PROJECT : GINGER & GARLIC

ARCHITECTS / DESIGNER : STUDIO DASHLINE


DATE : 05/05/2024
INTERIOR CONTRACTOR :
SUMMARY
SL NO
A DEMOLITION WORKS 296,950

B CIVIL WORKS 1,163,300

C FLOORING WORKS 1,231,650

D WALL FINISHES WORKS 1,634,025

E CEILING WORKS 1,245,925

F CARPENTRY WORKS 1,917,540

G DOORS & GALZING & SKYLIGHTS 5,336,000

H ELECTRICAL WORKS 2,058,500

I PLUMBING WORKS 196,750

J DEEP CLEANING 40,000

15,120,640
Less Discount @ 8.5% over all -1,285,254
Total Cost + (50% GST) 13,835,386

NOTE:
GST AS APPLICABLE

SL.NO ITEM UNIT QTY RATE AMOUNT


A DEMOLITION WORKS
FIRST FLOOR
1 240MM WALL REMOVAL SFT 1200.00 20 24,000
2 FLOORING TILE REMOVAL SFT 6400.00 15 96,000
3 GLASS WITH SS ROD RAILING REMOVAL RFT 275.00 30 8,250
4 CONCRETE CHAJJA REMOVAL SFT 200.00 20 4,000
5 EXTERIOR FRONT STAIRCASE GRANITE REMOVAL SFT 250.00 20 5,000
6 LIFT FRAME REMOVAL - CHECK THE SITE IMAGE LMS 1.00 2000 2,000
7 EXISTING DOORS AND GLAZING REMOVAL LMS 1.00 4000 4,000
8 PARAPAT GRANITE JAMB REMOVAL RFT 275.00 10 2,750
10 SLAB CUTTING WORK FOR THE LIFT AND DOUBLE HEIGHT SFT 250.00 150 37,500
SECOND FLOOR 0
2 FLOORING TILE REMOVAL SFT 3600.00 15 54,000
3 GLASS WITH SS ROD RAILING REMOVAL RFT 315.00 20 6,300
5 PARAPAT GRANITE JAMB REMOVAL RFT 315.00 10 3,150
0
SHIFTING AND TRANSPORT OF ALL MATERIALS, DEBRIES
6 AND CLEANING WILL BE IN CONTRACTOR SCOPE ONLY LMS 1.00 50000
FOR BOTH FLOOR 50,000

TOTAL OF DEMOLITION WORKS 296,950

B CIVIL WORKS
1 Cinder Filling + Raised Floor (Brick Coba)
Providing and filling broken Autoclaved Aerated blocks for
sunken areas including compaction, watering and finishing with
PCC 1:3:6 screed concrete. As directed.
FF - Existing Sunken Area (Depth - 400mm) SFT 300.00 75 22,500
FF - Kitchen & Outdoor Area & Washrooms (205mm raised)
SFT 2500.00 50
125,000
FF - Niche Filling Near Fix Sofa Seating SFT 75.00 50 3,750
SF - Stage & Washrooms & outdoor bar + Live Kitchen (205mm
SFT 570.00 50
raised) 28,500
0
2 150mm thk. Wall Construction 0

Providing and laying machine moulded light weight non-load


bearing blocks of AEROCON/SIPOREX make set in CM 1:4
with absolute neat motor joints including necessary racking,
curing, etc complete with all lead and lifts at all levels.
(Note : All given wall thickness are inclusive of plaster so brick
work to be done accordingly.)
0
FF SFT 950.00 130 123,500
0
3 205mm thk. Wall Construction 0

Providing and laying machine moulded light weight non-load


bearing blocks of AEROCON/SIPOREX make set in CM 1:4
with absolute neat motor joints including necessary racking,
curing, etc complete with all lead and lifts at all levels.
(Note : All given wall thickness are inclusive of plaster so brick
work to be done accordingly.)
0
FF SFT 650.00 160 104,000
SF SFT 800.00 160 128,000
0
3 230mm thk. Wall Construction 0

Providing and laying machine moulded light weight non-load


bearing blocks of AEROCON/SIPOREX make set in CM 1:4
with absolute neat motor joints including necessary racking,
curing, etc complete with all lead and lifts at all levels.
(Note : All given wall thickness are inclusive of plaster so brick
work to be done accordingly.)
0
FF SFT 1550.00 160 248,000
SF SFT 250.00 160 40,000
0
4 Plastering Works 0

