??? ???? - (Sheet 4 - Revision - Theoritical)
??? ???? - (Sheet 4 - Revision - Theoritical)
Revision-Theoretical
Transportation
Management
For the Fourth Year – Business Department
Contact us on :
Mr. AHMED ELHOMY: 01111729649
If you
0 | Registration – Mr. ELHOMY: need clarification
01111729649 -- For Qs on anyon any points:
point: 01008499765
01008499765 (Transportation Management -R)
Q1: Solve following transportation problem using NWC- minimum cost and Vogel method and then
answer the following questions: 1-7
To
A B C D Supply
From
1 8
2 3 5 1
2 10
7 3 4 6
3 4 1 7 2 20
Demand 6 8 9 15 38
1- According to northwest, cell A1 must contain __________.
a) 2 c) 6
b) 4 d) 15
To
A B C D Supply
From
1 -- -- 8
6 2 2 3 5 1 0
2
2 -- 7 -- 10
6 3 4 4 6 0
4
3 -- 2 20
4 1 5 7 15 0
15
6 8 9 15 38
Demand 0 0
0 6 5 0
2- According to northwest, the objective function would total__________.
a) 150 c) 117
b) 127 d) 116
Solution According to NWC the total cost for initial solution= 6×2 + 2×3 + 6×3 + 4×4 + 5×7 + 15×2 = $117
3- According to northwest, cell B3 must contain __________.
a) 2 c) 15
b) 4 d) Zero.
4- According to minimum cost Cell method, cell A1 must contain __________.
a. 6 b. 4 c. Zero d.9
To
A B C D Supply
From
1 -- -- -- 8
2 3 5 8 1
0
2 7 -- -- 10
1 3 9 4 6 0 1
3 -- 20 5
5 4 8 1 7 7 2
12 0
6 8 9 15 38
Demand 0 1 0 0 7 0
According to MCM the total cost for initial solution=
8×1 + 1×7 + 9×4 + 5×4 + 8×1 + 7×2 = $93
5- According to minimum cost to Cell method, cell D3 must contain __________.
a) 8. c) 7.
b) 9. d) Zero.
6- The total cost of transportation according to the minimum cost method is__________ than the total
cost according to the Vogel Method.
a) Higher c) the same
b) lower
Solution
1 | Registration – Mr. ELHOMY: 01111729649 -- For Qs on any point: 01008499765 (Transportation Management -R)
To
A B C D Supply P1 P2 P3 P4 P5
From
1 2 3 5 11 8 0
5 -- -- 3 2-1=1 1 1 3 X=0
5
2 10 0
1 7 -- 3 9 4 -- 6 4-3=1 2 2 3 3
1
3 20
-- 4 8 1 -- 7 12 2 0 2-1=1 2 X=0 X=0 X=0
12
6 8 9 15 0
Demand 0 38
1 0 0 3
P1 4-2=2 3-1=2 5-4=1 2-1=1
P2 2 X=0 1 1
P3 5 X=0 1 5
P4 5 X=0 1 X=0
P5 X X=0 X X
Tie: P1
Penalty Least Cost
Column A 2 2
Column B 2 1 √√
Another Tie: P2
Penalty Least Cost Quantity
Column A 2 2 6 = واألقل آخدهD/S اقارن الـ
Row 2 2 4
Row 3 2 2 12 √√
Another Tie: P3
Penalty Least Cost
Column A 5 2
Column D 5 1 √√
➢ According to VAM the total cost for initial solution= 5×2 + 3×1 + 1×7 + 9×4 + 8 ×1 + 12×2 = $88
7- According to the Vogel method, cell D3 is __________than Cell D3 according to the minimum cost method.
a) Higher. c) the same.
b) lower.
