Project Management Notes MBA - III Sem
Project Management Notes MBA - III Sem
MBA - FINANCE
III Semester
Note
MBA (Finance) – III Semester Paper code: MBFM s
Project Management
Objectives
Unit - I
Unit-II
Unit - III
2
Note
s
project evaluation – Commercial vs. National Profitability –
Social Cost Benefit Analysis, Commercial or National
Profitability, social or national profitability.
Unit - IV
Unit - V
References
3
Notes
UNIT - I
Unit Structure
4
Note
s
Lesson 1.1 - Project Management – An Overview
Learning Objectives
Concept of Project
5
Notes
basically; the first is preparation and construction, and the
second, its operation. Project planning deals with specified
tasks, operations or activities which must be performed to
achieved the project
6
Note
s
goals. Any project that we may consider has an
objective, or a set of objectives, to achieve. It has to be
operated within a given set of rules, regulations,
constraints and restrictions. Implementation of projects
needs resources or inputs. Every project converts the
given inputs into outputs through a process of
implementation. The outputs in the short run lead to
outcomes, which, in the long run, should result in
impact.
8
Note
s
Characteristics of a Project
1
0
Note
s
departments is very much essential. Thus, the use of
multiple talents from various departments
(sometimes from different organizations and across
multiple geographies) becomes the key for successful
project management. For example, take the
construction of house building; the expertise of very
many professionals and skills of various people from
various fields like architect, engineers, carpenters,
painters, plumber, electrician, interior decorator,
etc, are being coordinated to complete the house
project.
Operations
Resources
Conditions or Restraints
1
1
Notes
and designs by outside agencies. The delivery system
should be planned carefully in co-ordination with the
activities to be undertaken.
1
2
Note
s
The two basic activities which normally get
completed before undertaking the installation of
equipment in any project are: (a) land acquisition, and (b)
infrastructural development. Most of the projects are
undertaken next to a river or road/railway junction, or a
busy commercial centre with a view to cutting down the
expenditure for developing the external infrastructure
needed for the project, such as road/railway points,
schools, commercial centers, and residential
accommodation, which otherwise put a heavy burden on
the project authorities. There is a general sentimental
opposition from the landowners as well as tillers to
handover their land for fear of losing their earning
opportunities, and the project team must try to cope with
such contingencies.
White Elephants
1
3
Notes
a) Project Initiation Stage: In this stage, the specifications
of the project are defined along with the clear cut
project objectives. Project teams are formed and
their major responsibilities are assigned. More
specifically, this stage defines the goals,
specifications, tasks and responsibilities.
1
4
Note
s
1
6
Note
Classification of Projects s
1) Based on Ownership
2) Based on Investment
1
7
Notes
b) Minor Projects: The minor projects in academia are
those projects which will be completed within a year
and have a maximum funding of ` 1 lakh in social
science and ` 3 lakh in case of sciences.
1
8
Note
s
4) Based on Sector
5) Based on Objective
6) Based on Nature
2
0
Note
s
into: Low-Tech projects which relay on the existing
and well established base technologies; Medium-
Tech projects which rest mainly on existing base
technologies but incorporate some new
technology or feature; High-Tech projects in which
most of the technologies employed are new, but
existent, having been developed prior to the
project’s initiation; and Super High- Tech projects
which are based primarily on new, not entirely
existent technologies.
7) Based on Time
2
1
Notes
2
2
Note
s
b) Medium term projects: These projects take a medium
term duration like 3 to 5 years. For example,
Modernization projects, computerization of
operations, etc.
8) Based on Functions
2
3
Notes
executive a strategy, for example, mergers and
acquisition projects, Core Banking Solution
project introduced in banks, etc.
2
4
Note
s
9) Based on Risk
2
5
Notes
the ac- ceptance or rejection depends on the
decision to accept or reject multiple numbers of
other projects. Such projects may be comple-
mentary or substitutes. Let us take the example of
bio fuel plant cultivation in a large scale and the
decision to set up a bio fuel manufacturing unit. In
this case, the projects are complementary to
2
6
Note
s
each other. The cash flows of the plant cultivation will
be enhanced by the existence of a nearby
manufacturing plant. Conversely, the cash flows of the
manufacturing unit will be enhanced by the exist-
ence of a nearby cultivation farm.
2
7
Notes
some projects are capital intensive while some are
labour intensive. However, as technological
advancements are taking place in every sector in a
big way, many projects are becoming more
technology intensive and less labour intensive. The
gestation period of some of the projects also is
quite long. Large scale investments are made
2
8
Note
s
in the plant and machinery. Economies of scale and
the associated cost competitiveness also prompt the
establishment of large scale organizations.
Project Management
2
9
Notes
3
0
Note
s
effectively and efficiently. It’s a strategic competency for
organizations, enabling them to tie project results to
business goals — and thus, better compete in their
markets.It has always been practiced informally, but
began to emerge as a distinct profession in the mid-20th
century. It is no longer a special-need management. It is
rapidly becoming a standard way of doing business.
Project Management Institute’s A Guide to the Project
Management Body of Knowledge (PMBOK® Guide) identifies its
recurring elements. Project management processes fall
into five groups such as initiating, planning, executing, monitoring,
controlling and closing.
3
2
Note
s
it is executed is project management. Project management
includes: identifying requirements, establishing clear and
achievable objectives, balancing the competing demands
from the different stakeholders and ensuring that a
commonality of purpose is achieved. It is clear that
unless there is a structured and scientific approach to the
practice of management, organizations would find
themselvesaimless and hence would be unable to meet
the myriad challenges that the modern era throws at
them. Hence, the importance of project management to
organizations cannot be emphasized more and several
reasons why project management is important is discussed
below.
b) Global Competition
3
3
Notes
c) Knowledge Explosion
3
4
Note
s
d) Corporate Downsizing
3
5
Notes
markets have started introducing their products and
services into these markets. Many firms are using project
management techniques to establish distribution channels
and foreign bases of operations.
3
6
Note
An Integrated Approach to Project Management s
3
7
Notes
projects. The second dimension is the socio-cultural
side and this centers on creating a temporary social
system within a larger organizational environment that
combines the talents of a divergent set of professionals
working to complete the project.
3
8
Note
Conclusion s
****
3
9
Notes
Learning Objectives
4
0
Note
Thus, Project Portfolio Management is about more s
than running multiple projects. Each portfolio of projects
needs to be assessed by its business value and adherence to
strategy. The portfolio should be designed
4
1
Notes
to achieve a defined business objective or benefit. Project
management guru Bob Buttrick summarized it when he
said; “Directing the individual project correctly will
ensure it is done right. Directing ‘all the projects’
successfully will ensure we are doing the right projects.”
Project portfolio management organizes a series of
projects into a single portfolio of reports that capture
project objectives and other critical factors. While at
individual project level it is important to know how each
project is performing, the impact of each project on the
portfolio is also important. The following questions should
be asked:
4
3
Notes
If the answer to any of these questions is no,
immediate action is needed to bring the portfolio back on
track.
a) Implementation Gap
b) Organizational Politics
4
4
Note
significant role in the selection and successful s
implementation of projects. Politics can play a role not
only in project selection but also in the aspirations
behind the projects. Individuals can enhance their
powers within the organization by managing
extraordinary and critical projects. Thus, project
portfolio management system will help in reducing the
organizational politics.
4
5
Notes
c) Resource conflicts and multitasking
a) Classification of Project
b) Selection Criteria
4
6
Note
s
In case of net present value method, the project which
gives positive NPV is selected. NPV is the excess of present
value of cash inflows over present value of cash outflows.
Non-financial criteria may include the
4
7
Notes
following: a) restoring corporate image or b) enhancing
brand image. Many organizations are committed to
corporate citizenship and support community
development projects. Thus, the social desirability of the
projects is also equally important as financial viability.
4
8
Note
the current organizational strategies; and s
b) senior management must annual decide how they wish
to balance the available organizational resources among
the different types of projects. Given these inputs, the
priority team or project office can carry out its many
responsibilities, which include supporting project sponsors
and representing the interest of the total organization.
4
9
Notes
f) Balancing the portfolio for risks and types of projects
Conclusion
5
1
Notes
the viewing glass or perspective through which individuals
see their organization and its environment. An
organization can be structured in many different ways,
depending on their objectives. The structure of an
organization will determine the modes in which it operates
and performs. Organizational structure allows the
expressed allocation of responsibilities for different
functions and processes to different entities.
Organizational structure affects organizational action in
two big ways. First, it provides the foundation on which
standard operating procedures and routines rest.
Second, it determines which individuals get to participate
in which decision-making processes, and thus to what
extent their views shape the organization’s actions.
5
3
Notes
management channels. The functional organization is also
commonly used when, given the nature of project, one
functional area plays a dominant role in completing the
project or has a dominant interest in the success of the
project. Under these circumstances, a high ranking
manager in that area is given the responsibility of
coordinating the project. The following figure shows how
project is managed within the functional organization.
5
4
Note
s
b) Organizing Projects as Dedicated Teams
➢ It is expensive
5
5
Notes
➢ Sometimes, the technological expertise of the
specialized project teams may be very limited and
that will affect the project outcomes.
5
7
Notes
arrangement. Project, heavy weight, or strong matrix is
used to describe a matrix in which the balance of
authority is strongly on the side of the project manager.
Weak/Functional Matrix
Balanced/Functional Matrix
Strong/Project Matrix
5
9
Notes
➢ As the management principle unity of command is
violated, project participants have two bosses at the
least and hence it will create stressful situations.
➢ In case of balanced matrix form, the projects get slow down.
