Em Ec 3
Em Ec 3
Comprehensive Examination
(EC-3 Regular)
Q.1 Name the Organization you work for. What is meant by SWOT Analysis? Carry out a
SWOT Analysis of your Organization. [4]
Q.2 Project A has an initial investment of Rs. 19.5 million and projected cash inflows of Rs.
50,00,000 for 5 years. Project B has an initial investment of Rs. 16.5 million and projected
cash inflows of Rs. 45,00,000 for 5 years. Assume the discount rate to be 9 percent during
Year 1 and thereby increases by 1 percent each year. Work out the NPV of the two
projects and compare the results. Which project should be approved? Why? [7]
Q.3 Create a time-phased budget for the project given below. [5]
7 D 9
6
13 2 15
5 C 7 15 I 18
0 0
5 2 7 15 3 18
10 H 11
0 A 3
4
0
14 1 15
0 3 3
Activity Time Phased Work Packages by Month ($000)
Task Duration Budget 0 1 2 3 4 5 6
A Preliminary Plan 3 13 4 5 4
B Detail Plan 2 5 2 3
C Hire Staff 2 7 3 4
D Select equipment 2 10 6 4
E Train 3 13 5 3 5
F Purchase Clothing 3 15 6 4 5
G Plane transportation 5 77 15 20 20 11 11
H Get custom equipment 1 10 10
I Additional equipment 3 20 10 0 10
Total budget 170
Q.4 What is meant by a time-constrained project? What is the issue with the utilization of
resources in a time-constrained problem? How do we solve it? [2]
Q.5 If the indirect costs for each duration are $1,250 for 16 weeks, $1,150 for 15 weeks,
$1,000 for 14 weeks, $900 for 13 weeks, $850 for 12 weeks, $800 for 11 weeks, and $750
for 10 weeks, compute the total costs for each duration. What is the optimum cost-time
schedule? [10]
Q.6 Given the following project baseline, and status information; develop status reports for
periods 3–4. Based on your data, what is your assessment of the current status of the
project? [5]
Cumulative PV by Period 16 37 50 65 76 81