Lesson - 3.6 - Process and Performance Capability - Measure - Phase
Lesson - 3.6 - Process and Performance Capability - Measure - Phase
Certification Course
Process and Performance Capability
Learning Objectives
Sales Chart
How can we
summarize the current
performance of our
process to determine We need capability
if the product output is analysis to determine this.
meeting customers’ Then, we can decide what
needs? steps to take next.
Process and Performance Capability
Activities in the Measure Phase
?
Why does a process become
!
unstable?
A process becomes unstable due to special
cause of variation.
Example of CCV
400⁰F
CCV and SCV
Example of SCV
If all the data points are within the UCL and LCL (red lines), the process could be stable.
Run Charts
If p-values for any of the last 4 values provided in the chart are less than 0.05, the process has
special causes of variation, and the chances of the process being unstable are high.
Verifying Process Stability and Normality
If the P value is greater than 0.05, the data set could be described as normally distributed.
Process Capability Analysis
Customer needs
Process
and expectations
Process capability is how well the process is meeting customer needs and
expectations.
Consists of Upper Control Limit (UCL) and Consist of Upper Specification Limit (USL)
Lower Control Limit (LCL) and Lower Specification Limit (LSL)
Natural Process Limits and Specification Limits
LCL UCL
If the control limits lie within the specification limits, the process could be considered capable. Conversely, if
the specification limits lie within the control limits, the process will not meet customer requirements.
Actions after Comparing Natural Limits and Spec Limits
Condition Action
Reduce variability by
Process limits fall outside
partitioning and targeting
specification limits
the largest offender
Process Capability Studies
The same data used for stability and normality analysis can also be used for capability.
Process Capability Index
Measures performance
OR
USL − LSL
Process capability CP =
6σ
Process Capability Index
The formula assumes the process is perfectly centered between the upper and lower specification limits.
It does not reflect how the process is actually performing in relation to the specification limits.
Process Capability Index
Process Capability (Cpk) was developed to objectively measure the degree to which a
process meets or does not meet customer requirements.
𝑋ത − LSL
𝐶𝑝𝑙 =
3σ
USL − 𝑋ത
𝐶𝑝𝑢 =
3σ
Comparison of Process Capability Indices
Cpk < Cp
Cpk < Cp Cpk = Cp
Cpk is negative
Mean is not centered between Mean is centered between
Mean exceeds specification limits
specification limits specification limits
Cpk cannot be larger than Cp because Cp represents the maximum capability with the current process
variation.
Interpretation of Process Capability Indices
4 1.33
Capable 5 1.67
6 2.00
Interpretation of Process Capability Indices
Process
Sigma Level
Capability
2 0.67
3 1.00
4 1.33
5 1.66
6 2.00
Process Capability: Example
?
• Mean diameter = 3.02 centimeters
• Standard deviation = 0.02 centimeters
• Lower engineering specification limits = 2.95 inches
• Upper engineering specification limits = 3.05 inches
• Process is stable
• Diameters are normally distributed
!
𝑈𝑆𝐿 − 𝐿𝑆𝐿 3.05 − 2.95 0.10
𝐶𝑃 = = = = 0.833
6𝜎 6(0.02) 0.12
If the Cp index shows process is capable but Cpk indicates a lack a capability, then it would mean that the
process variation is small enough to allow for a capable process.
Identifying Characteristics
For a Six Sigma project, the characteristic is typically the “Y” or output variable defined in the
charter.
Identifying Specifications or Tolerances
OR
Industry standards based on Organization in consultation
the customer requirements with the customer
Process Performance Indices
Process Performance Index verifies if the sample generated from the process is
capable of meeting the customer requirements.
USL −LSL
Pp =
6s
Where,
USL = upper specification limit
LSL = lower specification limit
s = natural process variation
Process Performance Indices (Pp)
x−LSL
PpL (lower process capability index) =
3s
Where,
x = process average (തx)
s = sample standard deviation
Cpm and Ppm
Where,
USL = upper specification limit
LSL = lower specification limit
μ = process average
σ = process standard deviation
T = target value (typically, the center of tolerance)
ത sample average
𝑋=
Cpm and Ppm: Interpretation
Improved
Improved
position
Cpm or Ppm
Improved Improved
variation Cpm or Ppm
• As the process variation reduces and/or as the process average reaches the target value, the Cpm or
Ppm index improves or becomes larger.