Q2: Use the following cost matrix for transportation to solve questions from 1-10: NWC
To
A B C Supply
From
Plant1 10 35
5 10
Plant 2 20 30 40
20
Plant 3 40
𝔇𝔯.𝔈𝓜𝓸 𝟚𝟘𝟚4
5 8 12
Demand 45 50 20 115
Solution
To
A B C Supply
From
Plant1 35 -- -- 35
5 10 10
0
Plant 2 10 20 30 -- 40 0
30 20
30
Plant 3 -- 5 20 8 20 12 40 0
20
45 50 20 115
Demand 0 0
10 20 0
According to NWC the total cost for initial solution= 35×5 + 10×20 + 30×30 + 20×8 + 20×12 =$ 1,675
Testing the optimality:
Test the number of Occupied cells: R+C-1= 3+3-1 =5 = used cells So, we can test the optimality
21 | Registration – Mr. ELHOMY: 01111729649 -- For Qs on any point: 01008499765 (Transportation Management -R)
➢ Search unoccupied (unfilled Cells): 1B, 1C, 2C, 3A ^-^بدورعلى الخاليا الفاضية وجمعها
Unoccupied cell Closed path Net cost change
1B 1B→ 2B→ 2A→1A = +10 -30 +20 -5 = -5
1C 1C→ 1A→ 2A→2B→ 3B→3C = +10 -5 +20 -30 +8 -12 = -9
2C 2C→ 3C→ 3B→ 2B = +20 -12 +8 -30 = -14
3A 3A→ 2A→2B→3B = +5 -20 +30 -8 = 7
1- Using the Northwest Corner Cell method. The number of units that will be assigned to cell 1A is:
a) 35 c) 45
b) 10 d) None of this.
2- Using the Northwest Corner Cell method. The number of units that will be assigned to cell 1B is:
a) 10 c) 0
b) 35 d) None of this.
3- Using the Northwest Corner Cell method. The number of units that will be assigned to cell 2A is:
a) 0 c) 20
b) 10 d) None of this
4- Using the Northwest Corner Cell method. The number of units that will be assigned to cell 3C is:
a) 20 c) 40
b) 12 d) None of these.
5- The initial feasible solution would be equal to__________.
a) $1,675 c) $775
b) $1,435 d) None of these. 𝔇𝔯.𝔈𝓜𝓸 𝟚𝟘𝟚4
6- In Testing the optimality of the initial feasible solution, the improvement index of cell 1B will be equal:
a) It will not be tested. It's an occupied cell. c) -9
b) -5 d) None of these.
7- In Testing the optimality of the initial feasible solution, the improvement index of cell 2B will be equal:
a) It will not be tested. It's an occupied cell. c) 7
b) -5 d) None of these.
8- In Testing the optimality of the initial feasible solution, the improvement index of cell 1C will be equal:
a) It will not be tested. It's an occupied cell. c) -9
b) -5 d) None of these.
9- In Testing the optimality of the initial feasible solution, the improvement index of cell 2C will be equal:
a) It will not be tested. It's an occupied cell. c) -14
b) -5 d) None of these.
10- After testing the optimality of the initial feasible solution, it was found that:
a) The initial feasible, Is the optimal solution.
b) The initial feasible, is not optimal, and it can be reduced by assigning units to cell 2C.
c) The initial feasible, is not optimal, and it can be reduced by assigning units to cell 1C.
d) The initial feasible, is not optimal, and it can be reduced by assigning units to cell 3A.
Q3: Consider the following transportation tableau which shows
the initial solution. Evaluate the cost of allocating units to cell DR.
A) -5
B) -2
C) 0
D) 3
E) 5
Solution:
Unoccupied cell Closed path Net cost change
DR DR→ DT→ BT → BS→AS→ AR = +0 -0 +5 -1 +2 -1 = 5
13 | Registration – Mr. ELHOMY: 01111729649 -- For Qs on any point: 01008499765 (Transportation Management -R)
Q4:North-West:
Total Cost- NWC = 6(450) + 8(50) + 9(300) + 7(80) + 10(340) + 0(50) ='9760,
Answer the following:
