term ―functional area‖ was chosen by DWR’s Division of Flood Management
(DFM) managers to describe the type of work being done, rather than the organizational
structure. Each functional area is specialized in/with
specific technical expertise (Center of Excellence) Seven Functional Areas
with distinct technical roles and responsibilities. Each
functional area is closely aligned to a DWR office as FA 1 Emergency Response
shown in Section 3. FA 2 Operations & Maintenance
and Environmental Stewardship
This implementation plan provides strategic-level
guidance for implementation of California’s FA 3 Floodplain Risk
FloodSAFE initiative by providing descriptions of Management
how work will be accomplished in seven different FA 4 Flood Protection Projects
functional areas. The plan will be supported by & Project Grants
strategic plans or other detailed management plans FA 5 Evaluation & Engineering
for programs and projects as appropriate within each
FA 6 Flood Management
functional area. The implementation plan describes
Planning and Conservation
major elements and components for each functional
Strategy
area; descriptions of detailed work activities and tasks
will be left for other reports under each functional FA 7 Legislation, Budget, and
area. Communication
The FloodSAFE Implementation Plan was prepared
for DWR internal use to help all managers understand the relationships among the
functional areas and to help them monitor expected outcomes (deliverables and
performance measures). The implementation plan is intended to be flexible, with updates
prepared as conditions evolve.
Central Valley. The Central Valley contains the majority of the State’s flooding
problems and the majority of its flood protection facilities (reservoirs, weirs,
levees, etc.), including the State-federal flood protection system. In addition, the
area includes local flood management facilities that are not part of the State-
federal system.
FloodSAFE 2 DRAFT
Implementation Plan December 2009
0901D2
Delta. The Delta (738,239 acres) was given a legal boundary (Section 12220 of
the Water Code) in 1959 with the passage of the Delta Protection Act. The 1992
Delta Protection Act refined the definition to provide primary and secondary
zones within the previously defined legal Delta. Due to unique issues in the Delta
and the State’s interest in benefits provided by Delta levees, the State provides
financial assistance to local levee maintaining agencies (LMAs) for 732 miles of
non-project Delta levees and 385 miles of project levees.
Area Outside of Central Valley. The area of the State outside of the Central
Valley also has flooding problems and flood management facilities, but these
generally affect local areas and are smaller in scale than those in the Central
Valley. The State provides cost sharing with local communities for flood
management projects.
In addition, California is divided into ten hydrologic regions. The descriptions of the
functional areas in Appendices A through G identify the geographic area(s) to which they
apply.
FloodSAFE 3 DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE 4 DRAFT
Implementation Plan December 2009
0901D2
1.3 Background
In January 2005, Governor Schwarzenegger drew attention to the State’s flood problem,
calling for improved maintenance, system rehabilitation, effective emergency response,
and sustainable funding. In a white paper entitled Flood Warnings: Responding to
California’s Flood Crisis, DWR outlined the flood problems that California faces and
offered specific recommendations for administrative action and legislative changes. The
major flood system issues are shown in the text box.
Since that time, Hurricane Katrina and the resulting flooding in New Orleans provided a
vivid reminder of levee vulnerability and consequences of flooding urban areas.
California’s own flooding in 2006 produced by storms with recurrence intervals of as
little as five to ten years highlighted that the system is fragile and deteriorating.
Emergency appropriations and the repair of critical levee erosion sites necessary before
the winter of 2006 contributed to furthering public awareness of potential flooding.
Flood System
There are several threats to California’s flood systems that must be considered together
when looking for ways to reduce the risk of flooding.
Channel Capacity. Flood channels and adjacent levees must have capacity to
carry design flood flows that vary throughout the system. In part, this means that
levees must be high enough to contain the design flows.
Seepage. Water seepage through or under a levee embankment can lower the
integrity of a levee.
Erosion. High velocity flows can erode levee material, making a levee unstable and
subject to failure.
Encroachments. A levee should generally be clear of inappropriate structures or
debris that can cause problems with inspections, maintenance, flood fights, or the
stability of levees.
Vegetation. Growth of some vegetation, especially large trees in certain areas on
levees, may weaken levees and reduce public safety. However, research will be
initiated to determine the extent to which various types of vegetation may be
beneficial in the design of flood control systems or substantiate the need for
rigorous application of current maintenance standards on the levee prism.
Structural Instability. The levees must be structurally stable and established on
foundations with adequate strength to retain flood flows.
Seismic Loadings. Many levees that were constructed without the benefit of
modern engineering practice may perform poorly during earthquakes.
FloodSAFE 5 DRAFT
Implementation Plan December 2009
0901D2
The need for adequate flood management is more critical now than ever before. Over the
years, major storms and flooding have taken many lives, caused significant property
losses, and resulted in extensive damage to public infrastructure. However, a combination
of recent factors has put public safety and the financial stability of State government at
risk. California’s flood protection system, comprised of aging infrastructure with major
design deficiencies, has been further weakened by deferred maintenance. Escalating
development in floodplains has increased the potential for flood damage to homes,
businesses, and communities.
Court decisions have resulted in greater State government liability for flood damages. In
2003, Paterno v. State of California, the court held the State of California liable for flood-
related damages caused by a levee failure. In the Arreola v. Monterey County decision of
July 2002, local agencies were held liable for the 1995 flood damages that resulted from a
failure to properly maintain the Pajaro River project. The maintaining agencies had not
been able to use standard mechanical clearing methods to remove vegetation in the
channel because of environmental requirements to protect riparian habitat.
Due to funding and environmental concerns, both the State and local agencies in all
regions of the State have found it increasingly difficult to carry out adequate maintenance
programs using previous methods. Environmental regulations are requiring development
of new approaches for local and State agencies to deal with the backlog of maintenance
activities.
DWR designed the FloodSAFE initiative to make the first significant improvements in
flood safety since the flood systems were constructed.
FloodSAFE 6 DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE 7 DRAFT
Implementation Plan December 2009
0901D2
2 FloodSAFE Initiative
FloodSAFE is more than investing the funds from Propositions 1E and 84. The initiative
recognizes that DWR’s base flood management programs must continue indefinitely,
long after bond funds are expended. The initiative will require additional State bond
funding, cost sharing from federal and local entities, continued general fund
contributions, or other funding to ensure that integrated flood management is sustainable.
FloodSAFE 8 DRAFT
Implementation Plan December 2009
0901D2
2.2 Vision
The FloodSAFE Vision is:
2.3 Goals
Goals represent desirable outcomes of
the FloodSAFE initiative that will Sustainable Flood Management System
continue to be important in the future.
DWR will work with partners to make An objective of the FloodSAFE initiative is to
formulate strategies that will result in a sustainable
the decisions and investments necessary
flood risk management system in California.
to meet the following goals:
The sustainable flood management system is designed
Reduce the Chance of to provide for:
Flooding – Reduce the
frequency and size of floods that Ease of operation and maintenance of flood
could damage California facilities, with reasonable costs.
communities, homes and Enhancement of sustainable environmental
property, and critical public resources, recreational opportunities, creation
infrastructure. of open space, and protection of agricultural
lands.
Reduce the Consequences of
Flooding – Take actions prior to Integration of multi-purpose projects and
resources use, to share out flood system
flooding that will help reduce
maintenance and enhancement costs.
the adverse consequences of
floods when they do occur and Safe communities for a sustainable economic
allow for quicker recovery after growth that can fuel sustainable funding for
flooding. operation and maintenance of flood facilities
and future enhancement needs of the system.
Sustain Economic Growth –
Provide continuing opportunities To create a sustainable flood risk management
for prudent economic system, flood managers need to integrate flood
development that supports storage, levee setbacks, floodway easement, bypass
robust regional and statewide system, and groundwater recharge with other flood
economies without creating management strategies.
FloodSAFE 9 DRAFT
Implementation Plan December 2009
0901D2
1. Provide 200-year (or greater) level of flood protection to all urban areas of
California.
2. Provide 100-year (or greater) level of flood protection to all small (populations
less than 10,000) communities of California.
3. Restore 1957-level design performance for rural areas in the Sacramento-San
Joaquin Valley and expand flood protection where feasible.
4. Maintain and improve the integrity of Delta levees for long-term protection for
multiple Delta resources.
5. Provide additional Delta flood protection to support other ongoing programs to
achieve a sustainable Delta.
6. Improve ecosystem processes in conjunction with flood system improvements by
developing and implementing a long-term conservation strategy.
7. Establish an interagency mitigation banking program that provides lasting
environmental benefits.
8. Improve coordinated reservoir operations in the Central Valley to reduce flood
risks.
9. Develop a comprehensive Central Valley Flood Protection Plan (CVFPP) (as
described in SB5) with extensive stakeholder input by January 1, 2012.
10. Delineate expected floodplains for 100- and 200-year flood flows for all urban
communities in the Sacramento - San Joaquin Valley.
11. Achieve 90 percent annual pass rate for urban levees in the Central Valley when
inspected according to federal and State levee standards (e.g., maintenance,
encroachment, etc.).
12. Improve operations and maintenance so flood facilities continue to operate as
designed.
13. Improve procedures for flood emergency preparedness, response, and recovery.
FloodSAFE 10 DRAFT
Implementation Plan December 2009
0901D2
Each of DWR’s flood management functional areas will contribute to meeting one or
more of these foundational objectives (see Section 3).
FloodSAFE 11 DRAFT
Implementation Plan December 2009
0901D2
Land use decisions that explicitly consider flood threats will reduce risks and liabilities.
Throughout much of the Central Valley, the State government has assumed responsibility
for the integrity of levees built by local reclamation districts or the USACE. In many
cases, FEMA has accredited these levees as being capable of withstanding a 100-year
flood event based on old engineering certifications, or has merely ―grandfathered‖ these
levees into the accredited system. Local agencies make decisions on where to allow urban
development, sometimes without the benefit of accurate risk information.
Better information regarding flood risk management must be made available to local
officials. Because it is in everyone’s interest to prevent catastrophic flooding, all parties,
both public and private, must work together to make sound decisions that protect lives
and property.
Sustainable systems are also more economical over time. The goal of an environmental
stewardship ethic is to create human systems consistent with natural systems, where each
is ultimately sustainable.
FloodSAFE 12 DRAFT
Implementation Plan December 2009
0901D2
DWR will focus on non-structural solutions that reduce susceptibility to flooding, aim for
watershed-based solutions, and use traditional structural approaches where appropriate.
Timely and accurate flood information and emergency preparedness at local and
individual levels can help make people safer. Accurate information on flood risks is also
essential to help inform individual choices, local land use decisions, and development of
effective emergency response plans.
Preference should be given to actions that provide desired multiple benefits at the
minimum net cost to the taxpayers when selecting projects or policies for
FloodSAFE 13 DRAFT
Implementation Plan December 2009
0901D2
implementation, and when considering initial capital costs and expected future costs for
Operations and Maintenance.
FloodSAFE 14 DRAFT
Implementation Plan December 2009
0901D2
During the preparation of this FloodSAFE Implementation Plan, it was recognized that
coordination is required at many different technical, managerial, and business levels and
coordination is required at all stages of work beginning with identifying needed work to
final reporting. This includes coordination vertically throughout the FloodSAFE
Program to mobilize and fully utilize the available DFM resources. Additionally,
communication and coordination is necessary horizontally across the different parts of
FloodSAFE to collaborate on work items that support several different parts of
FloodSAFE. This coordination occurs at two basic levels: (1) accomplishing and sharing
work products, and (2) managing the overall FloodSAFE initiative.
Some functional areas have been part of DWR flood management for decades and some
are new to the FloodSAFE initiative. This section describes how the work is organized
into closely coordinated functional areas. This approach is based on the
acknowledgement that flood management includes much more than improvements to
existing flood facilities. Prior to FloodSAFE, USACE traditionally conducted work for
some functional areas.
Following is a brief description of each functional area. Each is described in further detail
in separate sections (see Appendices A through G).
FloodSAFE 15 DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE 16 DRAFT
Implementation Plan December 2009
0901D2
administering the Delta Subventions and Delta Special Projects programs. This
has been a base program within DFM. See Appendix D.
