Design Report NCCC 2019 NAU
Design Report NCCC 2019 NAU
Table of Contents
List of Contents
Executive Summary ................................................................................................................................................ ii
Hull Design and Structural Analysis........................................................................................................................1
Development and Testing ........................................................................................................................................3
Construction .............................................................................................................................................................6
Project and Quality Management .............................................................................................................................8
Organizational Chart ..............................................................................................................................................10
Project Schedule.....................................................................................................................................................11
Construction Drawing ............................................................................................................................................12
List of Figures
Figure 1: VolCanoe 3D Hull Model.........................................................................................................................1
Figure 2: Simplified Beam Analysis of 4-Person Racing Scenario .........................................................................2
Figure 3: Comparison of Loading Scenarios ...........................................................................................................2
Figure 4: Sieving Crushed Pumice Aggregate .........................................................................................................3
Figure 5: VolCanoe Cross-Section...........................................................................................................................5
Figure 6: Mold Construction in Progress .................................................................................................................6
Figure 7: Shadow Sanding of Mold .........................................................................................................................6
Figure 8: Flex Seal Applied on Mold ......................................................................................................................6
Figure 9: Exterior Finishing .....................................................................................................................................7
Figure 10: Placement of Spine and Structural Layer ...............................................................................................7
Figure 11: Body Reinforcement and Interior Finishing Layer ................................................................................7
Figure 12: Construction of Curing Chamber ...........................................................................................................7
Figure 13: Kindergarteners’ Fieldtrip to NAU ........................................................................................................8
Figure 14: Summary of Project Cost........................................................................................................................8
Figure 15: Total Hours Allocated ............................................................................................................................9
List of Tables
Table 1: Innovative Features ................................................................................................................................... ii
Table 2: VolCanoe General Properties ................................................................................................................... ii
Table 3: VolCanoe Concrete Properties .................................................................................................................. ii
Table 4: Structural Analysis Results ........................................................................................................................2
Table 5: Finishing Mix Aggregate Proportions .......................................................................................................5
Table 6: Monetary Value of Donated Material ........................................................................................................8
Table 7: Monetary Value of Purchased Materials ...................................................................................................9
Table 8: Project Milestones .....................................................................................................................................9
List of Appendices
Appendix A - References.................................................................................................................................... A-1
Appendix B - Mixture Proportions and Primary Mixture Calculation ................................................................B-1
Appendix C - Example Structural Calculations...................................................................................................C-1
Appendix D - Hull Thickness/Reinforcement and POA Calculations................................................................ D-1
ii
Northern Arizona University
VolCanoe
Executive Summary
Desert, cacti, and 100-degree weather are the mentee involvement. Notably, a female mold was
general public’s idea of life in Arizona. Yet, Flagstaff, constructed for the first time in five years, natural
in the heart of Northern Arizona, is the home to the occurring aggregates including recycled glass and
largest contiguous Ponderosa Pine forest, capable of expanded polystyrene (EPS) foam were introduced to
producing approximately 36 inches of snow in one the mix design, and a practice canoe was constructed
day. The drastic change in scenery surrounding for the first time in history at NAU. Table 1 summarizes
the innovative features VolCanoe implemented.
Flagstaff can largely be attributed to the historic
VolCanoe’s general properties and concrete mix
volcanic activity in Northern Arizona. The San
properties are found in Table 2 and 3 respectively.
Francisco Peaks, Mount Elden, and Sunset Crater are Table 1: Innovative Features
a few of the 600 volcanos which make activities such Task Notable Feature
as hiking, snowboarding, high elevation star gazing, Decreased length by 15% and thickness by 40%;
Hull Design implemented first female mold at NAU since
and sight-seeing possible in Flagstaff (USGS 2001). 2014
Northern Arizona University (NAU) selected a Structural
Eliminated need for post tensioning
volcano theme for the National Concrete Canoe Analysis
Competition (NCCC), branding it as VolCanoe. The Mixture Doubled structural mix compressive strength;
Design tripled structural mix flexural strength
team felt a volcano theme would fully encompass and Practice canoe implemented; new and improved
highlight the reasons Flagstaff and NAU are unique. Construction
curing chamber constructed
For many, volcanos symbolize upward Project Increased amount of donated materials by
challenges and the value beyond merely a destination, Management $1,221; increased mentee involvement by 60%
but also within the journey. VolCanoe aims to adopt the Recycled foam glass aggregate, basalt
same methodology when competing at the 2019 Pacific Sustainability reinforcement mesh, recycled EPS foam, natural
pumice, and shale incorporated into mix design
South West Conference (PSWC). The team aims to
gain valuable experience and learning opportunities at Table 2: VolCanoe General Properties
every step within the project. Hull Dimensions
In recent history, NAU’s Canoopa (2018), Maximum Length 219 in
Paddlegonia (2017), and Polaris (2016) regionally Maximum Width 33 in
placed 11th, 8th, and 6th, respectfully. Understanding Maximum Depth 16 in
the journey to the top will be difficult, VolCanoe seeks Average Thickness 0.75 in
to be encouraged by the long trail ahead, identifying Estimated Weight 300 lbs
Reinforcement
and celebrating the milestones achieved and lessons
Primary Basalt Mesh
learned along the way. Unsatisfied with conference 8mm PVA Fibers and MasterFiber
outcomes in previous years, VolCanoe identified areas Secondary
MAC Matrix Fibers
of improvement and executed innovative solutions Color
within each major category for the NCCC. Interior Finishing Mix Red
Compared to Canoopa, VolCanoe increased Structural Mix N/A
maneuverability by decreasing the length by 15 percent Exterior Finishing Mix Black
and thickness of the canoe by 40 percent, eased
constructability by eliminating the need for post Table 3: VolCanoe Concrete Properties
tensioning reinforcement, increased compressive Mixes Finishing Structural
strength by a factor of two, increased flexural strength Wet Unit Weight 59.4 pcf 63.7 pcf
by a factor of three, and redesigned the curing chamber Oven-Dry Unit Weight 47 pcf 53 pcf
to increase efficiency. Support for NAU’s canoe team 28-Day Compressive Strength 1,950 psi 2,080 psi
and general awareness for the American Society of 28-Day Tensile Strength 270 psi 300 psi
Civil Engineers (ASCE) was gained and shown 28-Day Flexural Strength 1,330 psi 1,500 psi
through a substantial increase in donated materials and Concrete Air Content 10.0% 9.1%
ii
ii
Northern Arizona University
VolCanoe
1
Northern Arizona University
VolCanoe
Figure 2: Simplified Beam Analysis of 4-Person Racing Scenario The nominal shear was analyzed as a 4 inch by
4 inch area with a thickness of ⅝ inch for a two-way
Various placement scenarios of the paddlers slab to mimic a 200 pound male paddler’s knee during
were considered before finalizing each paddler’s racing. The equation for nominal shear is governed by
location during racing. The team determined the most the American Concrete Institute (ACI 318-14) Building
conservative analysis occurs when the paddlers are Code. The compressive strength of our concrete
positioned 6 feet from the bow and stern of the canoe cylinders is used in this calculation as well as a
for the 2-person race. Paddlers will be placed at 3 feet lightweight concrete factor. This value was calculated
intervals from the center of the canoe to the bow or to be 1,095.5 pounds without regards to the layers of
stern for the 4-person races. The moment diagram for mesh reinforcement.
