0% found this document useful (0 votes)
15 views4 pages

Assignment 4

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
15 views4 pages

Assignment 4

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Assignment 4

Answer the following questions:

Scheduling
1. What characteristic of the critical path times makes them critical?
2. What is a dummy activity?
3. What is “slack” and why is it important?
4. How is uncertainty in project scheduling dealt with?
5. Given the following information, draw the AON diagram:

6. Convert the AON diagram below to an AOA diagram.

7. Convert each of the following AOA diagrams into AON diagrams.


8. Given the following network,

a. What is the critical path?


b. How long will it take to complete this project?
c. Can activity B be delayed without delaying the completion of the project? If so, how
many days?

9.

*The nomenclature AB means the activity between nodes A and B.


Find
a. The AOA network and the critical path.
b. All event slacks.
c. The effect if CD slips to 6 days; to 7 days; to 8 days.
Resource Allocation
1. What is resource loading? How does it differ from resource leveling?
2. What is an activity slope and what does it indicate?
3. Name three efficiency criteria that might be considered when choosing a multi-project
scheduling system.
4. What are two methods for addressing the constrained resource allocation problem?
5. Given the following network and the additional information below,

Find,
a. Find the crash cost per day.
b. Which activities should be crashed to meet a project deadline of 10 days with a minimum
cost? Assume partial crashing.
c. Find the new cost.
d. Is partial crashing an appropriate assumption in this kind of project?
Monitoring and Information Systems
1. List some factors that would be difficult to monitor.
2. What are the primary difficulties experienced in the design of project reports?
3. Describe the three variances of an earned value chart and explain their significance.
4. What is the purpose of “earned value”? How would the progress of the project as a whole
be calculated?
5. A sales project at month 5 had an actual cost of $34,000, a planned cost of $42,000, and a
value completed of $39,000. Find the cost and schedule variances and the CPI and SPI.
6. Given an activity in an advertising project whose planned cost was $12,000 but the actual
cost to date is $10,000 so far and the value completed is only 70 percent, calculate the cost
and schedule variances. Will the client be pleased or angry?
7. For the following test marketing project at week 6:
Use the 50–50 percent completion rule for PV and EV, and calculate the cost, schedule, and
time variances. Also calculate the CPI, SPI, CSI, and the ETC and EAC.

Project Control and Project Termination


1. What is the purpose of control? To what is it directed?
2. List and briefly describe the ways projects may be terminated.
3. Identify the four reasons for project termination.
4. What does the Project Final Report include?
5. What factors are considered most important in the decision to terminate a project?
6. What issues should be considered when using the termination-by-integration method?

You might also like