Figure 3-1 identifies the functional areas and lists major program elements and DWR
supporting offices. Work within each functional area is supported by elements, which
represent major divisions of work within a functional area. Each element is supported by
two or more components, which represent programs or groups of projects. Each
component is made up of a number of activities. Each activity is made up of a number of
tasks, a unit of work such as data
collection. This FloodSAFE
Implementation Plan only introduces Functional Area
elements and supporting components o Element This Plan
for each functional area. This Component
hierarchy is shown in the adjacent Activity
o Task
sidebar. Vertical coordination and
communication between the groups
FloodSAFE 17 DRAFT
Implementation Plan December 2009
0901D2
completing the work is necessary to ensure that there continuity between the tasks and
activities and the components and elements that they support.
DWR’s work organization in functional areas is closely aligned with how the USACE
organizes its work under ―Community of Practice‖. USACE flood-related work is
organized into four areas – Emergency Management, Structural Safety, Planning and
Policy, and Operations and Regulatory. USACE provided information contained in
Figure 3-2, which shows the USACE Communities of Practice for flood work and where
they fit with respect to DWR’s functional areas.
The combination of work for these seven functional areas will meet the FloodSAFE
foundational objectives. Table 3-1 shows which functional areas will play a role in
meeting each FloodSAFE foundational objective. Work in all functional areas is also
guided by the principles shown in Section 2. The Legislation, Budget, and
Communication Functional Area (FA 7) provides management support to the six
technical functional areas. Table 3-2 identifies where the specialized technical expertise
resides within the Functional Areas.
FloodSAFE 18 DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE 19 DRAFT
Implementation Plan December 2009
0901D2
Figure 3-2 Flood Management Functional Areas and USACE Communities of Practice
FloodSAFE 20 DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE Foundational FA 1 FA 2 FA 3 FA 4 FA 5 FA 6 FA 7
Objectives Flood Operations & Floodplain Flood Evaluation Flood Legislation,
Emergency Maintenance Risk Protection and Management Budget and
Response and Management Projects Engineering Planning and Communication
Environmental and Project Conservation
Stewardship Grants Strategy
1. Provide 200-year (or greater) level of flood
protection to all urban areas of California.
2. Provide 100-year level of flood protection to
all small (populations less than 10,000)
communities of California.
3. Reduce flood risks in rural areas in the
Sacramento-San Joaquin Valley.
4. Maintain and improve the integrity of Delta
levees for long-term protection of multiple Delta
resources and to achieve a sustainable Delta.
5. Improve ecosystem processes in
conjunction with flood system improvements.
6. Establish an interagency mitigation banking
program that provides lasting environmental
benefits.
7. Design and implement Forecast-coordinated
operation program for Central Valley
reservoirs.
8. Develop a comprehensive Central Valley
Flood Protection Plan (as described in SB5)
with extensive stakeholder input.
9. Identify opportunities to improve integrated
flood management statewide.
10. Delineate expected floodplains for 100 and
FloodSAFE 21 DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE 22 DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE 23 DRAFT
Implementation Plan December 2009
0901D2
Figure 3-3 identifies the Functional Area responsibilities assigned to each DFM office
and selected DWR offices.
FloodSAFE 24 DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE 25 DRAFT
Implementation Plan December 2009
0901D2
Figure 3-4 shows the link between the Functional Areas and the FAXCTs.
Figure 3-4 Functional Area Cross-Coordination Teams
FloodSAFE 26 DRAFT
Implementation Plan December 2009
0901D2
Flood Models Analysis and Dissemination – The Flood Models Analysis and
Dissemination FAXCT primarily relies on work from the Emergency Response
(FA1), Floodplain Risk Management (FA3), and Evaluation and Engineering
(FA5) Functional Areas. This FAXCT requires a significant amount of
coordination between the modeling efforts that are spread throughout the three
functional areas to support technical analyses needed to delineate the floodplains
and to define the natural resources and functions of floodplains.
FloodSAFE 27 DRAFT
Implementation Plan December 2009
0901D2
Levee Risk Assessment – The Levee Risk Assessment FAXCT primarily relies
on information gathered by levee inspections conducted by the staff of
Emergency Response (FA1) and O&M and Environmental Stewardship (FA2)
Functional Areas, and the evaluations conducted by Evaluation and Engineering
(FA5). Close coordination between functional areas will be needed for successful
assessment of the levees.
Flood and Water Management and Statewide Planning – The Flood and
Water Management and Statewide Planning FAXCT primarily relies on
information prepared by Flood Management Planning and Conservation Strategy
Functional Area (FA6), and system reoperation information conducted by
Emergency Response Functional Area(FA1), as well close coordination with local
agencies. Cross coordination activities by all participants is needed for successful
preparation of the Statewide Integrated Flood Management Plan.
FloodSAFE 28 DRAFT
Implementation Plan December 2009
0901D2
- Prepare and update schedule for preparation of the H&H models and studies
- Coordinate activities of the DWR offices engaged in H&H, USACE
hydrology study group, and consulting teams conducting hydraulic studies
- Work with all functional areas and other programs within DWR to identify
various programs’ H&H needs; guide the H&H technical work to ensure all
needs are met
FloodSAFE Information Management Technical Group – Representatives
from the California Data Exchange Center, Hydrology and Flood Operations
Office, Flood Project Integrity, Levee Evaluations, Floodplain Management, and
Integrated Flood Management Planning Office are members of this Group. The
Information Management Technical Group is responsible for identifying, planning
for, and gathering the FloodSAFE programs’ engineering information. This
Group provides an oversight role for FloodSAFE geo-referenced data
management and is responsible for:
FloodSAFE 29 DRAFT
Implementation Plan December 2009
0901D2
3.3.3 Meetings
Some of the coordination activities associated with FloodSAFE implementation is
addressed through a series of standing meetings. Over 60 different standing meetings
have been identified which included FloodSAFE management, technical work groups,
executive level meetings, etc. Each of these standing meetings focuses on a specific
aspect of the FloodSAFE program, and is defined based on the following conditions:
Additional information is being developed for each meeting to improve the overall
effectiveness and efficiency of the meeting ensure the right people are included.
FloodSAFE 30 DRAFT
Implementation Plan December 2009
0901D2
1. Budget & Fiscal Tracking and Reporting – The purpose of this item is to track
and manage financial resources in a manner that builds public trust and meets
bond accountability expectations. This item includes planning, managing, and
tracking bond funds and reporting back to Legislature.
FloodSAFE 31 DRAFT
Implementation Plan December 2009
0901D2
2. Program Tracking & Status (Weekly, Monthly) – The purpose of this item is
to demonstrate performance of ongoing programs by timely reporting on progress
on meeting various program schedules and objectives. Many of the technical
elements in the FloodSAFE Program were developed at the program level, and
their progress should be tracked and reported to other FloodSAFE programs and
other interested parties.
5. Project Review Board – The purpose of this item is to provide clear direction
and feedback of work in progress and to empower project teams in accomplishing
FloodSAFE objectives. Project Review Boards will provide consistent review and
feedback of program activities to the managers to deliver a consistent high-quality
product.
6. Legislative and Legal Coordination – The purpose of this item is to develop and
apply a business risk management strategy for implementing FloodSAFE that
reduces unnecessary legal and financial liabilities for the people of California.
This includes providing legal and legislative review of bills, legislative requests,
and public record requests.
10. Management Systems and Tools Development – The purpose of this item is to
improve analytical tools and data management systems to develop, archive, and
share new information as it becomes available. This includes developing a simple
FloodSAFE 32 DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE 33 DRAFT
Implementation Plan December 2009
0901D2
For example, Section-level staff is primarily responsible for completing and managing
technical work. Coordination is required with other staff who provide information to
them and to others that are dependent upon their work. Much of this coordination will be
conducted through project-specific meetings. Section-level staff may have limited
outreach responsibilities that are focused on their technical work.
Staff with more management responsibilities may have smaller roles in completion of
technical work, but larger roles in coordinating the work between functional areas and
conducting outreach activities.
The DFM FloodSAFE Program Office is responsible for integrating both technical work
and program management in support of developing flood management policies that are
then communicated to project partners and stakeholders through the outreach program.
As with many aspects of the FloodSAFE Program, communication and outreach are
multi-dimensional, and may be based on a combination of technical issues, regional
issues, or local agency responsibilities. Regional coordinators will be used to ensure a
comprehensive outreach program addresses local issues while maintaining consistency
with the FloodSAFE Program. A detailed communications plan is being developed to
document the internal and external communications plan.
FloodSAFE 34 DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE 35 DRAFT
Implementation Plan December 2009
0901D2
To meet the FloodSAFE foundational objectives, each functional area must deliver
specific work products within its area of expertise. The need to produce these
deliverables is what this FloodSAFE Implementation Plan is all about. Resourcing
defines what entities will be responsible for producing the deliverables.
4.1 Deliverables
Appendices A through G contain detailed listings of deliverables for the functional areas.
Many of these are preliminary or interim products that lead to the major deliverables. The
listings in the following sections are a summary of the major deliverables for each
functional area. Table 4-1 summarizes the number of deliverables by Element and
Component that have been identified to date by the Functional Areas and by other
sources. Some review is needed to reconcile the deliverables to be included in the
FloodSAFE Implementation Plan.
FloodSAFE 36 DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE 37 DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE 38 DRAFT
Implementation Plan December 2009
0901D2
Implement two pilot projects for real-time monitoring and reporting of seepage
through and movement of the levees during high water events, including
installation of monitoring devices
Prepare an annual local agency reporting summary for the Central Valley Flood
Protection Board (CVFPB)
Inspect and report to USACE on an annual basis the maintenance status of the
Sacramento and San Joaquin River flood control systems, including federal
project levees, channels, and major flood control structures
Develop and implement a plan for enhancement of real-time data collection and
exchange, including a provision for data collection network redundancy
In cooperation with federal, local, and State agencies, install additional sensors
and monitor network climate data for rain/snow transition
FloodSAFE 39 DRAFT
Implementation Plan December 2009
0901D2
Develop tools for five-day reservoir release forecasts as part of the San Joaquin
River Watershed F-CO program
Develop and implement a flood response training plan for DWR staff, particularly
for FOC, Incident Commands, and local LMA staff; train about 2,800 DWR and
LMA staff in flood fighting methods, Incident Command, and other emergency
operation activities
Conduct annual table top and functional exercises and training to prepare for
flood events
Using the pilot projects, work with local emergency services managers throughout
the State to incorporate flood operations emergency response into local agencies’
emergency response plans
In cooperation and coordination with State, federal, and local agencies, prepare
Delta Multi-Agency Integrated Flood Emergency Operations Plan
Working with USACE, prepare an updated hydrology for Central Valley streams
FloodSAFE 40 DRAFT
Implementation Plan December 2009
0901D2
Channel Maintenance
Develop and implement vegetation management plans for the Sacramento River
Flood Control Channels
Manage vegetation to pass design flows in a manner that also protects and
enhances the environment within Cache Creek Settling Basin, Butte Creek, Bear
River, Cherokee Creek, and Feather River
Develop sediment removal plans for the Sacramento River Flood Control
Channels
Complete planning and obtain permits for removal of 500,000 cubic yards of
sediment from Cherokee Canal in Butte County
Remove 50,000 cubic yards of sediment from Sycamore Creek near Cohasset
Road in Chico
Obtain permits to remove 60,000 cubic yards from in front of the Sacramento
Weir and complete the removal
Develop hydraulic models for the Sacramento River Flood Control System. The
current plan is to complete hydraulic models used for vegetation management
plans for Cache Creek, Elder Creek, and Sutter Bypass by December 2011, and
begin developing hydraulic models to address sediment management issues
associated with the Cache Creek Settling Basin and Bear River
FloodSAFE 41 DRAFT
Implementation Plan December 2009
0901D2
Repair and/or replace flood control structures assigned to DWR in Water Code
Section 8361
o Bridges are considered special structures and are budgeted and managed
as a separate component. The Bridge Inspection Program is intended to
identify rehabilitation and repair issues with bridges within the
Sacramento River Flood Control System and will be implemented in
Fiscal Year 2009-2010. This program is expected to identify additional
bridge projects once initial inspections are completed.
Trim existing trees consistent with new DWR Vegetation Management Standards
FloodSAFE 42 DRAFT
Implementation Plan December 2009
0901D2
Inspect DWR-maintained levees after high water, identify damage, obtain permits
to repair damage, and work with Maintenance Yards to perform repairs
Levee Repairs
Repair 350 PL84-99 sites as listed in the 2006 inventory (187 sites are eligible for
federal funding)
Repair 154 Sacramento River Bank Protection Project (SRBPP) sites as listed in
the current USACE inventory by the end of 2016.
