7-Activity On Arrow Networks and Activity On Node Network - Examples-05-09-2024
7-Activity On Arrow Networks and Activity On Node Network - Examples-05-09-2024
Module II
1
Network Planning Models
Models the project activities and their
relationships as a network.
Two Methods:
PERT – Program Evaluation Review Technique
CPM – Critical Path Method
Both PERT and CPM used AoA initially and later
Precedence network became popular which
follows AON.
Activity on node (AON)-the ‘nodes’ are the boxes
which represent activities and links between them
represent precedence (sequencing)
Activity on arrow (AOA) – ‘arrows’ represent
activities and nodes represent possible start/end
of an activity.
Do B
AON
Do A Do D
Do C
AOA
Do B
Do A
Do D
Do C
CPM uses an activity-on-arrow notation
4
where the arrows are the activities
PERT
11
Resolving Dangle
17
Start to Start: When one activity starts another
has to start as well. e.g. when prototype testing
starts amendment documentation has to start as
well.
18
Finish to finish: when one activity finishes the other must
finish too. A successor activity can only finish after its
predecessor has been completed.
e.g. when the testing of the prototype is completed so is
the documentation of any amendments
Eg.First task: Connect system to interfaces and devices
Second task: Install and configure software
We can only complete the software configuration after all
interfaces and devices have been connected.
19
Start to finish: the start of a successor activity is
dependent on the finish of the predecessor activity.
(Dependency: handover of tasks from A to B)
A logical relationship in which the predecessor
activity can only complete once the successor task
has started.
Eg. A new accounts payable system (successor) has
to start before the old accounts payable system can be
shut down (predecessor).
Eg. Switching to power grid from generator power
while operating.
20
You can only deactivate the old system once the new
system has been enabled and users can work with it.
When the cutover to the new system takes place, the
operation of the temporary system is no longer needed.
Operate temporary
system
21
The first task, hoisting the object, can only be completed
once team 2 is ready to receive the object (second task).
Dependency Relationships
Fragment of precedence network
31
Earliest start date
Earliest start date for the current activity =
earliest finish date for the previous
When there is more than one previous activity,
take the latest earliest finish
Note ‘day 7’ = end of work on day 7
EF = day 7
ES = day10
EF = day10
33
Example
earliest start = day 5 earliest finish =?
latest finish = day 30 EF= ES + Duration
duration = 10 days = 5+10= day15
latest start = ?
LS= LF- duration
= 30-10= day 20
A Hardware selection 6
B Software design 4
C Install hardware 3 A
D Code and test software 4 B
E File take-on 3 B
F Write user manuals 10
G User training 3 E,F
H Install and test system 2 C,D
Precedence network/activity network
Work out the earliest start and end dates for each activity
A 6 wks C 3 wks
Hardware Install
selection hardware
A 0 6 6
B 0 4 4
C 6 3 9
D 4 4 8
E 4 3 7
F 0 10 10
G 10 3 13
H 9 2 11
37
The forward pass – to calculate earliest date on which
each activity may be started and completed
By convention, dates indicate the end of a period. The project is shown as starting at the end of week 0 (or the
beginning of week 1)
A 6 wks C 3 wks
0 Hardware 6 6 Install 9
selection hardware
A 6 wks C 3 wks
0 Hardware 6 6 Install 9
2 selection 8 8 hardware 11
A 0 6 6 2 8 2
B 0 4 4 3 7 3
C 6 3 9 8 11 2
D 4 4 8 7 11 3
E 4 3 7 7 10 3
F 0 10 10 0 10 0
G 10 3 13 10 13 0
H 9 2 11 11 13 2
40
FLOAT
Float (also known as slack) is the amount of time
by which the start of an activity can be delayed
without delaying the project completion time.
Activity Float – Difference between its earliest
and latest finish date or difference between
Latest (LS) and Early Start (ES)
LS-ES or LF- EF
or
Float / Total Float = Latest finish - Earliest start -
Duration
Example
A 6 wks C 3 wks
0 Hardware 6 6 Install 9
2 selection 8 8 hardware 11
2 wks 2 wks
0 Hardware 6 6 Install 9
2 selection 8 8 hardware 11
8 wks 2 wks 5 wks 2 wks
0 Hardware 6 6 Install 9
2 selection 8 8 hardware 11 D can be further 2wk late . It
affects H but not the project
2 wks 2 wks
end date = Interfering float