Binomial Distribution
Binomial Distribution
00-6
n!
r!(n-r)!
where p + q = l.
P = C p r q n-r •
r n r
In this expression, prqn-r represents the probability
(given by PRl) of exactly r 'successes' and n-r 'failures' in
some particular order, eg, r consecutive 'successes' followed
by n-r consecutive 'failures'. The coefficient nCr accounts
for the number of possible ways to order r 'successes' and
n-r 'failures'.
n
(p + q}n = l:
r n-r
C p q •
n r
r=O
June 1981 - 1 -
121. 00-6
Example 1
Solution
0 5 1
Po = 5 COP q = IT
4 5
P
1 = sclpq = IT
'2 3 10
P
2 = 5 C2 P q = IT
3 2 10
P
3 = SC 3 P q = 32
4 5
P
4 = SC 4 P q = 32
5 0 1
Ps = SC 5 P q = 32
Pr 12 -.
(x32 )
~
8 -f-
-
4 -
-
o 11
o 1 2 3 4 5
r Heads
Figure 1
- 2 -
121.00-6
Example 2
Proof
n
E(r) = L rP (by PR9)
r=O r
n
= L: r n: prqn-r (0 •• no contribution from r=O)
r:(il-r):
r=l
m
m: p s q m-s
= np L:
s: (m-s) :
(m = n - 1)
s=O (s = r - 1)
np (1) m (p + q = 1)
= np QED
Example 3
Solution
- 3 -
121.00-6
P
r
(x2 56)
I
o
o 1 2 3 4
r Successes
Figure 2
Probability Distribution of
Successes in 4 Trials
Example 4
Solution
Example 5
- 4 -
121.00-6
solution
_.
Let Q' \ 1
, !Q
=:
represent
.
unavailabilities
_ _
of a dousing valve,
douslng system~ respectlvely. Then
= C Q 3R 5 + C Q 4 R 4 +
8 3 v v 8 4 v v
8' 3 5 8' 4 4
= 3!5! (.01) (.99) + 4!4! (.01) (.99) + ••• +
= 5 x 10- 5
Note that only the lead term on the RHS contributed signi-
ficantly to the answer, the probabilities of higher order fail-
ures (failure of 4, 5, ••• , 8 valves) being negligible by
comparison to the probability of 3 valves failing.
Peak Load
Load (MW)
Base Load
o 12 24
Time (Hours)
Figure 3
Average Daily Load Variation
- 5 -
121.00-6
o Days/Year 365
Figure 4
DEFINITION
The E#pected Load Curtailment (ELC) is the number of
days per annum for which a load loss occurs, ie,
- 6 -
121.00-6
DEFINITION
[,-_E_L_L_=_~_Pk_Lk
__ l
where Pk is the probability of the kth outage, and
DEFIl'~ITIO~J
Example 6
solution
- 7 -
121.00-6
Daily Peak
Load (MW)
15
----------------1
Installed Capacity
Reserve 5 MW
10
o
o Days/Year 365
Figure 5
ELL = L LkPk
k
= 0.013365 MW
all losses
ELC = L Pktk
k
= 23 hours/y
- 8 -
1.21.00-6
Example 6
Table 1
Outage Ok
1 0 0 0.912673 0 0
2 1 5 0.084681 0 0
3 2 10 0.002619 5 0.013095
4 3 15 0.000027 10 0.000270
Example 7
- 9 -
121.00-6
Solution
= 1.181975 MW
all losses
ELC = L Pktk
k
16
= (l: P )
k
(365 d/y) (t k = 365 diY, k = 2, •.• ,16)
k=2
= 19.7 days/year
16
(Note that L P
k
= 1 - PI in the above.)
k=2
Example 7(a)
Outage Ok
k Units Capacity Pk 4< ~Lk
Table 2
- 10 -
l~l.OO-b
120
----- -;:-
------ ---------~ Reserve Capacity
J~---
= 30 MW
80
0--------------1-
o Days/Year 365
Figure 6
365
ie, t
k = 120
L
k
16
ELC = L: Pkt k
k=2
= 3.6 days/year
- 11 -
121. 00-6
Example 7(b)
Otc 365
k Units Capacity 11t Lk tk • 120 ~ l'Jt tk
1 0 0 .946066 0 0 0
2 1 x 40 40 .014262 10 30.4167 .433803
3 50 50 .019307 20 60.8333 1.174509
4 60 60 .019307 30 91.2500 1.761764
5 "I. x 40 80 .000072 50 152.0833 .010950
6 40, 50 90 .000291 60 182.5000 .053108
7 40, 60 100 .000291 70 212.9167 .061959
8 50, 60 110 .000394 80 243.3333 .095873
9 3 x 40 120 .000000 90 273.7500 .000033
10 2x40,50 130 .000001 100 304.1667 .000304
11 2x40,60 140 .000601 110 334.5833 .000335
12 40,50,60 150 .000006 120 365 .002190
13 3x40 ,50 170 .000000 140 365 .000001
14 3x40,60 180 .000000 150 365 .000001
15 2x40,50,60 190 .000000 160 365 .000004
16 3x40,50,60 230 .000000 200 365 .000000
Table 3
- 12 -
121. 00-6
ASSIGNMENTS
80
(.2,55)
40
(1.0,20)
O'----+--+---+--t----+-......--+-__....---+--4--
o .5
Year/Year Load Exceeded
1.0
- 13 -
121.00-6
L. Haacke
- 14 -