Repair five critical Levee Stability Program sites by the end of 2010
Schedule proposed repair sites looking two to three years ahead, with six to 12
repair sites per year
Environmental Initiatives
Complete Feather River Pilot Program General Permit and use the gained
experience to develop and obtain a second ―Regional General Permit‖ for
maintenance activities
FloodSAFE 43 DRAFT
Implementation Plan December 2009
0901D2
Expand Regional General Permit for channel clearing activities consistent with
the Feather River General Permit Pilot Program; review the Maintenance Yards’
activities and USACE regulations for working in waterways and determine if
additional permits are required for routine maintenance practices
Complete annual Surface Mining Reclamation Act reports for two sites
FloodSAFE 44 DRAFT
Implementation Plan December 2009
0901D2
Additional technical assistance to all levels of government and the public beyond
the requirements of the FEMA-DWR Community Assistance Program contract
Technical support for all levels of government and the public related to FEMA’s
Map Mod and Provisionally Accredited Levees (PAL) programs.
A leadership role in the development of FEMA’s Risk Mapping, Assessment, and
Planning (MAP) program for FloodSAFE compatible applications in California
The award of FEMA and Housing and Urban Development (HUD) grants to
leverage state funding for floodplain mapping, multi-hazard planning, and hazard
mitigation
An Enterprise Geodatabase with updated data sets deployed at California Data
Exchange Center (CDEC)
Best Available Maps (BAMs) for communities in the Central Valley
BAMs outside the Central Valley
Aerial imagery for 9,000 square miles in the Sacramento and San Joaquin River
Basins
Light Detection and Ranging (LiDAR) survey data for 7,800 square miles in the
Sacramento and San Joaquin River Basins
Bathymetric survey data for major rivers and tributaries associated with the State
Plan of Flood Control
Channel cross sections and structures to support hydraulic model development for
major rivers and tributaries associated with the State Plan of Flood Control
New hydraulic models for major rivers, tributaries, and overbank areas associated
with the State Plan of Flood Control
Water surface profiles for 10-, 50-, 100-, 200-, and 500-year flood events
associated with the State Plan of Flood Control
New floodplain maps for 100-, 200-, and 500-year flood events associated with
the State Plan of Flood Control
Awareness Floodplain Mapping of an additional 15,000 stream miles over the
next five years
FloodSAFE 45 DRAFT
Implementation Plan December 2009
0901D2
Web viewer to facilitate use of floodplain maps such as Central Valley Floodplain
Evaluation and Delineation (CVFED) maps, Levee Flood Protection Zone
(LFPZs) and BAM maps
Floodplain mapping and other studies described in FEMA/DWR Mapping
Activity Statements (Inter-Agency agreements)
Floodplain mapping studies and hydraulic analyses requested by DWR on a case-
by-case basis that may include support for Delta planning and the State Water
Project (SWP)
Update LFPZs maps for areas protected by the State Plan of Flood Control
A parcel database with Geographical Information System (GIS) data for counties
within the area of influence of the State Plan of Flood Control
Annual notification letters to property owners in LFPZs beginning by September
1, 2010, of potential flood risks and mitigation measures
Collaborate with local, State, and federal agencies to increase flood risk
awareness and mitigation strategies
User’s Guide document for cities and counties to use in coordinating and
implementing 2007 flood legislation and land use planning
Notify the public of the availability of the User’s Guide, and conduct public
outreach workshops to assist in the implementation of the guidance
Integrated flood management input to the California Water Plan (CWP) Update
2009 including flood-related regional report data and flood risk management
strategy
Integrated flood management input to the Integrated Water Management plans
based on criteria, consistency, and compliance with program guidelines
Hazard Mitigation
o Grant applications to develop Hazards U.S. (HAZUS) models
o Develop Hazards U.S. Multi-Hazard (HAZUS-MH) flood models pending
funding
o Update HAZUS-MH ―default‖ databases such as essential facilities, utilities,
transportation systems and general building stock for use by various State
agencies, local governments and others pending funding
o Enhance DWR’s ability to respond to requests from the Governor,
Legislature, and other officials concerning statewide flood risks
FloodSAFE 46 DRAFT
Implementation Plan December 2009
0901D2
Prepare solicitation packages and provide grant funding for selected projects in
the Flood Protection Corridor Program
Provide State share of funding for flood protection projects outside the Central
Valley through the Flood Control Subvention Program
FloodSAFE 47 DRAFT
Implementation Plan December 2009
0901D2
Participate in and provide funding for levee repair project for Local Levee
Assistance
Revise current interim guidelines for local assistance under the Special Project
Program and develop final guidelines for distribution for Delta levee
rehabilitation flood projects
Incorporate results of the subsidence research and update when future research
recommends changes in guidance
Program Support
Levee Evaluations
FloodSAFE 48 DRAFT
Implementation Plan December 2009
0901D2
San Joaquin River Flood Control System Geotechnical Assessment Report – GAR
San Joaquin River Flood Control System Geotechnical Evaluation Report – GER
FloodSAFE 49 DRAFT
Implementation Plan December 2009
0901D2
Vegetation research paper describing the effects that woody vegetation growing
on or near levees has on levee integrity
Flood Control System Status Report (FCSSR) for the SPFC (December 31, 2010)
Status Report on the Progress and Development of the CVFPP (December 31,
2010)
FloodSAFE 50 DRAFT
Implementation Plan December 2009
0901D2
Conservation Strategies
As-needed materials for public meetings, workshops, and forums, and requests for
information
FloodSAFE 51 DRAFT
Implementation Plan December 2009
0901D2
Field requests for information from Legislature and provide timely responses
Annual budgets
Funding allocations
Policy documents
FloodSAFE 52 DRAFT
Implementation Plan December 2009
0901D2
4.2 Resourcing
The resourcing estimates for producing the deliverables listed above are shown in Tables
4-2 through 4-8. In these estimates, the work is broken down into 5 percent increments to
provide a broad indication on where the funding (see Section 6) is likely to be applied.
These resources and the total estimated percent allocation for all seven Functional Area
are shown below:
USACE __ percent
Consultants __ percent
Other entities such as resources agencies and academic institutions will also conduct
work, but their roles are expected to be smaller than the 5 percent increment used in
Tables 4-2 through 4-8. Resource allocations to local agencies include the State share of
expenditures for constructing flood protection facilities.
FloodSAFE 53 DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE 54 DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE 55 DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE 56 DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE 57 DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE 58 DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE 59 DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE 60 DRAFT
Implementation Plan December 2009
0901D2
DWR management, FloodSAFE partners, technical task staff, the Legislature and
Governor’s office, and the general public have a need to know how the FloodSAFE
initiative is progressing and what is being achieved for its multi-billion dollar investment.
Considering the complexity of flood system improvements, reporting, and tracking of
progress, including expenditures, will be keys in maintaining broad and up-to-date
understanding of progress. It is also important to have the information readily accessible
so customized reports can be assembled in a timely manner.
Provide a simple framework that can be efficiently (does not take much time) and
effectively (focuses on the pertinent information needed for reporting)
implemented by FloodSAFE staff and managers
o Front-End Accountability
o In-Progress Accountability
o Follow-up Accountability
FloodSAFE 61 DRAFT
Implementation Plan December 2009
0901D2
1. Define Project and Deliverables. Before any technical work on a project begins,
project staff will identify and define project deliverables, establish milestones and
performance measures, and assign the deliverables to project managers. This
front-end accountability sets the stage for a successful project. The project team
will prepare a project charter (see Figure 5-1 for example) to summarize the
project scope, roles, and responsibilities; refer to other more detailed documents;
etc. DWR management will review and comment on the charter before the team
begins its technical work. The step will be updated as needed during project
implementation.
2. Monthly Functional Area Reporting. By the last working day of each month,
project managers will complete a progress report for their project and submit the
report to their office chief. The report will be a simple one page document that
should be prepared in a fraction of an hour. See Figure 5-2 for instructions to
complete the template and Figure 5-3 for an example of a completed report and
level of detail desired. Each office chief will review the reports for completeness
and submit them to the FloodSAFE reporting staff managed by Functional Area 7
by the second day of the next month.
FloodSAFE 62 DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE 63 DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE 64 DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE 65 DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE 66 DRAFT
Implementation Plan December 2009
The completed reports are then usable for preparation of a wide variety of monthly
reports and additional reports, all using the same consistent information. Examples of
reports that can be prepared based on the collection of monthly project progress reports
are as follows:
Reports to CVFPB
External briefings
The reports will also be on record for follow-up accountability reporting when needed.
These completed reports are not only a valuable source of information for other reporting
needs of FloodSAFE, but should save project staff and project managers time in the
future. Rather than periodically being asked for quick updates to meet specific and
evolving needs of DWR management or the Legislature, project managers will only need
to prepare simple reports once each month. Roll-up of information into customized
reports to meet immediate needs will be prepared by Functional Area 7 using this
information without needing to request participation from the project managers.
Figure 5-4 is a graphical representation of this monthly process. Note that Step 1 will be
conducted initially and updated as needed during project implementation.
FloodSAFE 67 DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE 68 DRAFT
Implementation Plan December 2009
0901D2
Figure 5-5 shows an example of these designators for the seven functional areas and their
elements and components.
FloodSAFE 69 DRAFT
Implementation Plan December 2009
0901D2
Figure 5-5. FloodSAFE Component Deliverable Glossary of Terms for Tracking System
FloodSAFE 70 DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE 71 DRAFT
Implementation Plan December 2009
0901D2
c) Executive briefings
b) Budget/Fiscal Report
d) FloodSAFE Newsletter
a) Expenditures Report
FloodSAFE 72 DRAFT
Implementation Plan December 2009
0901D2
As Needed Materials
a) State Legislature
b) Federal Congress
Executive Briefings
a) State executives
a) County Supervisors
b) LMAs
Guidelines
Annual budgets
Policy documents
FloodSAFE 73 DRAFT
Implementation Plan December 2009
0901D2
6 Investment Strategy
California must make significant investments in its flood management systems over the
next 20 years in order to provide public safety. No single source of funding will meet all
these infrastructure needs. Instead, a mix of federal, State, and local funds will be needed
to ensure adequate investment. This mix of funding sources will vary according to the
type of project or program, beneficiaries, availability of funds, urgency, and other factors.
Flood management investments are needed throughout the State. Based on expert
judgment, current cost estimates for flood system improvements statewide are in the $25
billion to $30 billion range over the next 20 years, far in excess of available funds that
can be used as State cost shares. Since the largest and most damaging floods in California
occur in the Central Valley, upgrade of flood protection facilities in the Central Valley
will demand the largest investments. The six main areas for investment are as follows:
1. Upgrade Central Valley Urban Levees. Upgrading urban levees (about 345
miles of project levees and 110 miles of non-project levees) to 200-year level of
protection is estimated to cost about $12 billion.
3. Delta Improvements. Upgrading Delta levees to protect life and property, water
supply, infrastructure, habitats, and recreational areas is estimated to cost about $4
billion.
5. Upgrade Flood Control Structures. The cost to upgrade existing flood control
structures (weirs, gates, pumping plants, outlets, and other structures) in the
Central Valley is estimated to be about $0.5 billion.
FloodSAFE 74 DRAFT
Implementation Plan December 2009
0901D2
These initial cost estimates total about $26 billion over the next 20 years. These estimates
will be refined in the coming years as better definition of system deficiencies and needed
improvements are available. Figure 6-1 provides a graphical representation of the
distribution of these estimated costs through 2030.
Figure 6-1. Estimated Distribution of Investment Costs
There are also many unknowns on the amount of funding that will be available over the
next five to ten years. The amount of State General Fund available for major flood
management improvement projects may not be significant, depends on appropriations
from the Legislature, and is subject to wide variations. State Bond funding depends on
the legislative actions and approval by California’s voters. Overall, the State’s varying
budgetary health can be expected to directly influence funding available for investments
in flood management. Similarly, federal funding contributions depend on Congressional
action. Local funding contributions can also vary by location and time.
These funding uncertainties (need and availability) are prime reasons why this
implementation plan needs to be periodically updated as more information becomes
available.