Providing & plastering 15mm thk cement plastering CM 1:5 to


internal wall finished smooth including raking/hacking the brick
and RCC work or making grooves as directed including
scaffolding, curing etc., fixing GI Arpita mesh at junction of brick
and RCL elements etc., complete
0
FF & SF SFT 4200.00 40 168,000
0
5 Block Work - As per Design 0
Providing and laying machine moulded light weight non-load
bearing blocks of AEROCON/SIPOREX make set in CM 1:4
with absolute neat motor joints including necessary racking,
curing, etc complete as per detail drawing with all lead and lifts
at all levels.
(Note : All given wall thickness are inclusive of plaster so brick
work to be done accordingly.)
0
FF - Center bench seating & Sofa seating SFT 500.00 130 65,000
FF - Internal Staircase SFT 275.00 130 35,750
FF - Niche blockwork Near Fix Sofa Seating SFT 75.00 130 9,750
SF - Smoking Area Bench SFT 110.00 130 14,300
0
6 LINTEL 0
Providing and Casting lintel with required raiforcement ms bars
and standard mixture of concrete to give proper strength to take
a load of the brick work above it. Finished price to be inclusive
of Polish finish as directed & all necessary cutting, lead and lift
as directed. 0
FF & SF - (1200x100X150/215/230) - Approx SFT 25.00 450 11,250
FF - Shelf near fix sofa seating (1200 x 475 x 100 - 2no.),
(9460 x 150 x 100mm) SFT 80.00 450
36,000
Note :
1) Shifting and Trasport of all materials, debries and cleaning will be in contractor scope only.
2) All given wall thickness are inclusive of plaster so brick work to be done accordingly.
3) The above estimate is based on areas provided by you. Actual areas may vary.
4) Billing shall be done on the basis of actual areas constructed.
5) If there will be any requirement of protecting sheet to cover any area shall be included in the above quote.
6) Scaffolding cost to be included in the contractor scope.
TOTAL OF CIVIL WORKS 1,163,300

C FLOORING WORKS
1 Granite Flooring

Providing and laying granite flooring with paper joint. Quality


and shade to designers detail. Thickness of the stone should be
a minimum of 18mm on 40 - 50mm thick cement mortar of 1:4
including necessary curing, cleaning, etc. All flooring to be
protected using vinyl sheet as approved. Joints to be filled with
required grout of approved shade & make. Finished price to be
inclusive of leather finish as directed & all necessary cutting,
lead and lift as directed.

Basic Price: ----/SFT (Only Labour Granite to be given by


client)
FF- Front Staircase and Entrance pathway SFT 1200.00 160 192,000
0
2 Tile Flooring (Nexion Endless category) 0
Providing and laying Anti skid tile flooring with paper joint.
Quality and shade to designers detail. Thickness of the tile
should be a minimum of 10mm on 40 - 50mm thick cement
mortar of 1:4 including necessary curing, cleaning, etc. All 0
flooring to be protected using vinyl sheet as approved. Finished
price to be inclusive of all necessary Cutting work, lead and lift
as directed.
Basic Price: ---/SFT (2'x4' tile size) (Only Labour, Tiles to
be given by client) 0
FF- Common Area - Color 1 ( argento) SFT 625.00 80 50,000 Cement sand included
FF& SF - Common Area - Color 2(avorio) SFT 1280.00 80 102,400
FF- Common Area - Color 3 (bianco) SFT 640.00 80 51,200
FF- Common Area - Color 4 (beige) SFT 675.00 80 54,000
FF& SF - Common Area - Color 5 (taupe) SFT 2800.00 80 224,000
0
3 Tile Flooring 0
Providing and laying Anti skid tile flooring with paper joint.
Quality and shade to designers detail. Thickness of the tile
should be a minimum of 10mm on 40 - 50mm thick cement
mortar of 1:4 including necessary curing, cleaning, etc. All 0
flooring to be protected using vinyl sheet as approved. Finished
price to be inclusive of all necessary Cutting work, lead and lift
as directed.
Basic Price: ---/SFT (Only Labour - Tiles to be given by
client ) 0
FF- Balconies (Smoking Area) SFT 400.00 75 30,000
0
4 Black Granite Threshold & Jamb 0

Providing & laying 20mm thk approved Jet black granite


threshold/Jamb on 20mm thk cement mortar of 1:4. Width of
threshold to match wall thickness. All exposed edges of the
0
granite to be machine polished. All granite to be protected using
3mm thick vinyl sheet. Finished price to be inclusive of all
necessary Cutting work, lead and lift as directed.