• The ideal value is 1.33 or greater.
Process Mean Shift
Long-term performance
● Actual performance of the process over time
(ZLT)
Process Mean Shift: Example
Sample at Time 3
Sample at Time 2
Sample at Time 1
Observations
Sigma Multiple No Mean Shift Mean Shift ±1σ Mean Shift ±1.5σ
±3σ 2700 DPMO 22800 DPMO 66810 DPMO
99.73% Good 97.72% Good 93.32% Good
±4σ 63 DPM) 1350 DPMO 6210 DPMO
99.9937% Good 99.865% Good 99.379% Good
±5σ 0.57 DPMO 32 DPMO 223 DPMO
99.999943% Good 99.9968% Good 99.9767% Good
±6σ 0.002 DPMO 0.29 DPMO 3.4 DPMO
99.9999998% Good 99.999971% Good 99.99966% Good
Summary of the defect levels at different Sigma multiple values and mean shifts
Observation
The effects of a mean shift become more negligible as the process capability increases. A Six Sigma
process level of defects is not affected much by long-term variation.
Conversion From Long-term to Short-term Capability
TO KNOW
Variance inherent in the process Shows variation within and between sub-
groups
Small number of samples collected at short Special causes have to be identified and
intervals corrected for improvement
2 Grand average = Sum of per week average/3 𝑇𝑜𝑡𝑎𝑙 𝑣𝑎𝑟𝑖𝑎𝑡𝑖𝑜𝑛 𝑤𝑖𝑡ℎ𝑖𝑛 𝑠𝑢𝑏𝑔𝑟𝑜𝑢𝑝𝑠
(𝑇𝑜𝑡𝑎𝑙 𝑠𝑎𝑚𝑝𝑙𝑒 𝑠𝑖𝑧𝑒 − 𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓𝑠𝑢𝑏𝑔𝑟𝑜𝑢𝑝𝑠)
Measure Value
Grand average 47.5
Total variation within subgroups 1023.8
Total variation between subgroups 161.67
Overall variation 1185.5
Standard Deviation short term 6.2
Standard Deviation long term 6.4
Process Performance
Process Less CCV, No SCV Less CCV, High CCV, High CCV,
SCV present No SCV SCV present
Variations Only CCV CCV and SCV CCV CCV and SCV
Variability Less High Moderate to High Very High
Capability High Less Very Less Poor
Possibility of defects Less High Very High Defective Process
DPU DPMO
The Quality Control department checks the quality of finished goods by sampling a
batch of 10 items from the produced lot every hour.
1 1 1 1 1 1 1 1 1 1 2 2 2 2 2
Hour 1 2 3 4 5 6 7 8 9
0 1 2 3 4 5 6 7 8 9 0 1 2 3 4
Defectives 2 1 0 0 2 3 1 4 5 1 2 0 0 1 2 1 1 1 4 0 0 0 1 2
Process Performance: Example
Observation
Defectives Defects
σ= 𝑝ഥ (1 − 𝑝)ҧ Τ𝑛 σ=
ഥ
𝑢
; 𝑐ҧ
𝑎
A. Process Capability
B. Process Stability
C. Normality
D. Sigma Shift
Knowledge
Check
In the Measure Phase, which of these options should be determined first?
1
A. Process Capability
B. Process Stability
C. Normality
D. Sigma Shift
Ensuring that the process only has common cause variation or is stable is the first activity in the Measure Phase.
Knowledge
Check
If Cpk = 1.1 and Cp = 1.33, what can we conclude about the process ?
2
Since Cp and Cpk are greater than 1, we can say the process is currently marginally capable and because Cpk is not
equal to Cp the process is not centered.
Knowledge
Check
If Cpk = 0.7 and Cp = 1.33, what actions should be taken?
3
The process needs to be centered since a Cp value of 1.33 indicates good capability and with Cpk value less than 1
indicates centering is the issue.
Knowledge
Check
If short-term variation is calculated at 3.5σ, what is the expected long-term variation?
4
A. 3.5σ
B. 2.0σ
C. 5.0σ
D. 1.0σ
Knowledge
Check
If short-term variation is calculated at 3.5σ, what is the expected long-term variation?
