Optimal Re-Planning of A 30kv Distribution Network With DG Penetration
Optimal Re-Planning of A 30kv Distribution Network With DG Penetration
1 – 2020 June
Abstract
In this paper an optimal and economic dispatch study will be performed for re-planning a large
section of Libyan Electrical distribution network, that include Electrical power plant ,considering
distribution generation (DG) penetration method instead of a conventional re-planning methods,
such as the expanding and adding methods that needs efforts and time.
The new approaches of electrical distribution system of economic operation and replanning are the
most efficient and interested to the electric power utilities now days.
The availability of high performance software's such as the MATLAB and NIPLAN helps in
redesigning and replanning of electric power system for enhancing performance and solving
system problems.
Libyan electric distribution networks are suffering many problems of voltage limits violation, high
system losses and low system performance.
The optimal power flow (OPF) with economic dispatch (ED) methods will be used to show the
benefits of using DG penetration.
Alzahra 30KV electric system is taken as the case study including AL Zahra power plant, with
different operation cases are considered includes the operation of the network as an isolated grid,
considering DG penetration during peak loads with OPF analyses.
This study shows the great effect of DG pentration with ED and OPF methods for reducing fuel
costs and power losses as well as increasing the power transfer for system transmission, the
reduction of 14.5% of fuel consumption is achieved, and about 70% of total power losses in the
studied network is reduced with an excellent performance of system voltage profile and line
loadings.
Key words: DG, optimal Re-planning, OPF, Economic Dispatch, NIPLAN
I. INTRODUCTION
The optimal power flow (OPF) has had a long history in its development it was first discussed
1950s in literature and then by CARPENTIER in 1962, then it takes a long time to become a
successful algorithm that could be applied in everyday use by the aid of fast computers and
software’s [1]. Current interest in the OPF algorithm around its ability to solve for the optimal
solution that takes account of the security operation of the system. Optimal Power Flow (OPF) is an
optimizing tool of power system operation analyses for scheduling and energy management. Use of
1
Al academia journal for Basic and Applied Sciences volume 2/No. 1 – 2020 June
the optimal power flow becoming more important because of its capabilities to deal with various
situations of power system operating modes.
This problem involves the optimization of objective functions of Optimal Power Flow (OPF) for
power system models, which are the main functions of Power Generation Operation and Control,
and for system power losses.
The aim of this paper is to propose an Optimal Dispatch calculation of ALZHRA power plant and a
study its optimal replanning with its 30kv network based on distribution generation (DG)
penetration methods.
The relation between power out puts in MW and MBTU/h are performed as shown in table (1),
using Excel software for curve fittings the heat rate curve is shown in figure (1), which similar for
all three power plant units of the chosen system.
2
Al academia journal for Basic and Applied Sciences volume 2/No. 1 – 2020 June
Mbtu/h
600
500
400
300
200
100
0
0 10 20 30 40 50 60 P(MW)
Fig (1) Heat rate curve for each thermal power plant units of the system
The heat rate equations for each generator are found to be:
𝐇 = 226.57 + 5.2392𝐏 +
0.0249𝐏 2 (1.1)
In the form of 𝐇 = 𝛂 + 𝛃𝐏 + 𝛄𝐏 𝟐
Where 𝛂 = 226.57 is constant in MBTU/h
𝛃 = 5.2392 MBTU/MWh
𝑀𝐵𝑇𝑈
𝛄 = 0.0249 (𝑀𝑊)2 ℎ
P= power output in MW
H= heat rate in MBtu/h
B- THE OBJECTIVE FUNCTION FOR SYSTEM POWER LOSSES
3
Al academia journal for Basic and Applied Sciences volume 2/No. 1 – 2020 June
Software NIPLAN is used for system simulation and analysis based OPF and ED.