6
1
The advantages of networked organizations include
3
4
Thus, managing projects has witnessed a lot of
changes depending on the changes in the organizational
structure from hierarchical to networkedorganizations
which are shown in above figure.
a) Organizational Considerations
3
6
Notes
➢ Number of Projects: If an organization has very few
projects, then a less formal arrangement is
sufficient. Temporary task forces can be created
on need based and the organization could
outsource project work also.
b) Project Considerations
36
Notes
recognized as one of the most effective business practices
used by successful organizations.
3
7
Notes
Understand the Impact of Culture on a PMO
38
Notes
departmental units. There are roles in the project office for
more than just project managers, including schedulers who
can
3
9
Notes
implement and track quality project schedules, and facilitators,
who can help guide projects in conjunction with a project
manager.
4
1
Notes
The PMO can also get a “project police”
reputation, which may not encourage good project
practices outside of the project office. This struc- ture is
effective when an organization is working with a large
number of complex projects and only if the culture of
the organization includes well- developed
communication and teamwork skills.
Conclusion
42
Notes
****
4
3
Notes
Learning Objectives
44
Notes
project participants for planning and measuring project
success. Scope describes what the organization expects
to deliver to the
4
5
Notes
customer when the project is complete. The project scope
should define the results to be achieved in specific,
tangible and measurable terms.
46
Notes
understanding and agreement of expectations. The
main concern is the understanding and agreement of
expectations.
4
7
Notes
and specific kinds of projects. Many projects suffer from
scope creep, which is the tendency for the project scope to
expand over time – usually by changing requirements,
specifications, and priorities.
Constrain
Enhance
Accept
48
Notes
the scope and performance or go over budget.
4
9
Notes
5
1
Notes
There are several inputs you will need to get you off on the right
foot:
5
3
Notes
certain tools as well. Finally, using these inputs and tools
you will create the following outputs:
54
Notes
Work Breakdown Structure
5
5
Notes
Work Packages
5
7
Notes
Pitfalls to Creating WBS
58
Notes
➢ WBS is not an Organizational Hierarchy: The WBS and
Organizational Hierarchy chart is never the same
thing. Although often similar in appearance, these
two documents are very different. The
Organizational Hierarchy shows things like chain
of command and lines of communication, but the
WBS is restricted simply to a project and shows
only the deliverables and scope of that project.
5
9
Notes
The WBS is an extremely valuable tool to the
project management methodology. It can make or break
a project. It sets the foundation for the rest of the
project planning. A solid WBS helps ensure proper
project baselines, estimating, resource use, scheduling,
risk analysis, and procurement.
60
Notes
commonly used scheme is numeric indention. Some
organizations use alphabet letters and most of the
organizations use the combination of both.
6
1
Notes
Project Roll-Up
6
3
Notes
Responsibility Matrix
64
Notes
Network
Person 1 Person 2 Person 3
Staff
Review Resumes R S
Interview I R S
Applicants
Hire Personnel R I I
Purchase A R
Equipment
6
5
Notes
can be defined with as much detail as makes sense.
66
Notes
RACI
6
7
Notes
the activities.
68
➢ Consulted - Those whose opinions are sought and
with whom there is two-way communication.
5
4
Notes
of work (deliverables). It’s not a list of every task: rather,
it’s a “tree” structure showing the meaningful groups of
activities that make up the main segments of the project.
5
6
Notes
Let us understand the external causes and internal
constraints of project delays.
➢ Government policies
➢ Import regulations
➢ Panic taxation
➢ Resource constraints
➢ Defense expenditure
➢ Political situation
➢ Inflation
➢ Non-development expenditure
➢ Budgetary deficits
➢ Economic stagnation
➢ Natural disasters, like earthquakes, floods, etc.
➢ Labour unrest
➢ Law and order problems
55
Notes
➢ Social turmoil like terrorists’ menace, communal vandalism, etc.
➢ Unscheduled mid-term elections
5
6
Notes
➢ Global recession, or unrest, and
➢ Interference from unexpected quarters.
Internal Constraints
5
8
Notes
➢ Price escalation because of change in exchange rates
➢ Delay in obtaining import licences
➢ Inadequate or improper liaison with customs, excise,
sales tax, police, octroi, etc.,
➢ Poor monitoring and control, and
➢ Infrequent monitoringand review
amongst members and contractors
6
0
Notes
4) What is project management?
5) Explain the importance of project management.
6) Explain the integrated approach to project
management.
7) What is project portfolio management system?
8) Explain the need for project portfolio management
system.
9) Explain the design of project portfolio management
system.
10) What is pipeline management?
11) Write short notes on
a) White elephants
b) Pearls
c) Oysters
d) bread and butter projects
12) Explain the various organization structure used in
managing projects.
13) How to manage projects in functional organizations?
14) How to manage projects within matrix structure?
15) Explain the various forms of matrix organizational
structure for managing projects.
16) How to manage projects in networked structure?
17) How to manage projects using dedicated project
teams?
18) Explain the considerations used while choosing
appropriate project management structure.
19) Explain the options available for project
management office structure.
20) Explain the steps in defining project.
21) What is work breakdown structure?
22) What are work packages?
23) Explain the process of creating work breakdown
structure.
24) Explain the pitfalls to work breakdown structure.
25) What is responsibility matrix?
26) Explain the steps in developing the responsibility
matrix.
27) What is project roll up?
61
Notes
28) What are project overruns?
29) What is time overrun?
6
2
Notes
30) What is cost overrun?
31) What are white elephants?
32) Explain the external causes of project delays.
33) Explain the internal constraints of project delays.
CASE STUDY
AmeriHealth Mercy Driving Results and Increasing Competitive
Advantage
63
Notes
implement the changes that were most important to the
organization. Using a building block approach, the PMO
developed a high-level plan that detailed, quarter by
quarter, the expected accomplishments. The AmeriHealth
Mercy Family of Companies strives to continue to grow,
support operations and
6
4
Notes
invest in its people. That’s what drives us,” says Ms.
Guerrero. She adds, “Since we’ve made the right
investments to improve organization project management,
we’ve seen the company meet its strategic and operating
plans. The benefits that we’re reaping from the enhanced
PMO are being used to fund additional project work,
including future improvements. The PMO has truly become
a strategic operations center for the organization.
According to Joanne McFall, Chief of Staff for AmeriHealth
Mercy’s Chief Operation Officer, “Our success in achieving
our strategic goals is directly linked to the effectiveness of
our overall portfolio management function. By continuing
to enhance our use of organization project management
practices, we expect to see even greater benefits in future
years.” Analyse the importance of PMO.
****
65
Notes
UNIT - II
Unit Structure
6
6
Notes
Learning Objectives
Introduction
a) Opportunity studies
b) Pre-feasibility studies
c) Techno-economic feasibility studies
Opportunity Studies
6
8
Notes
➢ Scope for forward or backward integration with
existing activities of the enterprise;
➢ Scope for diversification into related lines;
➢ Scope for expansion of existing capacity for
achieving economies of scale or for maintaining or
improving market share;
69
Notes
➢ The prevailing and expected investment climate in the
country;
➢ The industrial policies in vogue;
➢ The availability and the cost aspects of factors of
production;
➢ Opportunities for export.
Area Studies
Sub-Sectoral Studies
Resource-Based Studies
7
0
Notes
71
Notes
promotion and development agencies often provide this
information for prospective investors. The Gujarat
Industrial Development Corporation, the Gujarat
Industrial Investment Corporation and the Gujarat
State Financial Corporation have an appreciable
degree of coordination in extending all assistance to
prospective investors, in terms of information on
available locations, market situation, infrastructural
facilities, etc. and help in launching projects.
Pre-Feasibility Studies
7
2
Notes
➢ Whether, in the light of the information obtained, it is
found justifiable to go for a very comprehensive
scrutiny and analysis of the project prospects.
73
Notes
depth analysis, through further support or functional
studies. Market surveys may be necessary, or
laboratory tests may have to be carried out to
establish the attributes that the product is claimed to
possess. The production process may have to be tried
out through pilot plant tests.
7
4
Notes
taken. Their suitability to the local or domestic conditions
have to be examined carefully and the availability of
requisite skills for their proper maintenance to be
ensured.
75
Notes
choice of having a sales network or distributing through
wholesale outlets, etc. are aspects on which, at least.
Tentative decisions should be taken to guide the
feasibility study.
7
6
Notes
77
Notes
Materials input studies: The ready availability of raw
materials and other essential inputs has to be examined,
and reliable sources for these supplies have to be
identified. Need for developing proximate sources of
supply for critical items or components through vendor
development initiatives have to be assessed, as this would
involve additional project outlays. The prevailing and
anticipated price trends for these items have also to be
studied.
79
Notes
The functional or support are investigative in nature,
with reference to the specific areas of scrutiny and the
conclusions there from provide clear guidance for
proceeding with the subsequent stages of project
preparation. The support studies can precede or follow a
pre-feasibility study or a feasibility study. It is the outcome
of the felt need to examine, in depth, certain aspects that
are found to be critical, calling for closer investigation.
Such requirements may arise even after feasibility studies
have been completed.
Introduction
81
Notes
(n) Plant site, within the location
(o) Local conditions
(p) Layout and physical coverage of project
(q) Technology and equipment
(r) Civil engineering
(s) Plant organization
(t) Overhead costs
(u) Labour
(v) Staff
(w)Implementation scheduling
(x) Financial evaluation
(y) Economic evaluation
a) Executive Summary
83
Notes
interest in the project. The nature of preliminary and
subsequent studies that have proceeded from the
feasibility study should be mentioned, giving the
highlights and the costs incurred.
85
Notes
to materialize and the project slides down to disaster. We
have innumer- able examples of such projects that had
looked splendid paper, but could either produce the
quantities promised, or failed to find the market antici-
pated.
d) Demand Projections
8
6
Notes
87
Notes
➢ Identify the major factors that have influenced past
demand, and assess the extent of their influence;
➢ Project the expected impact of these factors on future demand; and
➢ Forecast the demand through extrapolation of the
influencing factors.
e) Forecasting Techniques
f) Exports Projections
8
8
Notes
➢ Countries to which these products have been, or are being, exported;
89
Notes
➢ Special aspects concerning these products, such as
quality stipulations, special selling arrangements,
etc.