1. Units shipped from warehouse 2 to market 3 is .....Zero...
2. Market 3 will receive .....340............ Units. ) النه مش حقيقي اصالDummy (الماركت مش هيستقبل من ال
3. How many units are shipped from warehouse W1 to market M2? (50 units(.
4. What is the total number of units shipped from warehouse W3? (420 units.
5. Which market received the smallest number of units? (Market M2 (received 430 units).
6. Which warehouse shipped the largest number of units? Warehouse W1 (shipped 500 units).
7. What is the total shipping cost from warehouse W3 to market M3? (10×340=3400)
8. If 20 additional units are added to the demand of market M1, how will this affect the table?
Answer: The table would need adjustments to redistribute the shipments accordingly
Q6:Minimum Cost:
𝔇𝔯.𝔈𝓜𝓸 𝟚𝟘𝟚4
41 | Registration – Mr. ELHOMY: 01111729649 -- For Qs on any point: 01008499765 (Transportation Management -R)
Q7:Vogel Method:
To
W X Y Z Supply
From
Source 1 15 23 16 22 25,000
Source 2 25 14 4 11 13,000
Source 3 12 19 7 17 23,500
Demand 17,500 23,000 9,500 11,500 61,500
Solution
To
W X Y Z Supply P1 P2 P3 P4 P5
From
Source 1 17,500 15 7,500 23 16 22 25,000
7,500 0 1 7 1 1 1
Source 2 25 14 9,500 4 3,500
13,000
11 7 3 3 X=0 X=0
3,500 0
Source 3 12 15,500 19 8,000
23,500 0
7 17 5 5 2 2 X
15,500
Demand 17,500 23,000 9,500 11,500 61,500
0 7,500 0 0 8,000 0
P1 3 5 3 6
P2 3 5 X=0 6
P3 X=0 5 X=0 6
P4 X=0 4 X=0 5
P5 X=0 4 X=0 X=0
The total initial cost for VAM =
= 17,500×15 + 7,500×23 + 9,500×4 + 3,500×11+ 15,500×19+ 8,000×17= $942,000
Answer the following:
1- The number of units that should be shipped from source 3 to Z is:
a. 15,500. d. 6,000.
b. 8,000. e. None of the above.
c. 23,500.
2- Demand Y will receive units from source 2:
a. 13,000 d. 1,500
b. 11,500 e.None of the above
c. 9,500
3- How many units are shipped from Source 1 to X: 𝔇𝔯.𝔈𝓜𝓸 𝟚𝟘𝟚4
a. 7,500 c. 25,000
b. 23,000 d. 9,500
4- What is the total number of units supplied by Source 2?
a. 11,500 c. 23,500
b. 13,000 d. 9,500
5- Which source supplies the largest number of units?
a. Source 1 c. Source 3
b. Source 2 d. None of the above
6- How many units are shipped from Source 3 to X?
a. 15,500 c. 7,500
b. 8,000 d. 9,500
7- Which destination (W, X, Y, Z) receives the smallest number of units?
a. W c. Y
b. X d. Z
52 | Registration – Mr. ELHOMY: 01111729649 -- For Qs on any point: 01008499765 (Transportation Management -R)
8- What is the total demand for destination Z?
a. 11,500 c. 23,000
b. 9,500 d. 17,500
9- What is the penalty cost for destination X during the first iteration of Vogel's method?
a. 4 c. 9
b. 5 d. 7
10- Which destination (W, X, Y, Z) will be selected first for allocation in Vogel's method?
a. W c. Y
b. X d. Z
11- After the first allocation using Vogel's method, how many units remain unallocated for Source 1?
a. 17,500 c. 25,000
b. 7,500 d. 10,000
12- What is the penalty cost for Source 2 in the second iteration?
a. 3 c. 7
b. 11 d. 4
13- Using Vogel's method, how many units will be allocated to destination Y from Source 3?
a. 15,500 c. 7,000
b. 9,500 d. None of the above
14- What is the total transportation cost after applying Vogel's method?
a. 120,000 c. 175,000
b. 150,000 d. None of the above
Q8:Stepping-stone:Which statement regarding this transportation table is best?
𝔇𝔯.𝔈𝓜𝓸 𝟚𝟘𝟚4
A. The solution is degenerate.
B. This solution can be improved by shipping from C to X.
C. This solution would be improved by shipping from B to W.
D. This solution was developed using the northwest corner rule.
Unoccupied cell Closed path Net cost change
BW BW→AW→AX→BX = +5 -3 +5 -4 = 3
CX CX→AX→AW→CW =+8 -5 +3 -10 = -4
Q9:In the following transportation matrix,What is the reduced cost if we decide to allocate to cell 2C?
16 | Registration – Mr. ELHOMY: 01111729649 -- For Qs on any point: 01008499765 (Transportation Management -R)
Q10: on Vogel & Stepping-stone:
To
D1 D2 D3 Supply
From
S1 500
6 8 8
S2 300
7 9 5
S3 520 1320
11 7 10
70 | Registration – Mr. ELHOMY: 01111729649 -- For Qs on any point: )01008499765 (Transportation Management -R
Unoccupied cell Closed path Net cost change
S1 D2 S1D2→ S1D3→ S3D3→ S3D2 = +8 -8 +10 -7 = 3
S1 D4 S1D4→ S3D4→ S3D3→ S1D3 = +0 -0 +10 -8 = 2
S2 D1 S2D1→ S2D3→ S1D3→ S1D1 = +7 -5 +8 -6 = 4
S2 D2 S2D2→ S3D2→ S3D3 → S2D3 = +9 -7 +10 -5 = 7
S2 D4 S2D4→ S3D4→ S3D3→ S2D3 = +0 -0 +10 -5 = 5
S3 D1 S3D1→ S1D1→ S1D3→ S3D3 = +11 -6 +8 -10 = 3
optimal Solution) فمفيش توزيع ينفع يحصل ثاني ويبقي انا وصلت للــ+ve( كلهم
Answer the following questions:
1. What is the total supply available from all sources (S1, S2, S3)?
A) 1320 C) 1325
B) 450 D) 1270
2. In the given table, what is the total demand from all destinations (D1, D2, D3)?
A) 1270 C) 1200
B) 1320 D) 1340
3. To obtain a balance between total supply and total demand in This in a transportation problem…..
A)Add Dummy Row by 50 units with 0 Costs. C) Add Dummy Column with 120 units with $1 Cost.
