Sgel100mw (Ac SLD
Sgel100mw (Ac SLD
LEGEND :-
1 INVERTER DUTY TRANSFORMER 30 CENTRAL INVERTER
CORE-3 CORE-3 12
1. 51N IDMT EARTH FAULT PROTECTION 41 PRV PRESSURE RELEASE VALVE
CL: PS 87T TO POWER TRANSFORMER LV SIDE CL: PS 87T TO POWER TRANSFORMER LV SIDE
13
1. DIRECTIONAL PHASE OVER CURRENT 42
67 VCB TRIP
PROTECTION TRIP
CORE-4 CORE-4
CL: PS SPARE CL: PS SPARE DIRECTIONAL EARTH FAULT
14 67N 43 SPRING CHARGED
PROTECTION SP.CH
P1 P1 50
33kV BUS PT # 1 R3 15
1. BREAKER FAILURE 44 TRIP CKT. HEALTHY-1
R3 BF TCH
33kV 110V 110V 110V
33kV VCB EDO 33kV VCB EDO
3 3 3 3 1250A 95 80 86 94 1250A 95 80 86 94
1 16 A DIGITAL AMMETER 45 VCB TEST
CORE-1:CL-0.5,10VA 25kA/ 1Sec. 25kA/ 1Sec. H TEST
2 H
E CORE-2:CL-3P,20VA E
CORE-3: OPEN DELTA (ANN-12W) R3 (ANN-12W) 17 46
ASS AMMETER SELECTOR SWITCH SER VCB SERVICE
EARTH SWITCH Bus coupler
33kV VCB EDO Bus CT
33kV EARTH SWITCH
1250A CORE-1,655-1400/1A
R3 CL:5P20 15VA 18 59 OVER VOLTAGE PROTECTION 47 SUPPLY ON
25kA/ 1Sec. ON
3.15A FUSE BAR 1400A @50°, 25kA/ 1Sec, AL. BUS BAR
BUS 33kV,
IC 1 OG-1 IC 2 IC 3 OG-2 IC 4 19 48
27 UNDER VOLTAGE PROTECTION SUPPLY OFF
95 80 86 94 OFF
51N 51 50
R3 50 50N
FROM BPT 20 63X AUX RELAY FOR TRANSFORMER 49 LOCAL / REMOTE SWITCH
R3 BF
R3 L/R
33kV VCB EDO 33kV VCB EDO 33kV VCB EDO 33kV VCB EDO 33kV VCB EDO
H 630A 95 80 86 94 H H 630A 95 80 86 94 H
630A 95 80 86 94 630A 95 80 86 94 630A 94 95 86 21 TC TRIPPING COIL 50 BREAKER CONTROL SWITCH
25kA/ 1Sec. 25kA/ 1Sec. 25kA/ 1Sec. 25kA/ 1Sec. 25kA/ 1Sec.
(ANN-12W) (ANN-12W) R3 (ANN-12W) (ANN-12W) H BCS
P1 P1 P1 P1 EMERGENCY STOP PUSH BUTTON
33kV CT 33kV CT 51N 51 50 33kV CT 33kV CT 51N 51 50 22 CLOSING COIL 51
51N 51 50 CORE-1,200/1A 51N 51 50 CORE-1,200/1A (ANN-12W) CC EPB
CORE-1,370/1A CORE-1,370/1A P1 (ELECTRICALLY)
CL:5P20 15VA 27 FROM BPT CL:5P20 15VA 27 FROM BPT CL:5P20 15VA 27 FROM BPT CL:5P20 15VA 27 FROM BPT 33kV CT
50 50 50 50 51N 51 50
50N BF 50N 50N BF 50N CORE-1,200/1A
BF BF 23 DC SUPPLY MONITORING 52 TVM
TRIVECTOR METER
CL:5P20 15VA 50
27 FROM BPT 80 WITH ABT
CORE-2,370/1A CORE-2,200/1A 50N
CL:0.5 10VA CORE-2,200/1A BF
CL:0.5 10VA CORE-2,370/1A R Y B