➢ Other countries with export assistance or export
incentive provided by the home country, and the
prospects of their being continued or improved.
➢ Risk of violent shifts in demand due to rapid
technological changes, or changes in political
situations.
g) Market Penetration
➢ Product quality;
➢ Packaging;
➢ Marketing and distribution methods, and;
➢ The after-sales services provided.
h) Sensitivity Analysis
91
Notes
➢ Unrealistic assumptions being made with no proper justifications;
➢ Rapid technical and technological changes.
9
2
Notes
therefore, these estimates have to be carefully
prepared, after considering possible interruptions,
delays, etc. that affects production volume. Choice of
promotional methods and distribution systems, have
significant implications for product costs and
93
Notes
these have to be clearly defined and properly estimated.
It is not uncommon to come across project estimates
where the sales quantities and prices are overstated
thereby boosting up the revenues, intentionally or
otherwise.
j) Production Programme
k) Plant Capacity
9
4
Notes
study.
95
Notes
reach maximum output figure, overtime as well as
excessive consumption of factory supplies, utilities,
spare parts, and wear and tear, will inflate the normal
level of production costs. With reference to the nature
of operations, technology and also the resource and
input constraints, the feasible normal plant capacity
has to be determined and the production costs
computed on that basis.
➢ Raw materials;
➢ Processed industrial materials (intermediates or components);
➢ Manufactured (subassemblies):
➢ Auxiliary materials;
➢ Factory supplies;
➢ Utilities.
97
Notes
m) Supply Programme
n) Location
o) Plant Site
9
8
Notes
p) Local Conditions
99
Notes
project. It is interesting to note that some of the State
Industrial Develop- ment Corporations, that build
international estates and invite promoters to set up
units, work on the premise that it is sufficient of the
land for the factory structure is made available initially
and that the infrastructure fa- cilities such as roads,
water, drainage, transports, etc., can be developed in
due course as the number of units in the estate
increases. The consequence has been that the earlier
units in these industrial estates were starved of
essential infrastructure facilities and had to struggle for
survival.
10
1
Notes
r) Technology and Equipment
s) Civil Engineering
t) Plant Organization
u) Overhead Costs
1
0
Notes
percentage surcharge on material cost, or on direct
labor cost, or on the sum of the two. This is too broad
an approximation and is inadequate for a proper
assessment of project feasibility.The cost items
accruing in the different production, service and other
cost centers should be identified, listed
10
3
Notes
and the expenditure under the individual items
estimated. Depreciation charges and financing cost
should also be duly reckoned.
v) Labour
w) Staff
1
0
Notes
of commercial production. While determining the
manpower requirements during the production phase,
the necessity to requite operators and managerial staff
for certain operations and functions, well in advance, for
training and familiarization with technology and related
aspects even during the construction stage should not be
overlooked. At the same time,the size of such workforce
and stuff should be optimal, in order to avoid excessive
pre-production costs.
10
5
Notes
Where foreign collaboration is involved is
involved, the commitments on foreign experts as per
agreed terms and the cost of training of selected
employees at the collaborator’s plant have to be duly
reckoned and included in the estimates. The
arrangements for training should not be confined to
preproduction phase, but should be planned and
organized even during the operation phase, since the
upgrading of skills and management development is a
continuous process.
x) Implementation Scheduling
1
0
Notes
10
7
Notes
y) Financial evaluation
z) Economic Evaluation
10
9
Notes
Detailed project report is a complete document for
investment decision- making, approval. Detailed project
report is base document for planning the project and
implementing the project. Preparation of detailed project
report is a step in firming up the proposal. When an
investment propos- al has been approved on the basis of
functional report and the proposal is a major proposal, it
would be necessary for detailed project report to firm up
the proposal for the capital cost as well as the various
facilities. It includes:
Conclusion
****
11
1
Notes
Learning Objectives
1
1
Notes
Formation (preparation), Analysis (appraisal),
Implementation (Supervision), operation and evaluation.
11
3
Notes
All the steps given in different studies can be grouped
into three main phases viz.,
➢ Pre-investment phase
➢ Investment/Implementation phase and
➢ Operational phase
a) Pre-investment Phase
11
5
Notes
➢ Licensing and governmental clearances
➢ Finance
➢ Systems and procedure
➢ Identification of project manager
➢ Design basis, general condition for purchase and
contracts
➢ Construction resources and materials.
➢ Work packaging
b) Implementation Phase
1
1
Notes
Project and Engineering Design
11
7
Notes
Negotiations and Contractions
Construction
c) Operation Phase
1
1
Notes
achieved the objectives for which it was taken up and
whether it has created the anticipated or intended
impact. This helps in developing an insight for future
investment and better planning. Thus the life cycle of a
project narrates the methodology of developing
maintaining and controlling an investment proposal at
its various phases in the life cycle.
11
9
Notes
Project Life Cycle
12
1
Notes
➢ Cost and staffing levels are low at the start, higher
toward the end, and drop rapidly as the project
draws to a conclusion. This pattern is illustrated in
the figure below:
12
3
Notes
Stages of Project Life Cycle
a) Project Initiation
1
2
Notes
➢ The Project Management Life Cycle
➢ A list of the alternative solutions available;
➢ An analysis of the business benefits, costs, risks and
issues;
12
5
Notes
➢ A description of the preferred solution;
➢ A summarized plan for implementation.
1
2
Notes
➢ Equipment, such as office furniture, computer
equipment, station- ery and materials;
➢ Communications infrastructure, such as telephones,
computer network, e mail, Internet access, file
storage, database storage and backup facilities;
12
7
Notes
➢ Documentation, such as a project methodology,
standards, pro- cesses, forms and registers;
➢ Tools, such as accounting, project planning and risk
modeling software.
b) Project Planning
12
9
Notes
1
3
Notes
each phase in the project (in other words, the budget). The
total cost of labor, equipment and materials is calculated
and an expense schedule is defined which enables the
project manager to measure the forecast spend versus the
actual spend throughout
13
1
Notes
the project. Detailed financial planning is an extremely
important activity within the project, as the customer will
expect the final solution to have been delivered within the
allocated budget.
1
3
Notes
Create an acceptance plan: To deliver the project
successfully, you will need to gain full acceptance from the
customer that the deliverables produced by the project
meet or exceed requirements. An acceptance plan is
created to help achieve this, by clarifying the completion
criteria for each deliverable and providing a schedule of
acceptance reviews. These reviews
13
3
Notes
provide the customer with the opportunity to assess each
deliverable and provide formal acceptance that it meets the
requirements as originally stated.
1
3
Notes
13
5
Notes
c) Project Execution
Perform
communications management
1
3
Notes
The execution phase is typically the longest phase of
the project in terms of duration. It is the phase within
which the deliverables are physically constructed and
presented to the customer for acceptance.
1
3
Notes
expenses such as labor, equipment and materials costs.
Expense forms are approved by the project manager and
recorded within an expense register for auditing purposes.
1
4
Notes
Acceptance management: Acceptance management is the
process of gaining customer acceptance for deliverables
produced by the project. Acceptance forms are used to
enable project staff to request acceptance for a
deliverable, once complete. Each acceptance form
identifies the acceptance criteria, review methods and
results of the acceptance reviews undertaken.
d) Project Closure
1
4
Notes
Perform project closure: Project closure, or ‘close out’,
essentially involves winding up the project. This includes:
14
3
Notes
1
4
Notes
Project Constraints
1
4
Notes
Physical constraints are caused by contractual or
environmental conditions. For example, due to space
limitations an activity such as painting a wall may have
to be performed by only one person (Gray and Larson,
2003).
1
4
Notes
Self Assessment Questions
CASE STUDY
Feasibility Study on Hainan Project
14
9
Notes
More about the company, Lippo is one of the major
business conglomerates in Asia with businesses
geographically diversified in Hong Kong, Singapore, China,
Korea, Macau, Philippines, Malaysia, Thailand, and other
countries. Property and retailing are the key focus. Lippo
also has interests in other businesses, e.g., hotels, food
business, securities broking and banking. The Client
proposes is to build a unique mixed use development in a
landmark building in Lingshui area. The project focused on
four main property markets: Residential; Serviced
apartment; Hotel and Retail (Shopping malls including
dining and retail facilities).
****
1
5
Notes
UNIT - III
Project Evaluation
Unit Structure
15
1
Notes
Learning Objectives
1) Traditional Methods
1
5
Notes
1) Traditional Methods
= ` 10,000
x 100 = 25%
` 40,000
5,000
Pay-back period = 3 years + = 3.25 years
20,000
Decision Criterion
15
5
Notes
Ignore taxation.
Solution
Machine X Machine Y
= 18,000 = 36,000
9,000 12,000
= 2 years = 3 years
1
5
Notes
Machine X has a shorter pay-back period; hence it
should be preferred to Machine Y.
15
7
Notes
Advantages of Payback Method
15
9
Notes
b) Accounting or Average rate of Return (ARR) Method
1
6
Notes
Decision Criterion
16
1
Notes
Accounting Rate of Return due to diverse concepts of
investments as well as earnings.
1
6
Notes
Each method gives different results. This reduces the
reliability of the method.
1
6
Notes
outflow in the year the project starts commercial
production. Profit after tax before depreciation represents
cash inflows. The Net Present Value (NPV) is the difference
between the total present value of future cash inflows and
the total present value of future cash outflows.