B)Add Dummy Column by 50 units with $ 0 Costs. D) Cancel Units Fron any Source
4. What is the demand quantity for D3?
A) 390 C) 430
B) 450 D) 50
5. What is the penalty cost for destination 2 during the first iteration of Vogel's method?
a. 4 c. 9
b. 1 d. 7
6. What is the penalty cost for Source 3 during the Fourth iteration of Vogel's method?
a. 4 c. 9
b. 3 d. 7
7. What is the supply quantity from source S1 to point D1?
A) 450 C) 430
B) 50 D) 300
8. Which source provides the highest total supply?
A) S1 C) S3
𝔇𝔯.𝔈𝓜𝓸 𝟚𝟘𝟚4
B) S2 D) S4
9. Using Vogel's method, how many units will be allocated to destination 2 from Source 3?
a. 430 c. 40
b. 450 d. None of the above
10. After the first allocation using Vogel's method, how many units remain unallocated for Source 1?
a. 470 c. 500
b. 430 d. 450
11. What is the Optimal Solution Cost to this transportation problem?
A)$8,010 C)7,500
B)8,200 D)8100
Q11: on Stepping-stone: test The optimality of The Following Table
To
A B C Supply
From
1 150
6 25 8 125 10
2 175
7 11 175 11
3 4 5 275
200 75 12
Demand 200 100 300 600
➢ The total cost for initial solution= 25×8+ 125×10 + 175×11 + 200×4 + 75×5= $ 4,550
81 | Registration – Mr. ELHOMY: 01111729649 -- For Qs on any point: 01008499765 (Transportation Management -R)
First Test the number of Occupied cells: R+C-1= 3+3-1 =5= used cells So, we can test the optimality
➢ Search unoccupied (unfilled Cells): 1A, 2A, 2B, 3C ^-^بدورعلى الخاليا الفاضية وجمعها
Unoccupied cell Closed path Net cost change
1A 1A→ 1B→ 3B→3A = +6 -8 +5 -4= -1 √√
2A 2A→ 3A→ 3B→ 1B→ 1C→ 2C = +7 -4 +5 -8 +10 -11 = -1
2B 2B→ 2C→ 1C→ 1B = +11 -11 +10 -8= +2
3C 3C→ 3B→ 1B→1C = +12 -5 +8 -10 =5
بس$ 1 مش بـ$4 بـT.C النها هتقلل الــ-4 هختار أكيد-4 و-1 فهاخد أي واحدة لكن مثال لو عندى-1 هنا انا كان عندى األثنين
To A B
^-^ هنعمل ايه بقا
From
-200 و-25 يعني هنا عندنا،)-Ve( مين الــLoop هنشوف جوه الــ
1 25 25
(+) 6 (-) 0
8 -: ونعمل ايه بقا ركز معايا25 ناخد اآلقل اللى هى
2 25 ) هننقص منه-( واللى قدامه25 ( هنضيفله الــ+) اللي عنده اشارة
7 11
.وده هيبقي التوزيع بتاعنا الجديد
3 200
(-) 175 4 (+)10075 5
To
A B C Supply
From
1 150
25 6 8 125 10
2 175
7 11 175 11
3 4 5 275
175 100 12
600
Demand 200 100 300
➢ The total cost = 25×6+ 125×10 + 175×11 + 175×4 + 100×5= $ 4,525
➢ Test again to make sure that $4,525 is the optimal solution:
Unoccupied cell Closed path Net cost change
1B 1B→ 3B→ 3A→1A = +8 -5 +4 -6 = 1
2A 2A→ 1A→ 1C→ 2C = +7 -6 +10 -11 =0
2B 2B→ 3B→ 3A→1A→1C→2C = +11 -5 +4 -6 +10 -11 = 3
3C 3C→ 1C→ 1A→ 3A +12 -10 +6 -4 = 4
optimal Solution) فمفيش توزيع ينفع يحصل ثاني ويبقي انا وصلت للــ+ve( كلهم
Q12:Consider the following transportation tableau with the initial solution provided. Use the stepping
stone method to identify a better allocation.