220/30KV 220/30KV
220/30KV
63MVA 100MVA
100MVA
مستشفى الزهراء
1.4 km
30/11KV
8.16 km 20MVA
6.61 km 14.35 km
8.16 km 14.35 km
10 km
1 الزهراء
6.61 km
الحشان الزهراء
السوانى بئر زينوبة
المعمورة 30/11KV
2 الزهراء 30/11KV 30/11KV 30/11KV
30/11KV 30/11KV 30/11KV 20MVA
20MVA 20MVA
4.2 km
20MVA
4.2 km
16 km
3.6 km
12 km
12 km
5.5 km
10 km
منعطف الزهراء
5.5 km
10 km
1- منعطف الزهراء
9 km
1.2 km
30/11KV 30/11KV
20MVA 10MVA
6 km مفرق السواني2- بئر ترفاس بئر ترفاس
أبو لمان
30/11KV 30/11KV
الورق
1.2 km
30/11KV
30/11KV 20MVA 20MVA
20MVA
30/11KV 30/11KV البيابصة 10MVA 30/11KV
20MVA 20MVA 10MVA
10 km
5.5 km
30/11KV
20MVA
6.2 km
المايا
بئر جمال
30/11KV 30/11KV
20MVA 20MVA
العامرية
30/11KV
30/11KV 20MVA 30/11KV 30/11KV
10MVA 20MVA 20MVA
7 km
الجليدة
30/11KV 30/11KV
10MVA 10MVA
4
Al academia journal for Basic and Applied Sciences volume 2/No. 1 – 2020 June
A-Application Normal Optimal Load Flow (OPF) for the System Analysis
In this case the normal OPF is applied and the results are shown in table (2)
Table (2) the normal optimal load flow for Alzahra power generators are connected
Iteration data
Iterations: 4
Mismatch: 4.00E-05
From To P Loss Q Loss P Imp Q Imp P Gen Q Gen P Load Q Load Gen. Cost
Area/Zone Area/Zone MW MVar MW MVar MW MVar MW MVar Curr. Units
Network 10.385 48.452 58.885 205.732 178.885 151.86 168.5 103.408 1427.926
Area 1 10.385 48.452 0 0 178.885 151.86 168.5 103.408 1427.926
Zone 1 10.385 48.452 0 0 178.885 151.86 168.5 103.408 1427.926
Overloads
Nodes (lower) %
المايا 94.94
N1077349456 94.62
N1077349425 94.52
الحشان 93.95
N1077349567 92.88
N1077349666 92.87
بئر جمال 92.81
N1077349666 92.48
2-30 بئر جمال 92.22
2- بئر زينوبة 91.88
N1077364627 90.28
الجليدة 89.7
N1077349410 89.7
2- بئر ترفاس 88.62
بئر زينوبة 88.27
البيابصة 87.99
البيابصة 87.97
N1077364627 86.52
N1077349465 86.2
N1077349462 86.19
N1077349456 85.62
مفرق السواني 84.31
2-30 مفرق السواني 84.3
بئر ترفاس 83.64
السوانى 82.73
Elements % Type
L1077364630 141.77 Line
U 129.99 Line
1 129.05 Line
The results for system analysis shows that the system suffering voltage violation for most bus bars
and high loadability of some lines as shown in table (2).
Figures (3) also shows the system weaknesses on the one-line diagram of the Net Work.
P=-40.000 MW
P=-40.000 MW Q=-0.751 Mvar
Q=27.020 Mvar
P=-40.000 MW
B-1077474069 Q=27.603 Mvar
U=20.000 kV
B-1077474064
U=20.000 kV B-1077474073
U=20.000 kV
P=-24.304 MW
ف. ك022 الزهراءQ=-126.661
Q=-79.071 Mvar
محطة
P=-34.581 MW
Mvar
220/30KV 220/30KV
220/30KV
63MVA 100MVA
100MVA
MW r مستشفى الزهراء
W MW r
.000 M1.4
va km
0M r .000 Mva U=29.976 kV
40 6 va 40
P=-29.578 MW P=- 7.06P=4.524 MW 0.00 M P=- 7.60
4
8.16 km P=-23.962 MW P=-4.445 MW Q=-80.905 Mvar =-4 .751 30/11KV
Q=-72.236 Mvar Q=-34.610 Mvar Q=2 Q=3.209PMvar -0 Q=2
P=7.621 MW 20MVA
Q= 14.35 km
Q=5.428 Mvar 6.61 km
P=16.038 MW P=4.500 MW P=14.441 MW
Q=13.800 Mvar Q=2.789 Mvar Q=11.684 Mvar
14.35 km
10 km 8.16 km
