TESP10405R3
TESP10405R3
TABLE OF CONTENTS
1. SCOPE
2. BURIAL DEPTH
5.1 General
5.2 Conduit or Duct Fill
5.3 Jam Ratio (JR)
5.4 Cable Clearances (CL) In Conduit
6. CABLE INSTALLATION
6.1 General
6.2 Direct Buried
6.3 Underground Structures
TABLES
Table-1 Minimum Cover Requirement from Grade Level to the Top Surface of a Cable or
Duct
Table-7 Variation in center to center phase spacing and their corresponding correction factor
Table-9 Clearance between power cables and communications facilities buried in the same
trench
Table-10 Clearances between National Grid Saudi Arabia Cables and other Utility
REFERENCES
CIGRE Electra # 143 & 144 Calculation of temperatures in ventilated cable tunnels
TA-800062, Rev. 0 Typical Duct Bank Sections, Concrete Duct Bank for 69kV to
380kV U/G Power Cables
FIGURES
10-01 Typical Cross-Section of Trench for 110 kV, 115 kV or 132 kV XLPE Power Cable;
Single Circuit, Trefoil Formation, Direct Buried
10-02 Typical Cross-Section of Trench for 110 kV, 115 kV or 132 kV XLPE Power Cable;
Single Circuit, Trefoil Formation, Concrete Ductbank
10-03 Typical Cross-Section of Trench for 110 kV, 115 kV, 132 kV XLPE or LPOF Power
Cable; Single Circuit, Flat Formation, Direct Buried
10-04 Typical Cross-Section of Trench for 230 kV or 380 kV XLPE or LPOF Power Cable;
Single Circuit, Flat Formation, Direct Buried
10-05 Typical Cross-Section of Trench for 110 kV, 115 kV or 132 kV XLPE or LPOF
Power Cable; Single Circuit, Flat Formation, Concrete Ductbank
10-06 Typical Cross-Section of Trench for 230 kV or 380 kV XLPE or LPOF Power Cable;
Single Circuit, Flat Formation, Concrete Ductbank
10-07 Recommended Clearances Between National Grid Saudi Arabia Underground Power
Cables 110kV to 132kV and Other Utility Lines
10-08 Recommended Clearances Between National Grid Saudi Arabia Underground Power
Cables 110kV to 380kV and Other Utility Lines
1.0 SCOPE
The purpose of this section is to provide design considerations for underground power cable
installations (direct buried, duct or tunnel applications) in the Transmission System of
National Grid Saudi Arabia.
2.2 For paved roads, the grade level is the surface immediately below the concrete or
asphalt pavement. Subgrade is another term for this surface. For unpaved roads or
areas, the grade level is the road shoulder surface or natural ground level.
3.1 Bending of Power Cable at a short radius may damage the insulation, shielding
or jacket of the cable, therefore, during cable installations, care must be taken
that no sharp bends or sharp twists are made. Whenever a bend in the route is
encountered, care shall be taken to ensure that rollers are properly positioned so that
the bending radius of the cable is always more than the minimum allowable
bending radius mentioned in Table-2 of this Standard.
3.2 The rollers shall be adequately braced against tensions and side pressure that will
be encountered during the cable pull. The transition through the angle and/or bend
shall be uniformed to conform to the arc of a circle. Radii at the angles shall be as
large as practical to minimize pulling tensions and sidewall pressures. The
bending radii shall match those used in tension and sidewall pressure calculations.
3.3 Power Cable's bending radius shall not be less, under any circumstances, than the
recommended values given by the power cable's manufacturer.
3.4 The cable shall not be bent to less radius than the drum's radius of the cable reel on
which it was shipped.
3.5 Minimum bending radius (r) to which cables may be bent refers to the inner
surface of the cable and not to the axis of the cable at the bend as shown in the
below figure:
The minimum bending radius for permanent turning during cable installation
shall be as shown in Table-2.
During cable installation, large diameter wheels, pulling sheaves and cable guides
shall be used to maintain the specified bending radius. Larger radii are
recommended wherever the cable is being pulled under tension, preferably not
less than twice the values for permanent turning.
Note: In case the cable manufacturer recommends larger bending radius, his
recommendation shall be complied with.
4.1 General
4.1.1 The axial and tangential forces applied during the pulling process shall
not damage any component of the cable assembly during the installation of
XLPE, UGNMFOC and LPOF Cables.
4.1.2 When installing cable in vertical runs, pulling the cable from the top of
the run rather than the bottom will greatly reduce the pulling tension, and
reduce mechanical forces on the cable accordingly.
4.1.6 The placement of all rollers that conforms to the radii bends and degree
angle curves shall be verified prior to commencing the cable pull.