➢ The Total Initial Cost = 80×1 + 20×2 + 100×1+ 10×5 + 50×0= $ 270
Solution
91 | Registration – Mr. ELHOMY: 01111729649 -- For Qs on any point: 01008499765 (Transportation Management -R)
First Test the number of Occupied cells: R+C-1= 3+3-1 =5= used cells So, we can test the optimality
Unoccupied cell Net cost change
AT = +3 -5+1 -2 = -3
BR = +4 -1 +2 -1 = 4
DR = +0 -1 +2 -1 +5 -0 = 5
DS =+0-1+5-0=4
(-) (+) 10 10 ناخد اآلقل اللى هى-20 و-10 يعني هنا عندنا،)-Ve( مين الــLoop هنشوف جوه الــ
10 وده هيبقي التوزيع بتاعنا25 ) هننقص منه-( واللى قدامه10 ( هنضيفله الــ+) اللي عنده اشارة
(+) (-) .الجديد
110 0
➢ The Total Cost after Re-allocation = 80×1 + 10×2 +10×3 +110×1+ 50×0= $ 240
Example 13 (NWC): D ≠S𝔈𝓜𝓸 𝟚𝟘𝟚𝟜
To
M1 M2 M3 Supply
From
F1 500
6 8 8
F2 300 1220
7 9 5
F3 11 7 10 420
To
From 1 2 3
A $7 $10 $5
B 12 9 4
C 7 3 11
D 9 5 7
Solution
The Transportation Tableau:
To
1 2 3 Supply
From
A 10 5 90
7
B 50
12 9 4 280
C 7 3 11 80
D 60
9 5 7
A)-12.
B) -9.
C) -6.
D) -2.
E) +3.
6. A transportation table contains an optimal solution when all the empty cell evaluations are
A) positive or 0 . C) positive .
B) negative or 0. D) negative.
7. A transportation table that has a cell evaluation of 0 means that
A) the table is optimal C) supply and demand are equal
B) an equivalent alternative solution exists D) the solution is not optimal.
10. The initial solution of a transportation problem can be obtained by applying any known method. However, the only condition
is that
A. the solution be optimal C. the solution not be degenerate
B. the rim conditions are satisfied D. all the above
11. An initial transportation solution appears in the table.
𝔇𝔯.𝔈𝓜𝓸 𝟚𝟘𝟚4
Can this solution be improved if it costs $5 per unit to ship from A to C; $7 per unit to ship
from A to D; $8 to ship from B to C; and $9 to ship from B to D?
A. Yes, this solution can be improved by $50.
B. Yes, this solution can be improved by $100.
C. No, this solution is optimal.
D. Yes, the initial solution can be improved by $10.
12. When the total supply is not equal to total demand in a transportation problem then it is called
(a) Balanced (e) Degenerate
(b) Unbalanced (d) None of these
13. With the transportation technique, the initial solution can be generated in any fashion one chooses. The only restriction is that
A. the edge constraints for supply and demand are satisfied.
B. the solution is not degenerate.
C. the solution must be optimal.
D. one must use the northwest-corner method.
14. The purpose of a dummy source or dummy destination in a transportation problem is to
A. prevent the solution from becoming degenerate.
B. obtain a balance between total supply and total demand.
C. make certain that the total cost does not exceed some specified figure.
D. provide a means of representing a dummy problem.
15. Which of the following is NOT needed to use the transportation model?
A. the cost of shipping one unit from each origin to each destination
B. the destination points and the demand per period at each
C. the origin points and the capacity or supply per period at each
D. degeneracy
16. In a transportation problem, we must make the number of __________ and__________ equal.
A. destinations; sources D. positive cost coefficients; negative cost coefficients
B. units supplied; units demanded E. warehouses; suppliers
C. columns; rows
1 | Registration – Mr. ELHOMY: 01111729649 -- For Qs on any point:
14 01008499765 (Transportation Management -R)
17. _________ or __________ are used to "balance" an assignment or transportation problem.
