Class Session 2 10 September 2023
Class Session 2 10 September 2023
1-1
PGDBM: Advanced Project
Management
Kenneth Ngwenya,
[email protected]
Session 2: 10 September 2023
Module Unit Content:
FIGURE 4.3
Project Time/Schedule Management
• Project Time Management includes the processes required to
manage the timely completion of the project (Project Management
Institute, 2017:24). Once the project scope has been defined and
the WBS derived to the work package level, the next step is to
derive the project schedule.
• The schedule will define how the project will achieve its objectives in
the time frame required. Sometimes the required time frame has to
be adjusted based on the resources available or resources needs to
be adjusted based on the time frame required.
Project Management
THE MANAGERIAL PROCESS
Clifford F. Gray
Eric W. Larson
• Terminology
–Activity: an element of the A
project that requires time.
–Merge Activity: an activity that
has two or more preceding B D
activities on which it depends.
–Parallel (Concurrent) Activities:
Activities that can occur C
independently and, if desired,
not at the same time.
6–12
Constructing a Project Network (cont’d)
• Terminology
–Path: a sequence of connected, dependent activities.
–Critical path: the longest path through the activity
network that allows for the completion of all project-
related activities; the shortest expected time in which
the entire project can be completed. Delays on the
critical path will delay completion of the entire project.
A B D
6–14
Activity-on-Node Fundamentals
FIGURE 6.2
6–15
Activity-on-Node Fundamentals (cont’d)
6–17
Project Management
THE MANAGERIAL PROCESS
Clifford F. Gray
Eric W. Larson
19
The risk event graph
20
The Risk
Management
Process
Managing risk
◼ Step 1: Risk identification
Generate a list of possible risks through brainstorming, problem
identification and risk profiling.
◼ Macro risks first, then specific events
◼ Step 2: Risk assessment
Scenario analysis
Risk assessment matrix
Failure Mode and Effects Analysis (FMEA)
Probability analysis
◼ Decision trees, NPV, and PERT
Semiquantitative scenario analysis
Risk severity matrix
User Interface
4 backlash problems
Likelihood
System
2 freezing
Hardware
1 malfunct- Green zone (minor risk)
ion
1 2 3 4 5
Impact
23
Managing risk (cont’d)
◼ Step 3: risk response development
Mitigating risk
◼ Reducing the likelihood an adverse event will occur
◼ Reducing impact of adverse event
Transferring risk
◼ Paying a premium to pass the risk to another party
Avoiding risk
◼ Changing the project plan to eliminate the risk or condition
Sharing risk
◼ Allocating risk to different parties
Retaining risk
◼ Making a conscious decision to accept the risk
Managing risk
◼ Step 4: risk response control
Risk control
◼ Execution of the risk response strategy
◼ Monitoring of triggering events
◼ Initiating contingency plans
◼ Watching for new risks
Establishing a change management system
◼ Monitoring, tracking, and reporting risk
◼ Fostering an open organization environment
◼ Repeating risk identification/assessment exercises
◼ Assigning and documenting responsibility for managing risk
Risk Management’s Benefits
◼ A proactive rather than reactive approach
◼ Reduces surprises and negative consequences
◼ Prepares the project manager to take advantage of
appropriate risks
◼ Provides better control over the future
◼ Improves chances of reaching project performance
objectives within budget and on time
26
Copyright © 2017 Pearson Education, Ltd. 1 - 27