4.1.7 The tensile capability of every cable formation is dependent upon the
tensile limitations of the conductor plus the overall integrity of the cable
design. Each factor has finite limitations which shall not be exceeded. The
cable manufacturer shall be consulted for recommendations in this regard.
4.2 The maximum pulling tension placed on a cable shall not exceed the following
4.2.1 For cable equipped with a pulling eye or bolt attached to the conductor.
4.2.2 For cable to be pulled with a cable grip over the sheath:
a. For a cable with a lead sheath, maximum tension in newtons (N) is
equal to 10.342 times the lead cross-sectional area in (mm2).
4.3 The pulling tension (T) for a given installation shall be calculated from the
following formulas or shall be as per manufacturer’s requirements:
Where:
T = 9.8 x L x W x f (Eq.02)
Where
OF = 1
N = 1
b. For three single-core cables in trefoil formation:
O.F = 1 (Eq.03)
1 - [d / (D-d )]2
Where
d = Outside diameter of each cable in mm
D = Inside diameter of duct in mm
T2 = T1 efa (Eq.04)
Where
4.4 The maximum sidewall pressure shall not exceed 29.2 kN/m, i.e. the tension in the
cable in kilo newtons as it leaves the bend shall not exceed 29.2 times the radius
of the bend in meters.
4.5 The following example outlines the applicable tensile considerations for duct
installation. Similar factors are applicable for direct buried cables. For a sample
calculations, assume the following:
4.5.1 Pull from point (A) to point (F) in Newtons (N) and meters (m):
OF = 1
N = 1
TC = TB efa
TC = 5939 x 2.718(0.5 x 45 x (π/180))
TC = 5939 x 1.48 = 8796 N
TD = 8796 + [9.8 x 20 x (20 x 1.01) x 0.5 x 1 x 1] = 10776 N
TE = 10776 x 2.19 = 23600 N
TF = 23600 + [9.8 x 30 x (20 x 1.01) x 0.5 x 1 x 1] = 26570 N
Using Equation 05 :
-3
SWBP (at C) = TC in Newton x 10 = 8796 x 10-3
Bend Radius, m 3
4.5.3 Because the sidewall pressure is rather high at point (E) though not outside
design limits it would be desirable to investigate the results if the cable is
pulled from at point (F) to at point (A).
4.6 During pulling operations, it is frequently necessary to re-reel the cable or pass it
over pulleys or sheaves, to avoid damage to the cable. It is imperative that the
cable shall not be bent over the minimum radius of the cable which may cause
damage.
4.7 For direct buried, or a combination of direct buried and ducts, cable installations
where the length of the circuit must be pulled in, National Grid SA approved
rollers, shall be used.
5.1 General
The following parameters shall be considered during the course of cable pulling:
The size of the inner diameter of the conduit and the outer diameter of the cable
will determine the percentage fill of the conduit.
Conduit or Duct Fill is based on the percentage-fill of the cross sectional area of the
conduit/duct. The number of conductors shall not exceed the percentage fill
specified in Table-4.
When three or more single or multicore cables are being pulled into a conduit,
their relative position in the conduit, when being pulled around bends can change,
causing a condition of “Jamming”. If the cables jam in the conduit during
pulling, the likelihood of cable damage is high. The Jam Ratio (JR) is defined as
the ratio of the conduit Inner diameter (D) to cable overall diameter (d). The
following formula is used to evaluate the jamming potential:
If (JR) = D is : -
d
larger than 3.0 then jamming cannot occur.
between 2.8 and 3.0 then jamming is likely to occur and should be
avoided, but clearance must be checked (see paragraph 5.4).
less than 2.8 then jamming is likely to occur
Where
d = Cable outer diameter in mm
D = Conduit inside diameter in mm
Clearances must be checked to ensure that the top cable will not press against the
top of the conduit. Clearance shall be between 6 mm and 25 mm. The larger
value is used for large cables and severe bends and pulls. The formulae for
calculating clearance are as follows:
CL = D-d
6.1 General
6.1.1 In the event of minor damage to outer jacket during installation, heat
shrinkable split sleeve shall be applied to repair the jacket.
6.1.3 Route of cable trenches shall avoid above ground and below ground
obstructions so as to maintain a reasonable access to the buried cables.
Trenches in unpaved areas are preferred. A minimum clearance shall be
maintained between underground runs and parallel runs of underground
piping. Cables shall not be located under present or future parallel runs of
low level underground piping which could block access to the cables.
Recommended clearances are shown on Fig.10-01 through Fig.10-06.
6.2.1 Power and associated control circuits can be laid adjacent. Three single
conductor cables comprising one three phase circuit (trefoil) shall be laid
without spacing. In order to achieve a reasonable derating factor, a minimum
spacing shall be determined between all 3-phase power circuits. Refer TES-
P-104.03 for derating effects of adjacent circuits.