FloodSAFE 75 DRAFT
Implementation Plan December 2009
0901D2
The amount of money available for flood management through the General Fund has
varied widely from year to year. After years of reduced General Fund budgets for State
flood programs in the early 2000s, substantial funding increases have occurred in recent
years. The General Fund contributions to DFM programs has increased from $________
million in fiscal year 2000-01 to $_______ million in 2008-09.
FloodSAFE 76 DRAFT
Implementation Plan December 2009
0901D2
The California Legislature has emphasized the need to make ―all feasible efforts to obtain
funding from the federal government in advance or by arranging to perform work which
is a federal responsibility prior to the availability of federal appropriations with the
intention that the costs will be reimbursed or eligible for credit by the federal
government‖ (Budget Act of 2008).
Table 6-1. Estimated Cost Shares for Needed Flood System Improvements through 2030
Major Investment Needs Total of $26,000 Million ± $5,000 Million
State Local Federal Total
1- Upgrade Central Valley Urban Levees 3,200 1,400 7,400 12,000
2- Upgrade Central Valley Non-Urban Levees 1,400 300 2,300 4,000
3- Delta Levee Improvements 3,110 890 0 4,000
4- Subvention Programs Outside Central Valley 1,000 410 2,590 4,000
5- Upgrade Flood Control Structures 190 0 310 500
FloodSAFE 77 DRAFT
Implementation Plan December 2009
0901D2
To date, little federal investment has been made to match the FloodSAFE investments.
The FloodSAFE initiative has developed a federal engagement and communication
strategy (see FA7 in Appendix G) to work with USACE to formulate a partnership
program that would fully engage USACE in the FloodSAFE program and that would gain
support for federal funding. In parallel, FloodSAFE staff will work with the Governor’s
Office and federal legislatures for federal authorizations and appropriation of flood
protection measures in California.
Cleared sediment from Fremont Weir and Tisdale Bypass to restore system
capacity.
Initiated public process for developing Central Valley Flood Protection Plan.
Stockpiled a quarter million tons of rock for the Delta levee emergency work.
Over a thousand people trained for flood fighting statewide this year.
Completed 235 urgent levee and river bank repairs throughout the Central Valley
at a cost of $283 million.
FloodSAFE 78 DRAFT
Implementation Plan December 2009
0901D2
$408 million allocated for Early Implementation Projects (EIP) in which $130
million has been paid to-date. EIP Projects include:
o Two Sacramento Area Flood Control Agency projects for Natomas Levee
Improvement.
o Levee District 1 levee setback work at Star Bend on the Feather River.
Table 6-2 in Section 6.6.2 shows State investments (bond and General Fund) already
expended (FY 2006-07 through 2008-09) for each of the seven functional areas. Since the
start of the FloodSAFE initiative, and through FY 2008-09, the State has invested a total
of $137 million in general funds and $2,259 million in bond funds.
FloodSAFE 79 DRAFT
Implementation Plan December 2009
0901D2
Table 6-2 shows expended and projected funding for each functional area with General
Fund and bond (1E & 84) funds through FY 2017-2018. A more detailed breakdown of
the anticipated funding for each functional area and its elements can be found in the
following section and in Appendices A through G. These will be updated at least
annually as more information is available.
FloodSAFE 80 DRAFT
Implementation Plan December 2009
0901D2
Table 6-2. Initial Investment Plan for State Flood Management Funds
Estimated State Funding ($millions)
Expended Projected Projected
State Funding 3 Years 5 Years 4 Years
Functional Area
Source (FY 2006-07 (FY 2009-10 (FY 2014-15 Total
Through Through Through
(2008-09) (2013-14) (2017-18)
$273.7
Flood Emergency
General Fund 65.4 11.8 49.5 126.7
Response
Bonds (1E & 84) 66.3 80.7 0 147.0
$328.5
Operations & Maintenance
and Environmental General Fund 30.9 12.5 52.4 95.7
Stewardship
Bonds (1E & 84) 49.5 168.7 14.6 232.7
$167.7
Floodplain Risk
General Fund 15.5 7.2 30.1 52.7
Management
Bonds (1E & 84) 46.1 69.0 0 115.0
$329.3
FloodSAFE 81 DRAFT
Implementation Plan December 2009
0901D2
7 FloodSAFE Governance
Deputy Director – The Deputy Director will serve as the Executive Sponsor
providing vision and leadership for FloodSAFE and to the FloodSAFE Executive
Manager; possess a broad and comprehensive knowledge of statewide flood
management systems, relation between flood management and other resources
management, policies, State and federal legislation, and issues affecting
FloodSAFE now and into the future; serve as a member of the FloodSAFE
Deputy Director Team; provide executive leadership in the development and
execution of FloodSAFE policy that supports the FloodSAFE strategic objectives;
approve policies supporting FloodSAFE; and takes direction from the Director of
DWR.
Assistant Deputy Director – The Assistant Deputy Director will assist the
Deputy Director to initiate, develop, and review policies related to a specialized
area of focus, such as environmental or engineering; serve as a member of the
FloodSAFE Management Team; work collaboratively with other policy
executives and managers; review and comment on ―Decision Memorandums‖;
and reports to the Deputy Director.
FloodSAFE 82 DRAFT
Implementation Plan December 2009
0901D2
programs to support the FloodSAFE objectives, and act as the main point of
contact and spokesperson to the State Legislature, Department of Finance, and
DWR Fiscal Services in regard to the FloodSAFE budget and resource needs;
exercise authority to make decisions regarding the management of FloodSAFE
resources; direct the FloodSAFE Communication and Outreach Program; direct
execution of FloodSAFE projects’ tracking, reporting, and Bond Accountability
and Management; recommend policy approval to the FloodSAFE Deputy
Director Team; report directly to the Chief of DFM; brief the Deputy Director
and Director as needed; and serves as the lead of the FloodSAFE Management
Team.
DFM Office Managers - Functional area managers are generally Office Chiefs
within DFM and take direction from and report to the Chief of DFM; are
responsible for execution of the programs and projects within their respective
functional area; directly supervise Project Managers for FloodSAFE projects
and provide oversight and direction to contracted resources; are responsible for
functional areas’ budgets and allocation of resources; provide direction and
oversight to Project Managers and Project Teams; and coordinate their activities
with the FloodSAFE Program Management Office. Managers of the Flood
Management Planning and Conservation Strategy Functional Area serve as
members of the FloodSAFE Integrated Water Management Team.
FloodSAFE 83 DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE 84 DRAFT
Implementation Plan December 2009
0901D2
These teams are responsible for coordinated delivery of FloodSAFE projects. Frequent
coordination between all team members is essential for successful implementation of
FloodSAFE.
Figure 7-2 shows how the managers described in Section 7.1 will use teams and
coordination groups as part of the FloodSAFE Governance structure. The figure includes
the organization for the integration of FloodSAFE with water management.
FloodSAFE 85 DRAFT
Implementation Plan December 2009
0901D2
Chief of FSESSRO
Office Chiefs will attend the meetings as needed for discussion of policy issues related to
any particular Functional Area. The FloodSAFE Deputy Team Meeting will be led by
the Chief of the FloodSAFE Program Management Office. The Team will be responsible
for the overall implementation of FloodSAFE. The Team will review and approve high-
level policies related to FloodSAFE implementation. Specifically, the Team will:
Review and approve the FloodSAFE Bond Expenditure Plan and establish and
implement annual program priorities
Ensure programs and projects are properly coordinated among all FloodSAFE
functional areas and other organizations within DWR and with partnering
agencies
Chief of FSESSRO
FloodSAFE 86 DRAFT
Implementation Plan December 2009
0901D2
The FloodSAFE Integrated Water Management Team is led by the Deputy Director in
Charge of Flood Management. This team will be responsible for coordination of
FloodSAFE Program activities across the Department and will address FloodSAFE
resources and services needs to ensure timely implementation of integrated programs and
projects. Specifically, the FloodSAFE Integrated Water Management Team
Members of the Environmental Conservation and Permitting Team include the Chief of
FSESSRO as the team leader, Chief of Delta Suisan Marsh Office, Flood Management
Planning and Conservation Strategy Functional Area (FA 6) Manager, Flood Protection
Projects and Project Grants Functional Area (FA 4) Manager, and Operations &
Maintenance and Environmental Stewardship Functional Area (FA 2) Manager.
FloodSAFE 87 DRAFT
Implementation Plan December 2009
0901D2
Briefing and updating the Functional Area Managers on policies and guidance
developed by the FloodSAFE Deputy Director Team and other issues discussed
at other Governance Teams meetings
Formulating and discussing high level issues that should be elevated and
addressed by the FloodSAFE Deputy Director Team or other Governance Teams
Coordinating work activities between all functional areas
Addressing FloodSAFE implementation issues including resource,
organizational, administrative, and scheduling issues
FloodSAFE 88 DRAFT
Implementation Plan December 2009
0901D2
7.3 Partnerships
Flood system improvement has been a coordinated partnership of State, local, and federal
agencies. Many agencies have roles and responsibilities in flood management in
California. The role and engagement of these agencies in relation to functional areas and
specific flood system elements are presented in Figure 4. FloodSAFE will continue the
tradition of working closely with local and federal partners to improve flood protection in
California. The key partners at the federal level are Federal Emergency Management
Agency and the USACE. Partnership with USACE is required for successful
implementation of the Program. Progress has been made in coordinating FloodSAFE
activities with USACE. Enhanced partnership with USACE will ensure USACE is a full
FloodSAFE partner, will engage in the Program, will provide leadership in program
development and implementation, and will support full cost-sharing for the FloodSAFE
Initiative.
Flood projects are generally funded by State, federal, and local agencies. Historically, this
mix of funding sources varied according to the type of project or program, beneficiaries,
availability of funds, urgency, and other factors. Although the process of providing cost-
sharing on a project-by-project basis has worked in the past, it is a time-consuming
process and it is not an appropriate or sufficient approach to implementation of
FloodSAFE, which consists of a wide range of programs/projects that provide broad
system-wide multiple benefits. FloodSAFE should negotiate a broad cost-sharing
agreement with USACE in which system-wide flood risk reduction program cost sharing
is agreed upon instead of a traditional project-by-project evaluation and cost sharing
arrangement.
FloodSAFE 89 DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE 90 DRAFT
Implementation Plan December 2009
0901D2
Some of the key roles of local agencies within FloodSAFE will be to:
FloodSAFE 91 DRAFT
Implementation Plan December 2009
0901D2
Promote appropriate land use planning to meet FloodSAFE goals and objectives
Implementation of the FloodSAFE initiative at the local level will require DWR to
interact with many local agencies that may have different and sometimes overlapping
jurisdictions, authorities, and responsibilities. Participation of local agencies also depends
on the functional area and the type of project or program that they are interested in
developing in their geographic area.
Figure 7-4 shows one example of how local agencies can participate in all the functional
areas and components performing work within their watershed. The participation can be
expected to be different depending on agencies’ jurisdictions, authorities, responsibilities,
and other circumstances. The example shows areas of participation for the LMAs, local
office of emergency services, water agency or reservoir operators, and local planning
agency. Each functional area manager should be aware of different levels of local area
participation.
In most cases, each functional area spans many geographic areas, referred to as
hydrologic regions. Ten hydrologic regions in the State are defined by distinctive
watersheds. Since local agencies and the public may not know where to begin within
DWR when they need assistance, DWR regional managers will help direct these inquiries
to the correct DWR manager.
FloodSAFE 92 DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE 93 DRAFT
Implementation Plan December 2009
0901D2
FloodSAFE 94 DRAFT
Implementation Plan December 2009
0901D2
This FloodSAFE Implementation Plan is intended to provide broad guidance on how the
work necessary to achieve FloodSAFE foundational objectives will be conducted.
Recognizing that there are still many unknowns, especially in costs, for flood system
improvement, this Plan is intended to be flexible and periodically updated as more
detailed information becomes available. Each functional area manager will prepare a
strategic plan and more detailed project and program management plans as needed to
support the program based on the guidance provided by this plan.
The first anticipated update of this FloodSAFE Implementation Plan is within six months
following the 2012 adoption of the CVFPP by the CVFPB. While the first CVFPP may
not be a definitive plan, it will provide better definition of the types of system
improvements and their costs for potential implementation within the Central Valley. At
a minimum, subsequent updates to the FloodSAFE Implementation Plan will follow each
five-year update of the CVFPP. Available funding is expected to be a major stimulus, or
constraint, to implementation. Changes in funding (federal, State, and local) will be a
prime reason for needing to adapt the Implementation Plan.