Decision Criterion
Example
16
5
Notes
machine. Two alternative machines (X and Y) have been
suggested, each having an initial
1
6
Notes
cost of ` 20,00,000 and requiring ` 1,00,000 as additional
working capital at the end of 1st year. Earnings after
taxation are expected to be as follows:
Year 1 2 3 4 5
PV of ` 1 at .9 .8 .7 .6 .6
20% 1 3 5 8 2
Solution
16
7
Notes
Total PV of cash outflows 209100 2091000
(` 2000000 + ` 100000*.91) 0
Net Present Value 501000 525000
1
6
Notes
Recommendations
Decision Criterion
1
7
Notes
Solution
1
7
Notes
Cash Inflows=1
Thus, in case of Cash
this method the discount rate is not
Outflo
known but the cash outflowsws and cash inflows are known.
Rate of Return is calculated as follows:
I = R i.e.,
Where I = Cash Outflow / I Initial Investment,
+r
R = Cash Inflow, r = Rate of return yielded by the
Investment (or IRR).
17
3
Notes
Decision Criterion
F=I/C
1
7
Notes
After applying the first trial rate the second trial rate
is determined when the total present value of the cash
inflows is greater or less than the
17
5
Notes
total present value of cash outflows. In case the total
present value of cash inflows is less than the total present
value of cash outflows. In case the total present value of
cash inflows is less than the total present value of cash
outflows, the second trial rate taken will be lower than the
first rate. In case the present total value of cash inflows
exceeds the present total value of cash outflows, a trial
rate higher than first trial rate will be used. This process
will continue till the two flows more or less set off each
other. This will be the ‘internal rate of return’.
Example
Solution
F=I/C
17
7
Notes
The factor in case of Project A would be:
22000
F=
7000
= 3.14; [where the average cash inflow
= (12000+4000+2000+10000)/4]
22000
F=
7000
= 2.86; [where the average cash inflow
= (2000+2000+4000+20000)/4]
Project A
Discounting
Year Cash inflow (`) Present Value (`)
Factor at 10%
1 12,000 .90 10,908
9
2 4,000 .82 3,304
6
3 2,000 .75 1,502
1
4 10,000 .68 6,830
3
Total Present Value 22,544
Cash outflow 22,000
Net Present Value +544
1
7
Notes
The present value at 10% comes to ` 22,544. The
initial investment is ` 22,000. Internal rate of Return may
be taken approximately at 10%.
17
9
Notes
In case more exactness is required another trial
rate which is slightly higher than 10% (since at this rate
the present value is more than initial investment) may be
taken. Taking a rate of 12%, the following results would
emerge:
Discounting
Year Cash inflow (`) Present Value (`)
Factor at 12%
1 12,000 .893 10,716
2 4,000 .797 3,188
3 2,000 .712 1,424
4 10,000 .636 6,360
Total Present Value 21,688
Cash outflow 22,000
Net Present Value -312
22544 -22000
= 10% + x2
22544 - 21688
544
= 10% + x 2 = 10% + 1.27% =
11.27%
856
1
8
Notes
present value is - 312.
18
1
Notes
544
= 10 + x2
544+312
= 10 + 1.3 = 11.27%
Project B
Discounting
Year Cash inflow (`) Present Value (`)
Factor at 15%
1 2,000 .870 1,740
2 2,000 .756 1,512
3 4,000 .658 2,632
4 20,000 .572 11,440
Total Present Value 17,324
Cash outflow 20,000
Net Present Value -2676
Discounting
Year Cash inflow (`) Present Value (`)
Factor at 10%
1 2,000 .909 1,818
2 2,000 .826 1,652
3 4,000 .751 3,004
4 20,000 .683 13,660
Total Present Value 20,134
Cash outflow 20,000
Net Present Value +134
1
8
Notes
At 10% the present value is
+ 134 At 15% the present
value is – 2,676 10% +
134 x 5
134 + 2676
= 10 + 0.24 = 10.24%
IRR of Project A is
11.27% IRR of
Project B is 10.24%
1
8
Notes
➢ The method is based on the presumption that cash
inflow can be invested at the discounting rate in
the new projects. However, this presumption does
not always hold well because it all depends upon
the available investment opportunities.
1) General techniques
➢ Risk Adjusted Discount Rate
➢ Certainty equivalent coefficient
2) Quantitative techniques
➢ Sensitivity analysis
➢ Probability assignment
➢ Standard Deviation
➢ Coefficient of variation
➢ Decision Tree
General Techniques
1
8
Notes
certain) cash flows to risky cash flows.
18
7
Notes
Riskless cash flow means the cash flow which the
management is prepared to accept in case there is no risk
involved. Naturally, this will be lower than the cash flow
which will be there in case the project is risky. Certainty
equivalent coefficients can be calculated for estimated cash
flows of each year. They are then multiplied with the cash
flows to ascertain cash flows which may be used for the
purpose for determining IRR or NPV for capital budgeting
decisions.
Quantitative Techniques
a) Sensitivity Analysis
➢ Pessimistic,
➢ Most likely, and
➢ Optimistic out-comes associated with the project.
b) Probability Assignment
18
9
Notes
c) Standard Deviation
d) Coefficient of Variation
1
9
Notes
Standard
Coefficient of variation =
Deviation
19
1
Notes
(e) Decision Tree Analysis
19
3
Notes
to be acceptable while others may be weak or
unacceptable. The firm may proceed with the
profitable alternative or alternatives or may decide to
reconsider them because of incomplete data or other
reasons.
****
1
9
Notes
Learning Objectives
➢ Technical Evaluation
➢ Commercial Evaluation
➢ Financial Evaluation
➢ Economic Evaluation
➢ Management Evaluation
➢ Government Consents
a) Technical Evaluation
19
5
Notes
➢ It is essential to get information on the process
know how and that is available, as also the basic
engineering package and the associated technical
services covering the quality control, pollution
control effluent and wastage disposal,
collaboration arrangements for the process licence
and the consultant services for detail engineering.
b) Commercial Evaluation
19
7
Notes
➢ Market surveys done on the specific products;
➢ Forecast of the planning commission
➢ Projections of the directorate of technical
development and other specialised bodies
c) Financial Evaluation
1
9
Notes
moratorium of 2 years from the commencement of
commercial production before the repayment of the loan
starts. The loan repayment is generally expected to be
completed in 8 – 10 years of the commencement of the
commercial production.
19
9
Notes
Syndication: where a group of institutions
participate in financing the project, they come to an
understanding on the proportion in which they will be
providing funds. IDBI is generally expected to take a
substantial share in such joint financing.
20
1
Notes
return on investment etc. depending on the nature of
projects being reviewed. It is expected that the project will
have a debt service ratio ranging from 1.5 to 2 and will be
able to pay a dividend on equity of not less than 10 %
within three years of commencement of production
d) Economic Evaluation
2
0
Notes
determination for the internal rate of return on these
values will give the economic rate of return. If this is in
excess of the social rate of discount, the project merits
acceptance.
20
3
Notes
e) Management Evaluation
Government Consents
➢ Letter of intent
➢ Industrial licence
➢ Capital goods clearance
➢ Import licence
➢ Foreign exchange permission
➢ Approval of technical/financial collaboration
➢ Clearance under MRTP Act
➢ Consent of the controller of capital issues (SEBI)
2
0
Notes
for which socio-economic considerations play a significant
part, rather than mere commercial profitability. Such
projects are analyzed for their net socio-economic benefits
and the profitability analysis of such projects is known as
social
20
5
Notes
or national profitability analysis which is nothing but the
socio-economic cost benefit analysis done at the national
level.
2
0
Notes
profitability analysis is mainly used for evaluating public
investment projects. From the society’s standpoint, the
project should maximize the aggregate consumption or
the addition to the flow of goods and services in the
economy. While the individual investor looks for
maximization on his individual basis, the society’s
interest should look for maximization of the total output
of the economy. The need thus
20
7
Notes
arises to have an analysis done of social costs and social
benefits. The various inputs required for the project are
drawn out of the resources of the economy and
constitute social costs. The outputs of the project
represent the social benefits. The inputs of goods and
services and the outputs should be valued with reference
to their relative value to society.
20
9
Notes
values fail to reflect the relative worth on the society’s
value scale. From society’s stand point, goods and
services should be valued in terms of relative
contributions to consumption. In the same manner the
social value of resource should be reckoned in terms of
its opportunity cost, represented by the output or
consumption value that it is capable of yielding in its
next best alternative use.
21
1
Notes
completing the big project, we need big investment. In
social cost benefit analysis (SCBA), we see whether return
or benefits on this investment are more than its cost from
point of view of society in which we are living. In public
investment, we analyze and compare government
expenditure with total benefits to society through SCBA. It
is also a good technique of financial evaluation of a
project because we reject those projects whose benefits to
society are less than their total cost because all the
resources are drawn from the society.
2
1
Notes
c) Tax and Subsidies: Tax is levied on the earning of the
project and it will reduce the overall benefits. On
the other hand, if government gives us subsidy for
operating any project, it will count for our cost
benefit analysis.
21
3
Notes
Arriving Net Benefit of Project to Society
2
1
Notes
as a result, there may be widely differing views
about their sizes. One might
21
5
Notes
think this could be considered under uncertainty,
however the two points are rather different: two
people agreeing that an outcome follows some
probability distribution are different from them
arguing about its mean and variance.
2
1
Notes
financial angle. Together, these two agencies have the
responsibility for the planned and the coordinated
development of the country.
21
7
Notes
such, the selection of their projects requires to be
synchronized with the national plan. This
synchronization process has two stages.
➢ Growth
➢ Equitable distribution of gains
➢ Self-reliance
2
1
Notes
numeraire in terms of savings in foreign exchange.
21
9
Notes
b) UNIDO Method
2
2
Notes
(SDR) to be used for evaluation is 12 per cent and the
costs and the benefits are to be discounted at this
rate.
