Operational Readiness Manual Rev.0
Operational Readiness Manual Rev.0
Copies or extracts of this document, which have been downloaded from the Intranet, are
uncontrolled copies and cannot be guaranteed to be the latest version.
The custodian of this manual is the Asset Integrity Managers and any suggested changes to
this procedure or queries about its applicability should be addressed to them.
The asset integrity managers are also responsible for coordinating periodic reviews of this
manual, which will take place every three years.
To Download the last version of Operational Readiness Manual, follow the below
link:
http://kpcweb.khalda-
eg.com/Operations/Asset_Integrity/SitePages/PSSR.aspx
Asset Integrity Team
Rev: 0 Operational Readiness System Manual
Date: Dec. 2021
Page 2
This Manual illustrates KPC process and methodology for verifying that shut down processes are
in a safe condition for re-start, addresses startups for new project/equipment and also all types
of shut down conditions considering the length of time the process was in the shutdown.
The manual is intended to provide a guidance and direction on how to supply a final review on
the equipment to ensure process safety activities have been completed prior to adding any
hazardous chemicals to new or modified equipment.
The custodian of this manual is operational readiness administrator; also he is responsible for
coordinating periodic reviews of this guideline which will take place every three years.
The Asset Integrity Managers who are the system owner and any suggested changes to this
manual, system policy or system administrator shall be approved by them.
Guideline Approval
1 Introduction
1.1 Preface
In recent years, there have been significant advances in process safety
management system, that aim to improve the safety and the integrity of
workplaces. Operational Readiness which known as Pre-Start Up Safety
Review (PSSR) system is one of the main elements of the process safety.
Khalda Petroleum Company (KPC) is continually seeking the improvement of
its rules and methods of identifying, managing the anticipated risks and
monitoring the directions where the industry is headed. Thus, KPC is
exploring certain changes to its rules and methods through the use of risk
based process safety.
The transition to a risk based framework through applying this manual and
other facility integrity management system (FIMS) manuals is expected to be
incremental while risk based and performance oriented approaches are being
developed and implemented.
To understand and apply this methodology, it is necessary that KPC
employees and management have a common understanding of the terms and
concepts involved and an awareness of how these concepts are to be
applied. This is the driving force for this manual.
1.2 Scope
This Manual illustrates KPC process and methodology for verifying that shut
down processes are in a safe condition to re-start, addresses startups for new
project/equipment and also all types of shut down conditions considering the
length of time the process was in the shutdown.
Item Definition
Hazard Any source that has the potential to cause harm to people, property,
or the environment.
Hazard identification The process of identifying what hazards are associated with a given
operation, activity, or design.
Hazard evaluation The process of identifying what could go wrong, harm that could
result, and what controls are in place to develop a hypothetical
sequence of events (scenario) that might lead to an incident.
Risk management The systematic application of policies and practices to the tasks of
identifying, assessing, and controlling risk in order to protect human
life, the environment, physical assets, and company reputation in a
cost-effective manner. Risk management includes appropriate
stewardship and communication of results.
Risk assessment Overall process of risk identification, risk analysis and risk evaluation.
Abbreviations:
Asset Integrity Team
Rev: 0 Operational Readiness System Manual
Date: Dec. 2021
Page 5
Item Definition
2 PSSR Process
2.1 Introduction
A Pre-Start-up Safety Review (PSSR) is intended to supply a final review of a
change to ensure process safety activities have been completed prior to adding
any hazardous chemicals to new or modified equipment.
It is more important to focus on the objectives of this activity rather than the
size of the capital budget involved. Projects that involve installing additional
fire protection, safety showers, breathing air stations, enhanced ventilation,
new heat transfer media, etc. shall be considered a facility change, and an
extended start-up checklist shall be used to assist with meeting the intent of
the pre-start-up safety review.
Asset Integrity Team
Rev: 0 Operational Readiness System Manual
Date: Dec. 2021
Page 7
Facility checklist in Appendix I shall be performed with this type. It is the most
extensive PSSR checklist and includes a check of safety systems (safety
showers, eyewash stations, help evacuate alarms, automation alarms, clear
paths for egress, etc.), as well as complete training and documentation.
Any facility change that impacts the process safety information also requires a
PSSR. After the change executed and before the changed part put in service
the checklist take place to ensure the continuing operations integrity and safety
of personnel.
Checklist in Appendix II: PSSR CHECKLIST AFTER MOC shall be completed prior
to startup. It is a subset of the facility checklist usually focuses on the part of
the process that was changed, but still ensures that all of the following PSM
requirements are met:
For maintenance work, the PSSR team shall check out the equipment through
checklist in Appendix III to ensure the work is complete and the equipment is
ready to start-up before returning the equipment back to production to ensure
the process will restart safely.
If the shutdown of equipment has been longer than two weeks, a restart
checklist in Appendix III shall be done by PSSR team. If the shutdown has
been less than two weeks, the unit team could recommend a restart checklist
for appropriate reasons.
For very minor changes, a smaller prestart-up safety review team may be used
and could consist of two team members. In this situation, the asset owner shall
designate the team members. Examples of minor changes include installation of
a new drain valve and instrument transmitter bracket modification.
Team composition is the key to maximizing the value and results of a PSSR. The
asset owner must take responsibility for assembling a multidisciplinary team
with knowledge and experience appropriate to the task. Team members should
Asset Integrity Team
Rev: 0 Operational Readiness System Manual
Date: Dec. 2021
Page 9
include personnel who were not directly involved on the applicable capital
project team.
For significant capital projects and for larger projects, a formal PSM audit
may be recommended. In this case the asset owner must ensure that the
team has the skills and capability to carry this out. Consideration should
be given to having one or more safety or occupational health consultants
on the team.