A. Destinations; sources D. Large cost coefficients; small cost coefficients
B. Units supplied; units demanded E. Artificial cells; degenerate cells
C. Dummy rows; dummy columns
18. The North-West Corner Method is used to:
a) Minimize transportation costs c) Test for optimality
b) Provide an initial feasible solution d) None of the above
19. Which cell is chosen first in the North-West Corner Method?
a) Cell with the highest cost c) Top-left corner of the cost matrix
b) Cell with the lowest cost d) Bottom-right corner of the cost matrix
20. What is the main limitation of the North-West Corner Method?
a) It always provides the optimal solution c) It is computationally expensive
b) It doesn’t account for costs d) It cannot handle unbalanced problem
21. The Minimum Cost Method focuses on:
a) Assigning maximum supply to any cell c) Assigning supply to the cell with the least cost
b) Allocating demand based on the highest cost cell d) None of the above
22. In the Minimum Cost Method, what happens after assigning supply to the least cost cell?
a) The row or column is deleted c) The supply and demand are updated
b) The cell cost is increased d) None of the above
23. What is the main advantage of the Minimum Cost Method over the North-West Corner Method?
a) Easier to compute c) Guarantees optimality
b) Results in lower transportation costs d) Requires fewer iterations
24. What does Vogel's Approximation Method aim to minimize?
a) Total transportation time c) Number of iterations
b) Total transportation cost d) Total supply
25. In VAM, how is the penalty cost calculated?
a) Difference between the two lowest costs in a row/column
b) Difference between the highest and lowest costs in a row/column
c) Average of all costs in a row/column
d) Sum of all costs in a row/column
26. What happens after the penalties are calculated in VAM?
a) The highest penalty is chosen, and allocation is made in that row or column 𝔇𝔯.𝔈𝓜𝓸 𝟚𝟘𝟚4
b) The row with the highest total supply is chosen
c) The column with the lowest cost is chosen
d) None of the above
27. The Stepping Stone Method is used to:
a) Calculate initial feasible solutions c) Allocate supply to the least cost cell
b) Check if the current solution is optimal d) Calculate penalties for VAM
28. In the Stepping Stone Method, a closed loop is formed to:
a) Test for optimality by calculating opportunity costs
b) Allocate supply to the highest cost cell
c) Update supply and demand
d) Eliminate unbalanced conditions
Answer: a
29. If all opportunity costs in the Stepping Stone Method are non-negative, the solution is:
a) Infeasible
b) Optimal
c) Degenerate
d) None of the above
Answer: b
30. Which of the following is NOT a step in the Stepping Stone Method?
a) Calculate opportunity cost
b) Form a closed loop
c) Select the highest opportunity cost
d) Calculate penalties for each cell
Answer: d
The concept of Supply Chain Management (SCM) is based on two core ideas:
1) every product that reaches an end user represents the cumulative effort of multiple organizations. These
organizations are referred to collectively as the supply chain.
2) supply chains have existed for a long time, most organizations have only paid attention to what was
happening within their “four walls.” Few businesses understood, much less managed, the entire chain of
activities that ultimately delivered products to the final customer. The result was disjointed and often
ineffective supply chains.
The organizations that make up the supply chain are “linked” together through physical flows and
information flows.
• Physical Flows:
Physical flows involve the transformation, movement, and storage of goods and materials. They are the
most visible piece of the supply chain. But just as important are information flows.
• Information Flows:
Information flows allow the various supply chain partners to coordinate their long-term plans, and to
control the day-to-day flow of goods and materials up and down the supply chain.
Q2: What is the meaning of Supply chain strategy?
• Supply chain strategy is an iterative process that evaluates the compromise between costs and benefits
of operational components; it also defines the combination of activities and functions within the value
chain.
• Business strategy involves leveraging the core competencies of the organization to achieve a defined high-
level goal or objective. It also includes the analytic and decision-making process surrounding what to offer
(e.g., products and services), when to offer (timing, business cycles, etc .), and where to offer (e.g., markets
and segments) as a competitive plan.
كما تتضمن أيضًا عملية التحليل واتخاذ القرار المحيطة بما يجب تقديمه.تنطوي على االستفادة من الكفاءات األساسية للمنظمة لتحقيق هدف أو هدف محدد رفيع المستوى
األسواق والقطاعات) كخطة، ومكان العرض (على سبيل المثال،) وما إلى ذلك، ودورات األعمال، ومتى يتم العرض (التوقيت،) المنتجات والخدمات،(على سبيل المثال
.تنافسية
Q3: What are the objectives of supply chain management?
• Supply Chain Management becomes a tool to help accomplish. corporate strategic objectives:
- Reducing working capital.
- Taking assets off the balance sheet.
- Accelerating cash-to- cash cycles.
- Increasing inventory turns and do on.
