Assignment Operation Management (2)
Assignment Operation Management (2)
Question # 01
Line Balancing
A company operates 7½ hours per day with a demand of 1,000 units per day, and it sets up its
assembly line as presented in the table below:
Task Preceding Task Preceding
Task Task
Time(seconds) Tasks Time(seconds) Tasks
A 15 G 11 C
B 24 A H 9 D
C 6 A I 14 E
D 12 B J 6 F,G
E 18 B K 15 H,I
F 7 C L 10 J,K
= 27000/1000 = 27 seconds
So,
Estimated no. of workstation = 6
I applied ranking formula in excel to check the position of every task according to the task time
and also, I wrote no. of following of every individual activity.
Line Balancing
= 147/(6*27)
= 90.7%
d) We can check the maximum units produced by line
We have a formula,
e) Demand is increased by 8%
Task
Precedi
Time Rankin Followe
Task ng
(Second g rs
Tasks
s)
A 15 3 7
B 24 A 1 6
C 6 A 11 4
D 12 B 6 3
E 18 B 2 3
F 7 C 10 2
G 11 C 7 2
H 9 D 9 2
I 14 E 5 2
J 6 F,G 11 1
K 15 H, I 3 1
L 10 J, K 8 0
Revised Line Balancing
As the demand increased from 1000 to 1080 units, we need an additional workstation
The activity L is not adjusted, that’s why 1 extra station was required.
Efficiency
Efficiency of Assembly Line = Required Time / (Actual Workstation) *Cycle time
= 147/(7*25)
=84%
Total Idle time = 4+1+0+2+2+2+15 =26 sec
Question # 02
Given Data
Duration of season = 60 days
Hours/Day = 8
Total hours of season = 60*8 = 480 hours
Productivity = 0.5 units/hour
Workers at fall = 30
Workers for temporary = 10 (in summer)
Inventory at beginning of fall = 1000 units
Overtime allowed in winter = 6000 hours
Season and demand forecast is given below;
Seasonal Output;
Working hour/season = 480
Productivity = 0.5/hour
Workers = 30
Output per season = 30*0.5*480 = 7200 units
Considering overtime;
Allowed overtime = 6000 hours
Overtime Output = 6000*0.5 = 3000 units
Total output (current+overtime) =7200 + 3000 = 10,200 units
Temporary workers;
Temporary workers in summer = 10
Output of workers = 10*480*0.5 = 2400 units
Production Plan
Ending
Starting Total Overtime Overtim Temporary
Season Demand Inventor Workers
Inventory Production Hours e Output Output
y
=7200+3000
Winter -1800 8,000 400 6,000 3,000 0 30
10,200
Summe 7200+2200
+600 10,000 0 0 0 2200 40
r =9400
Overtime
Cost Components Fall Winter Spring Summer
Hours
Regular Salary
$72,000 $72,000 $72,000 $96,000 $312,000
$5/hr
Overtime Salary
$48,000 $48,000
$8/hr
Back Order
$18,000 $18,000
$10/hr
Inventory
$2,000 $3,000 $5,000
$5/hr
Total Cost per
$90,000 $122,000 $75,000 $96,000 $383,000
Season
Ending
Starting Total Overtime Overtim Temporary Workers
Season Demand Inventor
Inventory Output Hours e Output Output
y
8,400+400
Winter -600 8,000 200 800 400 35
=8,800
Overtime
Cost Components Fall Winter Spring Summer
Hours
Regular Salary
$84,000 $84,000 $84,000 $84,000 $336,000
$5/hr
Overtime Salary
$6,400 $6,400
$8/hr
Back Order
$6,000 $6,000
$10/hr
Inventory
$2,000 $16,000 $18,000
$5/hr
Total Cost per
$90,000 $92,400 $100,000 $84,000 $366,400
Season
Question # 03
D(2) E(3)
b) MRP
Data Given;
Lead Time
A,B and C = 1 week
And for D, E = 2 weeks
On hand Inventory
A = 20 units
C = 10 units
D = 20 units
Scheduled Receipts
B: 10 units in Week 1
C: 50 units in Week 1
Customer Orders
30 units of A in Week 4
30 units of A in Week 7
40 units of A in Week 10
The above is actually the gross requirement of A. Similary we will calculate the gross
requirement of other acitvities depending on their no.of units required for making its parent
item.