each scenario can be seen in Figure 3 below. The values obtained from the compressive
stress, tensile stress, and nominal shear justifies the
exclusion of post tensioning reinforcement from
VolCanoe’s design. To air on the side of precaution, the
team decided to design concrete mixes that would
account for the absence of post tensioning. To achieve
this goal, the team introduced innovative and stronger
volcanic aggregates that have not been used before in
previous NAU concrete canoe teams.
2
Northern Arizona University
VolCanoe
3
Northern Arizona University
VolCanoe
4
Northern Arizona University
VolCanoe
5
Northern Arizona University
VolCanoe
Construction
The primary goal for the construction process glue. Once all the
was to successfully implement quality control cross sections were
measures to ensure the intended design was carried out glued and run through
as closely as possible throughout fabrication. Previous the steel rods, the rods
concrete canoe teams have suggested concrete were tightened to
placement was problematic and thickness was difficult compress the cross
to gage when using a male mold. Additionally, sanding sections together and
the exterior of the canoe was extremely time keep them as flush as
consuming and not ideal for the overall aesthetics of the possible (Figure 6).
canoe. As such, VolCanoe implemented a female mold Once the glue was left Figure 7: Shadow Sanding of Mold
for the first time since 2014’s Spirit. The mold was to dry for 24 hours, the
designed in SolidWorksⓇ (2018) to be 18 feet in length, mold was shadow
33 inches at the maximum width, and 16 inches at the sanded (Figure 7) and
maximum height. sealed after the cross
To construct the mold, 92 cross sections of the sections were
SolidWorksⓇ (2018) model were sent to XY Corp for assembled to provide
fabrication into Styrofoam cross sections. The material the smoothest surface
of the mold was chosen to be Styrofoam because it was for concrete
the most economical material which could be placement. This also
fabricated via a Computer Numeric Control (CNC) prevented any seepage
Figure 8: Flex Seal Applied on
machine. The mold’s cross sections were fabricated of material into the
Mold
utilizing a CNC machine because it was the most mold (Figure 8).
accessible fabrication option which provided the Additional quality control measures were taken
greatest accuracy. The thickness of the cross sections to improve the concrete mixing process and ultimately
increase consistency in results. All mixing was
varied depending on how drastically the canoe’s slope
conducted by weighing materials on a scale and then
changed throughout the body of the canoe. The ends of
mixing batches in 5-gallon buckets with a power drill
the canoe were printed into one-inch cross sections, and a mixing attachment. Batches were mixed in 5-
while the body of the canoe printed into four-inch cross gallon buckets with power tools instead of hand mixing
sections. For Canoopa, the cross sections of the male in tubs because losses were comparable, while the
mold were held together by a single steel rod running amount of time it took to mix was reduced drastically.
through the middle As well, a power drill was used to mix batches because
of the mold. This it allowed for uniform mixing of aggregates, fibers,
method was admixtures, water, and cementitious materials. The
unfeasible for a mixing procedure included separating the aggregate
female mold. and MasterFiber® MAC Matrix fibers from the
Instead, the cross cementitious material at the beginning of the mix
sections’ corners process to allow for the proper aggregate water to be
added. Water was added to the aggregate first to allow
were drilled into and
the aggregate to absorb the necessary water and allow
four steel rods were
for more free water to be added to the cementitious
run through the materials. Free water is the water that is added to allow
mold. In addition, the for the hydration process to commence. The
cross sections were Figure 6: Mold Construction in
coated in heavy duty Progress
6
Northern Arizona University
VolCanoe
Construction
cementitious materials were then mixed together and 10). Lastly, the final
added into the mix with water added shortly after. basalt mesh
Admixtures such as set retarder, shrinkage reducer, reinforcement was
water reducer, polymers, and latex were then added to placed throughout the
the mix at the same time as the free water was body of the canoe and
introduced. For the colored mixes, a pigmented covered by two, 1/8th
admixture was added at this point along with the rest of
inch interior red,
the additional water. Finally, the 8 millimeter PVA
finishing layers (Figure
fibers were added to reduce the cracking and add
durability to the concrete. The 8 mm PVA fibers were 11). The 1/8th inch
added last to the mix in order to reduce clumping of the rubber thickness
fibers and ensuring their distribution throughout the gauges and painted
mixture. Lastly, to achieve the desired consistency of nails were utilized for
the concrete, the concrete was mixed via drum mixers. each layer mentioned. Figure 10: Placement of Spine and
Structural Layer
The mixing procedure was found to be effective and
produce concrete that was homogeneous with minimal
clumps of fiber or cement.