22
1
Notes
b) Infrastructural Investment
Conclusion
2
2
Notes
22
3
Notes
3) What are the sophisticated methods of evaluating
projects financially?
4) What is Payback method? What
are its advantages and
disadvantages?
5) What is ARR method? What are its advantages and
disadvantages?
6) What is NPV method?
7) What is PI or BC ratio?
8) What is IRR method?
9) Evaluate the discounted cash flow methods.
10) The initial cost of the project is ` 5000. What is the
payback period for this investment if the projected
cash flows from a proposed investment are ` 1000, `
2000 and ` 5000 in the 1st, 2nd and 3rd years
respectively.
11) Following are the details of two projects, calculate
NPV and PI at 10% and rank them using both the
methods. Also calculate IRR of both the projects and
rank them.
2
2
Notes
19) What are the steps in decision tree analysis?
22
5
Notes
20) Explain the project evaluation methodology followed
by financial institutions.
21) What are the dimensions of technical evaluation of projects?
22) What are the dimensions of financial evaluation of projects?
23) What are the dimensions of economic evaluation of projects?
24) What are the dimensions of management evaluation of projects?
25) What is commercial/financial profitability?
26) What are the steps involved in determination of
social or national profitability?
27) What are externalities?
28) What is social cost benefit analysis?
29) Explain the rationale for SCBA?
30) How to arrive at net benefit of project to the society?
31) Explain the factors which complicate SCBA.
32) Explain the importance of SCBA.
33) Explain the methodologies used for SCBA.
34) Explain the SCBA considerations used for
appraising various categories of
investments/projects.
CASE STUDY
Financial Evaluation of Projects
1 2 3 4
Funds (960,00 (720,000 (540,00 (900,000
needed 0) ) 0) )
Present 1,134,5 866,80 672,280 1,045,94
value 40 0 0
of cash
inflows
Net $174,54 $146,80 $132,28 $145,94
present 0 0 0 0
value
Project life 6 years 12 years 6 years 3 years
Internal 16% 14% 18% 19
rate of %
2
2
Notes
return
(IRR)
Due to limited funds, all projects cannot be accepted.
22
7
Notes
Required
****
2
2
Notes
UNIT - IV
Unit Structure
22
9
Notes
Learning Objectives
23
1
Notes
with the computer. These revisions can be communicated
to all project participants quickly (for example, via e-mail or
project Web site).
23
3
Notes
shows dependency and project flow. The following diagram
shows the WBS/ Work packages to network for a software
project:
23
5
Notes
work packages. Developing a network requires sequencing
tasks from all work packages that have measurable work.
2
3
Notes
requires specific resources, includes technical
specifications, and has cost estimates for the package.
However, dependency, sequencing, and timing of each of
these factors are not included in the work package. A
network activity can include one or more work packages.
23
7
Notes
Constructing a Project Network
Terminology
23
9
Notes
Two Approaches
2
4
Notes
that of any activities that precede it.
6. Looping is not allowed (in other words, recycling
through a set of activities cannot take place).
24
1
Notes
7. Conditional statements are not allowed (that is,
this type of statement should not appear: If
successful, do something; if not, do nothing).
8. Experience suggests that when there are multiple
starts, a common start node can be used to indicate a
clear project beginning on the network. Similarly, a
single project end node can be used to indicate a
clear ending.
2
4
Notes
2) Which activities must immediately follow this
activity? These activities are called successor
activities.
3) Which activities can occur while this activity is
taking place? This is known as a concurrent or
parallel relationship.
24
3
Notes
2
4
Notes
concurrently or simultaneously if the project manager
wishes; however, it is not a necessary condition. For
example,
24
5
Notes
pouring a concrete driveway (activity Y) can take place
while landscape planting (activity Z) is being accomplished,
but land clearing (activity X) must be completed before
activities Y and Z can start. Activities Y and Z are
considered parallel activities. Parallel paths allow
concurrent effort, which may shorten time to do a series of
activities. Activity X is sometimes referred to as a burst
activity because more than one arrow bursts from the node.
The number of arrows indicates how many activities
immediately follow activity X.
24
7
Notes
Components of PERT/CPM Network
➢ Activities, and
➢ Events
2
4
Notes
24
9
Notes
amount of time by which the start of an activity may be
delayed without affecting the overall completion time of the
project. But a critical activity has no slack. To reduce the
overall project
2
5
Notes
time, it would require more resources (at extra cost) to
reduce the time taken by the critical activities to complete.
Step 1: Begin from the start event and move towards the end event.
Step 2: Put TE = 0 for the start event.
Step 3: Go to the next event (i.e., node 2) if there is an
incoming activity for event 2, add to calculate TE of
previous event (i.e., event 1) and activity time.
Step 4: Repeat the same procedure from step 3 till the end event.
Step 1: Begin from end event and move towards the start
event. Assume that the direction of arrows is
reversed.
Step 2: Latest Time TL for the last event is the earliest time,
TE of the last event.
Step 3: Go to the next event, if there is an incoming
activity, subtract the value of TL of previous event
from the activity duration time. They arrived value is
TL for that event. If there are more than one
incoming activities, take the minimum TE value.
25
1
Notes
Step 4: Repeat the same procedure from step 2 till the start event.
2
5
Notes
d) Determination of Float and Slack Times
TFij = LS ij – ESij..................(1)
or
TFij = (TL – TE) – tij................(2)
FF ij
= (Ej – Ei) – tij.................(3)
FFij= Total float – Head event slack
IF ij
= (Ej – Li) – tij..................(4)
25
3
Notes
IFij= Free float – Tail event
slack Where tail event slack =
Li – Ei
2
5
Notes
Critical Path: After determining the earliest and the
latest scheduled times for various activities, the
minimum time required to complete the project is
calculated. In a network, among various paths, the
longest path which determines the total time duration
of the project is called the critical path. The following
conditions must be satisfied in locating the critical path
of a network.
1.TL – TE = 0
2.TLj – tij – TEj = 0
25
5
Notes
b) To determine the critical path, compute the earliest
time TE and latest time TL for each of the activity of
the project. The calculations of TE and TL are as
follows:,
TE1 = 0
TE2 = TE1 + t1, 2 = 0 + 4 = 4
TE3 = TE1 + t1, 3 = 0 + 1 =1
TE4 = max (TE2 + t2, 4 and TE3 + t3, 4)
= max (4 + 1 and 1 + 1) = max (5, 2)
= 5 days
TE5 = TE3 + t3, 6 = 1 + 6 = 7
TE6 = TE5 + t5, 6 = 7 + 4 = 11
TE7 = TE5 + t5, 7 = 7 + 8 = 15
TE8 = max (TE6 + t6, 8 and TE7 + t7, 8)
= max (11 + 1 and 15 + 2) = max (12, 17)
= 17 days
TE9 = TE4 + t4, 9 = 5 + 5 = 10
TE10 = max (TE9 + t9, 10 and TE8 + t8, 10)
= max (10 + 7 and 17 + 5) = max (17, 22)
= 22 days
TL10 = TE10 = 22
TL9 = TE10 – t9,10 = 22 – 7
= 15 TL8 = TE10 – t8, 10 =
22 – 5 = 17
TL7 = TE8 – t7, 8 = 17 – 2 = 15
TL6 = TE8 – t6, 8 = 17 – 1 = 16
TL5 = min (TE6 – t5, 6 and TE7 – t5, 7)
= min (16 – 4 and 15 –8) = min (12, 7)
= 7 days
TL4 = TL9 – t4, 9 = 15 – 5 =10
2
5
TL3 = min (TL4 – t3, 4 and TL5 – t3, 5 )
= min (10 – 1 and 7 – 6) = min (9, 1)
= 1 day
TL2 = TL4 – t2, 4 = 10 – 1 = 9
TL1 = Min (TL2 – t1, 2 and TL3 – t1, 3)
= Min (9 – 4 and 1 – 1) = 0
16
7
Notes
16
8
Notes
Project Evaluation Review Technique (PERT)
16
9
Notes
expected time of an activity is arrived at. The average or
mean (Ta) value of the activity duration is given by,
17
0
Notes
Example
16
9
Notes
Solution
17
0
Notes
Calculate the time earliest (TE) and time Latest (TL) for all the activities.
To find Z0,
17
1
Notes
= 0.0901
= 9.01%
****
17
2
Notes
Learning Objectives
17
3
Notes
A simple representation of the possible
relationship between the duration of an activity and its
direct costs appears in the following figure. Shortening
the duration on an activity will normally increase its
direct cost. A duration which implies minimum direct
cost is called the normal duration and the minimum
possible time to complete an activity is called
17
4
Notes
crash duration, but at a maximum cost. The linear
relationship shown above between these two points
implies that any intermediate duration could also be
chosen.
17
5
Notes
17
6
Notes
direct cost and indirect cost values together. The optimum
project duration can be determined as the project duration
that results in the least project total cost.
17
7
Notes
17
8
Notes
Step 4: Find the project cost by the formula
Iteration Step
Step 7: In the new Critical path select the activity with the
next minimum cost slope, and crash by one day, and
repeat this step until all the activities along the
critical path are crashed up to desired time.
Step 8: At this point all the activities are crashed and
further crashing is not possible. The crashing of non
critical activities does not alter the project duration
time and is of no use.
Step 9: To determine optimum project duration, the total
project cost is plotted against the duration time given
by figure.
17
9
Notes
Proposed Work
18
0
Notes
Step 4: Compute the cost slope (i.e., cost per unit time) for
each activity according to the following formula:Cost
slope = (Crash cost- Normal cost)/(Normal time-
Crash time)
Step 5: Among the critical path identify the activity with the
minimum cost slope, and crash the activity by 1
day.
Step 6: Calculate the project cost. Identify new critical path.
