Document Code: Effective Date:
VVSCSPPC-DVO-PRP-09 January 09, 2017
Revision: 04 Page 1 of 13
Prerequisite Programs
Preventive Maintenance Program
ENGINEERING AND MAINTENANCE GOALS
TO PROVIDE QUALITY AND CONTINUES REFRIGERATION SYSTEM OPERATION
TO PROVIDE QUALITY PREVENTIVE MAINTENANCE SCHEDULE FOR EQUIPMENT
TO MAINTAIN AND REPAIR ALL ELECTRICAL AND ALL MECHANICAL INSTALLATION AND EQUIPMENTS
TO MAINTAIN AND REPAIR COLD STORAGE FACILITIES
TO MAINTAIN AND REPAIR ADMIN BUILDING AND OTHER FACILITIES
MACHINE ROOM OPERATORS RESPONSIBILITY
MACHINE ROOM OPERATORS ARE IN CHARGE OF STARTING AND SHUTDOWN OF REFRIGERATION SYSTEM.
THEY ARE ALSO IN CHARGE FOR MAINTAINING AND MONITORING THE TEMPERATURE OF COLD STORAGE
ROOMS, DEFROSTING AND HOURLY LOG IN OF TEMPERATURE, COMPRESSORS PARAMETERS, CONDENSER
PRESSURE AND AMMONIA PUMP.
CONDUCT ROVING INSPECTION AT COLD STORAGE AND FACILITIES
CONDUCT WEEKLY WARM UP OF GENERATOR SET
IN CHARGE OF PLUG IN AND PLUG OUT OF REEFER VAN
ASSIST IN THE REPAIR AND PREVENTIVE MANTENANCE OF EQUIPMENTS
ENGINEERING AND MAINTENANCE PROCESS
STARTING OF REFRIGERATION SYSYTEM
1. SWITCH ON CONDENSER FAN MOTOR AND PUMP
2. START RUNNING HIGH STAGE COMPRESSOR AT 20% CAPACITY
3. SWITCH ON AMMONIA PUMP OF -8 SEPARATOR AND EVAPORATORS FAN OF LOADING BAY
4. START RUNNING LOW STAGE COMPRESSOR AT 20% CAPACITY
5. SWITCH ON AMMONIA PUMP OF -37 SEPARATOR AND EVAPORATORS FAN OF TWO COLD ROOMS
6. SWITCH ON AIR PURGER
7. AFTER THE SUCTION PRESSURE AND DISCHARGE PRESSURE OF HIGH STAGE AND LOW STAGE
COMPRESSOR REACH THE SET POINT VALUE THEN
8. HIGH STAGE AND LOW STAGE COMPRESSOR CAN RUN ON AUTOMATIC OPERATION
9. SWITCH ON NOW ALL COLD STORAGE ROOM EVAPORATORS FAN
10. START MONITORING OF TEMPERATURE AND PARAMETERS OF COMPRESSORS
Prepared By: Approved By:
Jaya M. Andres Jay Silvano
Documents Controller Engineering Manager
Document Code: Effective Date:
VVSCSPPC-DVO-PRP-09 January 09, 2017
Revision: 04 Page 2 of 13
Prerequisite Programs
Preventive Maintenance Program
SHUTDOWN OF REFRIGERATION SYSTEM
1. SWITCH OFF EVAPORATOR FAN OF ALL COLD ROOMS AND LOADING BAY
2. SWITCH OFF AMMONIA PUMP OF -8 SEPARATOR AND -37 SEPARATOR
3. START UNLOADING LOW STAGE COMPRESSOR
4. AT ZERO LOAD CAPACITY SWITCH OFF THE COMPRESSOR
5. START UNLOADING HIGH STAGE COMPRESSOR
6. AT ZERO LOAD CAPAPCITY SWITCH OFF THE COMPRESSOR
7. SWITCH OFF CONDENSER
8. SWITCH OFF AIR PURGER
REFRIGERATION CYCLE
STARTING FROM THE HIGH STAGE COMPRESSOR, GAS AMMONIA IS COMPRESS TO A CERTAIN HIGH
TEMPERATURE AND PRESSURE AND THEN CONDENSE AT THE EVAPORATIVE CONDENSER TO BECOME LIQUID
AMMONIA GOING AT THE RECEIVER AND THEN AT THE -37 RE CIRCULATOR, LIQUID AMMONIA AT THE RE CIRCULATOR
IS PUMP UP TO THE EVAPORATOR OF EVERY COLD STORAGE ROOMS, LIQUID AMMONIA AT EVAPORATOR BECOME
SATURATED GAS GOING BACK AT -37 RE CIRCULATOR, BOOSTER OR LOW STAGE COMPRESSOR SUCTION SATURATED
GAS TO BOOST THE TEMPERATURE AND PRESSURE OF AMMONIA GAS TO INTERCOOLER AND HIGH STAGE
COMPRESSOR SUCTION IT AND COMPRESS IT AGAIN TO A CERTAIN HIGH TEMPERATURE AND PRESSURE TO FORM A
REFRIGERATION CYCLE.
