PSP LAB Manual Updated
PSP LAB Manual Updated
AIM:
To create a IEEE 5 bus system in a concerned MATLAB, PSCAD, ETAP software and
inject various faults and analyse the Load flow parameters.
TOOLS REQUIRED:
❖ MATLAB
❖ PSCAD
❖ ETAP
THEORY:
With the advent of power systems, the Load Flow Analysis became an important
consideration for the purpose of power system extensions, analysis of system parameter
majorly with respect to various bus like Slack bus, PV voltage control bus & PQ Load bus.
The various algorithm pretends to Load flow analysis & solution are:
❖ Gauss-Seidel method
❖ Newton-Raphson method
Adaptive Newton Raphson method
Modified Newton Raphson method
❖ Fast decoupled method
PROCEDURE:
1. Design the IEEE 5 bus system
2. Transmission lines has updated with positive, negative and zero sequence equivalent
impedances.
3. The Load flow analysis has to be executed.
IN MATLAB:
a) Once the design of standard system is done in MATLAB / SIMULINK, open the
CONTINOUS POWERGUI block.
b) Click the Load Flow Analyser block
c) The system will show the result, only if it converges.
IN ETAP:
a) Once the design of standard system is done in ETAP OLV mode, Click the PQ flow
mode.
b) Once selected, Click the Load Flow icon to perform LFA.
c) In the report manager, Click and save the file format as per the need like PDF, Word,
Descriptive inbuilt etc.
IN PSCAD:
a) Once the system has been designed by using tools from Master main Library, connect
Multi-meters across varies buses needed to know the P-Q-V-Del parameters.
b) The multi-meter output signal has to be filled in and plotted out with various signal
names for all 5 buses.
INJECTING FAULT:
a) Once the design of standard IEEE 5 bus system has been done, now injecting fault is
almost uncertain and it pertains to user
b) The Fault contributes to various dip in voltage and rise in fault currents which keenly
depends on the fault type.
c) Therefore, in order to appreciate all understandings, go through all types of shunt faults
like LG, LLG, LL, LLL, LLLG faults.
AIM:
To understand the concept of relay coordination and its operation & relaying principles by
using small reference zone
[ Reference: YG PAINTHKAR pg.no 50/301 – Fundamentals of power system protection]
TOOLS REQUIRED:
❖ ETAP
THEORY:
When considering the power system, each equipment and section has been protected by
various relaying schemes. In order to avoid the maloperation between the circuit breakers i.e.)
of primary and backup protection confusions and to increase the system stability and reliability,
the concerned power system or the zone has to be coordinated successfully.
Therefore, the system has to be behaved like the primary protection has to be in prior with
the back protection. The coordination has also in need to consider the worst case i.e.) if the
primary protection fails, then sure the secondary / backup protection should ignite relaying and
isolate the faulty system as soon as specified to operate. So that, the equipment remains to be
protected and system stability is reliable one.
EXAMPLE SYSTEM:
[ Ref: Fundamentals of Power system protection – YG PAINTHKAR – 1st edition – Pg.no 50 / 301 ]
As mentioned in the Ref., the problem statement and details will be appended in the
document last pages of appendix which is understood through a small 3 bus example of
protective relaying principles. In this example, we have to appreciate both the following:
a) Secondary / backup protection should not execute the protective relaying in prior to the
primary protection relaying scheme.
b) If primary protection fails i.e. due to sensor CT faults or any other physical damage
errors, then the secondary protection should operate without giving option for the failure
of particular equipment.
PROCEDURE:
1. Design the basic 3 bus system ( As mentioned in the Reference problem statement )
2. Operate for various loading considerations and
3. Run the Load Flow Analysis program first
4. Run the short circuit studies mode in ETAP to ruin over the data of CT heavy duty
burdens, CB insulation selections and percentage error of CT through this analysis.
5. Once these study cases are done, then the relaying characteristics are interruption
between the relaying principle, the STAR PROTECTION will ruin the cases
6. The curves should not allow to overlap, to avoid the maloperation of breakers and
confusion over operation of primary & backup protections.
AIM:
To apply the principle of MHO relaying for distance protection of overhead
transmission lines using PSCAD.
