Week 6 Project Time Management
Week 6 Project Time Management
Estimate Estimate
Define Sequence Develop
Activity Activity
Activities Activities Resources Durations Schedule
Plan Schedule Management
Tools & Techniques
Project management
plan Expert judgment
Project charter .Analytical techniques
Enterpriseenvironmental Inputs .Meetings
Schedule management
factors Output
plan
Organizational process
assets
Estimate Estimate
Define Sequence Develop
Activity Activity
Activities Activities Resources Durations Schedule
Schedule Management Define Activities
Enterprise Environmental Tools & Techniques
Factors
Decomposition
Organizational
Process Assets Templates
Activity List
Rolling wave planning
Project Scope
Statement Inputs Expert judgment
Activity Attributes
Work Breakdown Planning component Outputs
Structure
Milestone List
WBS Dictionary
Estimate Estimate
Define Sequence Develop
Activity Activity
Activities Activities Resources Durations Schedule
Define Activities
Rolling Wave Planning – Progressive planning where near
term work is broken down in detail and distant work is
kept at a higher WBS level
Planning Component – WBS items that cannot be broken
down into work packages are put in a:
• Control Account – High level planning dates for the scope to be defined
• Planning Package – Package includes scope to be completed but no activities.
Sequence Activities
Schedule Management
Tools & Techniques
Project Scope
Statement Precedence diagramming Project Schedule
Activity List method (PDM-AON) Network Diagrams
Arrow diagramming method
Activity
(ADM-AOA) Project Document
Attributes Inputs Updates :Activity List
Schedule network
Milestone List Updates/Activity
templates Outputs
Attributes/Requested
Enterprise environmental Dependency determination Changes
factors
Organizational process Applying leads and lags
assets
Estimate Estimate
Define Sequence Develop
Activity Activity
Activities Activities Resources Durations Schedule
Project Network Diagrams
show the precedence relationships among
activities
help to understand the flow of work in a
project
a useful tool for project planning and
control, as well as for scheduling
9
Building the Network
1- Precedence diagramming method
called also (Activity on Node) AON Network
emphasizes activities
no dummy activities
On the internet you can see many videos, this is one of these:
http://www.youtube.com/watch?v=nLiAvW7Xvq4
AON Network 2:
The first event in a project schedule is the start of the project. The
last event in a project schedule is the end of the project
Drawing networks
Activities on nodes (AoN)
A B
PROJECT MANAGEMENT 15
Drawing networks (cont.)
Many computer programs require one initial event and one exit/final event
A x
1 58
0 Many 60
activities
B y
2 59
Dummy start Dummy stop
PROJECT MANAGEMENT 16
If there is a loop, it indicates a fault logic. There can not be a looping.
A B C E
17
What is wrong with this activity naming?
60
A
20 40 50 70
B
80
30
6/7/2014 11:36 PM 18
There should be unique numbering and here we need dummies
45 60
A
20 40 50 70
B
80
30
19
Estimate Activity Resources
Inputs Tools & Techniques Outputs
Expert judgment
Schedule management
plan Alternatives analysis
Activity list Published estimating data
Activity attributes Activity resource
Resource calendars Inputs Project management requirements
Risk register software Outputs Resource breakdown
Activity cost estimates Bottom-up estimating structure
Enterprise environmental Project documents
factors updates
Organizational process
assets
Estimate Estimate
Define Sequence Develop
Activity Activity
Activities Activities Resources Durations Schedule
Estimate Activity Durations
Schedule management Tools & Techniques
plan
Activity list Expert judgment
Activity attributes
.Activity resource Analogous estimating Activity Duration
requirements Parametric estimating Estimates
Resource calendars Inputs
Project scope statement Three-point estimates
Outputs
Project Document
Risk register Reserve Analysis
Resource breakdown updates
structure Group Decision-making
Enterprise environmental Techniques
factors
Organizational process
assets
Estimate Estimate
Define Sequence Develop
Activity Activity
Activities Activities Resources Durations Schedule
Estimating Methods
CPM (Critical Path Method)
• One time estimate per task
• Controls cost with flexible schedule
• Only on AOA networks (can have dummies)
• Not the same thing as schedule critical path
PERT (Program Evaluation and Review Technique)
• Three estimates per activity (Optimistic, Pessimistic, most likely)
• Emphasis on meeting schedule with flexible cost
• Only on AOA networks (can have dummies)