TEMPERATURE MONITORING
1. HOURLY LOG IN OF COLD STORAGE TEMPERATURE
2. HOURLY ROVING MONITORING OF DIAL AND DATA LOGGER AT COLD STORAGE
3. CONTROLING OF COLD STORAGE ROOM TEMPERATURE AT CONTROL ROOM
COMPRESSOR MONITORING
1. HOURLY LOG IN OF COMPRESSORS PARAMETERS
2. HOURLY LOG IN OF AMMONIA PUMP PRESSURE
3. HOURLY LOG IN OF CONDENSER PRESSURE
ROVING INSPECTION
1. HOURLY INSPECTION AT COLD STORAGE FOR POSSIBLE AMMONIA LEAK
2. HOURLY INSPECTION AT COLD STORAGE FOR ICE BUILD UP
3. HOURLY INSPECTION AT COLD STOREGE FOR EQUIPMENT BREAKDOWN
4. HOURLY INSPECTION AT FACILITIES FOR ANY DAMAGES
Prepared By: Approved By:
Jaya M. Andres Jay Silvano
Documents Controller Engineering Manager
Document Code: Effective Date:
VVSCSPPC-DVO-PRP-09 January 09, 2017
Revision: 04 Page 3 of 13
Prerequisite Programs
Preventive Maintenance Program
5. HOURLY INSPECTION AT FACILITIES FOR BUSTED BULBS
6. HOURLY INSPECTION AT FACLITIES FOR PLUG IN REEFER VAN
WEEKLY WARM UP OF GENERATOR SET
1. CHECK UP OF BATTERY
2. CHECK UP OF DIESEL FUEL
3. CHECK UP OF COOLANT
4. CHECK UP OF ENGINE OIL
5. STARTING UP OF GENERATOR FOR 15 MINUTES
PLUG IN AND PLUG OUT OF REEFER VAN
1. CHECK REEFER VAN IF THERE IS A CABLE WIRE AND MALE SOCKET FOR PLUG IN
2. CHECK IF THE REEFER VAN IS 440V OR 220V POWER SUPPLY
3. IF THERE IS AN AVAILABLE FEMALE SOCKET PLUG IT DIRECTLY
4. IF THERE IS NO AVAILABLE FEMALE SOCKET REMOVE MALE SOCKET AND WIRED IT AT THE
EXTENSION WIRE WE PROVIDE AT PLUG STATION
5. LOG THE TIME, REEFER VAN NUMBER, CUSTOMER NAME AND MRO NAME
6. SIGN IT WITH THE CUSTOMER AND CHECKER
7. LOG THE DATA AT PLUG IN AND OUT LOG BOOK
ENGINEERING AND MAINTENANCE PREVENTIVE MAINTENANCE SCHEDULE
COMPRESSOR
1. SEMI ANNUAL REPLACEMENT OF REFRIGERATION OIL
2. SEMI ANNUAL COMPRESSOR MOTOR BEARING LUBRICATION
3. CLEANING OF OIL STRAINER
4. CLEANING OF SUCTION STRAINER
5. CHECKING OF COUPLING
6. CHECKING OF ELECTRICAL CONNECTION
7. CHECKING OF SENSOR AND CALIBRATION IF NEEDED
FORKLIFTS
1. YEARLY REPLACEMENT OF HYDRAULIC OIL
Prepared By: Approved By:
Jaya M. Andres Jay Silvano
Documents Controller Engineering Manager
Document Code: Effective Date:
VVSCSPPC-DVO-PRP-09 January 09, 2017
Revision: 04 Page 4 of 13
Prerequisite Programs
Preventive Maintenance Program
2. LUBRICATION OF LIFT MAST, MAST ROLLER, CHAIN AND CHAIN PULLEYS
3. LUBRICATION OF FORK CARRAGE
4. CHECK DISTILLED WATER OF BATTERY
5. CHECK LOAD WHEEL FOR DAMAGES AND DEFORMATION
6. CHECK BRAKE FLUID
7. CHECK HYDRAULIC HOSE LINE