Project Cost= [(Project Direct Cost + Crashing
cost of crashed activity)
+ (Indirect Cost*project duration)]
Step 7: Now in the new critical path select the activity with
the next minimum cost slope, and crash by one day.
Step 8: Repeat this process until all the activities in the
critical path have been crashed by 1 day.
Step 9: Once all the activities along the critical path are
crashed by one day, repeat the process again i.e.,
goes tostep5.
Step 10: Find the minimum project cost and identify the
activities which do not lie along the critical path
Step 11: Now perform un crashing, i.e., un crash the
activities which do not lie along the critical path.
18
1
Notes
Solution
SA = CC – NC
ND – CD
14000 – 12000
SA = 120 - 100 = ` 100/day
SB = `
200/day
SC= `
600/day
SD= `
60/day SE =
` 120/day
SF = `
300/day
18
2
Notes
created. In addition, the activity duration cannot be less
than the crash duration.SD = ` 60/day (least-cost slope)
Maximum of 10 days can be cut from this schedule by
reducing the duration of activity D to the crash duration of
20 days.
18
3
Notes
18
4
Notes
Activity A (` 100) + activity B (` 200)
Activity A (` 100) + activity C (` 600) + activity F (` 300)
18
5
Notes
The least-cost slope will be activity A + activity B for
a cost increase of ` 300 per day. Reducing the project
duration by 5 days will add 5*300
= ` 1500 dollar crashing cost and the total project cost
would be ` 51600. Activity B cannot be crashed any more.
Resource Leveling
18
7
Notes
tasks simultaneously. When more resources such as
machines or people are needed than are available, or
perhaps a specific person is needed in both tasks, the
tasks will have to be rescheduled concurrently or even
sequentially to manage the constraint. Project planning
resource leveling is the process of resolving these
conflicts. It can also be used to balance the workload of
primary resources over the course of the project[s],
usually at the expense of one of the traditional triple
constraints (time, cost, scope). When using specially
designed project software, leveling typically means
resolving conflicts or over allocations in the project plan
by allowing the software to calculate delays and update
tasks automatically. Project management software
leveling requires delaying tasks until resources are
available. In more complex environments, resources could
be allocated across multiple, concurrent projects thus
requiring the process of resource leveling to be performed
at company level. In either definition, leveling could result
in a later project finish date if the tasks affected are in the
critical path.
Resource Allocation
18
8
Notes
18
9
Notes
resources, especially in the near term, to achieve goals for
the future. It is the process of allocating resources among
the various projects or business units. The plan has two
parts: Firstly, there is the basic allocation decision and
secondly there are contingency mechanisms. The basic
allocation decision is the choice of which items to fund in
the plan, and what level of funding it should receive, and
which to leave unfunded: the resources are allocated to
some items, not to others. There are two contingency
mechanisms. There is a priority ranking of items excluded
from the plan, showing which items to fund if more
resources should become available; and there is a priority
ranking of some items included in the plan, showing which
items should be sacrificed if total funding must be
reduced.
19
0
Notes
➢ Listing engineering parameters and designs
➢ Mobilising community participation in planning
and implementa- tion
➢ Decentralised decision-making for fast implementation
19
1
Notes
➢ Continuity of the project manager, at least till the
start of the plant
➢ Adequate training of the workers, supervisors involved
➢ Anticipating omissions, mistakes and preparing the
organisation to face crisis
➢ Minimising managerial lapses
➢ Identifying transport bottlenecks by proper liaison
➢ Communication, and following-up with vendors
and subcontractors to know the latest status and
location of project material
➢ Regular follow-up with local, national and
international financial agencies
➢ Innovative attitude and skills of the project team
➢ Adequate project information system
➢ Maintaining ecological balance and avoiding
environmental pollution
➢ Clarity of scope on project objectives
➢ Lucid description of team and sub-team tasks
➢ Lucid financial cost estimates
➢ Milestone charts and project audit reports, and
➢ Minutes of the co-ordination committees’ meetings
with contractors and government agencies
Conclusion
****
19
2
Notes
Learning Objectives
Project Appraisal
19
3
Notes
the General Insurance Corporation (GIC) and the Unit
Trust of India (UTI) have for long been actively involved
in promoting industrial projects and
19
4
Notes
participating in their operational phases and have
emerged as major stockholders in most enterprises. They
participate in and underwrite equity and debentures and
provide medium and long-term loans, often accounting for
the major part of funds employed in enterprises. Before
they commit their funds, they have to necessarily satisfy
themselves about the feasibility of the projects to be
assisted.
The Application
19
6
Notes
in principle, further details for closer scrutiny are
obtained from the promoter.
19
7
Notes
financial, economic and management aspects of the
proposal.
➢ The appraisal team holds further discussions with
the promoter and obtains required clarifications.
19
8
Notes
➢ The appraisal team prepares flash report on the
project and circulates it to the senior executives of
the participating institutions for their
consideration.
19
9
Notes
20
0
Notes
the methods of appraisal and approval, though there can be
variations in emphasis on specific aspects depending on the
nature of the project.
Project Controls
20
1
Notes
➢ Taking corrective action.
20
2
Notes
relating to duration is derived from the work breakdown
structure (WBS) database; and time-sequence data are
derived from the network and resource scheduling
decisions. The WBS defines the work in discrete work
packages that are tied to deliverables and organization
units. In addition, each work package defines the work,
duration, and budget. From the WBS, the project network
schedule is used to phase all work, resources, and budgets
into a baseline plan.
20
3
Notes
20
4
Notes
Key Programme/Project Monitors, Controls and Reports
20
6
Notes
g) Highlight Reports: The highlight reports are used to provide
the Project Board (and possibly other stakeholders)
with a summary of the stage status at intervals
defined by them and to monitor stage and project
progress. The Project Manager also uses it to advise
the Project Board of any potential problems or areas
where the Project Board could help.
20
7
Notes
business case, and an assessment of how well the
project has done against its Project Initiation
Document.
20
8
Notes
approved by the Project Board then held centrally
for the benefit of future projects. If the project is
one of a number attached to a programme this
document will also be used as input to the
programme review.
Gantt Charts
Control Charts
20
9
Notes
project schedule performance and current performance
and to estimate future schedule trends. Control charts are
also frequently used to monitor progress toward
milestones, which mark events and as such have zero
duration. The following figure shows the sample control
chart.
21
0
Notes
21
2
Notes
Work packages, Deliverables, Organization units,
Resources and Budgets for each package.
21
4
Notes
Rules for Placing Costs in Baselines
Performance Indexes
21
5
Notes
accomplished to date:
21
6
Notes
Project Percent Complete Index
21
7
Notes
Although the percent complete rule is the most-
used method of assigning budgets to baselines and for
cost control, there are two additional rules that are
very useful for reducing the overhead costs of
collecting detailed data on percent complete of
individual work packages. These rules are the 0/100
percent rule and the 50/50 rule. These two rules are
typically used for short-duration activities and/or small-
cost activities.
21
8
Notes
Forecasting Final Project Cost
Baseline changes
Contingency Reserve
22
0
Notes
to the uncertainties and risk of schedule and cost estimate
inaccuracies. Contingency reserve is not a free lunch for all
who come. Reserve funds should only be released by the
project manager on a very formal and documented basis.
Budget reserve contingency funds are not for scope
changes. Scope changes are covered by management
reserve fund.
Scope Creep
22
1
Notes
categories. Make sure costs are recorded as soon as
they are incurred so that there is a clear
understanding of actual costs. Instruct project team
members who are responsible for approving bills;
otherwise costs can quickly escalate.
22
2
Notes
d) Requirements: Use a structured approach for defining
requirements so that the delivered project matches
the expectations of project stakeholders. Rather than
waiting until the end of a project to deliver what
stakeholders want, provide interim deliverables to
make sure the organization and the stakeholders are
in agreement with project progress. Waiting until the
end of the project to share information with users
could result in project cost overruns if changes must
be made in what was delivered.
Conclusion
22
3
Notes
products (outputs). In project management controls take
two forms - event driven and time driven. Event driven
means that the control occurs because of a specific event
has taken place. Examples of event driven controls include
End-Stage Reports, completion of a Project Initiation
Document (PID) and creation of an
22
4
Notes
exception plan. Time driven controls are regular progress
feedbacks. Examples of time driven controls include
checkpoint and highlight reporting. This does not replace
the need for the Board to maintain an overall view of
progress. Monitoring is used to oversee progress of
products, outputs, and outcomes. Reporting advises the
correct people at the correct time of positive and negative
events, allowing for progression or remedial action as
appropriate. Controls then assist with both monitoring and
reporting by provision of required review points such as
End Stage Assessments.
****
22
5
Notes
Learning Objectives
Project Audits
22
6
Notes
progress. It concentrates on project’s progress and
performance and checks if conditions have changed.
22
7
Notes
Post Project Audits
The depth and detail of the project audit depends on many factors:
➢ Organization size
➢ Project importance
➢ Project type
➢ Project risk
➢ Project size
➢ Project problems
22
9
Notes
g) The audit should be completed quickly.
h) The audit leader should be given access to senior
management above the project managers.
23
1
Notes
Step 2: Data Collection and Analysis
Step 3: Reporting
23
2
Notes
a) Time Management
23
3
Notes
b) Resource Management
c) Personnel Management
d) Information Management
23
5
Notes
Project Closure
a) Normal
b) Premature
23
6
Notes
For a few projects, the project may be completed
early with some parts of the project being eliminated. If
early project closure happens, it should have the support
of all project stakeholders. The decision should be left to
the audit group, project priority team or senior
management.
23
7
Notes
c) Perpetual
d) Failed Project
e) Changed Priority
Closure Process
23
8
Notes
➢ Who will be responsible for these tasks?
➢ When will closure begin and end?
➢ How will the project be delivered?
