Zulu Lithium Civils & Pipeline Draft 3

Program works for a lithium mining project in Zimbabwe

Uploaded by

kkkk
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

ID Task Task Name Duration Start Finish Predecessors Resource Names 11 Dec '22 8 Jan '23 5 Feb '23

Predecessors Resource Names 11 Dec '22 8 Jan '23 5 Feb '23 5 Mar '23 2 Apr '23
Mode S W S T M F T S W S T
1 ZULU LITHIUM PLANT CIVILS 56 days Tue 3/1/23 Mon 27/3/23

2 Priority 1 Areas 30 days Tue 3/1/23 Wed 15/2/23

3 Concrete Works 30 days Tue 3/1/23 Wed 15/2/23

4 Mica Float Plant 15 days Tue 3/1/23 Mon 23/1/23

5 Construction 13 days Tue 3/1/23 Thu 19/1/23

23 Punching 1 day Fri 20/1/23 Fri 20/1/23

27 C1 Completion Certificate 1 day Mon 23/1/23 Mon 23/1/23 26

28 Mica Filter Press 22 days Tue 3/1/23 Fri 3/2/23

29 Construction 20 days Tue 3/1/23 Wed 1/2/23

49 Punching 1 day Thu 2/2/23 Thu 2/2/23

53 C1 Completion Certificate 1 day Fri 3/2/23 Fri 3/2/23 52

54 Spodumene Float Plant 29 days Tue 3/1/23 Tue 14/2/23

55 Construction 25 days Tue 3/1/23 Wed 8/2/23

75 Punching 3 days Thu 9/2/23 Mon 13/2/23

79 C1 Completion Certificate 1 day Tue 14/2/23 Tue 14/2/23 78

80 P & H Disliming Area 17 days Tue 3/1/23 Wed 25/1/23

81 Construction 12 days Tue 3/1/23 Wed 18/1/23

100 Punching 4 days Thu 19/1/23 Tue 24/1/23

104 C1 Completion Certificate 1 day Wed 25/1/23 Wed 25/1/23 103

105 Spodumene Filter Press 30 days Tue 3/1/23 Wed 15/2/23

106 Construction 23 days Tue 3/1/23 Mon 6/2/23

126 Punching 6 days Tue 7/2/23 Tue 14/2/23

130 C1 Completion Certificate 1 day Wed 15/2/23 Wed 15/2/23 129

Task Project Summary Manual Task Start-only Deadline

Project: Zulu Lithium Civils & Pi Split Inactive Task Duration-only Finish-only Progress
Date: Wed 21/12/22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
ID Task Task Name Duration Start Finish Predecessors Resource Names 11 Dec '22 8 Jan '23 5 Feb '23 5 Mar '23 2 Apr '23
Mode S W S T M F T S W S T
131 Priority 2 Areas 56 days Tue 3/1/23 Mon 27/3/23

132 Mica & Spodumene Float Drain & Bundwalls 16 days Mon 20/2/23 Thu 16/3/23

133 Handover from Structural Steel Contractor 0 days Mon 20/2/23 Mon 20/2/23 22FS+20 days 20/2

134 Construction 10 days Tue 21/2/23 Wed 8/3/23 133

135 Joints Sealing 3 days Thu 9/3/23 Mon 13/3/23 134

136 Handover 3 days Tue 14/3/23 Thu 16/3/23 135

137 Air Receivers, Compresser and Electrical Panels 23 days Thu 2/2/23 Wed 8/3/23

138 Construction 18 days Thu 2/2/23 Wed 1/3/23

156 Punching 4 days Thu 2/3/23 Tue 7/3/23

160 C1 Completion Certificate 1 day Wed 8/3/23 Wed 8/3/23 159

161 Pipe Line 56 days Tue 3/1/23 Mon 27/3/23

162 Procurement 30 days Tue 3/1/23 Wed 15/2/23

166 Construction 36 days Fri 20/1/23 Thu 16/3/23

176 Punching 6 days Fri 17/3/23 Fri 24/3/23

180 C1 Completion Certificate 1 day Mon 27/3/23 Mon 27/3/23 179

181 Works Completion 0 days Mon 27/3/23 Mon 27/3/23 27,53,79,104,130,180 27/3

Task Project Summary Manual Task Start-only Deadline

Project: Zulu Lithium Civils & Pi Split Inactive Task Duration-only Finish-only Progress
Date: Wed 21/12/22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2