Class 06
Class 06
Budget
Chapter 6
Learning Objectives
} Develop a GANTT chart.
} Develop a project network diagram using a technique called activity
on the node (AON).
} Identify a project’s critical path and explain why it must be
controlled and managed.
} Develop a PERT diagram.
} Describe the concept of precedence diagramming and identify finish-
to-start, start-to-start, finish-to-finish, and start-to-finish activity
relationships.
} Describe the concept of critical chain project management (CCPM).
} Describe the various types of costs that make up the project’s
budget.
} Define what is meant by the baseline project plan.
Schedule and Budget Development
A B C E
10 Days
A B C E 10
D
Buffers
5
Days 2.5
Days
6-22
Critical Chain Project Management
} And the critical path are similar
} The difference is the CCPM takes into account resource contention
} Takes a more project portfolio view
} Other projects should be scheduled so that a resource can be dedicated to a
particular task
} Requires that everyone understand that each project task has a 50% chance
of being completed as scheduled, so about half of the tasks will be late.
} This is the reason for having the project buffer.
} Instead of tracking each task individually, we become more concerned with the
project buffer –i.e., the project will be late only if it uses more than the allotted
project buffer.
} Instead of penalties for being late, bonuses or other incentives for
completing tasks early may be needed
Project Management Software Tools
} A number of project management software tools are
available to plan and track the progress of your project
} However, having a fundamental understanding of these
project management techniques is important to make the
most of these software tools
GANTT Chart in Microsoft Project ®
Network Diagram and Critical Path in Microsoft
Project ®
Developing the Project Budget
1. Define what resources will be needed to perform
the work
2. Determine the quantity of resources that are needed
3. Define the cost of using each resource
4. Calculate the cost of the task or activity
5. Ensure that the resources are leveled, that is, not
over allocated. An example of over allocation is
assigning a project team member to two tasks
scheduled at the same time.
Project Resources Assigned to Project Tasks in
Microsoft Project ®
Other Costs
} Direct Costs
} The direct cost of labor or other resources
} Indirect Costs
} The cost for covering such things as rent, utilities, insurance, etc.
} Sunk Costs
} Costs incurred prior to the project, such as a project that has been
restarted after a failed attempt
} Learning Curve
} Often have to “Build one and throw it away” to understand a problem
or a new technology
} Prorated Costs
} The idea that there is a cost associated with using a resource
} Reserves
} Contingency funds to be used at the discretion of the project manager
Finalizing the Project Schedule and Budget