FloodSAFE 95 DRAFT
Implementation Plan December 2009
0901D2
Flood Emergency Response is one of seven functional areas necessary to implement the
FloodSAFE initiative. Flood Emergency Response refers to preparedness, response, and
recovery activities necessary before, during, and after a flood emergency. The Flood
Emergency Response functional area has been a long-standing base program in DWR’s
DFM, but FloodSAFE makes improvements to the program. While the composition of
the program is likely to change over time, Flood Emergency Response must continue
indefinitely into the future, regardless of the protection provided by the improved system.
1. Flood Preparedness and Planning. Actions identified under this phase are
designed to prepare flood emergency staff from DWR and other agencies to be
trained, informed, and ready for major flood events. This is the planning phase of
emergency response that puts the resources in place before a flood event. Some
work under this phase includes:
Develop the necessary tools, models, and information that will be needed in
an operational mode during a flood emergency
2. Flood Response. Flood response is the operational phase of the program that
occurs during the emergency. To effectively respond to flood emergencies, DWR
would:
Collect precipitation, temperature, and river stage data for use in preparing
watershed runoff forecasting, reservoir operations, and river forecasting
Patrol the flood control facilities and levees during high water to identify any
imminent threat to flood control structures and respond as necessary
Assist in flood fight activities such as placing sand bags on levees or placing
material to counter erosion from wind waves
3. Flood Recovery. The recovery phase includes evaluating the flood system,
identifying what needs to be fixed, evaluating the proposed recovery actions,
prioritizing recovery actions, and implementing mitigations and flood system
improvement actions. After the flood emergency has passed, an After-Action
Report is prepared that summarizes response and recovery activities conducted by
DWR offices and other entities. Flood management system evaluation and
implementation of specific mitigation measures are required to ensure flood
system integrity are preserved as part of the flood recovery phase. DWR flood
recovery responsibility is limited to assistance in evaluating and repairing
damaged flood management facilities and recovery of State infrastructure.
A.2.1 Goals
The over-arching goal of the Flood Emergency Response functional area is to strengthen
flood emergency response throughout the State to save lives and protect property. The
key program goals include:
Respond effectively to flood emergencies and reduce recovery time after flood
events
A.2.2 Objectives
The Flood Emergency Response Program will achieve the stated goals through
attainment of the following objectives:
Inspect, understand, and document the flood control system’s status and
deficiencies
Preserve the State’s investment in data collection, model development, and other
tools that are prepared for FloodSAFE
o Include an effective training program for DWR and local agencies’ staff in
flood emergency response including flood fights and flood emergency
exercises
Improve tools (i.e., forecasting models, data collection, and management) and
processes (i.e., flood warning, notifications, and reservoir operations) that can
significantly improve timing, reliability, and accuracy of flood warnings
River Forecasting. The river forecasting staff prepares river stage based on
forecasted releases from the reservoirs and forecasted watershed flows for
unregulated streams. The forecasts are available to first responders, LMAs, state
and federal agencies, and the public.
DWR Delta Flood Emergency Preparedness and Response Plan. Due to the
vulnerability of the Delta to flood hazards and the potential impact of major
flooding in the Delta on State water supply infrastructure and the resources of the
Delta, this component will prepare the State to effectively respond and quickly
recover from large-scale flooding in the Delta.
Update Central Valley Streams Hydrology. Under this component DWR will
work with USACE to update the hydrology of the Central Valley Streams.
Conduct System Re-operation Studies. Over the next five years, a multi-
faceted, multi-agency, comprehensive approach will be pursued to develop tools
to conduct system re-operation studies that integrate flood control and water
supply components of the reservoirs.
Implement two pilot projects for real-time monitoring and reporting of seepage
through and movement of the levees during high water events, including
installation of monitoring devices
Inspect and report to USACE on an annual basis the maintenance status of the
Sacramento and San Joaquin River flood control systems, including federal
project levees, channels, and major flood control structures
Develop and implement a plan for enhancement of real-time data collection and
exchange, including a provision for data collection network redundancy
Forecast-Coordinated Operations X X
Forecast-Based Operations X X
River Forecasting X X X X X X
In cooperation with federal, local, and State agencies, install additional sensors
and monitor network climate data for rain/snow transition
Develop tools for five-day reservoir release forecasts as part of the San Joaquin
River Watershed F-CO program
Develop and implement a flood response training plan for DWR staff, particularly
for FOC, Incident Commands, and local LMA staff; train about 2,800 DWR and
LMA staff in flood fighting methods, Incident Command, and other emergency
operation activities
Conduct annual table top and functional exercises and training to prepare for
flood events
Using the pilot projects, work with local emergency services managers throughout
the State to incorporate flood operations emergency response into local agencies’
emergency response plans
In cooperation and coordination with State, federal, and local agencies, prepare
Delta Multi-Agency Integrated Flood Emergency Operations Plan
Working with USACE, prepare an updated hydrology for Central Valley streams
A comprehensive program tracking and reporting system should be developed and used
by the program managers. Activities and achievement of each project should be noted
and tracked by the tracking system. Periodic progress reports should be prepared using
the program tracking system. Branch managers should use the tracking system to
evaluate the project’s progress in achieving performance measures on a quarterly basis
and make any adjustment or course correction needed for the projects under their
supervision.
(Goal 2, 3, & 4)
Project (Goal 1)
Response, and
Preparedness,
Delta Flood
1 Number of water quality studies
Recovery
2 Number of benefit/cost assessments
Engineering & Facility Assessments
1 Number of cut-sheet & pre-designs completed
2 Number of transfer facilities assessed and facilities developed
Hydrology
Hydrology and
System Re-
(Goal 1)
FloodSAFE California
Flood Emergency Preparedness, Response & Recovery Program
Climate Data Collection and Precipitation/Runoff Forecasting $5.1 $1.7 $1.7 $3.6 $2.9 $1.6 $11.5
Real Time Data Collection $2.7 $1.3 $1.5 $1.5 $1.2 $0.3 $5.8
Climate Analyses $0.9 $0.0 $0.0 $0.3 $0.2 $0.2 $0.7
QPF/Watershed Forecasting $0.2 $0.4 $0.2 $0.8 $0.8 $0.7 $2.9
Snowmelt/Runoff Forecasting $1.3 $0.1 $0.0 $1.0 $0.7 $0.4 $2.2
Reservoir Operations and River Forecasting $1.7 $0.8 $0.3 $2.0 $3.0 $1.8 $7.9
River Forecasting $1.2 $0.0 $0.0 $0.5 $0.5 $0.4 $1.4
Forecast -Coordinated Res. OP. $0.5 $0.8 $0.3 $1.0 $1.0 $0.5 $3.6
Forecast Based Operations $0.0 $0.0 $0.0 $0.5 $1.5 $0.9 $2.9
Flood Operatiion Emergency Response $1.0 $2.8 $1.0 $3.5 $5.0 $11.0 $23.3
Department Emergency Response $1.0 $0.1 $0.1 $1.5 $2.0 $0.5 $4.2
Local Emergency Preparedness & Response $0.0 $0.7 $0.9 $2.0 $3.0 $0.5 $7.1
NEW JOC $0.0 $0.0 $0.0 $0.0 $0.0 $10.0 $10.0
Delta Emergency Prep. & Response Plan $0.0 $2.0 $0.0 $0.0 $0.0 $0.0 $2.0
Delta Preparedness, Response & Recovery Project $0.0 $0.0 $5.0 $0.0 $0.0 $0.0 $5.0
Delta ER Communications $0.0 $0.0 $5.0 $0.0 $0.0 $0.0 $5.0
TOTAL Prop 84 Allocation $16.7 $5.3 $3.0 $11.8 $14.4 $16.5 $56.0
Levee Improvement (Local Assistance Funding) ** DSMO Managed $0.0 $0.0 $35.0 $20.0 $0.0 $0.0 $55.0
Hydrology & System Re-operation $0.0 $8.0 $3.0 $0.0 $0.0 $0.0 $11.0
Hydrology Update $0.0 $8.0 $0.0 $0.0 $0.0 $0.0 $8.0
Climate Change Hydrology $0.0 $0.0 $3.0 $0.0 $0.0 $0.0 $3.0
TOTAL Prop 1E Allocation $0.0 $18.0 $40.0 $36.0 $4.0 $3.0 $101.0
Operations and Maintenance is one of seven functional areas necessary to implement the
FloodSAFE initiative. Operations and Maintenance refers to the need to keep project
facilities in good working condition so they continue to operate as designed – wear and
tear on system facilities can reduce system capacity or make them more vulnerable to
failure. Operations and Maintenance has been a long-standing base program in DWR’s
DFM, but FloodSAFE makes improvements to the program. Operations and Maintenance
needs are expected to change over time as system upgrades are implemented. Work in the
functional area must continue indefinitely into the future, even after the FloodSAFE
functional objectives have been achieved.
Levees deteriorate with time because of rodent activity, vegetation growth, vehicle
traffic, encroachments, unauthorized construction or vandalism, high water erosion, and
other factors. The effectiveness and capacity of flood control bypass channels can be
reduced through sedimentation, vegetation growth, unauthorized obstructions, and other
means. Water control structures such as pumping stations and weirs can also degrade
with time and use. Flood maintenance work is needed on a consistent basis to fix flood
system deficiencies so that they will operate properly during storm events. The
Operations & Maintenance and Environmental Stewardship functional area will ensure
the continued proper functioning of the flood control system, and thus, the protection of
the region from flooding. In the case where critical levee repairs are needed to make
levees serviceable for the following flood season they are fixed on a fast-track basis
under this functional area.
The Operations and Maintenance and Environmental Stewardship functional area covers
State activities for maintaining 293 miles of levees, 11 weirs, 5 gate structures, 4
pumping plants, 10 bridges, 50 miles of drainage canals, and all channels in the
Sacramento system. In addition, 60 LMAs perform maintenance for the Sacramento
River Flood Control Project and 29 LMAS perform maintenance for the San Joaquin
River Flood Control System.
State activities also extend to levee repairs for project levees being maintained by the
LMAs or Reclamation Districts. These repairs are done under three federal authorized
programs; Levee Stability Program (LSP), Sacramento River Bank Protection Project
(SRBPP) and PL84-99 Rehabilitation Assistance Program. In addition, the State repairs
project levees under the Sacramento-San Joaquin Erosion Repairs Project (SSJERP). In
some cases, critical erosion sites and levee instability problems cannot wait for system
improvement projects, but demand rapid repair before the upcoming flood season. In
such cases, the project levees are repaired on the recommendations made by the Levee
Evaluations and Engineering functional area.
LMAs maintain the remaining project flood facilities in the Sacramento Valley, project
facilities in the San Joaquin valley, and non-project levees in the Sacramento Valley, San
Joaquin Valley, and the Delta. Under the Emergency Response functional area, however,
the State inspects the maintenance of project levees maintained by LMAs. Under the
Flood Protection Projects and Project Grants functional area, the State also provides
financial assistance to LMAs for non-project levees in the Delta.
B.2.1 Goal
The goal of the Operations & Maintenance and Environmental Stewardship functional
area is to save lives and protect property by ensuring the flood control features in the
Sacramento River Flood Control Project are properly maintained and deliver the level of
flood protection they were designed and built to provide.
B.2.2 Objectives
The Objectives of the Program include:
Reduce Risk - Reduce flood risk to the people of the Sacramento Valley, their
homes and property, the State’s infrastructure, and the public trust resources.
Protect and Enhance Ecosystems - Maintain the Sacramento River Flood Control
System in ways that protect, restore, and where possible, enhance environmental
resources.
Promote Sustainability - Take actions that improve compatibility with the natural
environment and reduce the expected costs to operate and maintain flood
management systems into the future.
Reduce the Consequences of Flooding - Take actions prior to flooding that will
help reduce the adverse consequences of floods when they do occur and allow for
quicker recovery after flooding.
Inspection and Evaluations. FMO staff are responsible for the periodic
inspection of flood structures under their care. These structures and facilities
would include pumping plants, weirs, bridges, and other appurtenant structures
identified in the Sacramento River Flood Control System.