P=10.261 MW P=15.742 MW 1 الزهراء P=10.213 MW
Q=7.589 Mvar Q=10.074 Mvar 6.61 km Q=7.860 Mvar
P=12.253 MW الزهراء U=30.000 kV
الحشان السوانى
Q=9.106 Mvar
U=30.016 kV بئر زينوبة
U=28.184 kV
المعمورة 2 الزهراء U=24.820 kV U=26.480 kV
Q=10.028 Mvar
30/11KV
P=14.130 MW
30/11KV 30/11KV
30/11KV U=29.336 kV 30/11KV 30/11KV U=30.000 kV 20MVA
30/11KV 20MVA 20MVA
20MVA
4.2 km
3.6 km
Q=4.638 Mvar
P=6.249 MW
P=4.631 MW
P=10.310 MW
Q=7.955 Mvar
P=12.028 MW
Q=4.346 Mvar
Q=10.393 Mvar
P=6.126 MW
Q=6.197 Mvar
P=13.729 MW
Q=4.346 Mvar
P=7.500 MW
16 km
P=9.306 MW
P=6.126 MW
Q=7.177 Mvar
12 km
Q=5.463 Mvar
منعطف الزهراء
12 km
P=7.637 MW
5.5 km
Q=4.648 Mvar
10 km
1- منعطف الزهراء
5.5 km
10 km
U=26.391 kV
P=7.739 MW
7 km
P=6.155 MW
Q=4.482 Mvar
الجليدة
U=26.910 kV
30/11KV 30/11KV
10MVA 10MVA
P=3.000 MW P=3.000 MW
Q=1.859 Mvar Q=1.859 Mvar
Legend
Overloaded Elements
Unfeeded Elements
11.000 kV
20.000 kV
30.000 kV
220.000 kV
5
Al academia journal for Basic and Applied Sciences volume 2/No. 1 – 2020 June
P=-3.914 MW
ف. ك022 الزهراءQ=-127.689
Q=-79.481 Mvar
محطة
P=-6.781 MW
Mvar
220/30KV 220/30KV
220/30KV
63MVA 100MVA
100MVA
W مستشفى الزهراء
M
17 var W MW
M r 52 var U=29.976 kV
1.2 M1.4 km 37 va 1.5 M
P=-4.137 MW -3 60 -4 94
P=-3.597 MW P=-2.123 MW P= 8.0 P=4.524 MW 0.4 M P= 9.7
8.16 km 4 -1 40 30/11KV
Q=-73.156 Mvar Q=-34.736 Mvar
Q=-82.534 Mvar P= 6.2
Q= Q=3.209 Mvar Q=
4
P=7.621 MW 2 20MVA
6.61 km Q=
Q=5.428 Mvar 14.35 km
P=8.404 MW P=4.500 MW P=3.301 MW
Q=6.038 Mvar Q=2.789 Mvar Q=2.384 Mvar
10 km 8.16 km 14.35 km
P=2.316 MW
P=5.501 MW P=7.083 MW 1 الزهراء
Q=5.296 Mvar 6.61 km Q=1.628 Mvar
Q=3.928 Mvar U=30.000 kV
P=12.253 MW الزهراء
الحشان السوانى
Q=9.105 Mvar
U=30.029 kV بئر زينوبة
U=30.000 kV U=29.621 kV
المعمورة 2 الزهراء U=29.263 kV
Q=10.027 Mvar
30/11KV 30/11KV
P=14.130 MW
30/11KV 30/11KV
30/11KV U=29.336 kV 30/11KV U=30.000 kV 20MVA
30/11KV 20MVA 20MVA
4.2 km
P=10.000 MW
P=0.013 MW
P=10.310 MW
Q=1.961 Mvar
Q=3.932 Mvar
Q=3.932 Mvar
P=6.089 MW
P=2.680 MW
Q=3.825 Mvar
P=4.093 MW
P=5.371 MW
12 km
Q=7.177 Mvar
Q=5.448 Mvar
12 km
منعطف الزهراء
P=7.633 MW
5.5 km
10 km
Q=4.648 Mvar
1- منعطف الزهراء
10 km
P=12.000 MW
5.5 km
Q=2.465 Mvar
9 km
U=29.634 kV
P=1.357 MW
7 km P=-8.898 MW
P=1.730 MW Q=-5.164 Mvar
Q=1.221 Mvar
الجليدة
U=30.000 kV
30/11KV 30/11KV
10MVA 10MVA P=-7.784 MW
Q=-5.494 Mvar
P=3.000 MW P=3.000 MW
Q=1.859 Mvar Q=1.859 Mvar
Fig (4) show the configuration line diagram with generators connected
Applying the OPF and ED analysis the results are shown in table (3)
6
Al academia journal for Basic and Applied Sciences volume 2/No. 1 – 2020 June
From table (3), the result shows that problems of the voltage violations are solved and voltage at
buses is within the limits as shown in figure (4)
Also the total losses are reduced to 3.215MW which is reduced by 68.68% of the base case the fuel
cost reduced to be 1185.578 MBTU/hr. the reduction is 16.97 %. The reduction in fuel cost is