23
9
Notes
Implementing the closedown plan includes several
wrap-up activities. Many organizations develop lengthy
lists for closing projects as they gain experience. These
are very helpful and ensure everything is taken care of.
Implementing closedown includes the following five major
activities:
Team Evaluation
24
1
Notes
Team evaluation should be beyond time, cost, and
specifications. Whether there are any other conditions
beyond these three criteria? The “characteristics of
highly effective teams” can easily be adapted as
measurements of team effectiveness.These “in-place
conditions” will support any evaluation approach for
teams and their members.
e) Life Cycle - How well did the team perform within the
life cycle of the project? Were deadlines met? If not,
identify overruns. Try to analyze what happened if
the life cycle of the project was longer than
anticipated. What could have been done differently?
24
3
Notes
f) Judge Individuality - By looking at individual
evaluations, analyze what each individual
contributed to the project. How well did each team
member do? Keep in mind that some team members
succeed in some areas while others succeed in
different areas. Did the individuals perform at a level
that was helpful to the team as a whole?
24
5
Notes
Individual Team Member and Project Manager Evaluation
Peer Evaluation
24
7
Notes
11) Explain the relationship between project time and cost.
12) Explain the crashing of project network with an example.
13) What is resource leveling?
14) What is resource allocation?
15) How to avoid cost and time overruns?
16) What is project appraisal?
17) Explain the steps in project appraisal process by
banks and financial institutions.
18) What is loan syndication?
19) What are project controls? Explain the steps in
Project Control Process.
20) What are the key project monitors, controls and reports used?
21) Explain the various project control issues.
22) What are the tools used for communicating project
schedule status?
23) Explain the need for an integrated information
system for project monitoring and control.
24) What are the steps in developing an integrated
cost/schedule system?
25) What are project baselines? What are the costs
included in baselines?
26) Explain the indices used to monitor progress.
CASE STUDY
Refurbishing Heathrow Airport Terminal 1, On Time, Within
Budget, With No Disruptions to Travelling Public
24
8
Notes
with this project that made success a big challenge.
Managing multiple stakeholders, suppliers, and
contractors within a strict deadline and budget would
ordinarily be difficult, but doing this alongside keeping the
terminal continuously open for passengers was a huge
issue that required strict planning and coordination. “Risk
had to be tightly managed and identified early on to ensure
that a solution could be found before it turned into a major
issue that would take the project off-time and off-budget.
David Buisson, PMP, Project Manager ensured that
communications management was strictly adhered to and
regular meetings are conducted. This large-scale project
had to be delivered whilst remaining completely
operational for customers—challenging enough in any
circumstances, but this was particularly the case for
Terminal 1 at Heathrow Airport given the fact that some
20 million people a year travel through the airport.
£6.3million worth of additional work was added without an
increase to the original project budget.
24
9
Notes
****
25
0
Notes
UNIT – 5
Project Management
Unit Structure
25
1
Notes
Learning Objectives
21
6
Differences between a Leader and Manager
21
7
➢ View work as an ➢ Develop new
enabling process; approaches to long-
➢ Establish strategies and standing problems and
makes decisions by open issues to new
combining people and options;
ideas; ➢ First, use their vision to
➢ Continually coordinate excite people and only
and balance opposing then develop choices
Conception
views; which give those im-
of work
ages substance;
➢ Are good at reaching
compro- mises and ➢ Focus people on shared
mediating conflicts ideals and raise their
between opposing expectations;
values and perspectives; ➢ Work from high-risk
➢ Act to limit choice; positions because of
strong dislike of
➢ Tolerate practical, mundane work.
mundane work because
of strong surviv- al
instinct which makes
them risk-averse.
➢ Prefer working with ➢ Maintain inner
others; perceptiveness that
➢ Report that solitary they can use in their
activity makes them rela- tionships with
anxious; are col- others;
laborative; ➢ Relate to people in
➢ Maintain a low level of intuitive, empathetic
emo- tional involvement way;
in relation- ships; ➢ Focus on what events
Relations ➢ Attempt to reconcile and deci- sions mean to
with others differ- ences, seek participants;
compromises, and ➢ Attract strong feelings of
establish a balance of iden- tity and difference
power; or of love and hate;
➢ Relate to people ➢ Create systems where
according to the role human relations may be
they play in a sequence turbulent, in- tense,
of events or in a and at times even disor-
21
8
decision- making ganized.
process;
➢ Focus on how things
get done; maintain
controlled, rational,
and equitable
structures;
➢ May be viewed by others
as in- scrutable,
detached, and ma-
nipulative.
21
9
➢ Report that their ➢ Reportedly have not had
adjustments to life have an easy time of it;
been straightfor- ward ➢ Lives are marked by a
and that their lives have continual struggle to
been more or less find some sense of
peaceful since birth; order;
➢ Have a sense of self as ➢ Do not take things for
a guide to conduct and granted and are not
attitude which is satisfied with the
derived from a feeling status quo;
of being at home and in
➢ Report that their “sense
harmony with their
Influence of self ” is derived from
environment;
of past a feeling of profound
➢ See themselves as separateness;
experience
conservators and
on self ➢ May work in
regulators of an existing
identify organizations, but they
order of affairs with
never belong to them;
which they personally
identify and from which ➢ Report that their sense
they gain rewards; of self is independent of
work roles,
➢ Report that their role
memberships, or other
harmo- nizes with their
social indicators of
ideals of re- sponsibility
social identity;
and duty;
➢ Seek opportunities for
➢ Perpetuate and
change (i.e.
strengthen ex- isting
technological, political,
institutions; display a
or ideological);
life development process
which fo- cuses on ➢ Support change; find
socialization. their purpose is to
profoundly alter human,
economic, and political
relationships;
➢ Display a life
development process
which focuses on
personal mastery.
Source: http://www.au.af.mil/au/awc/awcgate/sba/leadvmanage.htm
22
1
Notes
ect on track. They also innovate and adapt to ever
changing situations. They often come across deviations
from plans and introduce considerable changes in the
scope of the project and counter the unexpected threats
or opportunities.
22
1
Notes
plan. In contract, more leadership is required when the
degree of uncer- tainty encountered on projects is higher
in terms of changes in project scope, technological
problems, breakdown of relationship and coordina- tion
between people, etc. For example, strong leadership is
required for a software development project where the
parameters are always changing to meet the
developments in the industry.
1. Sponsor a project, or
2. Have an interest or a gain upon a successful completion of a project;
3. May have a positive or negative influence in the project completion.
22
2
Notes
range of individuals, many of whom do not report to
them. For example, during the course of a system
integration project, a project manager was surprised by
how much time she was spending negotiating and working
with vendors, consultants, technical specialists and other
functional managers.
22
3
Notes
When new project managers do find time to work
directly on the project, they adopt a hands-on approach to
managing the project. They choose this style not because
they are power hungry people but eager to achieve the
results. They quickly become frustrated by the slow
process and non-cooperation of various groups.
Unfortunately, as this frustration builds, the natural
temptation is to exert more pressure and get more heavily
involved in the project. These project managers quickly
earn the reputation of ‘micro managing’ and begin to lose
sight of the real goal they play in guiding a project.
Project Stakeholders
22
5
Notes
breadth and complexity of the relationships that need to be
managed distinguishes project management from regular
management. The project stakeholders include the
following:
22
6
Notes
e) Top Management: Top management approves funding
of the proj- ect and establishes priorities within the
organization. They define success and adjudicate
rewards for accomplishments. Significant
adjustments in budget, scope, and schedule typically
need their ap- proval. They have a natural vested
interest in the success of the project, but at the same
time want to be responsive to what is best to the
entire organism.
22
7
Notes
f) Project sponsors: Project sponsors champion the project
and use their influence to get approval of the project.
Their reputation is tied to the success of the project,
and they need to be kept informed of any major
developments. They defend the project when it
comes under attack and are a key project partner.
22
8
Notes
22
9
Notes
a) Identify: Who are the stakeholders on your project? A
stakeholder is anyone who has a vested interest in
the project – someone who wants it to succeed but
equally someone who doesn’t. You cannot start
managing stakeholders until you know who they are.
Who are the main groups or departments affected by
your project? Stakeholders can also be external to
your organization like the government and third
party providers as well. The identification exercise
should not be done in a vacuum: you will not be able
to complete the list yourself, so get your project team
involved too.
23
0
Notes
achieve your aims. Keep a close eye on people as
their opinions will swing between positive and
negative over the life of a project. A one-off analysis
exercise is never enough: you have to continually
monitor how people are reacting and manage
accordingly.
23
1
Notes
e) Review: People and job roles change. So do projects.
The person who put themselves forward to represent
the marketing team six months ago may not be the
right person today. If you notice that their influence
is slipping away, or they are less inclined to come to
meetings or respond to emails, then ask them if
they still want to be involved. If they say no, they
could suggest someone else who would be a relevant
addition to the team. Make sure you brief any new
stakeholder representative on their roles and
responsibili- ties, decisions in the pipeline and what
decisions you will expect of them in future.
a) Mapping Dependencies
23
2
Notes
manager and his or her key assistants need to ask the
following questions,
23
3
Notes
It is always better to overestimate rather than under
estimate de- pendencies on too often, otherwise talented
and successful project man- agers have been de-railed
because they were blindsided by some who’s position or
power that they had not anticipated. After identifying who
you are dependent on, you are ready to “step into their
shoes”, and see their project from their perspectives. To
help you do that asks yourself the fol- lowing questions:
23
5
Notes
Effective project managers initiate contact with key
payers to keep abreast of developments, anticipate
potential problems, provide encour- agement and re-enforce
the objectives and vision of the project. They are able to
intervene to resolve conflicts and prevent stalemates from
occur- ring. In essence, they “manage” the project. By
staying in touch with the various aspects of the project,
they become the focal point for information on the project.