Once the concrete was properly mixed, the
concrete was hand placed onto the female mold. The
mold had 1/8th inch rubber thickness gauges nailed
every 6 inches. The exterior black, finishing layer of
concrete was placed to be flush with the thickness
gauges. Once the thickness gauges were removed and
replaced with concrete
(Figure 9), the first layer
was checked by our Figure 11: Body Reinforcement and Interior Finishing Layer
quality control team. The Once the final finishing layer of concrete was
quality control team placed, the curing chamber was assembled through one
would check the inch polyvinyl chloride (PVC) pipes, elbow and tee
thickness of the canoe connections, plastic, duct tape, Velcro, and
using nails which were humidifiers, shown in Figure 12 below. Four
painted different colors humidifiers were
at each 1/8th of an inch placed on each
interval. The nails were Figure 9: Exterior Finishing corner of the
an additional quality control measure implemented to mold. The
ensure the areas in between the rubber gauges were a plastic covered
uniform thickness. While the rubber thickness gauges the PVC pipe
allowed the team to check each layer’s thickness was and was taped
an eighth of an inch, the painted nails also provided a onto the concrete
means to check the overall thickness of the canoe after floor, and Velcro
each layer was placed. Following, an additional 1/8th was used to
layer of exterior black, finishing layer was placed create a door to Figure 12: Construction of Curing
before placing the basalt mesh reinforcement spine in enter the curing Chamber
the canoe and 1/4th inch of structural concrete (Figure chamber.
7
Northern Arizona University
VolCanoe
monitoring funds closely via a MicrosoftⓇ Excel Modified A/NA Latex 1.00 gal $15.00/gal $15.00
spreadsheet which clearly identified the budget’s Tylac 4193 1.00 gal $15.00/gal $15.00
progress throughout the project, marking all donations Rovene 4040 1.00 gal $15.00/gal $15.00
and expenditures. The budget was addressed at each Ultra-Lightweight Foamed
21.00 ft3 $15.00/ft3 $315.00
Recycled Glass Aggregate
team meeting, and receipts were updated onto the
Material Crushing 42.00 ft3 $5.00/ft3 $210.00
MicrosoftⓇ Excel spreadsheet weekly, ensuring the
Total Value for Materials $1,230
8
Northern Arizona University
VolCanoe
9
Northern Arizona University
VolCanoe
Organization Chart
Virgilio Bareng Ernesto Mauricio
(Sr) (Sr)
Captain Captain
Structural Lead Mix Design Lead
Lead for the structural analysis, assisted Lead the design and draft of canoe mold,
with reinforcement and hull design plan, designed and tested reinforcement plan,
construction plan, paddling captain, and drafted final construction drawing, mold
assisted with other tasks as needed. construction, and assisted with other
tasks as needed.
ASCE registered participant Current Paddler # of years on previous NAU Canoe teams
10
Northern Arizona University
ID Task Name Duration Start Finish Predecessors Total Slack Aug '18 Sep '18 Oct '18 Nov '18 Dec '18 Jan '19 Feb '19 Mar '19 Apr '19
15 22 29 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14
1 Task 1.0: Mix Design 108 days Sat 9/1/18 Thu 1/24/19 0 days
2 1.1 Material Research 74 days Sat 9/1/18 Mon 12/10/18 0 days
3 1.1.1 Aggregates 14 days Sat 9/1/18 Wed 9/19/18 0 days
4 1.1.2 Material Procurement 60 days Thu 9/20/18 Mon 12/10/18 3 0 days
5 1.1.3 Develop Initial Mix Design 50 days Mon 10/1/18 Wed 12/5/18 4SS+7 days 0 days
6 1.2 Concrete Testing 37 days Thu 12/6/18 Thu 1/24/19 0 days
7 1.2.1 Slump Test 2 days Thu 12/6/18 Fri 12/7/18 5 0 days
8 1.2.2 Cylinder Sample Collection 2 days Thu 12/6/18 Fri 12/7/18 7SS 0 days
9 1.2.3 Compressive Strength Test 28 days Wed 12/19/18 Thu 1/24/19 8FS+7 days 0 days
10 1.2.4 Split Tensile Strength Test 2 days Wed 12/19/18 Thu 12/20/18 8FS+7 days 0 days
11 1.2.5 Dry Unit Weight 2 days Wed 12/19/18 Thu 12/20/18 8FS+7 days 0 days
12 1.3 Refining Initial Mix Design 14 days Fri 12/21/18 Wed 1/9/19 0 days
13 1.3.1 Creating Decision Matrix for Mix Design 7 days Fri 12/21/18 Mon 12/31/18 11 0 days
14 1.3.2 Finalizing Competition Mix Deliverables 14 days Fri 12/21/18 Wed 1/9/19 11 0 days
15 Task 2.0: Reinforcement Design 46 days Mon 10/1/18 Fri 11/30/18 0 days
16 2.1 Testing of Reinforcement Materials 28 days Mon 10/1/18 Wed 11/7/18 0 days
17 2.1.1 Thickness 3 days Mon 10/1/18 Wed 10/3/18 5SS 0 days
18 2.1.2 Mechanical Bonding Test 21 days Wed 10/10/18 Wed 11/7/18 17FS+3 days 0 days
19 2.1.3 Determine Percent Open Area 12 days Thu 10/4/18 Fri 10/19/18 17 0 days
20 2.2 Reinforcement Selection 2 days Mon 10/22/18 Tue 10/23/18 19 0 days