SOFTWARE REQUIRED:
PSCAD
THEORY:
When considering the protection of transmission lines, in specific we use the IMPEDANCE
RELAY, because when the distance is considerably large and system is a lumped one, then the
angle between voltage and current varies in a specified range. Thus the ratio of voltage to
current i.e. the Impedance is calculated and triggered to trip the circuit breaker.
MHO relay trips if the circuit touches the diameter of the MHO circle and penetrate into it.
Thus how it differentiates the region to be protected and also appreciates the unstable and
stable region of protection needed.
The system converts the phase sequence components into positive, negative and zero
sequence components which in turn used for forming the radius of the MHO circle. The FFT
filters used to split the phase and angles of the values. The Fault with various considerations
are observed here for the separation of LG, LL, LLG, LLLG faults and so to differentiate the
contribution of tripping of the CB’s. The MHO relay operates in a inversed manner i.e.
operating time for crucial fault like LLLG and LLL is lesser than the ordinary LG faults.
SMIB SYSTEM:
For the understanding and study case, a small SMIB feeding Infinite Bus is considered
where the transmission lines are varied to observe how the trip signal produced when there is
a change in the distance (length) of the transmission lines.
It includes LG fault and LL fault considerations, so that all the mentioned shunt faults gets
replicated in this system. The CB acts accordingly. The overall system designed and dedicated
for the Distance protection for transmission lines using MHO relay spilled in the PSCAD /
EMTDC platform is:
PROCEDURE:
FFT FILTERS:
LG FAULT IMPEDANCE CALCULATION:
Z1 = (0.11998*10-3+0.66475*10-3j)Ω/m
Z1 = (0.11998*+0.66475*j)Ω/Km
Z1 = (11.98+66.475j) For 100 Km transmission Line
Z1 = 67.549∟79.7688
Center = (4.799,26.59)
OUTPUT:
WHEN FAULT AT 39 KM:
AIM:
To simulate loss of synchronism or generator out of step by considering generator side faults
and power swings on power system side and design protection schemes.
APPARATUS REQUIRED:
MATLAB, MiCOM Relay.
THEORY:
Power system stability is the ability of an electric power system to regain a state of operating
equilibrium after being subjected to disturbances such as faults, load rejection, line switching, and loss
of excitation. Power systems are subjected to a wide range of small or larger disturbances during
operating conditions. Small changes in loading conditions occur continually. The power system must
adjust to these changing conditions and continue to operate satisfactorily and within the desired bounds
of voltage and frequency.
Under steady-state conditions, there is an equilibrium between the input mechanical torque and
the output electrical torque of each generator. All synchronous machines connected to the power
system operate at the same constant speed. The generator speed governors maintain the machine speed
close to its nominal value.
If the system is perturbed, this equilibrium is upset, resulting in acceleration or deceleration of
the rotors of the synchronous machines according to the laws of motion of a rotating body. If one
generator runs faster than another, the angular position of its rotor relative to that of the slower machine
will advance. The resulting angular difference transfers part of the load from the slow machine to the
faster machine, depending on the power-angle relationship. This tends to reduce the speed difference
and hence the angular separation. Beyond a certain limit, an increase in angular separation is
accompanied by a decrease in power transfer. This results into a further angular separation that leads
to instability caused by sustained torque imbalance.
Power system faults, line switching, generator disconnection, and the loss and application
of large blocks of load result in sudden changes of the electrical power, whereas the mechanical power
input to generators remains relatively constant. These major system disturbances cause severe
oscillations in machine rotor angles and severe swings in power flows. The time frame of interest in
transient stability is in the order of 3–5 seconds following a disturbance. Such disturbances result in
Loss of synchronism between one generator and the rest of the system, or between groups of
generators.
OUT OF STEP OPERATION OF AN ALTERNATOR:
Causes: – Loss of excitation with resulting asynchronous running
– Falling out of step with existing excitation intact, as a result of faults in the system
Due to Generator out of step operation, alternating mechanical stresses are impressed on
generator stators, rotors, shafts and coupling. Out of step operation starting with generator or part of
the system may spread to the other parts of the system and system may collapse.