Basic Price: ----/SFT (Only LabourFlooring material to be


0
given by client )
FF & SF - All opening Jambs and threshold and Planters Top
RFT 350.00 200 70,000
FF - Bar Counter Flooring SFT 150.00 180 27,000
0
5 Marble Flooring 0

Providing and laying marble pattern flooring with paper joint as


per designer's detail using combination of 20mm thick approved
marble as pattern shown, on 20-25 mm thick CM 1:5 base, or
over white cement slurry base in the case of white marble, of
various size & joints finished with matching grout/joint filling
chemical to match shade of marble, finished with 3
cutting/levelling courses, application of pore sealing, resin filling 0
& necessary curing, washing, 7 coats of polishing and finishing
with all chemicals hardeners of HI TEK / equivalent make,
curing, balance 4 courses of polishing till a perfect matt finish is
obtained. Including 3mm thick vinyl sheet protection cleaning
etc. , all complete in all levels. Finished price to be inclusive of
all necessary Cutting work, lead and lift as directed.

Basic Price: ----/SFT (Only Labour Flooring material to be


given by client ) 0
FF- Bar Counter and Pick-up window area flooring SFT 275.00 190 52,250
0
6 Flat Pebble Tile Flooring 0

Providing & fixing Flat Pebble tile Flooring with paper joint.
Quality and shade as specified by designer. Thickness of the
tile should be a minimum of 20-30mm on 15 - 20mm thk
cement mortar of 1:4 including necessary curing, cleaning etc.
Finished price to be inclusive of all materials, wastages, labour,
0
cleaning, scaffolding lead and lift at all floors as directed. The
mode of measurement for certification of payment will be on
actual laid area which includes necessary wastages. Finished
price to be inclusive of all necessary Cutting work, lead and lift
as directed.

Basic Price: ----/SFT (Only Labour Flooring material to be


given by client ) 0
SF- Outdoor Seating Area SFT 200.00 40 8,000
0
7 Rubble Stone Flooring 0

Providing & fixing Rubble Stone Flooring with required grouting


and spacer. Quality and shade as specified by designer.
Thickness of the tile should be a minimum of 20-30mm on 15 -
20mm thk cement mortar of 1:4 including necessary curing,
cleaning etc. Finished price to be inclusive of all materials,
0
wastages, labour, cleaning, scaffolding lead and lift at all floors
as directed. The mode of measurement for certification of
payment will be on actual laid area which includes necessary
wastages. Finished price to be inclusive of all necessary Cutting
work, lead and lift as directed.

Basic Price: ----/SFT (Only Labour Flooring material to be


given by client ) 0
SF- Outdoor Smoking Area SFT 250.00 100 25,000
0
8 Sand stone Flooring 0

Providing and laying Sand stone flooring with paper joint.


Quality and shade to designers detail. Thickness of the stone
should be a minimum of 20mm on 40 - 50mm thick cement
mortar of 1:4 including necessary curing, cleaning, etc. All
0
flooring to be protected using vinyl sheet as approved. Joints to
be filled with cementitious grout of approved shade & make.
Finished price to be inclusive of polishing sand stone as
directed & all necessary lead and lift as directed.

Basic Price: ----/SFT (Only Labour Flooring material to be


given by client ) 0
SF- Bridge, Cabana SFT 950.00 120 114,000
Note : Sand Stone has to be cut on site as per given size in the
drawing. Approx size will be 600x200mm. 0
0
9 Granite Cladding 0
Providing and laying granite flooring with paper joint in stepped
design as per the drawing. Quality and shade to designers
detail. Thickness of the stone should be a minimum of 18mm on
40 - 50mm thick cement mortar of 1:4 including necessary
curing, cleaning, etc. All flooring to be protected using vinyl 0
sheet as approved. Joints to be filled with required grout of
approved shade & make. Finished price to be inclusive of Polish
finish as directed & all necessary cutting, lead and lift as
directed.
Basic Price: ---/SFT (Only Labour Flooring material to be
given by client ) 0
FF- Front Waterbody SFT 450.00 180 81,000
0
10 Tile Flooring 0