Facilities include pumping plants, which transfer runoff and excess water from the
land side of levees in the flood system to flood channels; bridges, which provide
access over and to flood facilities; and water control structures such as weirs.
Routine Operations and Maintenance. Levees are distinct flood structures that
must receive annual maintenance attention. Most maintenance activities such as
mowing, disking, burning, dragging, and spraying as well as rodent control on the
levee are repeated every year for the levee to retain at least a minimum
satisfactory level of readiness for high water events.
The Erosion Repairs element is limited to erosion repairs of channels and levees
and includes the federal Sacramento River Bank Protection Project (SRBPP) and
the Sacramento and San Joaquin Erosion Repairs Project (SSJERP). The SSJERP
is Central Valley-wide and with regard to SRBPP, this cost-shared program will
be used to fix levees when the SRBPP authorization runs out.
The Erosion Repairs element includes but is not limited to erosion, seepage, and
underseepage repairs, and includes the federal Levee Stability Program and the
federal PL 84-99 Rehabilitation Assistance Program. Unless noted, the objectives
incorporate all applicable federal requirements and technical criteria.
Channel Maintenance
Develop and implement vegetation management plans for the Sacramento River
Flood Control Channels
Table B-1 Implementation of Operations & Maintenance and Environmental Stewardship Program Elements
Environmental Programs X X
Mitigation Activities X
Prepare documentation of the O&M requirements for weirs and gaging stations
Prepare documentation of the completed O&M activities for the listed pumping
plants
Prepare documentation of the completed O&M activities for the listed bridges
Levee Repairs
Repair 350 PL84-99 sites as listed in the 2006 inventory (187 sites are eligible for
federal funding).
Repair 154 SRBPP sites as listed in the current USACE inventory by the end of
2016.
Repair 76 SSJERP sites as listed in the 2007 inventory by the end of 2016.
Repair five critical Levee Stability Program sites by the end of 2010.
Schedule proposed repair sites looking two to three years ahead, with six to 12
repair sites per year
Environmental Initiatives
Table B-3 Operations & Maintenance and Environmental Stewardship (FA 2) State Investments
Floodplain Risk Management is one of seven functional areas necessary to implement the
FloodSAFE initiative. The primary purpose of Floodplain Risk Management is to reduce
loss of life and property caused by floods, and to restore the natural resources and
functions of floodplains. Floodplain Risk Management provides comprehensive guidance
and technical support to federal, State, and local officials in addressing floodplain
management issues, and assesses the floodplain management needs of California
communities while establishing strategies, measures, and priorities for meeting those
needs. The strategy includes identifying the most effective allocation of federal, State,
and local resources to address and provide the tools for identification, planning, and
mitigation of flood hazards, as well as promoting overall sound floodplain management
statewide. Floodplain Risk Management incorporates a comprehensive and system-wide
strategy designed to support an integrated federal, State and local planning approach by
developing appropriate and useful tools, providing technical assistance for resource
management support, and promoting more effective flood management efforts.
Floodplain Risk Management has been a long-standing base program in DWR’s DFM;
however, FloodSAFE makes improvements to the program. With changing land use in
the floodplain, this functional area needs to continue after the FloodSAFE functional
objectives are met. Floodplain Risk Management is based on the acknowledgement that
there will always be some risk to those living and working within the floodplain,
regardless of system improvements that are made to reduce the flooding potential. The
role of State National Flood Insurance Program Manager for California is part of
Floodplain Risk Management. This functional area is managed by the Levee Repairs and
Floodplain Management Office of DFM.
Floodplain management begins with better definition of the floodplain limits, the
frequency of flooding, and water depth and velocity. Flood risk data can then be
communicated to property owners and land use planners providing them with the
resources necessary to make better decisions; for example, setting aside greenways or
parks for recreation and environmental use in the deepest areas of the floodplain, and
implementing building codes that incorporate methods to significantly reduce property
damage.
Floodplain Management
In 2002, the Department of Water Floodplain management includes actions to the
Resources convened a California Floodplain floodplain to reduce losses to human resources
Management Task Force, which developed within the floodplain and/or protect benefits to
38 recommendations related to development natural resources associated with floodplains and
in flood-prone areas. The Task Force sought flooding. Sample actions include:
to recommend floodplain management
1. Minimizing impacts of flood flows to
strategies designed to reduce flood losses
both social and economic resources
and maximize the benefits of floodplains.
The Task Force found that existing 2. Maintaining or restoring natural
programs are inadequate to accomplish floodplain processes
these goals. 3. Recommendations for removing
obstacles within the floodplain flowage
The recommendations were divided into areas voluntarily or with just
three categories: 1) Recommendations for compensation
Better Understanding of and Reducing 4. Avoiding encroachments into the
Risks from Reasonably Foreseeable floodplain
Flooding, 2) Recommendations for Multi-
Objective Management Approach for 5. Educating and planning of both public
Floodplains, and 3) Recommendations for and private entities for emergency
preparedness
Local Assistance, Funding, and Legislation.
The 96-page report can be accessed at 6. Evaluating floodwater management
http://fpmtaskforce.water.ca.gov. systems to help ensure that they are
maintained to the design flow capacities
C.2 Goal and Objectives
Following are the goals and objectives for the Floodplain Risk Management functional
area.
C.2.1 Goal
The goal of the Floodplain Risk Management functional area is to develop a statewide
integrated approach for flood risk reduction and long term floodplain sustainability that
reduces loss of life and property damage, and minimizes the economic impacts associated
with flooding. More specifically, the key program goals include:
Communicate flood risk to the public, and local, State and federal agencies to
increase flood hazard awareness
Incorporate flood risk management into statewide and local land use decision
making to identify potential flood hazards and mitigation strategies to reduce
flood risks
C.2.2 Objectives
Floodplain Management Technical Support
Provide technical support to all levels of government and the public on the NFIP’s
Community Assistance Program, CRS, and FEMA’s Map Modernization and
Risk MAP programs
Collect and compile best available floodplain maps throughout the State and make
these maps digitally available to the public
Control that support FloodSAFE activities and future planning studies by DWR,
USACE, FEMA and others to provide the common building blocks in terms of
standards, methodologies, and tools needed for floodplain assessments.
For areas without any floodplain maps and expecting development within the next
25 years, develop advisory 100-year floodplain maps for use by government
agencies and the public
Delineate 100-year advisory floodplains for active and inactive alluvial fans for
areas subject to development in Southern California over the next 10 to 20 years
Utilize a third party parcel database to support annual risk notification to property
owners within the State Plan of Flood Control LFPZs and make it available for
other uses such as the Central Valley Flood Protection Plan outreach and
economic analyses
At all levels of government, incorporate flood risk into land use and hazard
mitigation planning on a local, regional, and statewide basis
Provide technical support and expertise as needed for development of State and
federal legislation and floodplain management policy
Support adoption of DWR proposed building code updates that address flood
threats to improve public safety and reduce damage to buildings
The Floodplain Risk Management functional area is organized around the four program
elements as shown graphically on Figure C-1.
through collaboration between DWR and FEMA, and has been expanded
continually since its creation.
Best Available Maps. Pursuant to Water Code § 9610, and as part of the overall
Central Valley Flood Management Planning process, DWR completed
preliminary Best Available Maps in July 2008 for the 100- and 200-year
floodplains located within the Sacramento-San Joaquin Valley watershed for
areas protected by the State-federal project levees and areas outside the protection
of project levees. The maps have been prepared for 32 counties and 91 cities.
While the maps do not replace existing FEMA regulatory floodplain maps, they
are intended for informational purposes to assist local communities in better
identifying flood hazard risks, improve land use planning, and update city and
county general plans as required by various Government and Water Codes. The
maps will also be used as a reference for the Annual Flood Risk Notification
component. In addition, DWR has initiated developing a similar set of
preliminary Best Available Maps for the 100- and 200-year floodplains located
outside the Sacramento-San Joaquin Valley watershed. There are a total of 40
counties and 381 cities either completely or partially outside the Sacramento-San
Joaquin Valley boundary. Currently, DWR is in the process of collecting
floodplain maps developed by USACE Los Angeles, Sacramento, and San
Francisco District Offices to incorporate into the data sets for the Best Available
Maps for outside the Sacramento-San Joaquin Valley watershed.
throughout the Sacramento and San Joaquin River Basins in the Central
Valley
o Delineate areas at risk of flooding
o Support analysis of future proposed flood management system
improvements
Information resulting from this program will include new high quality
topographical data; new hydraulic models; and detailed floodplain evaluations
and delineations for multiple flood events in the Sacramento and San Joaquin
River Basins.
Awareness Floodplain Mapping. This program is designed to improve the
identification of flood prone areas that are not mapped by FEMA or others. The
program does not implement a regulatory process such as the NFIP, but rather a
planning process providing advisory floodplain mapping to avoid unintentional
development in flood prone areas. The program provides the planning tools
necessary to help promote sound floodplain development. Other immediate
applications include support for the State’s development of advisory multi-
hazard mapping to be administered by the California Emergency Management
Agency under the authority of the Disaster Mitigation Act of 2000.
Alluvial Fan Floodplain Evaluation and Delineation. The Alluvial Fan
Floodplain Evaluation and Delineation has multiple goals, including improving
the quality and accuracy of alluvial fan flood hazard data and mapping available
to local Southern California communities. The program will provide these local
agencies information in making land use decisions with the necessary tools to
understand the characteristics and potential hazards of alluvial fan floodplains.
The intent is to delineate all alluvial fan flood-prone areas including active
alluvial fans. Initially this effort will not identify regulatory floodplains, only
advisory flood hazard areas. However, it will lead to studies for use by local
regulatory authorities for areas not already mapped by FEMA or others. These
floodplain maps will be developed by the State as recommended by the Alluvial
Fan Task Force in cooperation with FEMA, the California Geological Survey,
and local agencies. The ten southern California counties that participate in the
Alluvial Fan Task Force will be consulted throughout the duration of the
program.
Special Floodplain Mapping Projects. This component includes the following
special floodplain mapping efforts:
o FEMA 500-Year Floodplains. Pursuant to Government Code § 65865.5,
§ 65962, and § 66474.5, and associated with the Central Valley Floodplain
Evaluation and Delineation component, DWR will delineate 500-year
floodplains for the Sacramento-San Joaquin River basins focused on the
State Plan of Flood Control and urban areas outside the State Plan of
Flood Control, which will be incorporated into FEMA FIRM.
o Levee Flood Protection Zone Maps. Water Code § 9130 requires the
development of LFPZ Maps for areas protected by the 1,600 miles of
State-Federal project levees in the Central Valley. In addition to the total
inundation areas, those regions that would have depths greater than three
feet also need to be identified. DWR is in the process of launching an
aggressive multi-year program to evaluate and delineate detailed
floodplains for many of the areas protected by project levees. This
information will be used to update the LFPZ maps prepared during the
initial stage of the project. The LFPZ maps will be used for Annual Risk
Notification to landowners pursuant to Water Code § 9121.
LFPZ Parcel Database. As required by Water Code § 9130 for Annual Risk
Notification, parcel data are needed to develop mailing lists of property owners
who have properties protected by project levees. The parcel database consists of
GIS shape files and the associated attribute data (assessor parcel number,
addresses, owner names, lot size, land use, building square footage, etc.).
Annual Risk Notification. Water Code § 9121 requires DWR to provide written
notices of potential flood risk to property owners in the LFPZs by September 1,
2010, and annually thereafter. These efforts will be coordinated on a local, State,
and federal level to raise flood risk awareness, and to increase education and
outreach regarding potential flood hazard and mitigation strategies.
C.3.4 Flood Risk Planning
The Flood Risk Planning element is focused on planning approaches to help residents and
communities make better, safer decisions using an integrated approach that includes land
use planning, hazard mitigation, task forces, proposed legislation, water plans, and
building codes. These activities are discussed below.
The purpose of the task force is to increase understanding of alluvial fan hazards
and to develop recommendations specific to alluvial fan floodplain management
and land use planning.
Building Standards Code Update Project. Pursuant to the California Health
and Safety Code Section 50465 (HSC §50465), DWR is required to propose
building code improvements that help provide greater public safety and reduce
flood damage for the Central Valley. The DWR proposed updates to the
California Building Standards Code, if/when approved by the California Building
Standards Commission (CBSC), would apply to areas protected by the CVFPP
where flooding levels are anticipated to exceed three feet for the 200-year flood
event. A building code improvement package was submitted to the CBSC in July
2009, which is currently going through California Building Standards
Commission’s code modification process.
