Project Management SAM 2024
Project Management SAM 2024
Project
Management
Tools and Méthodology
23/09/2024 TITRE DE LA PRÉSENTATION
LEARNING OBJECTIVES
1/ What is a Project?
2/ What is Project Management?
3/ Who is a stakeholder in Project Management?
4/ Project Management approach: step by step
2
23/09/2024 TITRE DE LA PRÉSENTATION
What is a Project
3
23/09/2024 TITRE DE LA PRÉSENTATION
Definition
A Project:
“It's a temporary endeavor undertaken to create a unique product, service or result.»
Project Management Institute official definition.
https://www.pmi.org/
A project is unique in that it is not routine operation BUT a specific set of tasks designed to reach a singular
goal.
4
23/09/2024 TITRE DE LA PRÉSENTATION
Definition
Triple constraints/ Project Management triangle A Project is a dynamic system that needs to be
kept in balance!
5
23/09/2024 TITRE DE LA PRÉSENTATION
2
What is a Project
Management ?
6
23/09/2024 TITRE DE LA PRÉSENTATION
Definition
Project Management is a set of methodologies which aims to achieve all the Project requirements with in the given
constraints.
“Applicationofknowledge,skills,tools,andtechniquestoprojectactivitiestomeettheprojectrequirements”(PMI definition)
• Sequential approach : Final product / deliverable is known (main specificities have been defined)
• PMI:Projectsaredividedinto5processphases.
Not so much a methodology as it is an agreed upon set of standards and conventions for managing projects.
• Agile:Theprojectteamworksiniterativecycles,alwaysevaluatingresultsattheendofacycle.Dependingontheresultsoftheseevaluations,thefi
naldeliverablemaybemodified.
7
23/09/2024 TITRE DE LA PRÉSENTATION
Waterfall
Sequential approach
We will focus on this one
Agile
Incremental approach
8
23/09/2024 TITRE DE LA PRÉSENTATION
3
Project Team and
Stakeholders
9
23/09/2024 TITRE DE LA PRÉSENTATION
Vocabulary
• Contracting / Ordering authority=Maitre d’ouvrage (MOA).
•Contracting Authority support = Assistance Maitrise d’ouvrage (AMOA)
•/!\Project Management = Maitrise d’œuvre (MOE)
10
23/09/2024 TITRE DE LA PRÉSENTATION
11
23/09/2024 TITRE DE LA PRÉSENTATION
4
Project Management
Step by Step
12
23/09/2024 TITRE DE LA PRÉSENTATION
• And 5 processes:
• Initiating/ Definition
• Planning /Preparation
• Execution
• Performance monitoring
• Closure
13
23/09/2024 TITRE DE LA PRÉSENTATION
4.1 Initiating
14
23/09/2024 TITRE DE LA PRÉSENTATION
Collect relevant information to allow the project scope and objectives to be clearly assessed
Define the business case of the project
Get the formal approval to start the project with appropriate resources
Methods and / or tools that can help you and your team to clarify the needs
• 5 Ws
• SWOT
• SMART approach for objectives
But also more technical analysis such as market research , feasibility studies…
15
23/09/2024 TITRE DE LA PRÉSENTATION
16
23/09/2024 TITRE DE LA PRÉSENTATION
17
23/09/2024 TITRE DE LA PRÉSENTATION
18
23/09/2024 TITRE DE LA PRÉSENTATION
19
23/09/2024 TITRE DE LA PRÉSENTATION
4.2 Planning
20
• CHAP #4 • Project Management: overview
And 5 processes:
- Initiating /Definition
- Planning / Preparation
- Execution
- Performance monitoring
- Closure
PMBook,4th edition
23/09/2024 TITRE DE LA PRÉSENTATION
Driving question at this stage: what do we have to realize in detail and how can we ensure that we will
be successful in the end?
Methods and / or tools that can help you and your team to clarify the needs
• People organisation in effective teams
• Efficient work structuration
• Governance : define communication flow between stakeholders
• Responsabilty matrix (RACI)
22
23/09/2024 TITRE DE LA PRÉSENTATION
1) All the tasks that have to be accomplished to realize the expected deliverables
23
23/09/2024 TITRE DE LA PRÉSENTATION
The objective is to subdivise the total project scope into manageable components in terms of size,
duration, and responsibility.
• The smaller items of the structuration are named: work packages.
• Every work package is composed of several tasks.
Project
• For each task, a deliverable must be linked.