MFM MFM CL:0.5 10VA CL:0.5 10VA 24 80 DC FAILURE RELAY 53 PHASE INDICATION LAMP
MFM MFM CORE-2,200/1A DC H1 H2 H3
CL:0.5 10VA
FROM BUS PT FROM BUS PT MFM
FROM BUS PT 25 DR DC FAILURE RELAY 54 59 OVER VOLTAGE PROTECTION
P2 P2 P2 FROM BUS PT P2
P2 FROM BUS PT
VPI
EARTH SWITCH
VPI 26 86 MASTER TRIP RELAY
EARTH SWITCH
EARTH SWITCH EARTH SWITCH VPI
30kV LA 30kV LA
CL-II, 10kA CL-II, 10kA 27 94 ANTI PUMPING RELAY
30kV, 10kA, CL-II 30kV, 10kA, CL-II D
SURGE ARRESTER SURGE ARRESTER EARTH SWITCH 28 95 TRIP CIRCUIT SUPERVISION RELAY
INCOMER - 1 INCOMER - 2 INCOMER - 3 INCOMER - 4
29 87T TRANSFORMER DIFF. RELAY
D
33kV(E),1RX300Sqmm
AL.,AR.,XLPE CABLE
Detail- 1
33kV(E),1RX300Sqmm
AL.,AR.,XLPE CABLE
33kV(E),1RX300Sqmm
Detail-1
AL.,AR.,XLPE CABLE
Detail -1
33kV(E),1RX300Sqmm
AL.,AR.,XLPE CABLE
33kV(E),1RX300Sqmm
AL.,AR.,XLPE CABLE
30 VPI VOLTAGE PRESENCE INDICATOR
24
CT CORE-2 50 50N 59
370/1A CL:5P20,15VA 63X
51 51N 27 C
CT CORE-3
C 370/1A CL:PS 87T
P1
VPI
EARTH SWITCH
30kV, 10kA, CL-II
SURGE ARRESTER
33kV(E),1RX300SqMM.
TRAFO AUX. RELAY
AL, AR, XLPE CABLE
TRAFO ALARM TRAFO TRIP
INVERTER DUTY TRANSFORMER
17.6MVA,ONAN WITH NIFPS, WTI WTI WTI WTI WTI WTI
33kV/4x660 V LV1 LV3 (HV) OTI LV1 LV3 (HV) OTI
OCTC (-5% to +5% @ 2.5% STEP)
WTI WTI WTI WTI
Ynd11d11d11d11(AS PER INVERTER LV2 LV4 63A MOG LV2 LV4 63T PRV
MANUFACTURER RECOMMENDATION),
ONAN %Z:12.5%
4-20mA,
AT 4.4MVA BASE
WTI,OTI TO SCADA
CT (TYP.) WTI WTI WTI
TO DIFF. LV1 LV3
4650/1A (HV)
PROT. (87T)
CL: - PS
1.9/3.3KV,11R,1CX300/400Sqmm. WTI WTI
LV2 LV4 OTI
AR, AL, XLPE CABLE
CENTRAL INVERTER -1 CENTRAL INVERTER -2
CHANGEOVER
4400kW, 660V ± 10% 4400kW, 660V ± 10% B
SWITCH
@ 50°, PF .±0.95 @ 50°, PF .±0.95
33 kV AC SLD
EPC CONTRACTOR:-
PROJECT TITLE:-
100MW/ 140MWP SOLAR POWER PROJECT AT NAWANSHAHR PUNJAB
PROJECT LOCATION:-
50MW PV SOLAR POWER PLANT AT RURKI CHANDPUR
A NAME SIGN DATE DRAWING TITLE :- SCALE
A
DRWN VB 01/08/23
NTS
DSGN DR 01/08/23
PROJECTION
CHKD NM 01/08/23 SLD- SINGLE LINE DIAGRAM AC
APPD PM 01/08/23
PAPER SHEET REV.
SIZE
DWG . NO : SGEL100MW_BVG_RC_E_R000_115 A1 1 of 1 R3
TO AUX. DB (REFER AUX. SLD) RELEASED FOR PRELIMINARY SUBMISSION INFORMATION APPROVAL CONSTRUCTION
1 2 3 4 5 6 7 8