(Modified) Assignment 2 - Group - Project
(Modified) Assignment 2 - Group - Project
7. Enter the following resource assignment. At this moment, only tasks in the Study
Phase are assigned. Do not worry about tasks in the next two phases.
Table 3. Task List
Primitive task name Assignment
1.1.1 Defining Team Organization JA (100%), JB (100%)
1.1.2 Establish initial contact JA (50%), JC (100%)
1.1.3 Conduct initial interview JA (100%), JC (50%), JD (50%)
1.1.4 Define Problem/Opportunity JB (100%), JD (50%)
1.1.5 Problem ID Statement JA (100%), JD (50%)
1.2.1 Describe project scope JA (100%), JB (100%)
1.2.2 Conduct feasibility analysis JA (50%), JC (100%)
1.2.3 Define tasks and schedule JA (100%), JC (50%), JD (50%)
1.2.4 Refine project scope JB (100%), JD (50%)
1.2.5 Select baseline project plan* JA (100%), JD (50%)
1.3.1 Data needs analysis JA (100%), JB (100%)
1.3.2 Resource identification JA (50%), JC (100%)
1.3.3 Define major processes JA (100%), JC (50%), JD (50%)
1.3.4 Design preliminary models JB (100%), JD (50%)
1.3.5 Deliver preliminary models* JA (100%), JD (50%)
1.4 Project Closeout JA (100)
2
III. Deliverables
1. After you have successfully entered the above data, save your project under the name Project
Assignment – Group 1(if you are Group 1, Project Assignment – Group 2, if you are
Group 2..)
2. Collect the following information about your Project and Save with in one Folder Named by
your project (Project Assignment – Group 1, …)
a. Project information (Statistics) – Copy and paste on word document.
b. Produce a Critical Path Report for your project .
c. List all critical tasks on the critical path.
d. Show the following report about your project:
i. resource sheet,
ii. Resource usage,
iii. Task Usage,
iv. project summary,
v. Budget summary,
vi. “Who did what?” report,
vii. Working Days report.
.