21 2.3 Concrete Pre-Stressing Assessment 18 days Thu 11/8/18 Fri 11/30/18 0 days
22 2.3.1 Reinforcement Strength 14 days Thu 11/8/18 Mon 11/26/18 18 0 days
23 2.3.2 Risk/Benefit Analysis 2 days Tue 11/27/18 Wed 11/28/18 22 0 days
24 2.3.3 Determining Pre-Stressing Arrangement and Forces 2 days Thu 11/29/18 Fri 11/30/18 23 0 days
25 2.4 Reinforcing Mix Materials 2 days Thu 11/29/18 Fri 11/30/18 23 0 days
26 Task 3.0: Hull Design 92 days Thu 10/4/18 Sat 2/2/19 0 days
27 3.1 Draft Hull in SolidWorks 14 days Thu 10/4/18 Tue 10/23/18 17 0 days
28 3.2 Structural Analysis 7 days Wed 10/24/18 Thu 11/1/18 27 0 days
29 3.3 Mold Design 7 days Fri 11/2/18 Mon 11/12/18 28 0 days
30 3.4 Mold Procurement 64 days Tue 11/13/18 Sat 2/2/19 29 0 days
31 Task 4.0: Construction 98 days Sat 11/24/18 Tue 4/2/19 5 days
32 4.1 Construction Table 28 days Sat 11/24/18 Mon 12/31/18 28SS 0 days
33 4.2 Practice Canoe 20 days Tue 1/8/19 Thu 4/11/19 32 0 days
34 4.3 Final Canoe 41 days Wed 2/6/19 Tue 4/2/19 5 days
35 4.3.1 Material Set Up 3 days Wed 2/6/19 Fri 2/8/19 33FS+19 days 0 days
36 4.3.2 Placement 1 day Sat 2/9/19 Sat 2/9/19 35 0 days
37 4.3.3 Curing 28 days Sat 2/9/19 Tue 3/19/19 36SS 0 days
38 4.3.4 Finishing 8 days Wed 3/20/19 Fri 3/29/19 37 5 days
39 4.3.5 Lettering 2 days Mon 4/1/19 Tue 4/2/19 38 5 days
40 Task 5.0: Competition Deliverables 132 days Mon 10/15/18 Sat 4/6/19 2 days
41 5.1 Acknowledgment Form and Preliminary Schedule 14 days Mon 10/15/18 Thu 11/1/18 0 days
42 5.2 Project Overview and Technical Addendum 30 days Wed 1/23/19 Thu 2/28/19 41,14 0 days
43 5.3 Transportation 1 day Wed 4/3/19 Wed 4/3/19 42FS+20 days,39 5 days
44 5.4 Aesthetics 33 days Tue 2/19/19 Thu 4/4/19 4 days
45 5.4.1 Canoe Stand 12 days Wed 3/20/19 Thu 4/4/19 37 4 days
46 5.4.2 Cutaway Section 28 days Tue 2/19/19 Thu 3/28/19 37SS+7 days 9 days
47 5.4.3 Tabletop Display 9 days Mon 3/25/19 Thu 4/4/19 45SS+3 days 4 days
48 5.5 Design Paper 25 days Mon 2/4/19 Thu 3/7/19 14 3 days
49 5.6 Oral Presentation 21 days Mon 3/11/19 Sat 4/6/19 48 2 days
50 Task 6.0: Project Management 191 days Wed 7/25/18 Sat 4/6/19 2 days
51 6.1 Fundraising 158 days Sat 9/1/18 Mon 4/1/19 7 days
52 6.2 Meetings 187 days? Wed 7/25/18 Tue 4/2/19 6 days?
53 6.3 Schedule Management 187 days Mon 7/30/18 Fri 4/5/19 3 days
54 6.4 Safety Training 28 days Thu 10/4/18 Mon 11/12/18 0 days
55 Task 7.0: Attend PSWC at Cal Poly SLO 6 days Wed 4/3/19 Tue 4/9/19 48,49FF 0 days
Project: Critical Path Schedule Task Summary Project Summary Critical Critical Split Progress
Date: Wed 3/6/19
Page 1
11
12
VolCanoe
Appendix A - References
ACI (American Concrete Institute) Committee. (2014). “Building Code Requirements for Structural Concrete.”
ACI 318-14. Farmington Hills, MI.
ASCE (American Society of Civil Engineers). (2019). “2019 ASCE National Concrete Canoe Competition
Rules and Regulations.” ASCE National Concrete Canoe Competition. <https://www.asce.org/concrete-canoe-
rules-regulations/> (Sept. 5, 2018).
ASTM International. (2015). “Standard Test Method for Slump of Hydraulic-Cement Concrete.” ASTM
C143/C143M. West Conshohocken, PA.
ASTM International. (2017). “Standard Test Method for Splitting Tensile Strength of Cylindrical Concrete
Specimens.” ASTM C496/C496M. West Conshohocken, PA.
ASTM International. (2018a). “Standard for Making and Curing Concrete Test Specimens in the Field.” ASTM
C31/C31M. West Conshohocken, PA.
ASTM International. (2018). “Standard Test Method for Compressive Strength of Cylindrical Concrete
Specimens.” ASTM C39/C39M. West Conshohocken, PA.
Autodesk® AutoCAD® (2019). Computer Software. Autodesk, Inc., San Rafael, CA.
Jolin, M., and Beaue, D. (2003). Understanding Wet-Mix Shotcrete: Mix Design, Specifications, and Placement.
McCormac, J., and Brown, R. (2009). Design of Reinforced Concrete. John Wiley & Sons, Chichester.
Northern Arizona University Concrete Canoe. (2014). Spirit, PSWC Concrete Canoe Competition Design Paper
Northern Arizona University Concrete Canoe. (2015). Dreadnoughtus, PSWC Concrete Canoe Competition
Design Paper.
Northern Arizona University Concrete Canoe. (2017). Paddlegonia, PSWC Concrete Canoe Competition
Design Paper.
Northern Arizona University Concrete Canoe. (2018). Canoopa, PSWC Concrete Canoe Competition Design
Paper.
A-1
Northern Arizona University
VolCanoe
Appendix A - References
S. H. Hosmatka and M. L. Wilson. (2011). Design and Control of Concrete Mixtures. Portland Cement
Associtation, Skokie, IL.
Solidworks® Education Edition (2018). Computer Software. Dassault Systemes Solidworks Corporation,
Waltham, MA.
