Solution Tutorial 4
Solution Tutorial 4
Tutorial 4 solutions
Question 1
Question 2
1.
2.
Task Earliest start Latest start Total margin Free margin
A 0 11 11 0
B 0 3 3 2
C 4 15 11 11
D 0 0 0 0
E 12 14 2 1
F 8 8 0 0
G 15 16 1 1
H 12 12 0 0
I 8 9 1 0
3. The critical path is D-F-H
Project duration = 20 days
4. Tasks G and I are in series. A total margin of 1 day for each activity means that there is a one-day float
(a margin) in scheduling the two tasks without affecting the overall project duration. In simpler terms,
you have a one-day flexibility in planning these tasks without extending the total project timeline. This
means that if the start of each of the two activities were delayed by 1 day, or if their durations were
University of Tunis Fall 2023
Tunis Business School
increased by 1 day each, the overall project duration would extend by 1 day, and the critical path would
shift to D-I-G.
Question 3
1.
Only the earliest start dates of activity 4 will be affected, as shown in the table above.
Considering that material ordering (task 3), door and window ordering (task 5) are done with the same
supplier, they must be disjointed. Two solutions are possible: perform task 3 followed by task 5, or
perform task 5 followed by task 3.
Therefore, to resolve this disjointedness without affecting the minimum project duration, schedule task
5 as the predecessor of task 3.
Question 4
𝑥−20 18−20
𝑃(𝑥 ≤ 18) = 𝑃 ( ≤ ) = 𝑃(𝑍 ≤ −1.25) = 1 − 𝑃(𝑍 ≤ 1.25)
√2.55 √2.55
= 1 − 0.8944 = 0.1056
𝑥 − 20 𝑋 − 20
𝑃(𝑥 ≤ 𝑋) = 𝑃 ( ≤
) = 0.95
√2.55 √2.55
𝑋 − 20
𝑍=
√2.55
𝑈𝑠𝑖𝑛𝑔 𝑡ℎ𝑒 𝑛𝑜𝑟𝑚𝑎𝑙 𝑑𝑖𝑠𝑡𝑟𝑖𝑏𝑢𝑡𝑖𝑜𝑛′ 𝑠 𝑡𝑎𝑏𝑙𝑒𝑎𝑢 𝑡ℎ𝑒 𝑝𝑟𝑜𝑏𝑎𝑏𝑖𝑙𝑖𝑡𝑦 𝑜𝑓 0.95 𝑐𝑜𝑟𝑟𝑒𝑠𝑝𝑜𝑛𝑑𝑠 𝑡𝑜 𝑍 = 1.65
University of Tunis Fall 2023
Tunis Business School
𝑋 − 20
1.65 =
√2.55
𝑋 = 22.6 ≈ 23 𝑑𝑎𝑦𝑠
With a probability of 95%, the project will be completed before 23 days.
We cannot perform an earliest start scheduling because it requires 11 workers, but we only have 9
workers available.
Question 5
1. The most commonly used statistical distribution law to estimate the expected duration of an activity in
a probabilistic project environment is the beta distribution.
2. Average duration of an activity= (a+4m+b)/6
with
a = estimation of the activity duration under the most favorable conditions.
b = estimation of the activity duration under the most unfavorable conditions.
m = estimation of the activity duration under normal conditions.
Variance = (b-a)2/36
3.
2 4
B(5)
C(7) F(17)
E(9)
1
A(8) 3 5
D(6)
University of Tunis Fall 2023
Tunis Business School
4. If simultaneously the expected duration of task A increases by 5 weeks and that of D by 2 weeks, then
activity A will become critical instead of B and C (A will have a duration of 13 weeks, exceeding the
12 weeks total duration of B and C), while D will remain non-critical (D will have a duration of 8
weeks, below the 26 weeks total duration of E and F). Thus, the critical path becomes AEF with a
length of 39 weeks. In other words, the project execution will require one additional week.
Var(CC)=1,8+0,1+1+2,8=5,7
σ(CC)= 2,387
P (Z ≤ z) = 0,9
x = 41,055 weeks
Therefore, there is a 90% chance that the estimated duration of the project is 41.055 weeks.
Question 6
Given that only the durations of activities A, C, and D can still be reduced, no alternative reduction in these
tasks can affect the project duration. Therefore, the project duration cannot be accelerated further.
University of Tunis Fall 2023
Tunis Business School
coût
290000
285000
280000
275000
coût
270000
265000
260000
19 20 21 22 23 24
The optimal cost reduction corresponds to 21 weeks. Below 21 weeks, costs start to increase again.