Our products
GD series D.C. geo-electrical system is a world-leading multi-functional direct current (D.C.) method instrument, based on the latest digital and analog
circuitry technology. GD series comprises of GD-10 single-channel system and GD-20 multi-channel system. This series is capable of performing electrical
resistivity tomography (ERT), self-potential (SP) and induced polarization (IP) measurements. Apart from conventional electrical soundings, our products also
support cross-sectional profiling with 2D or 3D ERT arrays. GD series is not only supports conventional ground surveys, but also the geo-electrical
measurements in borehole logging, coal mining tunnels, marine and submarine surveys. This series is even equipped with online real-time field monitoring
mode, enabling our clients to perform unattended and automated surveys remotely for long durations.
Geomative has absorbed the advantages from both conventional centralized cabling system and distributed cabling system. We corporated the low-cost and
high reliability of the former along with the high efficiency and infinitely extensible cable sections of the latter system. A segment-centralized distributed wiring
mode was hence innovated by Geomative, acquiring both the rapidness of distributed cabling and the reliability of centralized cabling.
Major applications
l Groundwater and mineral exploration
l Underground contamination detection
l Urban engineering exploration
l Cavity exploration, Bedrock detection for pile foundation
l Seawater intrusion detection
l Dam seepage and leakage detection
l Geological mapping
l Archeological studies
l Real-time monitoring of landslides, tailings dams
l Sediment detection of river, lake and reservoir
l Borehole / Cross-hole invesigation
1D IP VES √ √ √ √
2D Res Imaging √ √ √
2D IP Imaging √
3D Res Imaging √ √
3D IP Imaging √
Centralized System / / √ / /
Distributed System / / / √ √
Channel 1 1 1 1 1
Online Upgrade √ √ √ √
Connecting with multi-electrode cable * Two multi-electrode sockets for two directions; Low side is female
connector and high side is male connector;
* Two banana clips for A,B interfaces (Red for A, Black for B) as a
Low protection for high current.
High
A,B
Connecting with the interface of
GD-10 "ERT Test Console" on the right
panel of GD-10 mainframe
1 2 3
1 2 3........................................................................................................7 8 9....................................
u Centralized Layout
CE5 CB10
P1 P1
on
P2 ly
GD-10 Mainframe
Model No.: Basic, Senior, Advanced 2D, Supreme
2D/3D, Supreme 2D+/3D+
L type cable SR-10 switch relay Multi-electrode cable
I. 1V VES Sounding
1.1 1D Resistivity Sounding
1.2 1D IP Sounding
GD-10 mainframe BP-145 power source
Solid non-polarization
Stailess steel electrode
electrode
SR-10
switch relay
SR-10
P1. P1. P1. P1.
switch relay
End Head Head End Head End
L type
1 2 3 ...............................................................13
cable 14 15 ........
ST Geomative Co., Ltd
www.geomative.com
Content II. Connection of 2D Imaging:
2.1 2D Resistivity Imaging - Conventional Res Mode
Function
2.1.2 GD-10 Series Single-takeout unidirectional Connection
I. 1V VES Sounding
1.1 1D Resistivity Sounding +/- power
1.2 1D IP Sounding uThe Mainframe is put only on one side of the survey line
uOnly P1 for staniless steel electrode.
II. Connection of 2D Imaging
2.1 2.2 Double Res Mode
2.3 Conventional IP Mode Banana clip for A,B
Connect with Multi-
2.4 Double IP Mode electrode socket interface
SR-10
switch relay
1 2 3 ...............................................................13 14 15 ........
ST Geomative Co., Ltd
www.geomative.com
Content II. Connection of 2D Imaging:
Function 2.2 2D Resistivity Imaging - Double Res Mode (Double Current)
I. 1V VES Sounding
1.1 1D Resistivity Sounding
1.2 1D IP Sounding
Head End
L type cable
Note:
III. Connection of 3D Imaging
1. BP-145 is optional item, not in the standard configuration;
2. P1 and P2 is relative concept;
3. Two survey lines layout in parallel,and connected with the two multi-electrode
cable sockets on L type cable;
4. The cable in low side takes the connection method of double Res mode, the cables in
high side only connect the solid non-polarization electrode with P2 as receiving.
5. Max current 4A;
6. The end of the survey line must connect one SR-10 cable leader for winding up.
* For each rolling along survey, the first or first two cables need to be moved to the end of the section, and the
GD-10 mainframe also move forward to the start of the section.
* At each rolling, please turn off mainframe, and then move the mainframe and cables. ST Geomative Co., Ltd
www.geomative.com
Content 2.5.2.GD-10 Mainframe is put in the middle of the survey line
System Configuration
u Please choose 1 cable or 2 cable rolling when setting
I. 1V VES Sounding new 2D task on mainframe.
1.1 1D Resistivity Sounding
1.2 1D IP Sounding
* For each rolling along survey, the first or first two cables need to be moved to the end of the section.
* At each rolling, please turn off mainframe, and then move the mainframe and cables.
ST Geomative Co., Ltd
www.geomative.com
Content III. Connection of 3D Imaging:
I. 1V VES Sounding
1.1 1D Resistivity Sounding GD-10 mainframe BP-145 power source
1.2 1D IP Sounding
Head
SR-10
switch SR-10 switch relay
End
relay
Head End