Kerb Casting
Kerb Casting
Construction of cement concrete kerb with channel with top and bottom width 115 and 165 mm respectively, 250 mm high in M 20 Grade PCC Using
code 8.2.B
1.17 Concrete Batching and Mixing Plant on M10 grade foundation 150 mm thick, kerb channel 300 mm wide, 50 mm thick in PCCM20 grade, sloped
of Price
towards the kerb, kerb stone with channel laid with kerb laying machine, foundation concrete laid manually, all complete as per clause 409
Software
Unit= Running metre
Taking output=300 metre length
Cement Concrete
Cement concrete of grade M20=17.48 cum
Cement concrete of grade M10 for base=23.18 cum
Total Concrete=40.66 cum
a) Labour
Mate Day 0.12 617 74.04 L-12
Mason (1st class) Day 1 738 738.00
Mazdoor Day 2 558 1116.00 L-13
b) Machinery 0.00
Batching and Mixing Plant (b) 15-20cum capacity hour 2.7 1873 5057.10 MR202