Providing and laying Anti skid tile flooring with 3mm spacers.
Quality and shade to designers detail. Thickness of the tile
should be a minimum of 10mm on 40 - 50mm thick cement
mortar of 1:4 including necessary curing, cleaning, etc. All
0
flooring to be protected using vinyl sheet as approved. Spacers
to be filled with epoxy/cement grout of approved shade & make.
Finished price to be inclusive of all necessary Cutting work, lead
and lift as directed.

Basic Price: ----/SFT (Only Labour Flooring material to be


given by client Tile size taken is 12x16, 2x2, 2X4 ) 0

FF- Male & Female Toilet SFT 200.00 80 16,000


SF - Male & Female Toilet SFT 100.00 80 8,000
0
11 Tile Flooring 0

Providing and laying Anti skid tile flooring with 3mm spacers.
Quality and shade to designers detail. Thickness of the tile
should be a minimum of 10mm on 40 - 50mm thick cement
mortar of 1:4 including necessary curing, cleaning, etc. All
0
flooring to be protected using vinyl sheet as approved. Spacers
to be filled with epoxy/cement grout of approved shade & make.
Finished price to be inclusive of all necessary Cutting work, lead
and lift as directed.

Basic Price: ----/SFT (Only Labour Flooring material to be


given by client Tile size taken is 12x16, 2x2, 2X4 ) 0

FF- Kitchen & Pizza Oven Area SFT 925.00 80 74,000


SF- Preparation & Storage Area SFT 110.00 80 8,800
0
12 Natural Stone Slab Flooring 0

Providing and laying Leather finished approved natural stone of


Quality and shade to designers detail. Thickness of the tile
should be a minimum of 25 to 30mm on 40 - 50mm thick
cement mortar of 1:4 including necessary curing, cleaning, etc. 0
All flooring to be protected using vinyl sheet as
approved.Finished price to be inclusive of all necessary Cutting
work, lead and lift as directed.

Basic Price: ---/SFT (Only Labour) 0


SF- Cabana Landscape Area (1300 x 560 - 3No.) SFT 50.00 80 4,000
Note : Bigger slab will be directly keeping on the base floor
0
0
13 Tile Skirting 0

Providing and laying Anti skid tile skirting of 75mm (Height)


flushed with the finished wall lvl. fixed onto 12-20mm thk CM 1:3
backing, joined with neat grey cement slurry mixed with pigment
to match the shade/colour of the slab including necessary 0
curing, cutting , rubbing , polishing, washing, mirror polishing on
surface and edges. Rate to include chipping wall & skirting to
flush with wall surfaces as directed.

Basic Price: (Only Labour) 0


FF RFT 380.00 50 19,000
SF RFT 420.00 50 21,000
0
TOTAL OF FLOORING WORKS 1,231,650
0
D WALL FINISHIES 0
1 Sand stone Cladding 0

Providing and laying Sand stone flooring with paper joint.


Quality and shade to designers detail. Thickness of the stone
should be a minimum of 20mm on 40 - 50mm thick cement
mortar of 1:4 including necessary curing, cleaning, etc. All
0
flooring to be protected using vinyl sheet as approved. Joints to
be filled with cementitious grout of approved shade & make.
Finished price to be inclusive of polishing sand stone as
directed & all necessary lead and lift as directed.

Basic Price: ----/SFT (Only Labour) 0


FF- Central Ledge Seating SFT 850.00 160 136,000
FF- Sofa Ledge Seating SFT 500.00 160 80,000
Note : Sand Stone has to be cut on site as per given size in the
drawing. Approx size will be 600x200mm. 0
0
2 Tile Cladding (Dado) 0

Providing and laying Anti skid tile Cladding with 3mm spacers.
Quality and shade to designers detail. Thickness of the tile
should be a minimum of 10mm on 40 - 50mm thick cement
mortar of 1:4 including necessary curing, cleaning, etc. All
0
flooring to be protected using vinyl sheet as approved. Spacers
to be filled with epoxy/cement grout of approved shade & make.
Finished price to be inclusive of all necessary Cutting work, lead
and lift as directed.