The leader of the PSSR team should foster an open atmosphere where
the project team members look on the review as an opportunity to
upgrade the process safety of the facility and do not become defensive of
the design or preparations for start-up.
For new facilities, a PHA has been performed and recommendations have
been resolved or implemented before start up and modified facilities
meet the requirements specified in MOC.
Standard operating procedures and emergency procedures have been
developed to ensure safe operation of the new process.
Basic safety, health, and environmental, also fire-protection items have
been checked during a physical inspection of the facility. These
inspections are usually guided via a previously pre-prepared “good
practice” checklist.
Installation is in compliance with local regulatory requirements and site
and unit operating permit(s), including environmental air permits and
approvals.
The facility is safe to start up. This may be contingent on completion of
certain recommendations.
2. System Administrator:
3. RAMS advisors:
Responsible for providing guidance through the PSSR process, Provide
helping in PSSR if invited to be a team member.
Asset Integrity Team
Rev: 0 Operational Readiness System Manual
Date: Dec. 2021
Page 11
The Asset Owner shall designate the team members and shall authorize
the checklist after the team members have signed it and shall ensure that
all recommendations required prior to startup are completed and prior to
the introduction of hazardous materials into the facility.
7. Field manager:
3.1 Introduction
All KPC employees and contractors in the company locations are responsible for
being adhere to process safety management system and PSSR is a vital
element in that system.
Basic This level is the minimum level for all staff personnel to
be familiar with their potential participation in
implementing the practice of PSSR.
advanced This level is for individuals who participate in PSSR
team, utilize the PSSR checklists and understand the
system features.
Asset Integrity Team
Rev: 0 Operational Readiness System Manual
Date: Dec. 2021
Page 14
Pre-startup safety review team leaders shall benefit from additional training on
the following topics,
Process Safety Management - Overview, current issues, and industry trends.
How to Facilitate Meetings - Basic skills for preparing, leading and capturing
the results from meetings.
KPIs can help boost each company’s risk related to PSSR understanding to
improve its operational readiness system and improve the whole PSM system.
KPIs can be used to assess system performance on a near-real-time basis and
at a more reasonable expenditure of effort.
Monitoring these key indicators can help KPC to detect the deviations in
implementing a PSSR system before these deviations can cause accidents.
Examples on some expected KPIs that could be used for PSSR in each company:
equipment found
during PSSRs
discovered during
the PSSR
5 Auditing
Operational readiness shall be included in PSM audit of all KPC facilities. The
auditing cycle maintains employee awareness of the overall PSM system. Audits
can be internal or external.
Internal audit typically means the facility audits itself or in a corporation with a
representative or appropriate positions from other plant, department within KPC
with no outside influence. This method brings outside experience and points of
view to a site and can be very helpful in sharing best practices as well as
communicating issues to other corporate facilities.
External third-party audits include an outside party to examine the system. This
can be a contractor, EGPC, or a customer. A third-party audit typically means
an outside consultant or organization comes in to look to system and compare
it with standards or regulations from yet another standpoint.
For internal audit Appendix IV: PSSR Auditing Questions shall be used in the
audit.
Asset Integrity Team
Rev: 0 Operational Readiness System Manual
Date: Dec. 2021
Page 20
Inspection Date:
Department/Area:
Project Number:
Title/Equipment:
QA Group Date
Asset Integrity Team
Rev: 0 Operational Readiness System Manual
Date: Dec. 2021
Page 21
1.
2.
3.
4.
5.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
Asset Integrity Team
Rev: 0 Operational Readiness System Manual
Date: Dec. 2021
Page 22
All “before start-up” items are completed / uncompleted and can / cannot start the
equipment / unit / facility.
Comments:
It is accepted to start-up the new equipment / unit / facility, as the pending items will not
have effect on the safe operation for the new equipment / unit / facility, The area authority
can go ahead with start-up procedure.
1.3 ERGONOMICS
Initial start-up?
Normal start-up?
Normal operations?
Normal shutdowns?
11.0 OTHER
11.1
11.2
Asset Integrity Team
Rev: 0 Operational Readiness System Manual
Date: Dec. 2021
Page 46
Inspection Date:
Department/Area:
Title/Equipment:
MOC Title:
Others Signatures:
Asset Integrity Team
Rev: 0 Operational Readiness System Manual
Date: Dec. 2021
Page 47
1.
2.
1.
2.
3.
4.
5.
6.
7.
8.
It is accepted to start-up the equipment, as the pending items will not have effect on
operating safely.
1. ADMINISTRATION
3. PRESSURE/VACUUM RELIEF
4. TEMPERATURE/REACTION
7. INSTRUMENTATION
8. ELECTRICAL SYSTEMS
9. FIRE PROTECTION
17. OTHER
17.1
17.2
Asset Integrity Team
Rev: 0 Operational Readiness System Manual
Date: Dec. 2021
Page 61
Inspection Date:
Department/Area:
Title/Equipment:
Others Signatures:
Asset Integrity Team
Rev: 0 Operational Readiness System Manual
Date: Dec. 2021
Page 62
1.
2.
1.
2.
3.
4.
5.
6.
7.
8.
It is accepted to start-up the equipment, as the pending items will not have effect on
operating safely.
3.14 Are all hot and cold surfaces, which may cause
burns, in the proximity of personnel insulated?
4. piping
5. Instrumentation
6. ELECTRICAL SAFETY
7. PROCESS VENTS
8.0 OTHER
8.1
8.2
Asset Integrity Team
Rev: 0 Operational Readiness System Manual
Date: Dec. 2021
Page 69
6 For new facilities, have PSSRs confirmed that PHAs have been
performed and recommendations have been resolved or
implemented before startup?