Participants turn to them, to obtain the most current and
comprehensive information about the project, which re-
enforces as cen- tral role as project manager.
23
7
Notes
an appropriate budget, responsiveness to unexpected
needs, and a clear signal to others in the organization
about the importance of cooperation. Visible top
management support is not only critical for securing the
sup- port of other managers within an organization, but it
also is a key factor in the project manager’s ability to
motivate the project team. Nothing es- tablishes a
manager’s right to lead more tan his/her ability to defend.
To win the loyalty of team members, project managers
have to be effective advocates for their projects. They
have to be able to get top management to withdraw
unreasonable demand, provide additional resources and
recognize the accomplishment of team members. Working
relationship with top management is a common source of
concern. While it may seem difficult for a subordinate to
manage a superior, smart project managers devote
considerable time and attention to influencing and
garnering the support of top management. Project
managers have to accept profound differences in
perspective and become skilled at the art of persuading
su- periors.
d) Leading by Example
23
8
Notes
****
23
9
Notes
Learning Objectives
24
1
Notes
stake in the project. They empower people to
experience the vision on their own. According to
Bennis “They offer people opportunities to create
their own vision, to explore what the vision will
mean to their jobs and lives, and to envision their
future as part of the vision for the organization.”
(Bennis, 1997).
24
2
Notes
who are negative - they bring us down. We want
leaders with enthusiasm, with a bounce in their step,
with a can-do attitude. We want to believe that we
are part of an invigorating journey - we want to feel
alive. We tend to follow people with a can-do
attitude, not those who give us 200 reasons why
something can’t be done. Enthusiastic leaders are
committed to their goals and express this
commitment through optimism. Leadership emerges
as someone expresses such
24
3
Notes
confident commitment to a project that others want to
share his or her optimistic expectations. Enthusiasm is
contagious and effective leaders know it.
24
4
Notes
end up doing all of the work themselves. As one
project management student put it, “A good leader is
a little lazy.” An interesting perspective!
24
5
Notes
problems. A leader with a hardy attitude will take
these problems in stride. When leaders encounter a
stressful event, they consider it interesting, they feel
they can influence the outcome and they see it as an
opportunity. “Out of the uncertainty and chaos of
change, leaders rise up and articulate a new image of
the future that pulls the project together.” (Bennis
1997) And remember - never let them see you sweat.
24
6
Notes
of tools and systems make it a science. However, there
are other things in managing projects than just
applying analytical tools to help monitor, track and
control. In managing a project team, a Project Manager
needs to possess excellent analytical and organizational
skills. A technical proficiency in the specialist area of
their project is also a distinct advantage. Remember,
though, that projects
24
7
Notes
achieve their outcomes through people – a variety of
people working together in a coordinated way to
produce the desired results. How are you encouraging
peak performance from your project team? As with any
manager getting the best out of their people, you will need
to pay attention to your general leadership and
management skills. Some of these skill areas that you will
need to pay attention to are:
24
9
Notes
Discussing the ground rules will uncover hitherto
unspoken assumptions. Each team member will come to
see more clearly where other team members are
coming from and what they need from the team to get
their job done. Be sure to post the agreed ground rules
in a visible place where the teams meet regularly. The
bigger problems for project managers are those
associated with the human element: conflict resolution,
team building, coaching, mentoring and negotiation.
This workshop is intended to provide team leaders with
fundamental skills necessary to copy with this element
of the art of managing project teams.
Learning Outcomes
25
1
Notes
b) Determine Available Resources: What people,
equipment, and money will you have available to
you to achieve the project objectives? As a project
manager, you usually will not have direct control
of these resources, but will have to manage them
through matrix management. Find out how easy or
difficult that will be to do.
e) List the Big Steps: What are the major pieces of the
project? If you don’t know, start by asking your team.
It is a good idea to list the steps in chronological
order but don’t obsess about it; you can always
change the order later.
25
2
Notes
h) Create Your Baseline Plan: Get feedback on your
preliminary plan from your team and from any other
stakeholders. Adjust your timelines and work
schedules to fit the project into the available time.
Make any necessary adjustments to the preliminary
plan to produce a baseline plan.
25
3
Notes
i) Request Project Adjustment: There is almost never
enough time, money or talent assigned to a project.
Your job is to do more with the limited resources
than people expect. However, there are often limits
placed on a project that are simply unrealistic. You
need to make your case and present it to your boss
and request these unrealistic limits be changed. Ask
for the changes at the beginning of the project. Don’t
wait until it’s in trouble to ask for the changes you
need.
j) Work Your Plan, But Don’t Die For It: Making the plan
is important, but the plan can be changed. You
have a plan for driving to work every morning. If
one intersection is blocked by an accident, you
change your plan and go a different way. Do the
same with your project plans. Change them as
needed, but always keep the scope and resources
in mind.
25
4
Notes
the team is aware of what everyone else is doing.
****
25
5
Notes
Learning Objectives
Stage 1: Forming
25
7
Notes
safe. They set about gathering impressions and data
about the similarities and differences among them and
forming preferences for future sub grouping. Rules of
behavior seem to be to keep things simple and to avoid
controversy. Serious topics and feelings are avoided.
The major task functions also concern orientation.
Members attempt to become oriented to the tasks as
well as to one another. Discussion centers around
defining the scope of the task, how to approach it, and
similar concerns. To grow from this stage to the next,
each member must relinquish the comfort of non-
threatening topics and risk the possibility of conflict.
Stage 2: Storming
Stage 3: Norming
25
8
Notes
25
9
Notes
cliques dissolve. When members begin to know-and
identify with-one another, the level of trust in their
personal relations contributes to the development of group
cohesion. It is during this stage of development (assuming
the group gets this far) that people begin to experience
a sense of group belonging and a feeling of relief as a
result of resolving interpersonal conflicts. The major task
function of stage three is the data flow between group
members: They share feelings and ideas, solicit and give
feedback to one another, and explore actions related to
the task. Creativity is high. If this stage of data flow and
cohesion is attained by the group members, their
interactions are characterized by openness and sharing of
information on both a personal and task level. They feel
good about being part of an effective group. The major
drawback of the norming stage is that members may begin
to fear the inevitable future breakup of the group; they
may resist change of any sort.
Stage 4: Performing
Stage 5: Adjourning
26
0
Notes
26
1
Notes
can create some apprehension - in effect, a minor crisis.
The termination of the group is a regressive movement
from giving up control to giving up inclusion in the group.
The most effective interventions in this stage are those
that facilitate task termination and the disengagement
process.
Team Focus
26
3
Notes
Effective Team Characteristics
Factors in Leadership
a) Enthusiastic Beginner
b) Disillusioned Learner
26
4
Notes
the situation; that it is hopeless. A leader who has
disillusioned followers may be most successful adopting an
autocratic leadership style that provides leadership
expectations that could override low motivation and
competence.
26
5
Notes
c) Reluctant Contributor
d) Peak Performer
26
6
Notes
26
7
Notes
the importance of the project and the management
structure being used to complete the project. For high
priority projects which are critical to the future of the
organizations, the project manager will be given complete
freedom to choose whomever he or she deems necessary.
For less significant projects, the project manager will have
to persuade personnel from other areas within the
organization to join the team. When selecting team
members, project managers look for individuals with the
necessary experience and knowledge/technical skills
critical for project completion. At the same time they are
less obvious considerations that need to be factored into
the recruitment process such as a) problem solving ability,
availability, technological expertise, credibility, political
connections, ambition, initiative and energy.
26
9
Notes
These ground rules involve not only organizational and
procedural issues but also normative issues on how the
team will interact with each other. Though specific
procedures will vary across organizations and projects,
some of the major issues that need to be addressed
include:
a) Planning decisions
b) Tracking decisions
c) Managing change decisions; and
d) Relationship decisions
27
1
Notes
e) Establishing a Team Identity
27
3
Notes
to motivate and recognize individual contributions
include letters of commendation, public recognition for
outstanding work, job assignments and flexibility.
27
4
Notes
interchange, but as long as the disagreement furthers the
objectives of the project, then the conflict is function.
Managing dysfunctional conflict is a much more
challenging task than encouraging functional conflict
because dysfunction conflict is hard to identify.
27
5
Notes
j) Rejuvenating the Project Team
a) Groupthink
27
7
Notes
adverse consequences that could follow their
preferred course of action; and they too quickly
dismiss any alternatives that on the surface appear to
be unsatisfactory.
c) Entrepreneurs Disease
27
8
Notes
parent organization or something to overcome. When this
attitude occurs on developmental project the team
members, enthralled with their accomplishments
sometimes quit the parent organization and start their
own business. While starting a new venture may be good
for the project team, it does little for the parent
organization that sponsored and financed the development
work.
27
9
Notes
d) Team Spirit Becomes Team Infatuation
e) Going Native
Conclusion
28
0
Notes
a matrix environment where members work on multiple
projects and maintain ties to their home department.
Likewise, the isolation of dedicated project teams can be
reduced by the timely involvement of external specialists.
In either case, the active involvement of relevant members
of the parent organization at project status meetings can
help maintain the link between the project and the rest of
the organization.
28
1
Notes
If the team appears to be suffering from group think, then
the project manager can encourage functional conflict by
playing the devil’s advocate to encourage dissent. Finally,
formal team-building sessions may reveal dysfunctional
norms and refocus the attention of the team on project
objectives.
CASE STUDY
28
2
Notes
emissions from stores; depots and transport; responsible
28
3
Notes
store development (e.g. Asda’s low carbon flagship store
in Bootle, Liverpool); minimising packaging on own-
label products; continually improving waste
management practices at store level; encouraging
customer and associate recycling through ‘bring back’
facilities and ‘green’ transport. Below are examples of
the finance team’s specific contribution to some recent
projects at ASDA.
28
4
Notes
****
28
5