Basic Price: -----/SFT (Only Labour) 0


FF- Male & Female Toilet SFT 750.00 80 60,000
SF - Male & Female Toilet SFT 350.00 80 28,000
0
3 Granite Cladding 0

Providing and laying granite cladding with paper joint. Quality


and shade to designers detail. Thickness of the stone should be
a minimum of 18mm on 40 - 50mm thick cement mortar of 1:4
including necessary curing, cleaning, etc. All flooring to be
0
protected using vinyl sheet as approved. Joints to be filled with
required grout of approved shade & make. Finished price to be
inclusive of Polish finish as directed & all necessary cutting,
lead and lift as directed.

Basic Price: -----/SFT (Only Labour) 0


FF- Internal Staircase SFT 200.00 200 40,000
0
4 Marble Dado 0

Providing and Cladding marble with paper joint as per


designer's detail using 20mm thick approved marble on 20-25
mm thick CM 1:5 base, or over white cement slurry base in
the case of white marble, of various size & joints finished with
matching grout/joint filling chemical to match shade of marble,
finished with 3 cutting/levelling courses, application of pore
sealing, resin filling & necessary curing, washing, 7 coats of 0
polishing and finishing with all chemicals hardeners of HI TEK /
equivalent make, curing, balance 4 courses of polishing till a
perfect polish finish is obtained. Including 3mm thick vinyl sheet
protection cleaning etc. , all complete in all levels.Finished price
to be inclusive of all necessary Cutting work, lead and lift as
directed.

Basic Price: ----/SFT (Only Labour) 0


FF- Bar Back Shelves SFT 475.00 175 83,125
0
6 POP Punning & Putty 0
Providing POP punning on walls including preparing the wall,
making the surface free from dust particles and applying POP
slurry to achieve absolute plumb level. Thickness varying from
3-12mm as per site conditions. Rate includes the necessary
scaffolding and all lead and lift at all levels as directed. The 0
mode of measurement for certification of payment will be on
actual laid area which includes necessary wastages.

Basic Price: 0
FF- Walls SFT 2500.00 25 62,500
SF - Walls SFT 2750.00 25 68,750
Exterior Facade SFT 2930.00 25 73,250
0
7 Tile Cladding (Dado) 0

Providing and laying Anti skid tile Cladding with 3mm spacers.
Quality and shade to designers detail. Thickness of the tile
should be a minimum of 10mm on 40 - 50mm thick cement
mortar of 1:4 including necessary curing, cleaning, etc. All
0
flooring to be protected using vinyl sheet as approved. Spacers
to be filled with epoxy/cement grout of approved shade & make.
Finished price to be inclusive of all necessary Cutting work, lead
and lift as directed.

Basic Price: ------/SFT (Only Labour) 0


FF- Kitchen & Pizza Oven Area SFT 1400.00 70 98,000
SF- Preparation & Storage Area SFT 450.00 70 31,500
0
8 Royal Emulsion Paint 0

Providing and applying three coats of pre-approved Royal


emulsion paint to walls using roller brush. Including surface
preparation with one coats of white cement based putty (ready
made), primer and sanding all complete. With the necessary
drying periods for each coat. The final finish should be of a 0
uniform and neat finish to the satisfaction of the Designer. Cost
to include all scaffolding and staging.(Low VOC content paint).
The mode of measurement for certification of payment will be
on actual laid area which includes necessary wastages.

Basic Price: 0
FF- Washroom Passage Area SFT 300.00 33 9,900
SF - Washroom Passage Area SFT 350.00 33 11,550
SF - Service Staricase Area SFT 1000.00 33 33,000
FF - Walls SFT 2500.00 33 82,500
SF - Walls SFT 2750.00 33 90,750
0
9 Enamel Paint 0

Providing and painting the synthetic matt Black finish enamel


paint of approved made, shade and colour after thoroughly
sandpapering the surface remove the dust filling dense with
0
metal putty applying 2 coats of spray paint over 1 coat of primer
as manufacturers specification including cost of all labour,
material, scaffolding etc. complete as directed as all floors.

