The Solana Solar Power Project is currently tracking below its planned progress, with overall actual progress at 5.11% against a planned 20.84% as of December 15, 2024. Key areas such as engineering, procurement, and construction are significantly behind schedule, with variances of -46.68%, -18.57%, and -7.95% respectively. The project is expected to catch up in the coming weeks, but remains behind its initial timeline.

Uploaded by

Jemuel Camacho
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
14 views1 page

Weekly Dashboard

The Solana Solar Power Project is currently tracking below its planned progress, with overall actual progress at 5.11% against a planned 20.84% as of December 15, 2024. Key areas such as engineering, procurement, and construction are significantly behind schedule, with variances of -46.68%, -18.57%, and -7.95% respectively. The project is expected to catch up in the coming weeks, but remains behind its initial timeline.

Uploaded by

Jemuel Camacho
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Solana Solar Power Project - Overall Progress S-Curve

18.0% 120%
Baseline Weekly Progress %
Actual Weekly Progress %
16.0% Catch Up Weekly Progress %
Baseline Weekly Cumulative Progress % 100%
Actual Weekly Cumulative Progress %
14.0%
Catch Up Weekly Cumulative Progress %

12.0% 80%
Weekly Percentage %

Cumulative Percentage, %
10.0%
23.31% 60%
8.0%

6.0% 8.62% 40%

4.0%
20%
2.0%

0.0% 0%
08- 15- 22- 29- 06- 13- 20- 27- 03- 10- 17- 24- 01- 08- 15- 22- 29- 05- 12- 19- 26- 02- 09- 16- 23- 02- 09- 16- 23- 30- 06- 13- 20- 27- 04- 11- 18- 25- 01-
Sep- Sep- Sep- Sep- Oct- Oct- Oct- Oct- Nov- Nov- Nov- Nov- Dec- Dec- Dec- Dec- Dec- Jan- Jan- Jan- Jan- Feb- Feb- Feb- Feb- Mar- Mar- Mar- Mar- Mar- Apr- Apr- Apr- Apr- May- May- May- May- Jun-
24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 25 Project 25 25 Week25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25

Progress as of Week-Ending-15-Dec-2024
13 14 15 This Week
Previous Week Current Week Next Week
Description Weight (%) 01-Dec-24 08-Dec-24 15-Dec-24
Planned Actual Variance Planned Actual Variance Planned Catch Up Variance Planned Actual Variance
ENGINEERING 5.00% 61.38% 14.70% -46.68% 61.72% 16.42% -45.31% 74.14% 35.30% -38.84% 0.34% 1.71% 1.37%
PROCUREMENT 55.00% 22.91% 4.35% -18.57% 25.52% 10.43% -15.09% 30.35% 17.15% -13.20% 2.61% 6.09% 3.48%
CONSTRUCTION 40.00% 12.91% 4.96% -7.95% 15.48% 5.15% -10.32% 18.29% 8.82% -9.46% 2.56% 0.19% -2.38%
OVERALL 100.00% 20.84% 5.11% -15.72% 23.31% 8.62% -14.69% 27.71% 14.72% -12.99% -40 days 5.52% 7.99% 2.47%

Week 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Date 08-Sep-24 15-Sep-24 22-Sep-24 29-Sep-24 06-Oct-24 13-Oct-24 20-Oct-24 27-Oct-24 03-Nov-24 10-Nov-24 17-Nov-24 24-Nov-24 01-Dec-24 08-Dec-24 15-Dec-24 22-Dec-24 29-Dec-24 05-Jan-25 12-Jan-25 19-Jan-25
Plan Week 0.04% 0.05% 0.30% 0.49% 0.76% 0.63% 0.48% 3.32% 6.60% 2.84% 0.83% 1.97% 2.53% 2.48% 4.40% 3.37% 6.96% 9.76% 13.58% 3.61%
Plan Cumulative 0.04% 0.09% 0.39% 0.88% 1.64% 2.27% 2.75% 6.07% 12.67% 15.51% 16.34% 18.30% 20.84% 23.31% 27.71% 31.09% 38.04% 47.80% 61.39% 64.99%
Actual Week 0.00% 0.02% 0.30% 0.50% 0.29% 0.12% 0.04% 1.47% 0.15% 0.26% 1.09% 0.59% 0.28%
Actual Cumulative 0.00% 0.02% 0.31% 0.81% 1.10% 1.22% 1.26% 2.74% 2.89% 3.15% 4.24% 4.83% 5.11%
Catch Up Week 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 8.62% 6.10% 5.08% 8.66% 11.46% 15.29% 5.31%
Catch Up Cumulative 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 8.62% 14.72% 19.80% 28.46% 39.93% 55.22% 60.53%

Solana Solar Power Project - Overall Progress S-Curve


45.0% 120%
Baseline Monthly Progress %
Actual Monthly Progress %
39.78%
40.0% Catch Up Monthly Progress % 38.72%
Baseline Monthly Cumulative Progress % 100%
Actual Monthly Cumulative Progress %
35.0% 33.54%
Catch Up Monthly Cumulative Progress %

30.0% 80%

Cumulative Percentage, %
Monthly Percentage %

25.0%
20.84% 60%
19.94%
20.0%

5.11%
15.0% 40%
12.28%
11.22%
10.0%

5.81% 5.81%
20%
5.0%
1.92% 1.92% 1.56% 1.56%
0.0% 0%
September 2024 October 2024 November 2024 December 2024 January 2025 February 2025 March 2025 April 2025 May 2025

Project Month
Progress as of Month of November 2024
2 3 4
Previous Month Current Month Next Month
Description Weight (%) October 2024 November 2024 December 2024
Planned Actual Variance Planned Actual Variance Planned Catch Up Variance
ENGINEERING 5.00% 25.34% 6.54% -18.80% 61.38% 14.70% -46.68% 87.93% 87.93% 0.00%
PROCUREMENT 55.00% 10.67% 2.39% -8.28% 22.91% 4.35% -18.57% 45.22% 45.22% 0.00%
CONSTRUCTION 40.00% 6.38% 3.08% -3.30% 12.91% 4.96% -7.95% 28.77% 0.00% -28.77%
OVERALL 100.00% 9.69% 2.87% -6.81% 20.84% 5.11% -15.72% 40.77% 38.66% -2.12%

OVERALL
Month 1 2 3 4 5 6 7 8 9
Date 30-Sep-24 31-Oct-24 30-Nov-24 31-Dec-24 31-Jan-25 28-Feb-25 31-Mar-25 30-Apr-25 31-May-25
Plan Month 1.31% 8.38% 11.15% 19.94% 38.72% 11.22% 5.81% 1.92% 1.56%
Plan Cumulative 1.31% 9.69% 20.84% 40.77% 79.50% 90.71% 96.52% 98.44% 100.00%
Actual Month 0.82% 2.06% 2.24% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Actual Cumulative 0.82% 2.87% 5.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Catch Up Month 0.00% 0.00% 5.11% 33.54% 39.78% 12.28% 5.81% 1.92% 1.56%
Catch Up Cumulative 0.00% 5.11% 38.66% 78.44% 90.71% 96.52% 98.44% 100.00%