A-2
Northern Arizona University
VolCanoe
FIBERS
Component Specific Gravity Volume (ft3) Amount of Fibers (mass/volume) (lb/yd3)
PVA Fiber 8mm 1.30 0.06 4.75 Total Amount of Fibers
Fiber 2 0.91 0.14 8.00 12.75 lb/yd3
AGGREGATES
ASTM Base Quantity (lb/yd3)
Abs
Aggregates C330* SGOD SGSSD Volume (ft3)
(%) OD SSD
Poraver® 1.0-2.0 mm* Yes 20.00 0.34 0.40 115.00 138.00 5.53
Pumice 4.76-6.35 mm* Yes 65.00 1.42 2.35 30.00 49.50 0.34
Pumice 2.89-3.36 mm* Yes 65.00 1.42 2.35 10.00 16.50 0.11
Pumice 0.07-0.84 mm* Yes 65.00 1.42 2.35 45.00 74.25 0.51
AeroAggregate UL-FGA 4.76-6.35mm No 64.00 0.23 0.38 15.00 24.60 1.04
AeroAggregate UL-FGA 2.89-3.36mm No 64.00 0.23 0.38 20.00 32.80 1.38
AeroAggregate UL-FGA 0.07-0.84mm No 64.00 0.23 0.38 50.00 82.00 3.46
EnStyro EPS Foam Beads 2.89- No 4.00 0.01 0.01 4.25 4.42 6.44
3.36mm
Utelite Fines 0.84-4.76 mm* Yes 18.90 1.36 1.62 65.00 77.29 0.76
Utelite #10 Mesh 0.07-0.30 mm* Yes 18.90 1.36 1.62 60.00 71.34 0.71
ADMIXTURES
Dosage
Admixture lb/gal (fl. oz / % Solids Amount of Water in Admixture (lb/yd3)
cwt)
Mallard Creek Polymers Rovene 4040 8.42 5.00 14.00 2.19
Mallard Creek Polymers Rovene 4193 8.39 12.00 26.00 4.12
Trinseo A/NA 8.76 8.00 51.00 1.69 Total Water from
MasterSet Delvo 9.93 8.00 52.00 1.65 Admixtures, ∑wadmx
MasterGlenium 7500 9.05 8.00 47.90 1.87 38.38 lb/yd3
MasterLife SRA 20 7.59 5.00 80.00 0.39
MasterColor Black 15.00 40.00 14.00 26.47
SOLIDS (LATEX, DYES, POWDERED ADMIXTURES, AND MINERAL FILLERS)
Component Specific Gravity Volume (ft3) Amount (mass/volume) (lb/yd3)
Trinseo A/NA 1.05 0.03 1.72 Total Solids from
Mallard Creek Polymers Rovene 4040 1.01 0.03 1.76 Admixtures
Mallard Creek Polymers Rovene 4193 1.01 0.03 1.79 9.58 lb/yd3
B-1
Northern Arizona University
VolCanoe
* Indicate if aggregate, other than manufactured glass microspheres and/or cenospheres, is compliant with ASTM C330.
B-2
Northern Arizona University
VolCanoe
Poraver® 1.0-2.0 mm* Yes 20.00 0.34 0.40 105.00 126.00 5.05
Pumice 4.76-6.35 mm* Yes 65.00 1.42 2.35 60.00 99.00 0.68
Pumice 2.89-3.36 mm* Yes 65.00 1.42 2.35 10.00 16.50 0.11
Pumice 0.07-0.84 mm* Yes 65.00 1.42 2.35 50.00 82.50 0.56
AeroAggregate UL-FGA 4.76-6.35mm No 64.00 0.23 0.38 25.00 41.00 1.73
AeroAggregate UL-FGA 2.89-3.36mm No 64.00 0.23 0.38 25.00 41.00 1.73
AeroAggregate UL-FGA 0.07-0.84mm No 64.00 0.23 0.38 30.00 49.20 2.07
EnStyro EPS Foam Beads 2.89- No 4.00 0.01 0.01 4.50 4.68 6.82
3.36mm
Utelite Fines 0.84-4.76 mm* Yes 18.90 1.36 1.62 75.00 89.18 0.88
Utelite #10 Mesh 0.07-0.30 mm* Yes 18.90 1.36 1.62 75.00 89.18 0.88
ADMIXTURES
Dosage
lb/gal
Admixture (fl. oz / % Solids Amount of Water in Admixture (lb/yd3)
cwt)
Mallard Creek Polymers Rovene 4040 8.42 5.00 14.00 2.19
Mallard Creek Polymers Rovene 4193 8.39 12.00 26.00 4.12
Trinseo A/NA 8.76 8.00 51.00 1.69 Total Water from
Admixtures, ∑wadmx
MasterSet Delvo 9.93 8.00 52.00 1.65 11.92 lb/yd3
MasterGlenium 7500 9.05 8.00 47.90 1.87
MasterLife SRA 20 7.59 5.00 80.00 0.39
SOLIDS (LATEX, DYES, POWDERED ADMIXTURES, AND MINERAL FILLERS)
Component Specific Gravity Volume (ft3) Amount (mass/volume) (lb/yd3)
Trinseo A/NA 1.05 0.03 1.72 Total Solids from
Mallard Creek Polymers Rovene 4040 1.01 0.03 1.76 Admixtures
Mallard Creek Polymers Rovene 4193 1.01 0.03 1.79 5.27 lb/yd3
B-3
Northern Arizona University
VolCanoe
* Indicate if aggregate, other than manufactured glass microspheres and/or cenospheres, is compliant with ASTM C330.