BAMs for communities in the Central Valley depicting 100- and 200-year
floodplains using FEMA, USACE, and DWR datasets
BAMs outside the Central Valley depicting 100- and 200-year floodplains using
FEMA, USACE, and DWR datasets
Aerial imagery for 9,000 square miles in the Sacramento and San Joaquin River
Basins
Digital Elevation Model for 6,200 square miles in the Sacramento and San
Joaquin River Basins
Bathymetric survey data for major rivers and tributaries associated with the State
Plan of Flood Control
Channel cross sections and structures to support hydraulic model development for
major rivers and tributaries associated with the State Plan of Flood Control
New hydraulic models for major rivers, tributaries, and overbank areas associated
with the State Plan of Flood Control
Water surface profiles for 10-, 50-, 100-, 200-, and 500-year flood events
associated with the State Plan of Flood Control
New floodplain maps for 100-, 200-, and 500-year flood events associated with
the State Plan of Flood Control
Awareness Floodplain Mapping
500-year floodplains for urban areas within the Central Valley and outside the
area of influence of the State Plan of Flood Control
Web viewer to facilitate use of floodplain maps such as CVFED maps, LFPZs and
BAM maps
Floodplain mapping and other studies described in FEMA/DWR Mapping
Activity Statements (Inter-Agency agreements)
Floodplain mapping studies and hydraulic analyses requested by DWR on a case-
by-case basis that may include support for Delta planning, the State Water Plan
(SWP) and the Central Valley Flood Protection Plan
Update LFPZ maps for areas protected by the State Plan of Flood Control
A parcel database with GIS data for counties within the area of influence of the
State Plan of Flood Control
Annual Risk Notification
User’s Guide document for cities and counties to use in coordinating and
implementing 2007 flood legislation and land use planning
Notify the public of the availability of the User’s Guide, and conduct public
outreach workshops to assist in the implementation of the guidance
Integrated flood management input to the CWP Update 2009 including flood-
related regional report data and flood risk management strategy
Integrated flood management input to the Integrated Water Management plans
based on criteria, consistency, and compliance with program guidelines
Hazard Mitigation
o Grant applications to develop HAZUS models
o HAZUS-MH flood models pending funding
o Update of HAZUS-MH ―default‖ databases such as essential facilities,
utilities, transportation systems and general building stock for use by various
State agencies, local governments and others pending funding
o Response to requests for information regarding regional and statewide flood
risks
Legislation and Policy Support
Flood Protection Projects and Project Grants is one of seven functional areas necessary to
implement the FloodSAFE initiative. Flood Protection Projects and Project Grants refers
to the State’s participation in improvements to the flood management system. This
functional area is responsible for the State’s input to project selection and funding. The
program provides grant money in the Delta and statewide through subvention programs.
This functional area is responsible for the majority of physical improvements to the flood
management system.
Flood Protection Projects and Projects Grants has been a long-standing base program in
DWR’s DFM, but FloodSAFE makes improvements to the program. The Flood
Management Planning and Conservation Strategy functional area is expected to identify
system improvements in which State participation is eventually implemented by Flood
Protection Projects and Project Grants. This functional area will likely continue
indefinitely into the future due to the long-lead time to implement individual projects and
the ongoing need for system improvements. This functional area work is based on the
acknowledgement that the State will continue to be a partner in viable flood management
projects in the Central Valley, in the Delta, and statewide. The work is managed by the
Flood Project Office of DFM, with Delta projects managed by the Delta Suisun Marsh
Office.
D.2.1 Goals
The over-arching goal of the Flood Protection Projects and Project Grants functional area
is to make timely and cost-effective investments of State money in improving flood
management systems throughout California in cooperation with federal and local
partners. The key program goals include:
D.2.2 Objectives
The Flood Protection Projects and Project Grants Program functional area aims to
achieve its stated goals and will support meeting the FloodSAFE foundational objectives
by attaining its own objectives:
Figure D-1 Flood Protection Projects and Project Grants Functional Area
Feasibility Studies. The State participates and provides cost share for feasibility
studies with USACE and local partners. Several studies are underway and new
ones are expected in the future.
Flood System Improvement Projects – EIP. Although much of the bond money
from Propositions 1E and 84 will be expended after completion of the CVFPP in
2012, there is an identified need to proceed with some high priority projects
before then, especially for increased protection of urban areas in deep floodplains.
EIP includes projects that are ready to proceed in advance of the CVFPP. An
element of approval for these projects ensures that they do not eliminate
opportunities or prejudice the flood risk reduction alternatives that would provide
regional or system-wide benefits. EIP projects will only be considered until the
CVFPP is ready for implementation.
especially with the added risks of sea level rise and the potential for larger floods due to
global climate change.
Historically, the Special Flood Control Projects program focused on flood control
projects and related habitat projects for the eight western Delta Islands--Bethel, Bradford,
Holland, Hotchkiss, Jersey, Sherman, Twitchell, and Webb Islands; for the Towns of
Thornton and Walnut Grove; and approximately 12 miles of exterior levees in the Suisun
Marsh. With the passage of Propositions 84 and 1E, the Special Projects has been
expanded and is now available to all Delta local levee maintaining agencies within the
legal boundary of the Delta.
Through cooperative efforts among local, state, and federal interests the program
has assisted local maintaining agencies to raise more than 45 miles of local non-
project levees to the Delta specific PL 84-99 Standard therefore improving the
stability and reducing the risk of levee over topping. Significant projects were
undertaken on New Hope Tract and Bethel, Bradford, Jersey and Twitchell
Islands. Continuing consolidation of the foundation, which is mainly peat soil,
will reduce the crest elevation of these levees over time and additional work will
be required before the levee sections will stabilize at the upgraded standard.
Through the assistance from Special Projects, local agencie has continued
maintaining the 50-acre habitat mitigation site on Bradford Island, which was
planted in 2007 with native species, to offset impacts associated with levee
improvement projects on the island is maintained.
Special improvement projects are projects which will restore levee sections, raise
the levee crest above the current elevation up to a level not exceeding PL 84-99
Delta-specific standard. In 2008 the Special Projects program was extended to all
islands in the Delta and eligible portions of the Suisun Marsh. In addition, the
USACE is actively engaged in projects within the Delta under PL108-361 and the
Water Resources Development Act of 2007 Section 3015, their CALFED levee
Integrity Program.
Habitat enhancement for shaded riverine aquatic and restoration projects have
resulted in the creation of approximately 33 acres of riparian and wetland habitat
along with 16,000 linear feet of Shaded Riverine Aquatic (SRA) habitat in the
Delta. Islands where this habitat enhancement has occurred include Decker,
Twitchell, Webb Tract, and McCormack Williamson Tract. The Program has
other significant habitat enhancement projects under development at Meins
Landing, Dutch Slough, and Sherman Island. Purchase of Meins landing was
finalized in 2005 and will eventually provide tidal estuary habitat in Suisun Marsh
and help to offset impacts of levee projects on Van Sickle Island. The restoration
at Meins landing is being coordinated with the Suisun Marsh Plan. Dutch Slough,
which encompasses 1,166 acres, will restore a large contiguous area of intertidal
habitat. A project to continue to create setback levees on Sherman Island and to
concurrently restore about 2000 linear feet of tidal lands and SRA along this reach
was permitted in 2007 and is under construction
Under the Interim Guidelines, the Delta levees program prepared and distributed a
Project Solicitation Package (PSP) in the beginning of 2009. Local agencies submitted 41
applications for funding, totaling about $55 million, in accordance with the interim
guidelines and the PSP prepared for this solicitation. Delta Flood Protection element
staff reviewed each project according to the guidelines and individually rated each of the
submittals. Each submittal was, then, presented to a selection panel of program staff and
was ranked by the panel according to how the submittals met the criteria and compared
with one another. This ranked list of submittals became the recommended project list for
funding. Through this process16 new projects were recommended for funding totaling
more than $22 million that will be made available to local agencies in the Delta.
Additionally, 60 local maintaining agencies requested funding for preparation of 5-year
plans costing the program nearly $4 million. Funding accounts for an additional $5
million to continue ongoing projects and research in the Delta.
Prepare solicitation packages and provide grant funding for selected projects in
the Flood Protection Corridor Program
Provide State share of funding for flood protection projects outside the Central
Valley through Flood Control Subvention Program
Participate in and provide funding for levee repair project for Local Levee
Assistance
Participate in and provide funding for levee repair projects and local assistance
projects in the Yuba-Feather Basin
Revise current interim guidelines for local assistance under the Special Project
Program and develop final guidelines for distribution for Delta levee
rehabilitation flood projects.
Complete DRMS
Incorporate results of the subsidence research and update when future research
recommends changes in guidance.
Program Support
Table D-1 Implementation of Flood Protection Projects and Project Grants Program Elements
Table D-3 Flood Protection Projects and Project Grants (FA 4) State Investments
Evaluation and Engineering is one of seven functional areas necessary to implement the
FloodSAFE Initiative. Evaluation and Engineering refers to assessments of existing flood
management facilities to identify deficiencies and needed improvements.
Evaluation and Engineering is a new functional area added to DWR’s DFM by the
FloodSAFE Initiative. Prior to FloodSAFE, most evaluations and engineering for existing
facilities were conducted by the USACE. Although this is a new program for DWR, it is
expected to continue after the FloodSAFE foundational objectives are met. This program
will work in coordination and partnership with the USACE. Evaluation and Engineering
is based on the acknowledgement that changing conditions, new knowledge about system
performance, and eventual facility deterioration will demand continued service.
The premise of the Evaluation and Engineering functional area is to learn more about the
condition of these existing levees and the role they can play in upgrades to the flood
management system. This information feeds into planning work being conducted for the
Flood Management Planning and Conservation Strategy functional area and provides
justification for needed flood projects and improvements that are implemented through
the Flood Protection Projects and Project Grants functional area as well as the Operations
& Maintenance and Environmental Stewardship functional area.
E.2.1 Goal
The goal of the Evaluation and Engineering functional area is to efficiently assess the
condition of existing levees and flood control structures, define flood system deficiencies,
formulate remedies, and conduct feasibility studies of the projects to fix flood system
deficiencies with consideration for environmental conservation. More specifically, the
key program goals:
Support flood basin certification efforts and the legislative mandate of urban 200-
year flood protection, and assist federal and local flood management programs by
providing geotechnical data and engineering analyses and remedial improvement
alternatives to local, State, and federal stakeholders, the CVFPP, and Federal
Emergency Management Agency (FEMA).
Improve geotechnical information collection, storage, exchange, and evaluation
methods between State, local, and federal flood management agencies.
Develop statewide policies for urban and non-urban levee performance,
emergency, and long-term levee remediation.
E.2.2 Objectives
The Program aims to achieve the stated goals through attainment of the following
objectives:
Urban Levee Evaluation (ULE). One of the highest priorities is the evaluation
of project levees protecting urban areas with populations greater than 10,000
residents. The ULE component includes a geotechnical evaluation on
approximately 350 miles of the State-Federal levee system (Project Levees) of the
Sacramento and San Joaquin Flood Control system. These efforts focus on levees
protecting urban areas within Sutter Basin; the City of Marysville; urban areas
within RD 784; the City of Woodland; urban areas within the Natomas basin; the
City of West Sacramento; the City of Davis; the metropolitan area of Sacramento,
protected from the American and the Sacramento Rivers; and, urban areas in the
lower San Joaquin Valley protected by levees maintained by the San Joaquin Area
Flood Control Agency, RD 404, and RD 17. This component consists of
geotechnical evaluations of urban levees including geotechnical exploration,
testing, and analysis that are required to evaluate the performance and safety of
existing urban Project Levees. This work will lead to prefeasibility designs and
cost estimates for potential levee repairs where deficiencies are noted.
Non-Urban Levee Evaluation (NULE). While it is clear that urban levees must
be consistently evaluated for their ability to provide at least a 200-year level of
protection, the NULE program is more complex in that some non-urban project
levees provide a relatively low level of protection for agricultural areas while
providing flood control system operational reliability. For example, the non-
urban project levees along much of the Sacramento River, north of Sacramento,
have three purposes:
Thus the NULE program must be done as an iterative process that takes into
account the system-wide evaluations as they are completed that may change one
or more of the project purposes, or vary the levee evaluation criteria to meet
varying design flood requirements.