4
A. 3.5σ
B. 2.0σ
C. 5.0σ
D. 1.0σ
The question requires the use of the 1.5 Sigma shift. Moving short-term to long- term Sigma will mean subtracting 1.5
from 3.5, which is 2.0.
Lean Six Sigma Activities and Tools: Measure
Activities
❑ Review Project Charter ❑ Process Map Flow Identify Root Causes ❑ Develop SOP’s, Training Plan
❑ ❑ Develop Potential Solutions
❑ Validate High-Level Value ❑ Identify Key Input, Reduce List of Potential and Process Controls
❑ ❑ Evaluate, Select, and
Stream Map and Scope Process and Output Root Causes ❑ Implement Solution and
Optimize Best Solutions
❑ Validate Voice of the Metrics Confirm Root Cause to Ongoing Process
❑ ❑ Develop ‘To-Be’ Process
Customer and Voice of the ❑ Develop Data Collection Output Relationship Measurements
Maps
Business Plan Estimate Impact of Root ❑ Confirm Attainment of
❑ ❑ Develop and Implement
❑ Validate Problem Statement ❑ Validate Measurement Causes on Key Outputs Project Goals
Pilot Solution
and Goals System Prioritize Root Causes ❑ Identify Project Replication
❑ ❑ Implement 5s Program
❑ Validate Financial Benefits ❑ Collect Baseline Data Statistical Analysis Opportunities
❑ ❑ Develop Full Scale
❑ Create Communication Plan ❑ Determine Process Complete Analyze Tollgate ❑ Training
❑ Implementation Plan
❑ Select and Launch Team Capability ❑ Complete Control Tollgate
❑ Cost/Benefit Analysis
❑ Develop Project Schedule ❑ Complete Measure ❑ Transition Project to Process
❑ Complete Improve Tollgate
❑ Complete Define Tollgate Tollgate Owner
❑ Project Charter ❑ Process Mapping ❑ Cause & Effect Matrix ❑ Process Flow ❑ Mistake-Proofing
❑ Voice of the Customer ❑ Data Collection Plan ❑ FMEA Improvement ❑ Standard Operating Procedures
❑ SIPOC Map ❑ Statistical Sampling ❑ Hypothesis Tests ❑ Design of Experiments (SOP’s)
❑ Project Valuation (ROI) ❑ Measurement System ❑ Simple & Multiple (DOE) ❑ Process Control Plans
❑ Stakeholder Analysis Analysis (MSA) Regression ❑ Solution Selection ❑ Visual Process Control Tools
❑ Communication Plan ❑ Gage R&R ❑ ANOVA Matrix ❑ Statistical Process Controls
❑ Effective Meeting Tools ❑ Control Charts ❑ Components of Variation ❑ Piloting (SPC)
❑ Timelines, Milestones, ❑ Histograms ❑ Pugh Matrix ❑ Visual Workplace
and Gantt Charting ❑ Normality Test ❑ Pull System ❑ Total Productive Maintenance
❑ Pareto Analysis ❑ Process Capability ❑ Metrics
Analysis ❑ Team Feedback Session
Tools
Measure Tollgate Questions
✓ Has a more detailed Process Map been completed to better understand the process and problem, and where in the
process the root causes might reside?
✓ Has the team conducted a process analysis, identifying areas where time and resources are devoted to tasks not critical
to the customer?
✓ Has the team identified the specific input (x), process (x), and output (y) measures needing to be collected for both
effectiveness and efficiency categories (i.e. Quality, Speed, and Cost measures)?
✓ Has an appropriate sample size and sampling frequency been established to ensure valid representation of the process
we’re measuring?
✓ Has the measurement system been checked for repeatability and reproducibility, potentially including training of data
collectors?
✓ Has the team developed and tested data collection forms or check sheets which are easy to use and provide consistent,
complete data?
✓ Has baseline performance and process capability been established? How large is the gap between current performance
and the customer (or project) requirements?
✓ Have key learning(s) to-date required any modification of the Project Charter? If so, have these changes been approved
by the Project Sponsor and the Key Stakeholders?
✓ Have any new risks to project success been identified, added to the Risk Mitigation Plan, and a mitigation strategy put in
place?
Note: With answers to these questions you are now ready to move to the Measure Phase.