B-4
Northern Arizona University
Appendix B - Primary Mixture VolCanoe
Calculatoin
Cementitious Materials:
Mass = Given
MassType 1 Portland Cement = 504.00 lbs
𝑴𝒂𝒔𝒔
Volume =
𝑺𝒑𝒆𝒄𝒊𝒇𝒊𝒄 𝑮𝒓𝒂𝒗𝒊𝒕𝒚 𝒙 𝟔𝟐.𝟒 𝒍𝒃𝒔/𝒇𝒕𝟑
𝟓𝟎𝟒.𝟎𝟎 𝒍𝒃𝒔
VolumeType 1 Portland Cement = = 2.56 ft3
𝟑.𝟏𝟓 𝒙 𝟔𝟐.𝟒 𝒍𝒃𝒔/𝒇𝒕𝟑
𝟓𝟏𝟒𝟎.𝟎𝟎 𝒍𝒃𝒔
VolumeClass N Natural pozzolan = = 0.79 ft3
𝟐.𝟓𝟎 𝒙 𝟔𝟐.𝟒 𝒍𝒃𝒔/𝒇𝒕𝟑
𝟏𝟐.𝟔𝟎 𝒍𝒃𝒔
VolumeMasterLife® D300 = = 0.10 ft3
𝟐.𝟏𝟎 𝒙 𝟔𝟐.𝟒 𝒍𝒃𝒔/𝒇𝒕𝟑
Fibers:
Mass = Given
𝑴𝒂𝒔𝒔
Volume =
𝑺𝒑𝒆𝒄𝒊𝒇𝒊𝒄 𝑮𝒓𝒂𝒗𝒊𝒕𝒚 𝒙 𝟔𝟐.𝟒 𝒍𝒃𝒔/𝒇𝒕𝟑
𝟒.𝟕𝟓 𝒍𝒃𝒔
Volume8mm PVA = = 0.06 ft3
𝟏.𝟑𝟎 𝒙 𝟔𝟐.𝟒 𝒍𝒃𝒔/𝒇𝒕𝟑
𝟖.𝟎𝟎 𝒍𝒃𝒔
VolumeMasterFiber® MAC360= = 0.14 ft3
𝟎.𝟗𝟏 𝒙 𝟔𝟐.𝟒 𝒍𝒃𝒔/𝒇𝒕𝟑
B-5
Northern Arizona University
Appendix B - Primary Mixture VolCanoe
Calculatoin
Aggregates:
Mass (WSSD) = Given
𝑾𝑺𝑺𝑫
Volume =
𝑺𝒑𝒆𝒄𝒊𝒇𝒊𝒄 𝑮𝒓𝒂𝒗𝒊𝒕𝒚 𝒙 𝟔𝟐.𝟒 𝒍𝒃𝒔/𝒇𝒕𝟑
.
VolumePumice 4.76-6.35mm= = 0.34 ft3
. . /
.
VolumePumice 2.38-3.36mm = = 0.11 ft3
. . /
.
VolumePumice 0.07-0.84mm = = 0.51 ft3
. . /
.
VolumeAeroaggregate Recycled Foam Glass 4.76-6.35mm = = 1.04 ft3
. . /
.
VolumeAeroaggregate Recycled Foam Glass 2.38-3.36mm = = 1.38 ft3
. . /
.
VolumeAeroaggregate Recycled Foam Glass 0.07-0.84mm = = 3.46 ft3
. . /
B-6
Northern Arizona University
Appendix B - Primary Mixture VolCanoe
Calculatoin
.
VolumeEPS Foam 2.38-4.76mm = = 6.44 ft3
. . /
.
VolumeUtelite Fines 0.84-4.76mm = = 0.76 ft3
. . /
.
VolumeUtelite #10 Mesh 0.07-0.30mm = = 0.71 ft3
. . /
𝑾𝑺𝑺𝑫 𝑾𝑶𝑫
Absorbance (Abs) = ∗ 𝟏𝟎𝟎%
𝑾𝑶𝑫
. .
AbsPoraver®1.0-2.0mm= ∗ 100% = 20.00%
.
. .
AbsPumice 4.76-6.35mm= ∗ 100% = 65.00%
.
. .
AbsPumice 2.38-3.36mm = ∗ 100% = 65.00%
.
B-7
Northern Arizona University
Appendix B - Primary Mixture VolCanoe
Calculatoin
. %
WPumice 4.76-6.35mm= 30.00 𝑙𝑏𝑠 ∗ (1 + ) = 31.95 lbs
%
. %
WPumice 2.38-3.36mm = 10.00 𝑙𝑏𝑠 ∗ (1 + ) = 10.65 lbs
%
. %
WPumice 0.07-0.84mm = 45.00 𝑙𝑏𝑠 ∗ (1 + ) = 47.93 lbs
%
. %
WAeroaggregate Recycled Foam Glass 4.76-6.35mm = 15.00 𝑙𝑏𝑠 ∗ (1 + ) = 15.15 lbs
%
. %
WAeroaggregate Recycled Foam Glass 2.38-3.36mm = 20.00 𝑙𝑏𝑠 ∗ (1 + ) = 20.20 lbs
%
. %
WAeroaggregate Recycled Foam Glass 0.07-0.84mm = 50.00 𝑙𝑏𝑠 ∗ (1 + ) = 50.50 lbs
%
. %
WEPS Foam 2.38-4.76mm = 4.25 𝑙𝑏𝑠 ∗ (1 + ) = 4.27 lbs
%
. %
WUtelite Fines 0.84-4.76mm = 65.00 𝑙𝑏𝑠 ∗ (1 + ) = 67.99 lbs
%
. %