8. COORDINATE WITH THE THIRD PARTY SERVICE PROVIDER FOR IMMEDIATE REPAIR OR SERVICE
EVAPORATIVE CONDENSER
1. THIRD PARTY SERVICE PROVIDER
2. DESCALING OF EVAPORATIVE COIL
3. HIGH PRESSURE WASHER CLEANING
4. SERVICE OF DIAMAGNETISM
EVAPORATOR FAN
1. FAN MOTOR REWINDING
2. INSPECTION OF AMPERES
3. INSPECTION OF VIBRATION
4. REMOVAL OF ICE BUILD UP
MAIN TRANSFORMER
1. THIRD PARTY SERVICE PROVIDER
2. INSULATION RESISTANCE TEST
3. WINDING RESISTANCE TEST
4. TRANSFORMER RATIO TEST
5. POLARIZATION TEST
6. TRANFORMER OIL TEST
7. OIL LEAK INSPECTION
VFD (VARIABLE FREQUENCY DRIVE
1. THIRD PARTY SERVICE PROVIDER
2. CLEAN FAN PCV BOARD AND CAPACITOR
3. CALIBRATION OF SENSOR
Prepared By: Approved By:
Jaya M. Andres Jay Silvano
Documents Controller Engineering Manager
Document Code: Effective Date:
VVSCSPPC-DVO-PRP-09 January 09, 2017
Revision: 04 Page 5 of 13
Prerequisite Programs
Preventive Maintenance Program
4. CLEANING OF FILTERS
HAND PALLETS
1. REPLACEMENT OF HYDRAULIC OIL
2. REPLACEMENT OF DEFECTIVE TIRE WHEEL AND BEARING
3. REPLACEMENT OF OIL SEAL
4. REPLACEMENT OF COMPRESSION SPRING
5. REPLACEMENT OF SHAFTING
FACILITY MAINTENANCE
1. REPLACEMENT OF BUSTED BULBS
2. REPAINTING WORKS
3. CIVIL WORKS
4. DOOR REPAIR
5. LEAK REPAIR
PREVENTIVE MAINTENANCE SCHEDULE OF COMPRESSOR
CHANGE OIL EVERY 6 MONTHS
COMPRESSOR MOTOR BEARING LUBRICATION
7 DRUMS OF CAPELLA OIL
1 PAIL OF POLYREX GREASE
PREVENTIVE MAINTENANCE SCHEDULE OF HAND PALLET
CHANGE OR TOP UP OIL EVERY 6 MONTHS
WHEEL BEARING LUBRICATION OR REPLACEMENT
3 PAILS OF HYDRAULIC OIL
1 PAIL OF GREASE
PREVENTIVE MAINTENANCE SCHEDULE OF FORKLIFT
CHANGE OR TOP UP OIL EVERY 6 MONTHS
MAST,CHAIN AND MAST BEARING LUBRICATION
EVERY WEEK BATTERY SOLUTION TOP UP
3 PAILS OF HYDRAULIC OIL
1 PAIL FOOD GRADE GREASE
Prepared By: Approved By:
Jaya M. Andres Jay Silvano
Documents Controller Engineering Manager
Document Code: Effective Date:
VVSCSPPC-DVO-PRP-09 January 09, 2017
Revision: 04 Page 6 of 13
Prerequisite Programs
Preventive Maintenance Program
10 GALLONS OF DISTILLED WATER
PREVENTIVE MAINTENANCE SCHEDULE OF REFIGERATION SYSTEM
ONCE A YEAR CHARGING OF AMMONIA
10 CYLINDRICAL TANK OF AMMONIA
PREVENTIVE MAINTENANCE SCHEDULE OF EVAPORATOR
REWINDING OF FAN MOTOR
PREVENTIVE MAINTENANCE SCHEDULE OF EVAPORATIVE CONDENSER
QUARTERLY COIL DESCALING
THEOVERM YEARLY CONTRACT FOR DESCALING
PREVENTIVE MAINTENANCE SCHEDULE OF GENERATOR SET
EMISSION TESTING EVERY 6 MONTHS
CHANGE OIL EVERY 10K RUNNING HOURS