This element includes the responsibilities for the engineering analyses needed to identify
flood system deficiencies and to develop remedial measures, called management actions,
to address the deficiencies. Information gathered under the Levee Evaluation element is
critical in conducting the engineering analyses as part of this element as identified below.
System Water Surface Impact Analysis. Flood system water surface impact
analysis (i.e. impact of water level for various levels of flood protections on the
levees) will be conducted as part of this component to determine the impact of
water surface profile for various levels of protection on levee free board and
seepage through the levees.
- Erosion: Normal and flood flows can erode levee foundations and
embankments.
- Through-seepage: Seepage through the levee embankment can result in
internal erosion and instability.
- Under-seepage: Seepage through the levee foundation can result in internal
erosion and instability.
- Stability: The levee embankment is subject to static forces which can result in
excessive movement.
- Settlement and subsidence: Consolidation and groundwater overdraft can
reduce effective levee height and associated hydraulic capacity of the channel.
Delta levee islands are subject to subsidence, which increases the effective
height of levees.
- Penetrations: Undetected animal or man-made defects (i.e., pipes, animal
burrows, construction problems) may generate uncontrolled, concentrated
seepage, and internal erosion.
This functional area will also prepare remedial alternatives and cost estimates to repair
levees in-place. The results of the above engineering evaluations will be the identification
of the Flood System deficiencies.
The information developed above will be used by the feasibility study team for preparing
technical feasibility and identification of system-wide benefits to cost ratios.
Levee Evaluations
San Joaquin River Flood Control System Geotechnical Assessment Report – GAR
San Joaquin River Flood Control System Geotechnical Evaluation Report – GER
System Evaluation and Engineering
Vegetation research paper describing the effects that woody vegetation growing
on or near levees has on levee integrity
Flood Management Planning and Conservation Strategy is one of seven functional areas
necessary to implement the FloodSAFE initiative. Flood Management Planning and
Conservation Strategy refers to planning and analyses necessary to evaluate the flood
systems as complete systems rather than a set of individual projects. This planning is
based on achieving the FloodSAFE foundational objectives and considering the
FloodSAFE guiding principles. Prior to FloodSAFE, most planning for the flood system
was conducted by USACE. The Flood Management Planning and Conservation Strategy
functional area is based on the acknowledgement that integrated flood management is the
model for improvements. Even though this is a new program for DWR, it is expected to
continue after the FloodSAFE foundational objectives are met, but will likely continue at
a reduced level of effort.
Most of the other functional areas require planning to fulfill their objectives and while all
functional areas require a degree of interaction, Flood Management Planning and
Conservation Strategy is heavily dependent on input from all the other functional areas.
The Central Valley work is managed by the Central Valley Flood Planning Office of
DFM. The Statewide Flood Management Planning work is managed by DSIWM. The
conservation strategies work is managed by the FloodSAFE Environmental Stewardship
and Statewide Resources Office.
F.1.1 Goals
The primary goal of the Flood Management Planning and Conservation Strategy
functional area is to conduct, support, and improve integrated flood management
planning to address flood risk and improve flood system performance.
F.1.2 Objectives
Identify significant flood risks throughout California, document needs and
opportunities to improve integrated flood management, and develop a strategy to
pay for system improvements and continuing maintenance
Prepare and implement conservation strategies that enhance the ecosystem while
improving flood management
Perform evaluations of system-wide performance for use in planning system
improvements
While planning for the Central Valley will be a system-wide analysis, the planning
approach will initially consider smaller portions of the system separately before they are
combined into one system. The technical work will be divided into five distinct focus
areas:
Area 3 - Lower San Joaquin River, with the major urban area of Stockton
The scope of work in each area will differ, reflecting variations in flood risks,
opportunities for flood system improvements, and the nature of potential improvements.
Figure F-1 Flood Management Planning and Conservation Strategy Functional Area
The planning team will use information gathered by all functional areas to formulate
potential projects, costs, and trade-offs for each focus area and will then consider
combinations or modifications of projects for the system-wide analyses.
Central Valley Flood Management Planning consists of two primary projects – the
Central Valley Flood Protection Plan (CVFPP) and the description of the State Plan of
Flood Control (SPFC).
There are several threats to California’s flood systems that must be considered
together when looking for ways to improve flood management and reduce the risk
of flooding. The extent to which these threats are present would define the flood
system deficiencies that must be addressed.
DWR anticipates that the CVFPP planning process will evaluate system
deficiencies and formulate potential management actions and solutions for the
first CVFPP (due in 2012) using existing information, expert judgment, and new
information as available from other ongoing FloodSAFE efforts. The system
deficiencies will be evaluated and defined by analyses of the following threats to
the flood system integrity.
Erosion. High velocity flows can erode river banks and levee material, making a
levee unstable and subject to failure. Critical erosion sites should be identified
and evaluated, and projects should be formulated to fix the sites. This includes a
system-wide evaluation of channel flow velocities and design of appropriate
measures to reduce/manage the flows and corresponding potential for continued
erosion.
Seepage. Water seepage through or under a levee embankment can reduce the
integrity of a levee. To study the threat of seepage to levee integrity and to design
measures to reduce the seepage threats, an extensive levee exploration and
geotechnical investigation is required for critical levees.
Many levees that were constructed without the benefit of modern engineering
may perform poorly during earthquakes. The Delta levees are especially
vulnerable as they are subject to future major earthquake threats and the risk of
multiple island flooding in the Delta.
Define the hydrology and hydraulics of the system by using information from the
―Comprehensive Study‖ or any other sources as available, modify as appropriate,
get input from stakeholders, and use the information as interim input data
Compile up-to-date levee evaluation data gathered by DWR, combine them with
other existing data, process the information, and conduct an assessment of the
existing system integrity for urban areas
Using the above information, define system deficiencies; deficiencies may be the
result of one or more of the flood threats described earlier
Using the above information, develop priorities (Project priority) for flood system
improvement management actions
Document the process and prepare recommendations for inclusion into the
CVFPP
Non-Urban Areas (Areas 1 and 3): Work to be completed for CVFPP: For non-urban
areas a different approach may be needed. The goal could be to reduce flood risks in
currently non-urbanized areas.
Define system deficiencies for rural areas and the existing small communities
within the rural area.
The actions identified above are designed to evaluate the ability of the proposed
system improvements to provide the desired level of flood protection, and the
system wide impact and benefits of the management actions. Specific outcomes
of this process include preparing feasibility studies of the proposed
improvements, and evaluating projects’ local, regional, and system-wide benefits.
Reservoir Operations:
The CVFPP should also address potential flood management benefits from re-
operation of reservoirs with flood control reservations. For the 2012 CVFPP, at a
minimum, some pilot re-operation studies should be conducted. The pilot re-
operation studies can provide opportunities to bracket the benefits of re-
operations. Implementation of most re-operation projects would require structural
changes as well as changes in the reservoir flood control diagram. To fully
address re-operation benefits and cost, the following steps should be taken:
Identify all reservoirs with flood reservation that could potentially provide flood
benefits from re-operations
Conduct two re-operation pilot studies—one in the Sacramento River system for
rain flood (i.e., Oroville) and one in the San Joaquin River system for snow melt
flooding (i.e., Merced River)
Document the costs of the study, potential structural modifications, and changing
the FCD
Upon completion of the above activities, the results of the engineering analyses,
environmental conservation strategies, and institutional guidance, together with
economic analyses and cost estimates, would provide feasibility-level information
Information for each area will be compiled into its own portfolio, or atlas, for easy
reference. This will include floodplain delineation, land use, population and
property at risk, existing flood facilities, identified deficiencies, and other
pertinent information.
improving integrated flood management, and develop a finance strategy for addressing
flood management needs and improvements statewide.
aquatic, and terrestrial ecosystems within the planning area of the flood control
project. DWR will be the lead agency in preparing and implementing the strategy.
The purpose of the strategy is to reconcile the management of flood risk with the
conservation of natural resources and establishment of natural processes. The
objective is to move beyond reacting to individual or incremental actions on a
case-by-case basis and develop advanced conservation strategies and actions that
meet or exceed baseline conditions; provide stability or enhancement to
associated fish, wildlife, and habitat; and contribute to recovery of target species.
The conservation strategy will function as a management plan for focus species
and ecosystems and will prescribe standards and guidelines that, when
implemented, will provide a high likelihood that viable habitats and populations
will continue to exist throughout the planning area.
Consistent with the broader plan for flood control maintenance, a short-term
(interim) and long-term conservation strategy will be developed. The purpose of
the short-term strategy is to avoid, minimize, and compensate for the effects of
immediate and ongoing corrective actions on focus species and ecosystems. The
long-term strategy will be more comprehensive and will interface with new
operations and maintenance standards established through development and
implementation of the FloodSAFE initiative.
Flood Control System Status Report (FCSSR) for the SPFC (December 31, 2010)
Status Report on the Progress and Development of the CVFPP (December 31,
2010)
Conservation Strategies
Table F-1 Implementation of Flood Management Planning and Conservation Strategy Program Elements
G.2.1 Goal
The primary goal of the Legislation, Budget, and Communication functional area is to
facilitate legislation, budget, and communication matters to aid the efficient work of all
functional areas in improving flood safety.
G.2.2 Objectives
Meet the Legislature-mandated quarterly, semi-annual, and annual reporting on
how bond funds are being used
Develop public outreach strategy for use as guidance for other functional areas
preparing their own outreach plans
Ensure BAM requirements are met and Prepare periodic status reports and bond
reporting to the Legislature
Serve as primary contact for coordination with USACE and in securing federal
funding
Serve as the primary manager or the FloodSAFE budget and as advocate for
sustainable FloodSAFE funding
the other functional areas in developing their own outreach plans. This component will
serve the other functional areas to provide consistency in preparing public meetings and
other communications with the public. This will provide guidance on meeting geographic
coverage and frequency depending on the type and stage of development for each
program. In addition, standards for reports, web sites, and other communications will be
developed in this component. Some publications, such as fact sheets and brochures, for
all functional areas will be prepared under this component. Periodic reporting that will be
prepared include:
c) Executive briefings
b) Budget/Fiscal Report
d) FloodSAFE Newsletter
a) Expenditures Report
As Needed Materials
USACE technical personnel will be involved in performing work for several of the
functional areas and will coordinate directly with each of those areas as needed. In
addition, this component will provide consistent communication and alignment with the
USACE at the management level. FEMA is ultimately responsible for levee
accreditation. Alignment with FEMA throughout FloodSAFE implementation will keep
FEMA involved and up-to-speed on developments affecting the flood protection system
and the floodplains.
Legislative Briefings
o State Legislature
o Federal Congress
Executive Briefings
o State executives
o County Supervisors
Guidelines development
o Fund commitment
o Invoice payment
o Fiscal reporting
o Expenditure projections
o Staff training
As needed materials for public meetings, workshops and forums, and requests for
information
Field requests for information from Legislature and provide timely responses
Annual budgets
Funding allocations
Policy documents
Legislation Liaison
Liaison and 1. Legislation tracking summaries up-to-date (State and federal)
Legal Issues
2. Regulation changes summaries up-to-date (State and federal)
Program Management
1. Number of coordination meetings
Management, 2. Strategic Plan up-to-date
Budget and
Fiscal Services 3. Bond Expenditures Plan updates prepared on time
4. PMI process, tools and training are active
5. Tracking system operable
Legislative Liaison $ -
Legislative Communication $ - $ - $ - $ 1,630 $ 9,780 $ 11,410
Bond Projects Progress Reporting $ -
Federal Engagement $ -
USACE Coordination $ -
Federal Funding $ -
FEMA Coordination $ -
Bond Budgeting $ -
General Fund $ - $ -
Prop 1E $ - $ 800 $ 800 $ 2,430 $ 14,580 $ 18,610
Prop 84 $ - $ - $ - $ - $ - $ -
Others (Fed) $ - $ - $ - $ - $ - $ -
Prop 1E & Prop 84 $ - $ - $ - $ - $ - $ -
Total $ - $ - $ 800 $ 800 $ 2,430 $ 14,580 $ 18,610
Arnold Schwarzenegger
Governor
Mike Chrisman
Secretary of Resources
Lester A. Snow
Director
Department of Water Resources