WUtelite #10 Mesh 0.07-0.30mm = 60.00 𝑙𝑏𝑠 ∗ (1 + ) = 62.76 lbs
%
B-8
Northern Arizona University
Appendix B - Primary Mixture VolCanoe
Calculatoin
𝑴𝑪𝒇𝒓𝒆𝒆
Free Water (wfree) = 𝑾𝑶𝑫 ∗ ( )
𝟏𝟎𝟎%
. %
WPoraver®1.0-2.0mm= 115.00 𝑙𝑏𝑠 ∗ ( ) = -22.43 lbs
%
. %
WPumice 4.76-6.35mm= 30.00 𝑙𝑏𝑠 ∗ (1 + ) = -17.85 lbs
%
. %
WPumice 2.38-3.36mm = 10.00 𝑙𝑏𝑠 ∗ (1 + ) = -5.95 lbs
%
. %
WPumice 0.07-0.84mm = 45.00 𝑙𝑏𝑠 ∗ (1 + ) = -26.78 lbs
%
. %
WAeroaggregate Recycled Foam Glass 4.76-6.35mm = 15.00 𝑙𝑏𝑠 ∗ (1 + ) = -9.45 lbs
%
. %
WAeroaggregate Recycled Foam Glass 2.38-3.36mm = 20.00 𝑙𝑏𝑠 ∗ (1 + ) = -12.60 lbs
%
. %
WAeroaggregate Recycled Foam Glass 0.07-0.84mm = 50.00 𝑙𝑏𝑠 ∗ (1 + ) = -31.50 lbs
%
. %
WEPS Foam 2.38-4.76mm = 4.25 𝑙𝑏𝑠 ∗ (1 + ) = -0.15 lbs
%
. %
WUtelite Fines 0.84-4.76mm = 65.00 𝑙𝑏𝑠 ∗ (1 + ) = -11.96 lbs
%
. %
WUtelite #10 Mesh 0.07-0.30mm = 60.00 𝑙𝑏𝑠 ∗ (1 + ) = -11.04 lbs
%
Admixtures:
Dosage = Given
DosageMasterSet Delvo = 5
DosageMasterGlenium 7500 = 8
DosageRovene 4040 = 8
DosageTylac 4193 = 8
DosageTrinseo AN™/A = 8
B-9
Northern Arizona University
Appendix B - Primary Mixture VolCanoe
Calculatoin
DosageMasterLife SRA 035 = 5
DosageMasterColor Black = 40
𝒇𝒍 𝒐𝒛 𝟏 𝒈𝒂𝒍 𝒍𝒃𝒔
Wadmix = dosage ( ) ∗ 𝒄𝒘𝒕 𝒐𝒇 𝒄𝒎 ∗ 𝒘𝒂𝒕𝒆𝒓 𝒄𝒐𝒏𝒕𝒆𝒏𝒕 (%) ∗ ∗ 𝒐𝒇 𝒂𝒅𝒎𝒊𝒙.
𝒄𝒘𝒕 𝟏𝟐𝟖 𝒇𝒍 𝒐𝒛 𝒈𝒂𝒍
.
WMasterSet Delvo = 5 ( )∗ ∗ (100.00% − 14.00%) ∗ ∗ 9.93 𝑜𝑓 𝑎𝑑𝑚𝑖𝑥. = 2.19 lbs
.
WMasterGlenium 7500 = 8 ( )∗ ∗ (100.00% − 26.00%) ∗ ∗ 9.05 𝑜𝑓 𝑎𝑑𝑚𝑖𝑥. = 2.75 lbs
.
WMasterLife SRA 20 = 5 ( )∗ ∗ (100.00% − 8.00%) ∗ ∗ 7.59 𝑜𝑓 𝑎𝑑𝑚𝑖𝑥. = 1.79 lbs
.
WRovene 4040 = 8 ( )∗ ∗ (51.00%) ∗ ∗ 8.42 𝑜𝑓 𝑎𝑑𝑚𝑖𝑥. = 1.76 lbs
.
WTylac 4193 = 8 ( )∗ ∗ (52.00%) ∗ ∗ 8.39 𝑜𝑓 𝑎𝑑𝑚𝑖𝑥. = 1.79 lbs
.
WTrinseo AN™/A = 8 ( )∗ ∗ (47.90%) ∗ ∗ 8.76 𝑜𝑓 𝑎𝑑𝑚𝑖𝑥. = 1.72 lbs
.
WMasterColor Black = 40 ( )∗ ∗ (14.00%) ∗ ∗ 15 𝑜𝑓 𝑎𝑑𝑚𝑖𝑥. = 4.31 lbs
B-10
Northern Arizona University
Appendix B - Primary Mixture VolCanoe
Calculatoin
𝑴𝒂𝒔𝒔𝒂𝒅𝒎𝒊𝒙 (𝒍𝒃𝒔)
Volumeadmixture = 𝒍𝒃𝒔
𝑺𝒑𝒆𝒄𝒊𝒇𝒊𝒄 𝑮𝒓𝒂𝒗𝒊𝒕𝒚 𝒙 𝟔𝟐.𝟒
𝒚𝒅𝟑
. ( )
VolumeRovene 4040 = = 0.03 ft3
. .
. ( )
Volumetylac 4193= = 0.03 ft3
. .
. ( )
VolumeTrinseo AN™/A = = 0.03 ft3
. .
. ( )
VolumeMasterColor Black= = 0.04 ft3
. .
Water:
𝒘
MassWater = ∗ 𝒄𝒎
𝒄𝒎
𝑴𝒂𝒔𝒔𝑾𝒂𝒕𝒆𝒓
Volume Water = 𝒍𝒃𝒔
𝑺𝒑𝒆𝒄𝒊𝒇𝒊𝒄 𝑮𝒓𝒂𝒗𝒊𝒕𝒚 𝒙 𝟔𝟐.𝟒
𝒚𝒅𝟑
.
Volume Water = = 4.21 ft3
. .