YEARLY TOP UP OF FUEL
RENEW PERMIT TO OPERATE AIR
MAINTENANCE WORK AT COLD STORAGE AND ADMIN OFFICE
REPLACEMENT OF 250 WATTS METAL HALLIDE BUSTED BULB
REPLACEMENT OF 250 WATTS BALLAST AND CAPACITOR
REPLACEMENT OF 36 WATTS FLOURESCENT BUSTED BULB
REPLACEMENT OF ELECTRONIC BALLAST
REPLACEMENT OF DAMAGE PLASTIC CURTAIN
REPAINTING WORKS
REPLACEMENT OF LOAD CELL FOR WEIGHING SCALE
WATER DISCHARGE PERMIT
WATER DISCHARGE TEST EVERY MONTH
RENEWAL OF WATER DISCHARGE PERMIT
PREVENTIVE MAINTENANCE SCHEDULE OF VARIABLE FREQUENCY DRIVE ( VFD )
ONCE A YEAR MAINTENANCE SERVICE BY DANFOSS
PREVENTIVE MAINTENANCE SCHEDULE OF 2MV TRANSFORMER
ONCE A YEAR MAINTENANCE SERVICE BY MEGA POWER
Prepared By: Approved By:
Jaya M. Andres Jay Silvano
Documents Controller Engineering Manager
Document Code: Effective Date:
VVSCSPPC-DVO-PRP-09 January 09, 2017
Revision: 04 Page 7 of 13
Prerequisite Programs
Preventive Maintenance Program
LIST OF MACHINES AND EQUIPTMENT
1 UNIT GENERATOR SET
BRAND NAME : CATERPILLAR
MODEL : SR4
SERIAL NUMBER: GPA 02632
STAND BY POWER: 1562 KVA, 1250 KW
VOLTAGE : 440 VOLTS
CURRENT : 1878 AMPERES
PRIME MOVER MODEL: 3512
SERIAL NUMBER: 1KZ01587
FUEL CONSUMPTION: 100 LITERS/ HOUR
2 UNITS SCREW COMPRESSOR ( BOOSTER )
BRAND NAME : FRICK
MODEL : RWF 11- 177
CAPACITY : 407 KW
TE / TC : - 37 C/ -8 C
REFRIGERANT : R717
PC : 91.2 KW
MOTOR RATING: 125 KW / 150 HP
RUNNING SPEED: 3600 RPM
CURRENT : 205.267 AMPERES
VOLTAGE : 440 VOLTS, 3 PHASE, 60 HZ
1 UNIT SCREW COMPRESSOR ( HI- STAGE )
BRAND NAME : FRICK
MODEL : RWF 11- 222
CAPACITY : 1552.4 KW
TE / TC : -8 C/ +35 C
REFRIGERANT : R717
PC : 386.1 KW
MOTOR RATING: 429 KW / 517 HP
RUNNING SPEED: 3600 RPM
CURRENT : 704.479 AMPERES
VOLTAGE : 440 VOLTS, 3 PHASE, 60 HZ
1 UNIT SCREW COMPRESSOR ( SWING )
BRAND NAME : FRICK
MODEL : RWF 11-222
CAPACITY : 1552.4 KW cond. 1 / 511.1 KW cond. 2
TE / TC : -8 C/ +35 C cond. 1 / -37 C/ -8 C cond. 2
REFRIGERANT : R717
PC : 386.1 KW cond. 1 / 112 KW cond. 2
MOTOR RATING: 429 KW / 517 HP
RUNNING SPEED: 3600 RPM
CURRENT : 704.479 AMPERES
VOLTAGE : 440 VOLTS, 3 PHASE, 60 HZ
Prepared By: Approved By:
Jaya M. Andres Jay Silvano
Documents Controller Engineering Manager
Document Code: Effective Date:
VVSCSPPC-DVO-PRP-09 January 09, 2017
Revision: 04 Page 8 of 13
Prerequisite Programs
Preventive Maintenance Program
1 UNIT SCREW COMPRESSOR ( BOOSTER SMALL ) FROM VVS 2 (ON GOING REPLACEMENT)
BRAND NAME : SABROE
MODEL : SAB 151E
CAPACITY : 262 KW
TE / TC : -37 C / -8 C
REFRIGERANT : R717
