Ch20 Inventory Control
Ch20 Inventory Control
No-shows Probability 0 1 2 3 4 5 6
1400
1200
Expected Cost ($)
1000
800
600
400
200
0
0 1 2 3 4 5 6 7 8 9 10
Number Overbooked
er your values for Co and Cu.
is the cost of overestimating cancellations. The hotel has
ms that are not filled.
is the cost of underestimating cancellations. The hotel will
e to pay to put the customer up at a nearby hotel.
he number of overbookings with the lowest expected total cost
red) should be selected.
verbooked
7 8 9 10
`
Example 20.2 - EOQ and Reorder Point Enter your demand, cost, and and lead time information in the blue cells
column E to generate the graph and reorder policy output.
100.0
Order Received
Usage Rate
Reorder Point
Quantity
50.0
13.7
0.0
0 20 40 60 80 100 120 140 160 180
Time Horizon
X ROP
0 13.7
164.3 13.7
T CumProd Q y
63 0 0 1000
63 300.0 164.3
Q0 = 90
Average Inventory = 45.0
Order Received
Usage Rate
Reorder Point
13.7
Q
Total Holding Cost
600 Total Setup Cost
Total Cost
500
400
Cost ($)
300
200
$111.8
100
0
0 50 100 150 200 250 300 350 400 450 500
Order Quantity
Increment Q 10
Q CumProd QBEP TC
96 0 0 90 0 112
96 112 112 90 96 112
Q THC TSC TC
0 0.0 0 0.0
10 6.3 500.0 506.3
20 12.5 250.0 262.5
30 18.8 166.7 185.4
40 25.0 125.0 150.0
50 31.3 100.0 131.3
60 37.5 83.3 120.8
70 43.8 71.4 115.2
80 50.0 62.5 112.5
90 56.3 55.6 111.8
100 62.5 50.0 112.5
110 68.8 45.5 114.2
120 75.0 41.7 116.7
130 81.3 38.5 119.7
140 87.5 35.7 123.2
150 93.8 33.3 127.1
160 100.0 31.3 131.3
170 106.3 29.4 135.7
180 112.5 27.8 140.3
190 118.8 26.3 145.1
200 125.0 25.0 150.0
210 131.3 23.8 155.1
220 137.5 22.7 160.2
230 143.8 21.7 165.5
240 150.0 20.8 170.8
250 156.3 20.0 176.3
260 162.5 19.2 181.7
270 168.8 18.5 187.3
280 175.0 17.9 192.9
290 181.3 17.2 198.5
300 187.5 16.7 204.2
310 193.8 16.1 209.9
320 200.0 15.6 215.6
330 206.3 15.2 221.4
340 212.5 14.7 227.2
350 218.8 14.3 233.0
360 225.0 13.9 238.9
370 231.3 13.5 244.8
380 237.5 13.2 250.7
390 243.8 12.8 256.6
400 250.0 12.5 262.5
410 256.3 12.2 268.4
420 262.5 11.9 274.4
430 268.8 11.6 280.4
er the demand, order cost and holding
in the blue cells to the right to generate the
cost curve.
e optimal order quantiity is calculated.
ve the bar below the graph to see the
ct order quantity has on total cost.
Q
Total Holding Cost
Total Setup Cost
Total Cost
INPUT:
OUTPUT:
Page 11
Example 20.4
Page 12
Example 20.4
Page 13
Example 20.4
Page 14
Example 20.4
Page 15
Example 20.4
Page 16
Example 20.4
Page 17
Example 20.4
Page 18
Example 20.4
Page 19
Example 20.4
Page 20
Example 20.4
Page 21
Example 20.4
Page 22
Example 20.4
Page 23
Example 20.4
Page 24
Example 20.4
Page 25
Example 20.4
Page 26
Example 20.4
Page 27
Example 20.4
Page 28
Example 20.4
Page 29
Example 20.4
Page 30
Example 20.4
problem
PUT table.
be
T table.
Standard Deviation
Page 31
Example 20.5 - Quantity to Order using Fixed-Time Period Model with Safety Stock
OUTPUT:
19.900 sT+L Standard deviation of demand over the review and lead time
2.054 z z-value for the stated service level
440 Average demand over the vulnerable period
40.87 Safety stock
330 q Order Quantity
Solved Problem 1 Enter your values for Co and Cu.
- Co is the cost of overestimating demand
Co = $Cost per
50.00
unit of demand overestimated - Cu is the cost of underestimating deman
- The order quantity with the lowest expec
Cu = Cost
$ per
30.00
unit of demand underestimated selected.
140
120
Expected Cost ($)
100
80
60
40
20
0
35 36 37 38 39 40
Number Purchased
for Co and Cu.
overestimating demand.
underestimating demand.
ity with the lowest expected total cost should be
urchased
- - - -
Solved Problem 3 Enter your values in the INPUT table. The resulting
reorder policy will be displayed in the OUTPUT table.
OUTPUT
137.477 sT+L Standard deviation of demand over the review and lead time
2.326 z z-value for the stated service level
2520 Average demand over the vulnerable period
319.82 Safety stock
2709 q Order Quantity
Solved Problem 4 Enter your values in the INPUT table. The resulting
reorder policy will be displayed in the OUTPUT table.
OUTPUT
22.913 sT+L Standard deviation of demand over the review and lead time
1.645 z z-value for the stated service level
420 Average demand over the vulnerable period
37.69 Safety stock
277 q Order Quantity