Concrete Analysis:
Densities:
∑Masses = MassConcrete = 1,388.60 lbs
∑Volumes = VolumeConcrete = 24.20 ft3
𝐌𝐚𝐬𝐬𝐂𝐨𝐧𝐜𝐫𝐞𝐭𝐞 𝟏,𝟑𝟖𝟖.𝟔𝟎 𝒍𝒃𝒔 𝒍𝒃𝒔
Theoretical Desnity (T) = = 𝟑
= 57.38
𝐕𝐨𝐥𝐮𝐦𝐞𝐂𝐨𝐧𝐜𝐫𝐞𝐭𝐞 𝟐𝟒.𝟐𝟎 𝒇𝒕 𝒚𝒅𝟑
𝒍𝒃𝒔
Measured Density (D) = 51.43
𝒚𝒅𝟑
𝒍𝒃𝒔 𝒍𝒃𝒔 𝒍𝒃𝒔 𝒍𝒃𝒔
𝑻( 𝟑 ) 𝑫( 𝟑 ) 𝟓𝟕.𝟑𝟖( ) 𝟓𝟏.𝟒𝟑( )
𝒚𝒅 𝒚𝒅 𝒚𝒅𝟑 𝒚𝒅𝟑
Air Content = 𝒍𝒃𝒔 ∗ 𝟏𝟎𝟎% = 𝒍𝒃𝒔 ∗ 𝟏𝟎𝟎% = 10.37%
𝑻( ) 𝟓𝟕.𝟑𝟖( )
𝒚𝒅𝟑 𝒚𝒅𝟑
B-11
Northern Arizona University
Appendix B - Primary Mixture VolCanoe
Calculatoin
𝒍𝒃𝒔
𝟐𝟕 𝒇𝒕𝟑 𝑽𝒐𝒍𝒖𝒎𝒆𝑪𝒐𝒏𝒄𝒓𝒆𝒕𝒆 ( ) 𝟐𝟕 𝒇𝒕𝟑 𝟐𝟒.𝟐𝟎 𝒇𝒕𝟑
𝒚𝒅𝟑
Air Content = ∗ 𝟏𝟎𝟎% = ∗ 𝟏𝟎𝟎% = 10.37%
𝟐𝟕 𝒇𝒕𝟑 𝟐𝟕 𝒇𝒕𝟑
Important Ratios:
𝒄 𝟓𝟎𝟒.𝟎𝟎 𝒍𝒃𝒔
Cement/Cementitious Material: = = 𝟎. 𝟕𝟕
𝒄𝒎 𝟔𝟓𝟔.𝟔𝟎 𝒍𝒃𝒔
𝒘 𝟐𝟔𝟐.𝟔𝟒 𝒍𝒃𝒔
Water/Cement: = = 𝟎. 𝟓𝟐
𝒄 𝟓𝟎𝟒.𝟎𝟎 𝒍𝒃𝒔
𝒘 𝟐𝟔𝟐.𝟔𝟒 𝒍𝒃𝒔
Water/ Cementitious Material: = = 𝟎. 𝟒𝟎
𝒄𝒎 𝟔𝟓𝟔.𝟔𝟎 𝒍𝒃𝒔
B-12
Northern Arizona University
Appendix C - Example Structural VolCanoe
Calculations
Known Values:
The 4-Person racing scenario is considered for the sample 2D structural calculations which include two male
and two female paddlers represented as 180lb point loads along VolCanoe’s length of 18ft. Other values
included into the analysis are shown under “Properties” to the right below.
Properties:
VolCanoe length = 18 ft
VolCanoe density = 59 pcf
VolCanoe weight = 300 lbs
VolCanoe thickness = 5/8 in
Assumptions:
1. VolCanoe is simplified into a beam.
2. The self-weight and the buoyant force of VolCanoe is represented as a uniformly distributed load.
3. Mesh reinforcement is neglected.
4. Cross-section is simplified to a “U-shape” comprised of three rectangles.
Centroid Calculation:
ȳ = 4.22 in
C-1
Northern Arizona University
Appendix C - Example Structural VolCanoe
Calculations
Moment of Inertia Calculations:
( . )( . )
𝐼 = =2 =2 Ix1 = 443.32 in4
( )( . )
𝐼 = = = Ix2 = 1.16 in4
𝐼 = 𝐼 + 𝛴ȳ 𝐴 = 𝐼 + 2 ȳ 𝑏 ℎ + (ȳ 𝑏 ℎ )
= 444.48𝑖𝑛 + [2(4.155𝑖𝑛 )(0.7𝑖𝑛)(15.25𝑖𝑛) + (−3.845𝑖𝑛 )(33𝑖𝑛)(0.75𝑖𝑛)]
Ixx = 1178.97 in4
0
-50
-100
-150
-200
0 2 4 6 8 10 12 14 16 18
Canoe Length (ft)
4 Person 2-Person Transportation Buggie/Canoe Stand
C-2
Northern Arizona University
Appendix C - Example Structural VolCanoe
Calculations
Calculating Compressive and Tensile Stresses:
The maximum moment used for the calculation occurs during the 4-Perosn race scenario.
Mmax = 360 lb-ft = 4320 lb-in
𝑦 =ℎ−ȳ 𝑦 =ȳ
𝑀 𝑦 𝑀 𝑦
𝜎 = 𝜎 =
𝐼 𝐼
(4320𝑙𝑏 − 𝑖𝑛)(16𝑖𝑛 − 5.50𝑖𝑛) (4320𝑙𝑏 − 𝑖𝑛)(5.50𝑖𝑛)
𝜎 = 𝜎 =
1178.97𝑖𝑛 1178.97𝑖𝑛
σt = - 38.47 psi σb = 20.15 psi
Transportation/Canoe Stand
C-3
Northern Arizona University
Appendix D - Hull VolCanoe
t1= 5.6mm
t2= 5.6mm
𝟓.𝟔
d1= 24.9+ 2 ∗ = 24.9+ 𝟐 ∗ = 30.1mm
𝟐
𝟑.𝟗
d2 = 26.7 + 2 ∗ = 26.7 + 𝟐 ∗ = 30.6mm
𝟐
n1 = 6
n2 = 6
Areaopen1= 25mm^2
Thickness Calculations:
The wall thickness is 0.75”. Each layer of reinforcement is 0.04” thick. There are two layers of reinforcement in
the canoe. So, 𝟎. 𝟎𝟖" 𝟎. 𝟕𝟓 ∗ 𝟏𝟎𝟎% = 𝟏𝟎. 𝟔𝟕% of the hull thickness is reinforcement.
D-1
Northern Arizona University