Estimating Methods
Critical Path
• Longest time through the network diagram, the shortest
time the project is expected to take
Slack (or Float)
• The amount of time a task can be delayed without
impacting the project
• Calculated using:
– Late Start – Early Start (LS-ES)
Or
– Late Finish – Early Finish (LF-EF)
• Early Starts computed by making a “forward pass”
through the network while late starts are computed using a
“backward pass”
Critical Path-Definition
A 2 4 8 4.3 1 1
days days days days day day
Develop Schedule
Tools & Techniques
Schedule management
plan Schedule network analysis
Activity list Critical path method Schedule baseline
Activity attributes
Project schedule
Project schedule
Inputs Schedule compression
network diagrams Schedule data
Activity resource Inputs What-if analysis Project calendars
requirements
Resource leveling Outputs Project management
Resource calendars plan
Activity duration Critical chain method updates
estimates
Project documents
Project scope statement Project management
Risk register updates
software
Project staff assignments
Resource breakdown Applying calendars
structure
Enterprise environmental Adjustable leads and lags
factors
Schedule model
Organizational process assets
Estimate Estimate
Define Sequence Develop
Activity Activity
Activities Activities Resources Durations Schedule
Let‘s Built a Network
A Sample Set of Project Activities and Precedences
Task Predecessor
a -
b -
c a
d b
e b
f c,d
g e
AON Network- Stage 1
A
Start
B
AON Network- Stage 2
A C
Start D
E
AON Network- Stage 1-
Completed
A C F
Finish
Start
D
B
G
E
AOA Network- Stage 1
A 1
Start
2
B
AOA Network- Stage 2
A 3
1 C
Start
4
2 D
B
E 5
AOA Network- Stage 3-
Completed
A 3 F
1 C
Start Finish
D
2 G
B
E 4
Critical Path-Example
3 Weeks 4 Weeks 2 Weeks
A C D
Start Finish
B E F
4 Weeks
1 Week 3 Weeks
Critical Path
Activity Name
Latest Start Time (LST) Total Float Latest Finish Time (LFT)
Critical Path Determination
EFT=EST+DUR-1
LST=LFT-DUR+1
Total Float=Slack=LFT-EFT or LST-EST
Critical Path=A-C-D
6 5 10
Non-Critical Path=A-B-D
B
1 5 5 11 5 15 16 15 30
A D
1 0 5 6 10 15 16 0 30
C
6 0 15
Control Schedule
Tools & Techniques
Schedule network
analysis Work performance
Project management plan information
Project schedule Critical path method .Schedule forecasts
Work performance data Inputs Schedule compression .Change requests
Project calendars Project management plan
Schedule data What-if analysis Outputs updates
Organizational process Resource leveling .Project documents
assets updates
Critical chain method .Organizational process
Project management assets updates
software
Applying calendars
Adjustable leads and lags
Scheduling tool
Plan Schedule Control
Management Schedule
Estimate Estimate
Define Sequence Develop
Activity Activity
Activities Activities Resources Durations Schedule
Gantt Charts
http://www.matchware.com/images/special/gantt-chart-template-640.jpg
Gantt Chart-ex 2
http://www.matchware.com/images/special/gantt-chart-template-640.jpg
AON using earliest possible start of the activities
AON using latest possible start of the activities
Ghant Chart with Floats
Important to Notice
A project usually have tens of activities and might have much
more complex dependencies than this example,
Project managers usually use software to set up the activities
and dependencies and let the software calculate the critical
path(s).
If an activity is delayed the project manager can enter the
delay in the software and see how it affects the overall finish
of the project.
If the project is delayed the project manager can use the
software to rearrange activities, dependencies or suggest
additional activities as needed to bring the project back on
track.
The critical path is critical to the Time Management
knowledge area.
Make sure you know how to use it correctly whenyou manage
a project.
Other Important Terms
Lag – Inserted waiting time between tasks
Free Slack – Available delay time without impacting start of
successor
Total Slack – Amount of time a task can be delayed without
delaying project completion date
Project Slack – Amount of time a project can be delayed without
impacting completion dates imposed by client
Crashing – Adding resources to critical path items to shorten
schedule
Fast Tracking – Performing critical path tasks in parallel rather
than series
Resource Leveling – Adjusting completion dates of tasks to meet
available resources
Heuristics – Rules of thumb
Individual Homework
Given the information provided by Instructor please construct a Gantt
chart, with overlaps as specified. You should use a computer software
package