PC : 64.4KW
MOTOR RATING: 86 KW / 103.75 HP
RUNNING SPEED: 3600 RPM
CURRENT : 141.22 AMPERES
VOLTAGE : 440 VOLTS, 3 PHASE, 60 HZ
1 UNIT SCREW COMPRESSOR ( HIGH STAGE SMALL ) FROM VVS 1
ON GOING REPLACEMENT
BRAND NAME : SABROE
MODEL : SAB 163
CAPACITY : 762 KW
TE / TC : -8 C / +35 C
REFRIGERANT : R717
PC : 222.1 KW
MOTOR RATING: 280 KW / 267.94 HP
RUNNING SPEED: 3600 RPM
CURRENT : 364.72 AMPERES
VOLTAGE : 440 VOLTS, 3 PHASE, 60 HZ
2 UNITS EVAPORATIVE CONDENSER
BRAND NAME : SNOWKEY
MODEL : SEC – 1585
CAPACITY : 1150 KW / 283 TONS per unit
REFRIGERANT : R717
PUMP MOTOR : 5.5 KW
FAN MOTOR : 5 X 4 KW
VOLTAGE : 440 VOLTS, 3 PHASE, 60 HZ
CIRCULATION RATE : 850 gallons per minute
EVAPORATION : 7.65 gallons per minute
RATE OF MAKE UP WATER : 12.75 gallons per minute
1 UNIT EVAPORATIVE CONDENSER
BRAND NAME : SNOWKEY
MODEL : SEC – 2490
CAPACITY : 1844 KW / 566 TONS
REFIGERANT : R717
PUMP MOTOR : 2 X 5.5 KW
FAN MOTOR : 2 X 11 KW
VOLTAGE : 440 VOLTS, 3 PHASE, 60 HZ
CIRCULATION RATE : 1,698 gallons per minute
EVAPORATION : 15.28 gallons per minute
RATE OF MAKE UP WATER : 25.47 gallons per minute
Prepared By: Approved By:
Jaya M. Andres Jay Silvano
Documents Controller Engineering Manager
Document Code: Effective Date:
VVSCSPPC-DVO-PRP-09 January 09, 2017
Revision: 04 Page 9 of 13
Prerequisite Programs
Preventive Maintenance Program
2 UNITS AMMONIA PUMP
BRAND NAME : LEDERLE
SERIAL NUMBER: 400002007 / 400002008
PUMP TYPE : CNF 50 – 200
MOTOR TYPE : AGX 8.5
CAPACITY : 7.2 CUBIC METER / HOUR
TEMPERATURE: -37 C AT 60 HZ
PC : 7.81 KW
RUNNING SPEED: 3519 RPM
CURRENT : 20 AMPERES
VOLTAGE : 440 VOLTS, 3 PHASE, 60 HZ
3 UNITS AMMONIA PUMP with 1 SPARE
BRAND NAME : WITT
MODEL : HRP 5050
CAPACITY : 3.5 CUBIC METER / HOUR
PC : 4.8 KW
RUNNING SPEED: 3500 RPM
CURRENT : 12 AMPERES
VOLTAGE : 440 VOLTS, 3 PHASE, 60 HZ
4 UNITS AMMONIA PUMP
BRAND NAME : WITT
MODEL : HRP 8050
CAPACITY : 5.5 CUBIC METER / HOUR
PC : 4.8 KW
RUNNING SPEED: 3500 RPM
CURRENT : 12 AMPERES
VOLTAGE : 440 VOLTS, 3 PHASE, 60 HZ
2 UNITS EVAPORATOR ( BLAST FREEZER )
BRAND NAME : THERMOFIN
MODEL : X-TAFA090.1-H-3-32-16-8-HG
CAPACITY : 167 KW
RT : -30 C
VOLTAGE : 440 VOLTS, 3 PHASE, 60 HZ
19 UNITS EVAPORATOR ( COLD STORAGE ROOMS)
BRAND NAME : THERMOFIN
MODEL : X-TEN.1-065-E-3-7-E
CAPACITY : 40 KW
RT : -27 C
VOLTAGE : 440 VOLTS, 3 PHASE, 60 HZ
4 UNITS EVAPORATOR ( LOADING AREA )
Prepared By: Approved By:
Jaya M. Andres Jay Silvano
Documents Controller Engineering Manager
Document Code: Effective Date:
VVSCSPPC-DVO-PRP-09 January 09, 2017
Revision: 04 Page 10 of 13
Prerequisite Programs
Preventive Maintenance Program
BRAND NAME : THERMOFIN
MODEL : TADNO45.1-E-2-10
CAPACITY : 30 KW
RT : + 10 C
VOLTAGE : 440 VOLTS, 3 PHASE, 60 HZ
4 UNITS EVAPORATOR ( ANTE ROOM )
BRAND NAME : THERMOFIN
MODEL : S-GHT050-2C/310-HL/24P.1
CAPACITY : 30 KW
RT : +7 C
VOLTAGE : 440 VOLTS, 3 PHASE, 60 HZ
3 UNITS PRESSURE VESSEL TANK
-37 RE CIRCULATOR
MODEL : HORIZONTAL RE CIRCULATOR ( 1.83MO X 3.0M SL )
-8 INTERCOOLER
MODEL : HORIZONTAL INTERCOOLER WITH COIL ( 1.83MO X 3.0M SL )
SEPARATOR
MODEL : HORIZONTAL LIQUID RECEIVER ( 1.2MO X 3.85M SL )
1 UNIT VARIABLE FREQUENCY DRIVE
BRAND NAME : DANFOSS
SERIAL NUMBER: 000230H363
P/N : 131G7079
CAPACITY : 450 KW / 600 HP
RATED INPUT : 3 X 380 – 480 VOLT, 50 HZ / 60 HZ, 787 AMPERES / 718 AMPERES
RATED OUTPUT : 3 X 0 – VOLT INPUT, 0 – 590 HZ, 800 AMPERES / 730 AMPERES
1 UNIT AUTOMATIC AIR PURGER
BRAND NAME : HANSEN
MODEL : APO8
SERIAL NUMBER: 7298H
VOLTAGE : 120 VOLTS, 1 PHASE, 60 HZ
CURRENT : 3.0 AMPERES
1 UNIT HIGH VOLTAGE SWITCH GEAR
BRAND NAME : COOPER
SERIAL NUMBER: 12E501
TYPE : VN2-24
CAPACITY : 13.8 KV, 3 PHASE, 3 WATT, 60 HZ
1 UNIT PAD MOUNTED TRANSFORMER
BRAND NAME : DONG A ELECTRIC LTD.
SERIAL NUMBER: 13-3P 3017
RATED CAPACITY: 2000 KVA
Prepared By: Approved By:
Jaya M. Andres Jay Silvano
Documents Controller Engineering Manager
Document Code: Effective Date:
VVSCSPPC-DVO-PRP-09 January 09, 2017
Revision: 04 Page 11 of 13
Prerequisite Programs
Preventive Maintenance Program
PRIMARY VOLTAGE: 13200 VOLTS
SECONDARY VOLTAGE: 480 VOLTS
PRIMARY CURRENT: 87.5 AMPERES
SECONDARY CURRENT: 2405.6 AMPRES
COOLING METHOD : ONAN
2 UNITS DRY TYPE TRANSFORMER
BRAND NAME : DELTA STAR / MOBILECT
SERIAL NUMBER: 2K14MO911-883 / 250 2014-2
CAPACITY : 250 KVA, 3 PHASE, 60 HZ
PRIMARY VOLTAGE: 480 VOLTS
SECONDARY VOLTAGE: 240 VOLTS
PRIMARY CURRENT: 300.7 AMPERES
SECONDARY CURRENT: 601.4 AMPERES
1 UNIT LOW VOLTAGE SWITCH GEAR
BRAND NAME : SCHNEIDER
VOLTAGE : 440 VOLTS, 3 PHASE, 3 WATTS, 60 HZ
CURRENT : 2500 AMPERES
1 UNIT DISTRIBUTION PANEL
CAPACITY : 440 VOLTS, 3 PHASE, 60 HZ
CURRENT : 1250 AMPERES CB, 1600 AMPERES CB, 680 AMPERES CB, 2 X 400 AMPERES CB
2 UNIT CONTROL PANEL FOR CORRIDOR 1 AND 2
CAPACITY : 440 VOLTS, 3 PHASE, 60 HZ
CONTROL TYPE: TEMPERATURE CONTROLER
BRAND NAME : DANFOSS
2 UNIT LIGHTING PANEL
CAPACITY : 220 VOLTS, 1 PHASE, 60 HZ
1 UNIT REEFER VAN PLUG IN AND OUT PANEL
CAPACITY : 440 VOLTS, 3 PHASE, 60 HZ
