W10 Labour & Sub-Contractor Management
W10 Labour & Sub-Contractor Management
Management
Risk assessment, site safety Appraisals, weekly & Prepare & check snag list, Long/medium/short term Compliance towards
audits, health & safety monthly cost control, assist supervision, recording of tests, programmes, monitoring & environmental requirement.
equipments, health & safety valuation, claims & record performance, and quality recording progress, schedules
records/audits, health & safety payments administration. for information requirements,
administration planning & progress meetings
Organise Sub-Contractors,
To ensure site
safety Objectives To maintain the
health of workers
Identify the numbers
and types of labour To produce
required (scheduling quality work
and leveling) To keep proper record
of workers
Sub-contractor Sub-contractor
claims & requirement
payments schedule
Resourcing &
appointment of
sub-contractor
Copyright.Fadzil@UiTM2020
2. Labour/Sub-Contractor Schedule
Determine the pattern of use
Schedule of use
QS/Taker Off/Construction Manager
3. Labour/Sub-Contractor Requisition
Inform HQ or Purchasing Department
QS/Construction Manager/Purchasing(Procurement) Manager
5. Work Supervision:
Sub-contractor coordination
Quality of work
Work progress (site meeting/daily supervision)
QS/Construction Manager/Site Manager/Site Supervisor
• Excavator
• Bricklayer/Block layer
• Mason
• Carpenter
• Joiner
• Ceiling Fixer
• Tiler
• Electrician
• Foreman
• Ganger
• Groundworker
• Labourer
• Painter/Decorator
• Plasterer
• Plumber
• Scaffolder
• Steel Fixer
Refer Short
Term Program
Work Breakdown
Structure (WBS)
N O AK T I V I T I T R E D K U A N T I T I J E N T E R A B U R U H A N G K A T A P P E N G I R A A T E M P O H (HARI) K O S ( R M )
N
3 3
2 P e n g o r e k a n Syarika 4 5 . 9 M B a c k h o e ( 1 Unit) 1 4 M / j a m 45.9 = 1 2 j a m 1 1/2 545. 0 0
t
4
3 3
4 Lapisan T u k a n g 3 9 . 3 M Jentera P e m a d a t ( 1 2 1 . 5 M / ja m 39.3 = 1 1/2 1, 422. 2 5
tegar Unit) 1 3 j a m
Konkri B a c k h o e ( 1 Unit) 1.5 x 2
t
2 2
5 A c u a n T u k a n g 3 3 M - 2 3 M / j a m 3 3 = 5.5jam 1 946. 6 5
K a y u 3 x 2
3 3
6 Konkrit Alas T u k a n g 1 3 . 1 M M e s i n P e m b a n c u h 2 1 . 6 M / ja m 13.1 = 4 j a m 1/2 1, 465. 9 5
G r e d 1 5 Konkri Konkrit (1Unit) 1.6 x 2
t
2 2
7 Lapisan T u k a n g 2 6 2 M - 1 3 5 M / j a m 2 6 2 = 8 j a m 1 525. 0 0
Kalis
L e m b a b Konkri 3 5
t
2 2
8 B R C T u k a n g 3 1 0 M - 2 2 0 M / j a m 3 1 0 = 8 j a m 1 2, 520. 0 0
B e s i 2 0 x 2
3 3
9 Konkrit T u k a n g 5 0 . 7 M M e s i n P e m b a n c u h 4 1 . 6 M / ja m 50.7 = 8 j a m 1 6, 768. 3 4
lantai
b a w a h Konkri Konkrit (1 Unit) 1.6 x 4
t
G r e d 3 0
2 2
1 0 M e n a n g g a l k a T u k a n g 3 3 M - 2 6 M / j a m 3 3 = 3 j a m 1/2 30. 0 0
n
A c u a n K a y u 6 x 2
Copyright.Fadzil@UiTM2020
E SUPERSTRUCTURE
1 Column
30 nos of column at 6m height
(size 0.75 x 0.75 m) = 3.375 m3 *use same productivity & resources as Ground Beam
15 x 1.55
some of productivity in column using the size & nos of set formwork on site 23.25
2 Roof Beam & Slab (Slab at water tank only)
a) rebar 7,430 kg 150 - 250kg/man/day RM3.50-4.80/kg RM31,206
200kg / man / day x 6 man = 1200kg/day 7 days 6 barbender, 1 general worker 2 barbending cutting machine
G ARCHITECTURAL WORKS
1 Brickwork (6m Height) 840 m2 6-12 m2/ man / day RM38-45/m2 RM35,280
8m2/man/day x 8man = 64m2/day 13 days 8 bricklayer, 1 general worker 1 forklift
2 Door & Window Frame 12 nos 1 door / man / day x 2 man 6 days 1 door & window installer 1 Skylift RM300 RM3,600
32 nos 4 window / man / day x 2man 4 days 1 door & window installer RM100 RM3,200
3 Plastering (Ext & Int) 1,680 m2 8-14 m2/ man / day RM18-28/m2 RM42,000
10m2/man/day x 8man = 80m2/day 21 days 8 plasterer, 1 general worker 1 cement mixer
4 Ceiling Finishes - Aluminium Strip 480 m2 8-12 m2/ man / day RM90-120/m2 RM45,600
10m2/man/day x 6man = 60m2/day 8 days
5 Ceiling Finishes - Mineral Plaster Board 1,320 m2 8-12 m2/ man / day RM60-90/m2 RM105,600
12m2/man/day x 8man = 96m2/day 14 days 8 ceiling installer, 1 general worker
6 Wall Finishes (Tiles) - toilet area 720 m2 6-12 m2/ man / day RM90/m2 RM64,800
8m2/man/day x 8man = 64m2/day 12 days 8 tilers
7 Glazing Works (Glass Wall) 360 m2 12-20 m2/ man / day RM350-420/m2 RM136,800
10m2/man/day x 4man = 40m2/day 9 days 4 installer
8 Floor Finishes (Tiles) 480 m2 8-16 m2/ man / day RM110/m2 RM52,800
12m2/man/day x 4man = 48m2/day 10 days 4 tilers,1 general worker
11 Door & Window 12 nos 1 door / man / day x 2 man 6 days 1 door & window installer RM2000/nos RM24,000
32 nos 4 window / man / day x 2man 4 days 1 door & window installer RM600/nos RM19,200
12 Sanitary Fittings 12 set 2-6 nos @ set / man / day RM420/set RM5,040
4nos @ set/man/day 3 days
Forecasting / Planning
Organise
Control
Motivate
Communicate
Lead
Labour Employment
in construction
Sub-Contract / Kepala:
Total Sub-contract or Labour Only
The best preparation for tomorrow is doing your best today.
Considerations for Subcontractor
Appointment
Considerations:
1. Experience
2. Work load
3. Quality of work
4. Capital
The best preparation for tomorrow is doing your best today.
Implications of Wrong Appointment of
Labour / Sub-Contractors
Delays
Conflicts
2. Working 3. Subsidised
1. Salary
Hours Meals
7. 8. Competent 9. Sub-
Transportation managers and contracting
to workplace supervisors the work
Contractors QS
verify the sub-
Main contractor contractors claim
receives the by notify the sub- CMs approve the QS Prepare
progress claims contractor and agreed amount payment
from the sub- conduct a joint to sub-contractor certificate
contractor valuation to avoid
any dispute on
the evaluation
contingent
payment