ID Task Task Name Duration Start Finish Predecessors Resource Names 11 Dec '22 8 Jan '23 5 Feb '23
Predecessors Resource Names 11 Dec '22 8 Jan '23 5 Feb '23 5 Mar '23 2 Apr '23
Mode S W S T M F T S W S T
1 ZULU LITHIUM PLANT CIVILS 56 days Tue 3/1/23 Mon 27/3/23
2 Priority 1 Areas 30 days Tue 3/1/23 Wed 15/2/23
3 Concrete Works 30 days Tue 3/1/23 Wed 15/2/23
4 Mica Float Plant 15 days Tue 3/1/23 Mon 23/1/23
5 Construction 13 days Tue 3/1/23 Thu 19/1/23
23 Punching 1 day Fri 20/1/23 Fri 20/1/23
27 C1 Completion Certificate 1 day Mon 23/1/23 Mon 23/1/23 26
28 Mica Filter Press 22 days Tue 3/1/23 Fri 3/2/23
29 Construction 20 days Tue 3/1/23 Wed 1/2/23
49 Punching 1 day Thu 2/2/23 Thu 2/2/23
53 C1 Completion Certificate 1 day Fri 3/2/23 Fri 3/2/23 52
54 Spodumene Float Plant 29 days Tue 3/1/23 Tue 14/2/23
55 Construction 25 days Tue 3/1/23 Wed 8/2/23
75 Punching 3 days Thu 9/2/23 Mon 13/2/23
79 C1 Completion Certificate 1 day Tue 14/2/23 Tue 14/2/23 78
80 P & H Disliming Area 17 days Tue 3/1/23 Wed 25/1/23
81 Construction 12 days Tue 3/1/23 Wed 18/1/23
100 Punching 4 days Thu 19/1/23 Tue 24/1/23
104 C1 Completion Certificate 1 day Wed 25/1/23 Wed 25/1/23 103
105 Spodumene Filter Press 30 days Tue 3/1/23 Wed 15/2/23
106 Construction 23 days Tue 3/1/23 Mon 6/2/23
126 Punching 6 days Tue 7/2/23 Tue 14/2/23
130 C1 Completion Certificate 1 day Wed 15/2/23 Wed 15/2/23 129
Task Project Summary Manual Task Start-only Deadline
Project: Zulu Lithium Civils & Pi Split Inactive Task Duration-only Finish-only Progress
Date: Wed 21/12/22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Summary Inactive Summary Manual Summary External Milestone
Page 1
ID Task Task Name Duration Start Finish Predecessors Resource Names 11 Dec '22 8 Jan '23 5 Feb '23 5 Mar '23 2 Apr '23
Mode S W S T M F T S W S T
131 Priority 2 Areas 56 days Tue 3/1/23 Mon 27/3/23
132 Mica & Spodumene Float Drain & Bundwalls 16 days Mon 20/2/23 Thu 16/3/23
133 Handover from Structural Steel Contractor 0 days Mon 20/2/23 Mon 20/2/23 22FS+20 days 20/2
134 Construction 10 days Tue 21/2/23 Wed 8/3/23 133
135 Joints Sealing 3 days Thu 9/3/23 Mon 13/3/23 134
136 Handover 3 days Tue 14/3/23 Thu 16/3/23 135
137 Air Receivers, Compresser and Electrical Panels 23 days Thu 2/2/23 Wed 8/3/23
138 Construction 18 days Thu 2/2/23 Wed 1/3/23
156 Punching 4 days Thu 2/3/23 Tue 7/3/23
160 C1 Completion Certificate 1 day Wed 8/3/23 Wed 8/3/23 159
161 Pipe Line 56 days Tue 3/1/23 Mon 27/3/23
162 Procurement 30 days Tue 3/1/23 Wed 15/2/23
166 Construction 36 days Fri 20/1/23 Thu 16/3/23
176 Punching 6 days Fri 17/3/23 Fri 24/3/23
180 C1 Completion Certificate 1 day Mon 27/3/23 Mon 27/3/23 179
181 Works Completion 0 days Mon 27/3/23 Mon 27/3/23 27,53,79,104,130,180 27/3
Task Project Summary Manual Task Start-only Deadline
Project: Zulu Lithium Civils & Pi Split Inactive Task Duration-only Finish-only Progress
Date: Wed 21/12/22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Summary Inactive Summary Manual Summary External Milestone