6.2.2 Where cables cross under main roads, concrete slabs, paved areas, railroad,
or any areas that would require extensive or impractical excavations to
replace, then they shall be run in ducts. Where such duct runs exceed 3
meters, overall cable ampacity shall be based on the duct portion of the run.
Bell end or protective bushings shall be provided on each duct end where it
terminates.
6.2.3 If underground cables are routed through a concrete encased duct bank, PVC
/ HDPE conduits shall be of encased-in type and when routed through direct
buried PVC / HDPE conduit, they shall be of direct buried (DB) type. All
conduits shall have bell ends or protective bushings where the conduits
terminate underground.
If underground cables in concrete encased duct bank are crossing the road and
at the same time crossing over other existing underground utilities making the
clearance between the concrete duct bank closer to the road surface, additional
steel reinforcement shall be provided. This helps concrete duct bank structure
withstand the impact of loads brought by the vehicles passing on the affected
roads/highways.
6.2.4 Special Back fill shall be used to gain the required ampacity and the cable
shall be protected with concrete, steel wire mesh and warning tapes as per
Clause 5.4 of TCS-P-104.03.
6.3.3 Adequate access space shall be provided to maintain and operate equipment.
6.3.4 Power and communication cables shall be racked into separate walls.
Crossing of the two circuits shall be avoided.
6.3.5 All cables which exit from transformer, switchgear, vault, manhole,
handhole or switch enclosures and terminal structures shall be tagged for
identification. Tags shall be permanent, non-corrodible and clearly
readable. The following minimum information shall be put in English and
Arabic on the tag:
b. Distribution:
ii. Secondary:
Voltage
Phase for Single Core Cables
Destination
iii. Service:
Destination or Customer Address
Circuit Type
Destination
6.3.9 Power cables shall be fire retardant, except where fireproofing is not
necessary.
6.3.10 In manholes and other structures containing no oil filled equipment (i.e.
where no oil fire hazard is involved), fireproofing is only necessary where
separation between cables is 45 cm or less.
Distance between circuits and the number of circuits have an effect on rating
current which represented by Correction factors, which is corresponding to
the number of buried circuits and center to center distances between each
circuit for both trefoil and flat formation as shown in the tables below.
However these calculations are obtained based on IEC 60287-1-1 & IEC
60287-2-1 and are applicable for HV & EHV power cables (rated from 110
kV to 380 kV).
Separation between HV & EHV power cables (rated from 110 kV to 380 kV) to be
unified in the figures of Clause 11 of TES-P-104.05, Rev.03 as the following table.
Phases
200 250 300 400
Spacing (mm)
Correction
0.92 0.95 0.97 1.00
Factor
In case of crossing between power cables and other power cables, a vertical
clearance of at least 500 mm shall be maintained (bottom to bottom distance)
notice that cables with lower voltages shall be on top of higher voltages
cables. Furthermore, security of top power cables shall be ensured by passing
them through a concrete duct bank at the crossing point.
If the bottom cables are passing through ducts, top cables which are being
laid shall not necessarily pass through ducts unless the condition warrants.
Like many other cable laying projects, the critical part of implementing any
installation in the marine environment begins with a sound systems
engineering and project management approach. The basic principles consist
of:
Conceptual design
Design reviews
Trade-off analysis
Concept of operations
Risk analysis
Technical
Cost
Schedule
Project plan
Procurement
Mobilization
Trialing and testing
Validation and verification
8.1 Figure 10-01 through 10-06 indicate standard design parameters for the cable
trench depth, width, backfill and circuit separation.
b. Refer to Figures 10-01 through 10-06 for the required width and
depth of cables trench.
ii. The pipe shall be made of steel. The nominal size of the pipe
shall be minimum of 1067 mm. Thrust boring with PE pipe to
be followed whenever possible as it is much better for cable
ampacity.
vii. All ducts including spare ducts shall be terminated with bell
ends
ix. Test mandrel (6mm less in diameter than the normal inside
diameter of the duct) and wire brush cleaner 16mm larger
than the duct as per TCS-P-104.03) shall be pulled through to
each duct. A nylon pull line (13mm diameter) shall be pulled
at each duct line (Power & Communication). After cleaning,
construction drawings which indicate duct line length and
routing shall be verified & field noted in conjunction with
duct testing operations.
8.3.1 Warning posts shall be installed along the center line of the trench at not over
50m intervals on congested areas and not over 90m intervals on open areas
and at all locations where the trench changes direction.
8.3.2 On straight route, the warning post shall have a two-arrow sign to indicate
cable route direction.
8.3.3 On right angle turn, the warning post shall have two signs each having an
arrow pointing to the cable route direction. The signs will be placed on the
applicable side of the post.
8.3.4 On oblique turn, the cable route direction shall be indicated by two warning
posts each having an arrow.