Power swings can be classified as either stable or unstable. Basically, a relay which is expected
to issue trip decision on a fault should not pick up on a swing (either stable or unstable). When a power
swing is a consequence of stable disturbance, unwanted line tripping can aggravate disturbance and
lead to instability. On the other hand, when the power swing is a consequence of disturbance, classified
as unstable, then interconnected operation of the system is simply not possible.
OSD RELAY:
Total transfer impedance 𝑍𝑇 = 𝑍1𝑆 + 𝑍1𝑅 + 𝑍1𝐿 (6)
𝑍𝑇
𝑍𝑇
−1 2
𝐴𝑛𝑔 𝑅7 = 2 × tan ( 𝑅 ) (8)
1 𝑅7
Let the fastest unstable swing frequency be 𝑓𝑠𝑙𝑖p
(𝐴𝑛𝑔 𝑅6 −𝐴𝑛𝑔 𝑅7 )×𝑓𝑛𝑜𝑚
𝑂𝑆𝑇𝐷 = (9)
360×𝑓𝑠𝑙𝑖𝑝
SYSTEM MODEL:
Kundur two area system is most suitable test system for the study of out-of-step protection
because it consists of two areas which are connected by two weak tie lines. The electrical center of the
system lies on the tie line. If a fault occurs on one of the tielines, the power swing will be created with
swing center on the second tie-line. The out-of-step relay is implemented on this second tie line to
observe the system stability.
The test system contains four generators in two symmetrical areas connected by two tie lines.
Area 1 has the load of 967MW and generation of 1400MW. Area 2 has a load of 1767MW and
generation of 1463MW. Each tie line is carrying approximately 200MW.
WAVEFORMS:
Case 1: Three phase fault on bus 1 cleared after 0.2 second
Case 2: Three phase fault on bus 1 cleared after 0.22 second
No trip signals are issued for case I (stable power swing), whereas Trip signal is issued for case II
(unstable power swing).
Similar waveforms and observations can be made by fault injection at various locations to generate
different test cases and analyze corresponding power swings.
RESULT:
Thus, Out-of-step protection based on dual blinder protection scheme has been designed and
its operation has been verified with several test cases in Kundur two area system.
EX.NO: 05 NON-DIRECTIONAL OCR
AIM:
The design of digital non-directional over current relay and its performance on
MATLAB / SIMULINK.
TOOLS REQUIRED:
❖ MATLAB Simulink
THEORY:
In general, the inverse time characteristics of an over current relay can be expressed as in
terms of,
𝐾
𝑇= for I < Ix < ( Is/Ip )
𝐼𝑓−1
MEASURING Ipc :
AC current signal(I) of frequency ‘f’ entering the relay must first converted to a
representative dc value (peak/RMS) for comparison with the pre-set pick-up current of relay.
By measuring the slope at the zero crossing of the current signal, we get its peak value (Ic) as
mathematically given as,
2. Severe fault current setting (IS) is more than the initial starting current of the motor
(1000A peak). The relay RA has higher Is setting than that of relay RB.
3. Constant K is such selected that it does not cause false tripping during motor starting and
transient conditions.
The K and Ts setting of RA is kept greater than that of RB for proper relay coordination.
The circuit breaker contacts operating time is assumed zero here.
RELAY SETTING:
In this case, the relay RB will operate much quicker than the previous case because the
current is more and the relay follows inverse current-time characteristics. The operating time
of the relay can also be found by:
It indicating the relay performance during the fault current of 770A, which clearly shows
inverse characteristic as compared to previous case.
Case.2: For Fault current Ic = 770 Amps
Case 5: For fault current Ic=1350A (I S(RB) <IC<I S(RA)) with CBB failing to ‘open’.
In this case, relay RA will provide the backup protection. However since the level of fault current
falls in the inverse characteristic region of RA, therefore the time taken by it to operate will be given
by (rather than instantaneous)
Case.5: For fault current Ic=1350A (I S(RB) <IC<I S(RA)) with CBB failing to ‘open’.
Case 6: for fault current Ic=2000A (>IS) with CBB failing to ‘open’.
The relay RA will provide the backup protection and operate after 0.2 sec of fault, maintaining
coordination with relay RB. Fig. 15f indicating the relay’s instantaneous characteristic performance
during the severe fault current of 2000A.
Case.6: for fault current Ic=2000A (>IS) with CBB failing to ‘open’.