24
23/09/2024 TITRE DE LA PRÉSENTATION
2/ Creating a WBS should be done with a top down AND bottom up approach
-Deliverables can be compulsory
-Deliverables can be identified by breaking down tasks
New Project
=> WBS Example Launch
Sales and
Development & Industrial
Project Management Marketing
Testing Production
Preparation
26
23/09/2024 TITRE DE LA PRÉSENTATION
Project Leader
27
• CHAP #4.2
• Project Management : Stage 2= Planning
Based on the WBS and the OBS, you have to organize and plan the work
to do (tasks) in order to achieve the project objective.
You will define the sequence of activities/tasks that must be completed taking
into account resources, costs and delay constraints.
Used more in projects where time is the major factor rather than cost Duration
Rules: Name of
- Every identified task must be scheduled. the task
Start End
- Every task must have a predecessor and successor date date
PERT network: Program Evaluation & Review Technic (2/2) TOOL BOX
In practice:
1/ Identify a predecessor and successor for every task
2/ Evaluate the duration of every task (based on similar projects and/or experts)
3/ Build the PERT chart by positioning all the tasks in the appropriate order.
PERT Network : Program Evaluation & Review Technic (2/2) TOOL BOX
4/ Calculation of « the earliest » dates: start from the beginning of the PERT (left) and move forward to the
end (right)
Earliest Start Date: date before which the task can not start (predecessor)
Earliest End Date: Earliest start date + task duration
• CHAP # 4.2
• Project Management : Stage 2= Planning
PERT Network: Program Evaluation & Review Technic (2/2) TOOL BOX
4/ Calculation of the latest date : start from the end of the PERT (right) and move backwards to the
start (left)
Latest End Date : date beyond which the task can not end (successor)
Latest Start Date: Latest End Date at the latest - task duration
• CHAP # 4.2
• Project Management : Stage 2= Planning
PERT Network: Program Evaluation & Review Technic (2/2) TOOL BOX
WBS
1/ Task listing & structuration into
consistent and independent subsets
GANT
3/ Finalize the reference schedule
T Integrate constraints and optimize
important milestones
Projected curves / 4/ Build the projection tools to follow
indicators the project: Cost / Delay / Resources
Assess the project progress
Communicate
• CHAP # 4.2
• Project Management : Stage 2= Planning
Risk analysis
• Risk: one-time event which can jeopardize the project
TOOL BOX
FMEA.xlsx
Severity
Occurence
Detection
Criticality = Severity x
Occurence X Detection
• CHAP # 4.2
• Project Management : Stage 2= Planning
• Communicate efficiently
• Provide relevant material for the
decision makers.
http://southbayrobot.com/tag/project-governance-structure-template/
• CHAP # 4.2
• Project Management : Stage 2= Planning
Phase 3 &4:
Phase 1: Phase 2: Phase 5:
Execution &
Initiating Planning Closure
Monitoring
GO/ NO GO KO meeting
DELIVERABLES
4.3 Realization
44
• CHAP #4 • Project Management: overview
And 5 processes:
- Initiating / Definition
- Planning / preparation
- Execution
- Performance monitoring
- Closure
PMBook,4th edition
• CHAP # 4.3
• Project Management : Stage 3 = Realization
Project meetings:
- Progress: monitor the realization of Kick off
planned tasks according to the meeting
reference schedule.
Project reviews
- Coordination: manage interfaces and Steering « Ad hoc » channel
« Ritual » channel
between the subteams of the project. Committee
Project review :
- Monitor the delivery of deliverables required for a
specific project milestone.
Getting approval from decison makers to move Closure
forward. meeting
Phase 3 &4:
Phase 1: Phase 2: Phase 5:
Execution &
Initiating Planning Closure
Monitoring
GO/ NO GO KO meeting
Feasibility studies
DELIVERABLES
4.4 Closure
52
• CHAP #4 • Project Management: overview
And 5 processes:
- Initiating / Definition
- Planning / Preparation
- Execution
- Performance monitoring
- Closure
PMBook,4th edition
• CHAP # 4.4
• Project Management : Stage 4 = Closure
Closure meeting
Phase 3 &4:
Phase 1: Phase 2: Phase 5:
Execution &
Initiating Planning Closure
Monitoring
GO/ NO GO KO meeting
Feasibility studies
DELIVERABLES
Cost effectivness study Project Management Plan Meeting minutes Closure meeting minutes
Market research(es) Documentation versioning Communication plan : Closure report
Specification V1 Risk Management Plan Project reporting document Financial assessment
Project Charter Functional Analysis (updated Project schedule, Project archival
Project Manager Budget action plans, budget
55
proposal Kick off (KO) meeting tracking...)