8.3.5 Warning Post shall not obstruct vehicle access along the side of the track or
infringe structure gauge. In yard areas, they shall not obstruct footpaths,
walkways or vehicle access ways.
Refer to National Grid Saudi Arabia Standard Drawing TA-800062 for “Typical
Duct Bank Sections, Concrete Duct Bank for 69kV to 380kV U/G Power Cables”.
9.1 In areas where laying the HV/EHV cable circuits in conventional way (direct
buried) is not possible due to space constraint/right of way, underground power
cable tunnel can be considered as an alternative. The power cable tunnels can be
divided into two parts.
The cable tunnel shall be designed/constructed with but not limited to the following
considerations:
9.1.1. The cable tunnel shall be designed to accommodate the two or more power
cable circuits.
9.1.2. In case of two circuits, the cable circuits shall be installed in vertical
formation along tunnel sidewalls to create more space for installing cable
accessories (cable joints & link boxes etc.) and maintenance work. All cable
circuits shall be installed as per approved formation submitted in current
rating calculations.
9.1.3. For cable current rating calculations tunnel ambient temperature shall be
considered as 50°C and appropriate ventilation/cooling system shall be
designed to keep tunnel ambient temperature below 50ºC.
9.1.4. Size of the tunnel (width & height) shall be determined upon the required
current rating for the number of circuits being installed and current rating
calculations shall be done according to CIGRE ELECTRA # 143 & 144 /
IEC 60287. Space required for entrance/exit, installation of link boxes,
joints, monitoring system of cable & tunnel (Distributed Temperature
Sensing/DTS system for power cable, partial discharge monitoring at each
joint and termination, SVL monitoring and tunnel temperature monitoring
system) as applicable, sagging/snaking of power cables and any other
maintenance work shall also be considered.
9.1.6. Proper Lighting, Fire Fighting & Loss prevention system shall be provided
in accordance with latest revised TES-P-119.21 and other relevant
standards.
9.1.7. Cable Tunnel shall be constructed at least two meters lower than lowest
existing/future services/utilities/Ground Level along the tunnel route with
the approval of all concerned authorities.
9.1.9. Emergency exits to the tunnel shall be provided at every 75-100 meters (as
per Civil Defense requirements).
9.1.10. The tunnel should be water proof and entrances should be water tight.
Suitable water drainage (sump pump) system shall be provided.
9.1.11. The alarm system for smoke, water level and heat shall be provided on zone
bases and to be connected to Power Control Centre/Substation Automation
System.
9.1.12. The cable support system shall carry/support the weight of 40kg/m for
aluminum alloy sheathed cable to 65kg/m for lead alloy sheathed cable. The
cable support shall be designed to carry the cable load with enough safety
margins taking into consideration the force exerted during short circuit
conditions as well.
9.1.13. Grounding system should be included for the entire length of the cable
Tunnel.
9.2.1. Cable outer sheath shall be fire retardant or painted with fire retardant paint.
9.2.3. Sheaths for both end sections of cable circuit shall be single point bonded
and sheaths for remaining sections shall be fully cross bonded.
9.2.4. Tunnel ventilation system, fire detection/alarm system, lighting and power
distribution system, communication system and drainage system shall be
provided in the tunnel.
9.2.5. RTTR (Real Time Thermal Rating) System shall be provided. The function
of the RTTR System is to integrate the tunnel DTS system and fan stations
automatically for controlling the tunnel cooling system to maintain the cable
& tunnel temperature within design limits. The system shall be redundant
and has a conventional temperature gauge system to back up the tunnel
system DTS in the event of malfunction.
9.2.6. Cable DTS system, partial discharge monitoring for each joint &
termination and SVL monitoring system shall be provided.
9.2.7. At about every 350 to 500m distance local earthing grid for joint bays shall
be installed (for earthing of link boxes) and earthing connections shall be
brought in side the tunnel.
FIGURE 10-01
110 kV, 115 kV or 132 kV XLPE STANDARD TRENCH
FIGURE 10-02
110 kV, 115 kV or 132 kV XLPE STANDARD TRENCH
FIGURE 10-03
110 kV, 115 kV or 132 kV XLPE or LPOF STANDARD TRENCH
FIGURE 10-04
230 kV or 380 kV XLPE or LPOF STANDARD TRENCH
FIGURE 10-05
110 kV, 115 kV or 132 kV XLPE or LPOF STANDARD TRENCH
FIGURE 10-06
230 kV or 380 kV XLPE or LPOF STANDARD TRENCH
Figure 10-07
Recommended Clearances Between National Grid Saudi Arabia Underground
Power Cables 110kV to 132kV and Other Utilities Lines
Figure 10-08
Recommended Clearances Between National Grid Saudi Arabia Underground
Power Cables 110kV to 380kV and Other Utilities Lines