Gross requirement of B and D will be equal to Plan order release of A
Gross requirement of C will (Plan order release of A*2)
Similary D and E are dependent on C.
Week Week Wee Week Week Week Week Wee Week Week
Item Week
1 2 k3 4 5 6 7 k8 9 10
Gross Requirement 30 30 40
Item: A Schedule Receipts
OH=20
Project available balance 20 20 20 20
LT =1
Net Requirement 10 30 40
SS:0
Planned order receipts 10 30 40
Planned order release 10 30 40
Week Week Wee Week Week Week Week Wee Week Week
Item Week
1 2 k3 4 5 6 7 k8 9 10
Gross Requirement 10 30 40
Item: B Schedule Receipts 10
OH=0
Project available balance 10 10 10
LT =1
Net Requirement 0 30 40
SS=10
Planned order receipts
Planned order release 30 40
Week Week Wee Week Week Week Week Wee Week Week
Item Week
1 2 k3 4 5 6 7 k8 9 10
Item: C Gross Requirement 20 60 80
OH=10 Schedule Receipts 50
Project available balance 10 60 60 40 40 40 30 30 30
Net Requirement 20 50
LT =1 Planned order receipts 50 50
SS=50 Planned order release 50 50
Week Week Wee Week Week Week Week Wee Week Week
Item Week
1 2 k3 4 5 6 7 k8 9 10
Gross Requirement 10 100 30 100 40
Item: D Schedule Receipts
OH=20 20 20 20 10 10 10 80 80 80 40
Project available balance
LT=2
SS=0 Net Requirement 90 20 20
Planned order receipts 100 100 100
Planned order release 100 100 100
Week Week Wee Week Week Week Week Wee Week Week
Item Week
1 2 k3 4 5 6 7 k8 9 10
Gross Requirement 150 150
Item: E Schedule Receipts
OH=0
Project available balance
LT=2
SS=10 Net Requirement 150 150
Planned order receipts 150 150
Planned order release 150 150
The same format will be applied. In this case we have no inventory and schedule receipts.
Week Week Wee Week Week Week Week Wee Week Week
Item Week
1 2 k3 4 5 6 7 k8 9 10
Gross Requirement 30 30 40
Schedule Receipts
Item: A
Project available balance
LT =1
Net Requirement 30 30 40
Planned order receipts 30 30 40
Planned order release 30 30 40
Week Week Wee Week Week Week Week Wee Week Week
Item Week
1 2 k3 4 5 6 7 k8 9 10
Item: B Gross Requirement 30 30 40
LT =1 Schedule Receipts
Project available balance
Net Requirement 30 30 40
Planned order receipts 30 30 40
Planned order release 30 30 40
Week Week Wee Week Week Week Week Wee Week Week
Item Week
1 2 k3 4 5 6 7 k8 9 10
Gross Requirement 60 60 80
Schedule Receipts
Item: C 40 40 40 30 30 30
Project available balance
LT =1
Net Requirement 60 20 50
Planned order receipts 100 50 50
Planned order release 100 50 50
Week Week Wee Week Week Week Week Wee Week Week
Item Week
1 2 k3 4 5 6 7 k8 9 10
Gross Requirement 200 30 100 30 100 40
Schedule Receipts
Item: D 70 70 70 40 40 40
Project available balance
LT=2
Net Requirement 200 30 30 60
Planned order receipts 200 100 100 100
Planned order release 100 100 100
Week Week Wee Week Week Week Week Wee Week Week
Item Week
1 2 k3 4 5 6 7 k8 9 10
Gross Requirement 300 150 150
Schedule Receipts
Item: E
Project available balance
LT=2
Net Requirement 300 150 150
Planned order receipts 300 150 150
Planned order release 300 150 150
Here we got a problem, the quantity red highlighted should be released two week earlier but we
cannot.