RESULT:
Thus, the modelling of Non-directional Overcurrent relay has been done and verified with
various cases successfully.
EX.NO: 6 DIFFERENTIAL PROTECTION OF
TRANSFORMER
AIM:
To simulate the differential protection of transformer using MATLAB
APPARATUS REQUIRED:
❖ MATLAB / SIMULINK
THEORY:
The differential protection scheme of the transformer is based on Merz Price's circulating
current principle. For the protection of 3 phase delta-delta connected power transformer against
phase to phase and phase to ground fault. CTs on the two sides of the power transformers are
connected in star. This arrangement compensates phase difference between transformer
primary and secondary winding.
• Differential relay actuates when the phase difference of two or more similar electrical
quantity exceeds a predetermined value.
• The differential relay operates only for internal faults.
The principle of such protection is the comparison of the currents entering and leaving the ends
of a Transformer.
The vector difference of current (I1-I2) passes through the operating coil and the average
current (I1+I2)/2 flows through the restraining coil.
In normal operating conditions, the two currents at two ends of the transformer are equal and
balance. No current flows through the operating coil and hence operating coil remains
Inoperative , but when an internal fault occurs in the transformer like phase to phase fault or
phase to ground. The differential current passes through the operating coil due to which the
differential protection relay operates and it trips the circuit breaker.
1
CIRCUIT DIAGRAM
2
SIMULATION OF DIFFERENTIAL PROTECTION OF
TRANSFORMER
3
SIMULATION RESULTS
4
RESULT:
Thus, the differential protection of transformer was simulated and
analysed using MATLAB
5
6
EX NO. 9
DATE: HARDWARE-IN-LOOP SIMULATION WITH GENERATOR
PROTECTION RELAY
AIM
To verify relay tripping characteristics for generation protection using MiCOM P343 and omicron
relay testing kit CMC 356.
REQUIRED EQUIPMENT
PRECAUTION
Please ensure ground terminal is connected proper at earth point in rear side of Test kit (CMC 356)
And Constant AC supply (230V AC).
THEORY
Each relay includes an extensive range of control and data gathering functions to provide a
completely integrated system of protection, control, instrumentation, data logging, fault, event and
disturbance recording. The relays have a user – friendly display with 7 push buttons, which allow
menu navigation and setting changes. Also, by utilizing the either the front or rear serial ports of the
relay, functions can be read, reset and changed on demand from a local or remote personal computer
loaded with the MiCOM S1 software.
The CMC 356 is the universal solution for testing all generations and types of protection relays.
Its powerful six current sources (three-phase mode: up to 64 A / 860 VA per channel) with a great
dynamic range, make the unit capable of testing even high-burden electromechanical relays with very
high power demands. The CMC 356 is the first choice for applications requiring the highest versatility,
amplitude and power. Commissioning engineers will particularly appreciate its ability to perform wiring
and plausibility checks of current transformers, by using primary injection of high currents from the
test set.
The P342 and P343 relays provide extensive protection for generators from a few hundred
kilowatts to several hundred mega-watts.
Front plate Familiarization
The front plate of the relay includes the following,
16-character by 2-line alphanumeric liquid crystal display (LCD)
7-key keypad comprising 4 arrow keys, an enter key, a clear key, and a read key.
1
12 LEDs; 4 fixed function LEDs on the left hand side of the front panel and 8 programmable
function LEDs on the right hand side.
Battery compartment to hold the ½ AA size battery which is used for memory backup for the real
time clock, event, fault and disturbance records.
A 9-pin female D-type front port for communicating with a PC locally to the relay (up to 15m
distance) via an EIA(RS)232 serial data connection.
A 25-pin female D-type port providing internal signal monitoring and high speed local downloading
of software and language text via a parallel data connection.
Trip LED (red) - This indicates that the relay has issued a trip signal. It is reset when the associated fault
record is cleared from the front display. (Alternatively the trip LED can be configured to be self –resetting)*.
The trip LED is initiated from relay 3, the protection trip contact.
Alarm LED (yellow) - Flashes to indicate that the relay has registered an alarm. This may be triggered by a
fault, event or maintenance record. The LED will flash until the alarms have been accepted (read), after
which the LED will change to constant illumination, and will extinguish when the alarms have been cleared.