1 UNIT DEEP WELL PUMP
BRAND NAME : FRANKLIN ELECTRIC
MODEL : 2366028120
CAPACITY : 8.6 KW / 10 HP
SPEED : 3460 RPM
VOLTAGE : 230 VOLTS, 3 PHASE, 60 HZ
CURRENT : 32.2 AMPERES
DEEP : 9 PIPES DEEP
Prepared By: Approved By:
Jaya M. Andres Jay Silvano
Documents Controller Engineering Manager
Document Code: Effective Date:
VVSCSPPC-DVO-PRP-09 January 09, 2017
Revision: 04 Page 12 of 13
Prerequisite Programs
Preventive Maintenance Program
5 UNITS BATTERY CHARGER FOR FORKLIFTS
BRAND NAME : BPI
SERIAL NUMBERS: 14018319,14018320,13002155,13003607,13001161
OUTPUT DC : 48 VOLTS DC
CURRENT : 120 AMPERES
CAPACITY : 750 Ah
INPUT AC : 230 VOLTS, 3 PHASE, 60 HZ
POWER : 7.34 KW
5 UNITS BATTERY FOR FORKLIFTS
BRAND NAME : BAE
MODEL : 8P2S 700, 5P2S 700
SERIAL NUMBERS: 14001,14002,14003,14017,14018
CELL : 24 CELLS
CAPACITY : 700 Ah
VOLTAGE : 48 VOLT DC
3 UNITS BATTERY FOR FORKLIFTS
BRAND NAME : MIDAC
SERIAL NUMBERS: 112545,112544,112543
CELL : 24 CELLS
CAPACITY : 700 Ah
VOLTAGE : 48 VOLT DC
2 UNITS BATTERY FOR FORKLIFTS
BRAND NAME : HAWKERS
SERIAL NUMBERS: 117488 E15 / 117483 E15
CELL : 24 CELLS
CAPACITY : 700 Ah
VOLTAGE : 48 VOLTS DC
1 UNIT BATTERY CHARGER FOR GENERATOR SET
BRAND NAME : UPEI
MODEL : UPEI RBC 24 VDC-20A
INPUT VOLTAGE: 24 VOLTS, 1 PHASE, 60 HZ
OUTPUT VOLTAGE: 24 VOLTS DC
OUTPUT CURRENT: 20 AMPERES
5 UNITS FORKLIFT TRUCKS
Prepared By: Approved By:
Jaya M. Andres Jay Silvano
Documents Controller Engineering Manager
Document Code: Effective Date:
VVSCSPPC-DVO-PRP-09 January 09, 2017
Revision: 04 Page 13 of 13
Prerequisite Programs
Preventive Maintenance Program
BRAND NAME : LINDE
MODEL SERIAL NUMBER MAST NUMBER
R20S – 12 H2X115D03036 / 2013 (H2X187D00852) M187-020T02-1045-06 / 115
R20S – 12 H2X115D03042 / 2013 (H2X187D00851) M187-020T02-1045-06 / 115
R20S – 12 H2X115D03029 / 2013 (H2X187D00853) M187-020T02-1045-06 / 115
R20HD – 01 H21120F01851 / 2015 (H21502F00725) M1502-02T00-1065-06 / 112
R20HD – 01 H21120F01804 / 2015 (H21502F00745) M1502-02T00-1065-06 / 112
3 UNITS WEIGHING SCALE
BRAND NAME : ASUKI
MO0DEL : E 120
CAPACITY : 2 TONS
3 UNITS WEIGHING SCALE
BRAND NAME : ASUKI
MODEL : E 120
CAPACITY : 750 KILOGRAMS
12 UNITS PALLET TRUCKS
BRAND NAME : EURO LIFTER / MHEG
CAPACITY : 2500 KILOGRAMS
20 UNITS DATA LOGGER ( FOR COLD ROOM )
BRAND NAME : TESTO
MODEL : 174T
2 UNITS DATA LOGGER ( FOR BLAST FREEZER )
BRAND NAME : TESTO
MODEL : 175T3
Prepared By: Approved By:
Jaya M. Andres Jay Silvano
Documents Controller Engineering Manager