21
1 | Registration – Mr. ELHOMY: 01111729649 -- For Qs on any point: 01008499765 (Transportation Management -R)
Chapter 5: Issues in Supply chain Management:
Q1: what are the Characteristics of the logistics information system? 𝔇𝔯.𝔈𝓜𝓸 𝟚𝟘𝟚4
Logistics management: is connected with acquisition, collection, processing, and transmission of large amounts
of information. Meeting the information demand of the management functions requires that an information
system be created, which would provide continuous access to timely, accurate and truthful information.
From the perspective of logistics, the basic benefits of implementing information systems include:
- customer service improvement.
- increasing the atmosphere of trust and confidence through good communication within the logistics chain.
- The possibility to use electronic signatures.
- stock levels reduction.
- synchronization of supply, production, and distribution processes.تزامن عمليات التوريد واإلنتاج والتوزيع
- the capacity to produce to order - as opposed to "to stock" production.
- the reduction of possible downtime caused by shortage of materials for production.
- cost levels reduction.
- improvement of delivery timeliness, lessening probable errors made in orders.
- reduction of the number of documents in circulation.
Logistics information systems, is a guarantee of business performance improvement, which manifests itself in:
- operations speed improvement. - the quality of customer service,
- production quality improvement.
- cost reduction, and thereby higher competitiveness in the market.
Q2: What are the significant sources of information that are the reports of the logistics system?
First: the new market environment which is created by access to a global network.
Second: the market space convergence resulting from the absence of geographic isolation of companies and economies.
Third: the new technologies that enable people and organizations to interact in a network environment.
Fourth: the convergence of infrastructure consisting of a combination of different technologies for distribution of data
-
and information.
Fifth: the convergence of processes involving
Sixth: the convergence of products that may exist in various forms of physical and electronic formats, depending on the
level of relevance to the consumer.
Q3: What are the most commonly used applications, systems and advisory services in Logistics?
- The make or buy issue.
- production planning, including the development of assortment planning,
- raw material supply planning, including the choice of supplier, supply forecasting.
- customer service, including identification of customers' needs and requirements.
- forecasting the demand, in terms of time and space.
- planning the deployment of storage bases, including determination of their size and number.
- warehouse management, including warehouse space planning, admissions, and releases scheduling.
- stock control, including the estimation of safe stock level.
- transport management/ transportation planning, including cargo distribution and complementation,
planning of removals (route-planning).
Q4: What are Logistics flows infrastructure?
➢ The implementation of logistics processes requires infrastructure, which should facilitate the efficient and
effective physical transfer of goods and services from the place of origin to the final destination.
➢ logistics infrastructure: The Dictionary of Logistics Terminology
- is a system of roads, waterways, airports, seaports and/or telecommunication networks located in a
given area.
- there are three components of logistics infrastructure:
• The linear component: the network existing in a given country, understood as every separate strip
of land, intended for transportation traffic or stopping-places.
• The point component: separate facilities for stationery cargo handling (discharge areas, stations,
yards and transshipment points, logistics centers).
• Communication infrastructure: the media, the data exchange standards and the measures to ensure
their flow.
1 | Registration – Mr. ELHOMY: 01111729649 -- For Qs on any point:
22 01008499765 (Transportation Management -R)
Q5: What are Logistics flows infrastructure?
➢ Definition of Logistics Costs: 𝔇𝔯.𝔈𝓜𝓸 𝟚𝟘𝟚4
- Logistics costs are the purposeful consumption of economic system resources, expressed in monetary
units.
- These costs result from the flow of material goods, supply, maintenance, and processing information
connected with logistics operations in the economic system and its supply chain.
➢ Scope of Logistics Costs:
- First Subsystem:
• Major burden in the cost structure.
• Directly connected with logistics processes (materials purchase, transportation, warehousing,
packaging).
• Related to maintaining necessary customer service standards.
- Second Subsystem:
• Costs arising from extraordinary events, losses, and the decrease of assets due to logistics operations.
• Caused by inadequate standards and quality of raw materials and products.
• Stemming from penalties and random factors, including crisis situations.
- Third Subsystem:
• Costs (tangible and intangible) of lost benefits.
• Result from inventory shortages due to unforeseen needs, such as emergency or crisis situations.
- Cognitive Aims of Analyzing Logistics Costs:
• Determine the relation of costs to basic types of logistics processes: physical and information flows,
inventory maintenance, transport, exploitation, etc.
• Understand costs in relation to the supply and materials flow.
• Examine the use of expenditure in specific decision-making situations.
• Explore the origin of costs and their use in Activity Based Costing (ABC).
➢ from the perspective of the most basic components of logistics processes divides them into three
groups:
• the costs of the physical flow of materials.
• The costs of the stocks.