Out of service (Yellow) - indicates the relay protection is unavailable.
Healthy (Green) - indicates that the relay is in correct working order, and should be on at all times. It will
be extinguished if the relay’s self-test facilities indicate that there is an error with the relay’s hardware or
software. The state of the healthy LED is reflected by the watchdog contact at the back of the relay.
2
Loss of the excitation causes the internal emf to collapse and the reduction of active power output.
Under this condition the generator can over-speed and draw reactive power from the system. The difference
in speed between the rotor and the system causes low frequency currents to flow in the rotor circuit, which
may result in damage to the machine depending upon its construction. The P342 and P343 utilises a mho
characteristic to detect this condition and disconnect the machine if appropriate.
Connect AUX DC supply from CMC365 to J Slot terminals ( J2 +ve & J1-Ve)
and BINARY ANALOG INPUT to H slot – Output contacts ( H1 & H2) terminals of
the relay as shown below.
Check that the power supply is set at the appropriate auxiliary voltage, see under top
flap for auxiliary voltage range.
Connect VOLTAGE OUTPUT & CURRENT OUTPUT A & B to voltage and current
terminal of relay kit indicated by V , A in the Relay’s slot C & E. ( Slot – C for
Neutral side of Generator CT’s & Slot-E for Phase side of Generator CT’s).
Plug in the serial connection leads between the computer and the 9 pin port on the front of
the MiCOM relay.
Switch on the auxiliary power supply
The relay will now run through a self – check and perform an SRAM check. After the
relay has finished its internal checks it will have the following message: Description
MiCOM P343
3
2) Transplay Module
o In order to playback the COMTRADE file simulated from modeling of the power
system/equipment by using software like PS-CAD, we have option via “Transplay
Module” in the test kit , so that the simulation can be verified with relays protection
functionality checking.
o Click “TransPlay module” to open as below,
o Select TransPlay add the required COMTRADE file which need to playback via
test kit to relay by clicking add to listselect the file set the values of voltage,
current and transformation ratio on comtrade import window.
o Click the file name on test view window to see the waveform to be injected &
ensure all quantities are configured in secondary side only. This step is carried out
ensure the limit the voltages and currents to be transplayed. The same can be
viewed by using WaveWin tool in MiCOM S1 Agile software of MiCOM P343.
1. Locate the CONFIGURATION column and then enable “Field Failure”. Ensure that all other
protection functions are disabled in this column.
2. Locate the GROUP 1 FIELD FAIL column and then apply the settings for Status, Alarm, Angle
etc. The operation of Field Failure alarm/start/trip signals can be shown in the Test Port Status cell
in the Commission Test menu.
3. Apply the following voltage and current: Va = 100V<0°, Ia = 0.25A<+90°. The applied
impedance is at position “A” of the polar diagram.
4. Increase the current until the relay operates. This should occur at roughly 0.42A (100V/(220+20))
and indicates that we are now at the outer edge of the circle – point “B” (Xa1+Xb1).
5. Increase the current to 0.5A. The relay should be operating strongly as the relay impedance is now
at point C.
4
figure: Micom P343
6. Rotate the phase angle of the current anti-clockwise until the relay drops off and it is possible to
reset it. Slowly rotate the current phase angle clockwise until the relay just operates again. Record
the phase angle between the current and voltage (Ɵ1 on the polar diagram).
7. Without changing the magnitude of the current and voltage, rotate the current phase angle
clockwise, passing through the operating area, until once again it is possible to reset the relay.
Slowly rotate the current phase angle anti-clockwise until the relay again just operates. Measure
the new angle, Ɵ2 on the polar diagram. The relay characteristic angle is the mean of the two
measured angles and should be roughly 0°.
8. Apply the following voltage and current: Va = 10V<0°, Ia = 1.0A<+90°. The applied impedance is
at position “D” of the polar diagram.
9. Slowly increase the voltage until the relay again just operates. This should occur at 20V
(20ohm/1Amp). The relay impedance is now at point “E”, thus proving that the characteristic has
the correct dimensions and position.
10. It can be observed that the relay trips when the trajectory falls inside the circle.
RESULT:
The relay tripping characteristics for Generator Protection during field failure was studied
successfully using MiCOM P343.