427.923 MBTU/hr. ,that can transferred to Dinar/hr.
Also Fig (5) shows the voltage profile curve of the system busbars.
Fig (5) shows the voltage profile curve of the system busbars
7
Al academia journal for Basic and Applied Sciences volume 2/No. 1 – 2020 June
P=-12.552 MW
P=-34.388 MW Q=-8.492 Mvar
Q=-24.447 Mvar I=0.437 kA
I=1.218 kA P=-45.843 MW
B-1077474069 Q=-32.990 Mvar
I=1.630 kA
U=20.000 kV
B-1077474064 u=100.0 %
U=20.000 kV B-1077474073
u=100.0 % U=20.000 kV
u=100.0 %
P=0.000 MW
ف. ك022 الزهراءQ=0.000
Q=0.000 Mvar
I=0.000 kA
محطة
P=0.000 MW
Mvar
I=0.000 kA
MW
43 var
5.8 0 M
-4 9
P= 2.9 kA
-3 87
220/30KV Q= 1.0
220/30KV 220/30KV I=
100MVA
100MVA 63MVA
M
W مستشفى الزهراء
88 var M
W
U=29.976 kV
4.3 1 M1.4 km 52 r
-3 1 va
P= 4.4 P=4.524 kA MW 2.5 M u=99.9 %
-2 12 =-1 .492 kA
8.16 km Q= 0Q=3.209
.8 PMvar
-8 92 30/11KV
P=7.621 MW I= I=0.107 kAQ= 0.2 20MVA 14.35 km
Q=5.429 Mvar 6.61 km I=
I=0.180 kA P=8.559 MW P=3.239 MW
Q=6.291 Mvar P=4.500 MW
Q=2.789 Mvar Q=2.285 Mvar
I=0.204 kA
I=0.275 kA 14.35 kmkA
I=0.076
10 km 8.16 km P=2.315 MW
P=5.605 MW P=6.821 MW 1 الزهراء
Q=4.872 Mvar 6.61 km Q=1.627 Mvar
Q=4.097 Mvar
P=12.253 MW الزهراء
U=30.000 kV
الحشان
I=0.136 kA I=0.161 kA I=0.054 kA
السوانى
Q=9.106 Mvar
U=29.985 kV u=100.0 % بئر زينوبة
U=30.000 kV I=0.294 kA
المعمورةu=100.0 % 2 الزهراء U=29.621 kV U=29.243 kV
u=100.0 % u=98.7 %
U=29.336 kV U=30.000 kV u=97.5
30/11KV %
Q=10.032 Mvar
30/11KV
P=14.130 MW
30/11KV 30/11KV
I=0.334 kA
30/11KV 30/11KV 30/11KV 20MVA 20MVA
u=97.8 % u=100.0 % 20MVA
4.2 km
20MVA 20MVA 20MVA
20MVA 10 km
P=6.000 MW P=1.985 MW
30/11KV Q=3.718 Mvar P=7.000 MW
30/11KV
20MVA I=0.384 kA Q=4.338 Mvar Q=1.189 Mvar P=5.000 MW P=7.000 MW
20MVA 3.6 km
I=0.437 kA 4.2 km P=12.000 MW
Q=-0.028 Mvar
Q=3.099 Mvar Q=4.338 Mvar
Q=2.728 Mvar
P=0.011 MW
P=10.310 MW
Q=1.927 Mvar
Q=7.437 Mvar
P=3.849 MW
P=10.000 MW
P=2.737 MW
I=0.045 kA
10 km kA
P=4.094 MW
I=0.093 kA
Q=1.794 Mvar
I=0.412 kA
Q=3.932 Mvar
I=0.290 kA
I=0.066 kA
P=6.089 MW
P=2.578 MW
Q=7.177 Mvar
Q=3.823 Mvar
منعطف الزهراء I=0.710 kA
Q=3.932 Mvar
Q=6.197 Mvar
16 km
I=0.060 kA
P=6.089 MW
I=0.139 kA
P=5.371 MW
P=7.500 MW
12 km
Q=5.448 Mvar
12 km
I=0.127 kA
I=0.139 kA
1- الزهراء
kA منعطف
P=7.633 MW
I=0.242
I=0.001
I=0.624 kA Q=2.465 Mvar
5.5 km
Q=4.648 Mvar I=0.183 kA
10 km
5.5 km
I=0.449 kA P=12.000 MW U=29.839 kV
9 km
7 km
P=1.731 MW P=-9.000 MW
Q=1.223 Mvar Q=-5.331 Mvar
I=0.041 kA I=0.201 kA
الجليدة
U=30.000 kV
30/11KV u=100.0
30/11KV %
10MVA 10MVA P=-7.785 MW
Q=-5.495 Mvar
I=0.183 kA
P=3.000 MW P=3.000 MW
Q=1.859 Mvar Q=1.859 Mvar
I=0.172 kA I=0.172 kA
Applying the OPF and ED analysis, table (4) shows the results.
8
Al academia journal for Basic and Applied Sciences volume 2/No. 1 – 2020 June