Summary: There are no instances where the net requirements exceed the planned order releases,
and the lead times are respected, so the manufacturer can fulfill the order for 30 units in Week 4,
30 units in Week 7, and 40 units in Week 10.
Thus, the manufacturer can meet the required demand as long as the orders are placed according
to the MRP schedule.
d) Production capacities for items C, D, and E are limited to a maximum of 100 units per
week.
Week Week Wee Week Week Week Week Wee Week Week
Item Week
1 2 k3 4 5 6 7 k8 9 10
Gross Requirement 30 30 40
Schedule Receipts
Item: A
Project available balance
LT =1
Net Requirement 30 30 40
Planned order receipts 30 30 40
Planned order release 30 30 40
Week Week Wee Week Week Week Week Wee Week Week
Item Week
1 2 k3 4 5 6 7 k8 9 10
Gross Requirement 30 30 40
Schedule Receipts
Item: B
Project available balance
LT =1
Net Requirement 30 30 40
Planned order receipts 30 30 40
Planned order release 30 30 40
Week Week Wee Week Week Week Week Wee Week Week
Item Week
1 2 k3 4 5 6 7 k8 9 10
Gross Requirement 60 60 80
Schedule Receipts
Item: C 40 40 40 110 110 110 30
Project available balance
LT =1
Net Requirement 60 20
Planned order receipts 100 100
Planned order release 100 100
Week Week Wee Week Week Week Week Wee Week Week
Item Week
1 2 k3 4 5 6 7 k8 9 10
Item: D Gross Requirement 200 30 200 30 40
Schedule Receipts
Project available balance 70 70 70 40 40 40
LT=2
Net Requirement 200 30 130
Planned order receipts 200 100 200
Planned order release 100 200
Week Week Wee Week Week Week Week Wee Week Week
Item Week
1 2 k3 4 5 6 7 k8 9 10
Gross Requirement 300 300
Schedule Receipts
Item: E
Project available balance
LT=2
Net Requirement 300 300
Planned order receipts 300 300
Planned order release 300
Summary;
Yes, the manufacturer can execute the request based on the following considerations:
1. The production capacity of C, D, and E is limited to 100 units per week, however scheduled
receipts and planned order releases meet customer demand for 30 units in Week 4, 30 units in
Week 7, and 40 units in Week 10.
2. The minimum scheduled receipts for D and E are correctly positioned, ensuring that the limits
are met while not exceeding production capacity.
Question #04
CR = (1.0)/(1.0+0.5)
CR = 0.6667
We will check the value of z-score from standard table which is 0.43
Average daily demand = 250
Standard deviation = 25
Putting the values in formula,
b) Percentage of Demand
The percentage of demand that can cannot be served is equal to the probability of stockout.
Using the formula and the area left to the optimal order quantity,
z = (Q - µ)/ϭ
z = (261-250)/25
z = 0.44
using the standard normal distribution table, the commutative probability against z value is 67%.
We know that total probability is = 100%
Probability of demand served = 67%
Probability of demand unserved =33%
c) No. of Newspapers to serve 90% demand
We have formula
Q* = µ + z.ϭ
Using the standard normal distribution table, the value of z score for cumulative 0.9 probability is 1.28
Q = 250 + 1.28*25
Q = 250 + 32 = 282 units
d) Percentage of demand if 300 newspapers are carried
z = (Q - µ)/ϭ
z = (300 -250)/25
z=2
using standard table of normal distribution, the commutative probability for z = 2 is 0.9772
It means if the shop carries 300 newspapers, it can serve 97.72% of demand.
z = (300-250)/25 = 2
0.9972 = (P – 0.5)/(P-0.5+0.5)
P = 0.50/0.0228
P = $21.93 (approx.)
To make 300 newspapers the optimal quantity, the shop must sell newspapers for $21.93 each