The costs of information processes
Questions on chapter 1
1. is the active management of supply chain activities to maximize customer value and achieve a sustainable competitive
advantage
A. forecasting. C. planning.
B. supply chain D. Strategic management.
2. __________ Represents a conscious effort by the supply chain firms to develop and run supply chains in the most effective
and efficient ways possible.
a) forecasting. c) planning.
b) supply chain management. d) Strategic management.
3. __________ activities cover everything from product, development, sourcing production and logistics as well as information
system needed to coordinate these activities
a) forecasting. c) planning.
b) supply chain management. d) Strategic management.
4. __________ Is the management of network of all business processes and activities involving procurement of row materials
manufacturing and distribution management of finished the goods.
a) forecasting. c) planning.
b) supply chain. d) Strategic management.
5. __________ Is also called the art of management of providing the right product at the right time right place and the right
goes to the customer.
A. forecasting. C. planning.
B. supply chain. D. Strategic management.
6. The concept of supply chain management is based on:
a) Every product that reaches an end user represents the commutative effort of multiple organizations.
27
1 | Registration – Mr. ELHOMY: 01111729649 -- For Qs on any point: 01008499765 (Transportation Management -R)
Questions on chapter 4
1- the management information systems are allowed for:
a. The use of any branch systems & data sources.
b. Making available reports to selected users according to the policy adopted. 𝔇𝔯.𝔈𝓜𝓸 𝟚𝟘𝟚4
c. preparation of reports & analysis ad hoc.
d. all of them.
2- The management information systems are allowed for:
a. Making available reports to selected users according to the policy adopted.
b. Automatic refreshing of reports & making the reports available.
c. sharing the central data repository through a corporate for portal.
d. all of them.
3- In TS & __________ that decision situation has been defined in the information database & the models of the decision-making
process (if they occur) are a permanent element of the user's software.
a) transaction systems.
b) The management information system MIS
c) Decision support systems
d) Knowledge management.
4- __________ is mostly used to solve non structured or poorly structured problems.
a) transaction systems. c) Decision support systems.
b) The management information system MIS. d) Knowledge management.
5- __________ supports the reasoning process whilst not eliminating it & makes decisions more efficient & not just quicker.
a) transaction systems. c) Decision support systems.
b) The management information system MIS. d) Knowledge management.
6- The computerized __________ allows the decision maker to use the data & models in order to recognize, underst& &
formulate the problem
a. transaction systems. c. Decision support systems.
b. The management information system MIS. d. Knowledge management.
7- __________ supports creating solution projects, enables multi-dimensional forecasts & analysis of their efficiency.
a. transaction systems. c. Decision support systems.
b. The management information system MIS. d. Knowledge management.
8- The basic functions of decision support system include:
a) data bases management. c) analysis & structurization of the model.
b) presenting results — in the right form. d) all of them
9- The basic functions of decision support system include:
a) construction of the model of mathematical solutions to the problem.
b) statistical techniques & models. d) all of them.
c) forecasting & simulation models.
10- __________ allow the managers to gain a wider perspective on the problem & enable simulation of effects of different variants
of the decision & the impact of various situation development scenarios in the company's surroundings on the effects achieved
through the decisions Made.
a) transaction systems. c) Decision support systems.
b) The management information system MIS. d) Knowledge management
11- __________ are characterized by Separating the base of decision models from the user's software, the possibility of simulating
decision Situations, the possibility of analyzing the model selection process & generating justifications for the executed
process.
a) transaction systems. c) Decision support systems.
b) The management information system MIS. d) Knowledge management.
12- __________ Supported by: computers through the systems of physical facilities design support & those based on the so-
called artificial intelligence.
a) transaction systems. c) Decision support systems.
b) The management information system MIS. d) Knowledge management.
13- The main objective of a __________ making the flows between the supplier & the recipient more efficient. It is achieved by
optimization of the supplies needed for production.
a) transaction systems. c) Decision support systems.
b) Material requirements planning system. d) Knowledge management.
24- Most important functions in planning MRP II production resources are performed
a) MRP - material requirements planning. c) Both of them.
b) CRP - capacity requirements planning. d) none of them.
25- In order to plan the material requirements well, you need to introduce the following into the data base:
a) Forecast of the ready goods sales.
b) Number of components, raw materials & materials falling on one unit of sale of the ready good.
c) Dates of supply of components, raw materials, & materials.
d) All of them.
26- In order to plan the material requirements well, you need to introduce the following into the data base:
a) The length of the production cycle of the ready good.
b) Warehouse state of the ready goods, components, raw materials, & materials