Figure (7) shows the comparative results of system power losses between different operation
scenarios
Also figure (8) shows the voltage profile for different operation senarios
VII- CONCLUSIONS
In this paper both economical dispatch and optimal power flow were considered based on
distribution generation penteration (DG) in the network.
The study shows the benefits of using new techniques for power system replanning and redesign,
and for solving system suffered problems, and enhancing system performance.
Many case studies are performed considering DG pentration with case Economic dispatch
procedure which results in the following benefits:
• The power losses are extremely reduced by more than 70% and reactive power losses is reduced
by 32%.
• The fuel cost for the power station is reduced by 14.5%with economic dispatch.
9
Al academia journal for Basic and Applied Sciences volume 2/No. 1 – 2020 June
• The imported power from the main circuit is also reduced by 95% which reduces the main
transmission losses, and increasing its power transition ability.
• The overall voltage profile is enhanced to be within the standard limits
• The grid is stable with minimum losses when it is isolated.
Isolation operation is found to be the best solution and it can be applied to solve the over all
National Grid problems and reduces the Black Out events.
VIII- AEFERENCE
1- Wood, Allen J. Power generation, operation, and control
2- Ward ,J.B, Hale ,H, W, Digital computer solution of Power flow Problems ,ALEE
Transactions , Part III Power Apparatus and system Vol 75, June 1956.PP 398-404
3- Tinney , w.F, Hart ,C.E, Power Flow solution by Newton's Method '' IEEE
Transaction on Power Apparatus and system, Vol Pas-86 Novembr1967 pp 1449-
1460.
4- VanNess, J.E, ''Iteration Methods for Digital load Flow studies '' AIEE Transactions on
Power Apparatus and system, Vol.78A august 1959, PP583-588.
5- Stott, B.,Alsace, O., ''Fast Decoupled Load Flow,'' Lee Transactions on Power Apparatus
and Systems, Vol, PAS -93,May /June 1974,PP. 859-869
6- Carpienter, J., ''Contribution el etude do Dispatching Economies, ''Bulletin Society
Françoise Electricians, Vol 3, August 1962.
7- Carpentier, J ''Optimal power Flows '' Int. J Electric power and Energy system, Vol April
1979, PP3-15.
8- Ross, D. W., “Dynamic Economic Dispatch,” IEEE Transactions on Power Apparatus
and Systems, November/December 1980, pp. 2060-2068.
9- General electric company of Libya(GECOL) data and studies
10- The National Scientific Research Association (NSRA) Funding project “Economic
Operation Of Libyan Electric Network power plants )by Prof. A. Fadel and etal..2013
10