Work Breakdown Structure Template
Work Breakdown Structure Template
NAME>
The WBS is a view into the project that illustrates the work the project encompasses. The
Project Manager and project team use the WBS to develop the project schedule, resource
requirements, and costs. There are many ways you can present the WBS for your project;
this template provides some of the popular layouts from which you can choose. Different
layouts may be more suitable for different purposes (presentations vs. plan documentation,
for example).
In order to save space in this template we only developed the WBS examples down to the
third level. In your project you may want to develop them further.
Note: Instructions for what to include in each section appear in gold italics.
CONTENTS
Outline View......................................................................................................................... 2
Hierarchical Structure......................................................................................................... 2
Tabular View......................................................................................................................... 4
Tree Structure View............................................................................................................ 5
WBS Dictionary.................................................................................................................... 6
Glossary of Terms................................................................................................................ 8
Page 1 of 9
WORK BREAKDOWN STRUCTURE: < PROJECT
NAME>
OUTLINE VIEW
The outline view presents an easy to view and understand layout for the WBS. It is also a
good layout to use when developing the WBS because you can easily make changes,
especially since the Microsoft Word auto numbering feature updates the WBS Code
automatically.
Page 2 of 9
WORK BREAKDOWN STRUCTURE: < PROJECT
NAME>
HIERARCHICAL STRUCTURE
The hierarchal structure is similar to the outline view but without indentation. Although this
format is more difficult to read, it may be useful where you have many levels and indenting
each level would make the table too large to fit into a document.
Page 3 of 9
WORK BREAKDOWN STRUCTURE: < PROJECT
NAME>
TABULAR VIEW
The Tabular View is a nicely organized table view of the WBS. It is a good option for
organizations which prefer table formats.
Page 4 of 9
WORK BREAKDOWN STRUCTURE: < PROJECT
NAME>
Page 5 of 9
WORK BREAKDOWN STRUCTURE: < PROJECT
NAME>
User Training
1.3.8
Go Live
1.3.9
WBS DICTIONARY
The WBS Dictionary contains all the details of the WBS which are necessary to successfully
complete the project. Most importantly it contains a definition of each Work Package which
can be thought of as a mini scope statement. Resources on the project will look at the WBS
dictionary to determine the scope of the Work Package they've been assigned, so it's
important to be clear when writing the definition.
Page 6 of 9
WORK BREAKDOWN STRUCTURE: < PROJECT
NAME>
Page 7 of 9
WORK BREAKDOWN STRUCTURE: < PROJECT
NAME>
1 1 Widget Management System All work to implement a new widget management system.
2 1.1 Initiation The work to initiate the project.
3 1.1.2 Develop Project Charter Project Manager to develop the Project Charter.
3 1.1.4 Project Sponsor Reviews Project sponsor reviews the Project Charter.
Project Charter
3 1.1.5 Project Charter The Project Sponsor signs the Project Charter which
Signed/Approved authorizes the Project Manager to move to the Planning
Process.
2 1.2 Planning The work for the planning process for the project.
3 1.2.1 Create Preliminary Scope Project Manager creates a Preliminary Scope Statement.
Statement
3 1.2.2 Determine Project Team The Project Manager determines the project team and
requests the resources.
3 1.2.3 Project Team Kickoff Meeting The planning process is officially started with a project
kickoff meeting which includes the Project Manager,
Project Team and Project Sponsor (optional).
3 1.2.4 Develop Project Plan Under the direction of the Project Manager the team
develops the project plan.
3 1.2.5 Submit Project Plan Project Manager submits the project plan for approval.
3 1.2.6 Milestone: Project Plan The project plan is approved and the Project Manager has
Approval permission to proceed to execute the project according to
the project plan.
2 1.3 Execution Work involved to execute the project.
3 1.3.1 Project Kickoff Meeting Project Manager conducts a formal kick off meeting with
the project team, project stakeholders and project
sponsor.
3 1.3.2 Verify & Validate User The original user requirements is reviewed by the project
Requirements manager and team, then validated with the
users/stakeholders. This is where additional clarification
may be needed.
3 1.3.3 Design System The technical resources design the new widget
management system.
3 1.3.4 Procure Hardware/Software The procurement of all hardware, software and facility
needs for the project.
3 1.3.6 Testing Phase The system is tested with a select set of users.
3 1.3.7 Install Live System The actual system is installed and configured.
3 1.3.8 User Training All users are provided with a four hours training class.
Additionally, managers are provided with an additional
two hours class to cover advanced reporting.
3 1.3.9 Go Live System goes live with all users.
2 1.4 Control The work involved for the control process of the project.
3 1.4.1 Project Management Overall project management for the project.
3 1.4.2 Project Status Meetings Weekly team status meetings.
3 1.4.3 Risk Management Risk management efforts as defined in the Risk
Management Plan.
2 1.5 Closeout The work to close-out the project.
3 1.5.1 Audit Procurement An audit of all hardware and software procured for the
project, ensures that all procured products are accounted
for and in the asset management system.
3 1.5.2 Document Lessons Learned Project Manager along with the project team performs a
lessons learned meeting and documents the lessons
learned for the project.
3 1.5.3 Update Files/Records All files and records are updated to reflect the widget
management system.
3 1.5.4 Gain Formal Acceptance The Project Sponsor formally accepts the project by
Page 8 of 9
WORK BREAKDOWN STRUCTURE: < PROJECT
NAME>
GLOSSARY OF TERMS
It's important that you provide a glossary of terms as some of the terms are not understood
by persons without a project management background.
Level of Effort: Level of Effort (LOE) is how much work is required to complete a task.
WBS Code: A unique identifier assigned to each element in a Work Breakdown Structure
for the purpose of designating the elements hierarchical location within the
WBS.
Work Package: A Work Package is a deliverable or work component at the lowest level
of its WBS branch.
WBS Component: A component of a WBS which is located at any level. It can be a Work
Package or a WBS Element as there's no restriction on what a WBS
Component is.
WBS Element: A WBS Element is a single WBS component and its associated attributes
located anywhere within a WBS. A WBS Element can contain work, or it can
contain other WBS Elements or Work Packages.
Page 9 of 9