First step
Assume that the project start date is 1-Jan-2023 and the finish date is 30-Dec-2023.
Second Step
On all days just subtract the finish date and start date, It will give you all the days without
any weekends or holidays.
This is the equation.
Third Step
Add the holidays of the year.
Final Step
The equation is “=NETWORKDAYS.INTL(Start date ,end date, (weekend),Holidays).
Choose the date under the start date and the date under the finish date then at the
weekend choose which days are your weekend, you have a variety to choose from, If it is
two days or one day only.
From 363 actual days starting from the start date till the finish date to 257 working days.
---------------
Useful links:
---------------
Keep in Touch:
WhatsApp: +201277767728
Email: [email protected]
Twitter: https://twitter.com/PlanningEEst
Instagram: https://www.instagram.com/planningengineerest/
TikTok: https://www.tiktok.com/@planningengineerest
---------------