Basic Price: 0
Whole Metal Structure Frame Work (Exposed Surface) - 8500
RFT 8000.00 40 320,000
Railing RFT 5000.00 40 200,000
SF - Cabana Ornamentation RFT 0
0
10 Exterior Emulsion Paint 0

Providing and applying three coats of pre-approved Exterior


emulsion paint to walls using roller brush. Including surface
preparation with one coats of white cement based putty (ready
made), primer and sanding all complete. With the necessary
drying periods for each coat. The final finish should be of a 0
uniform and neat finish to the satisfaction of the Designer. Cost
to include all scaffolding and staging.(Low VOC content paint).
The mode of measurement for certification of payment will be
on actual laid area which includes necessary wastages.

Basic Price: 0
Exterior Facade SFT 2930.00 40 117,200
0
11 POP Arches 0

POP arches to be done as per the detailed drawing, finished


with approved paint. Price including cost of all labour, material, 0
scaffolding, base coat etc. complete as directed as all floors.

SF - (Size : As per Drawing) Nos 2.00 4000 8,000


0
TOTAL OF WALL FINISHES WORKS 1,634,025
0
E CEILING WORK 0
1 Putty work 0

Providing POP punning on ceiling including preparing the wall,


making the surface free from dust particles and applying POP
slurry to achieve absolute plumb level. Thickness varying from
3-12mm as per site conditions. Rate includes the necessary 0
scaffolding and all lead and lift at all levels as directed. The
mode of measurement for certification of payment will be on
actual laid area which includes necessary wastages.

Basic Price: 0
FF- Ceiling SFT 2200.00 30 66,000
SF - Ceiling SFT 1900.00 30 57,000
0
2 Gypsum/POP False Ceiling 0

Providing and fixing gypsum Borad / POP false ceiling on


standard India Gypsum perimeter channels, intermediate
channels, hangers and accessories( 80x26x0.5mm of GYPROC
heavy duty suspended from true ceiling spaced at every 450mm
c/c, perimeter channels of Gypsteel Ultra 20x28x30x0.5m,
45x15x15x0.9mm intermediate channels at 1200mm c/c).
12.5mm tapered edge Gypsum board panels to be fixed to
channels using 25mm self tapping fasteners at 250mm centres.
Hangers and suspenders to be fixed using 2nos. anchor
fasteners each at anchorage ends. Joints between boards to be
0
sealed with appropriate joint tape and finished with India
Gypsum make sealer. The rate is inclusive of coves, cornice &
steps wherever shown in Drawing, Upstands upto 600mm to be
considered with necessary supports, necessary Cut-outs for the
speakers,lights,smoke detectors, sprinklers, trap doors, A/C
grills and other services to be considered in final cost.
Additionally, 12x 12mm groove to be provided at periphery as
indicated in drawings , to be assumed in final cost. Finished rate
to be inclusive of all necessary scaffolding at all levels. Mode of
measurement will be on actual laid area.

Basic Price: 0
FF- Ceiling SFT 2200.00 80 176,000 Gypsum Ceiling
SF - Ceiling SFT 1900.00 80 152,000
0
3 Calcium Silicate False Ceiling 0

Providing and fixing Calcium silicate board false ceiling board


on standard Saint Gobain perimeter channels, intermediate
channels, hangers and accessories. 8mm tapered edge calcium
silicate panels to be fixed to channels using 25mm self tapping
fasteners at 250mm centers. Hangers and suspenders to be
fixed using 2nos. anchor fasteners each at anchorage ends.
0
Joints between boards to be sealed . Cut-outs for the
speakers,lights,smoke detectors, sprinklers, trap doors, A/C
grills and other services to be considered in final cost. 12mm
groove at periphery as indicated in drawings , to be assumed in
final cost. Finished rate to be inclusive of all necessary
scaffolding at all levels.

Basic Price: 0
FF- Male & Female Washroom Ceiling SFT 165.00 100 16,500
SF - Male & Female Washroom Ceiling SFT 60.00 100 6,000
FF- Outdoor Area SFT 110.00 100 11,000
0
4 Ply Boxing (Under the False Ceiling) & Pelmets 0
Providing and fixing in place, Ply boxing using 50x25mm
aluminum framework anchored true ceiling as detailed fixed with
12-18mm thick approved ply wood as detailed in drawing. 0
(Height to be considered : 650mm)

FF (9450 x 600 x 550 - 2 No.) RFT 0


0
5 Bamboo Ceiling 0

Providing and fixing 50mm dia treated bamboo keeping next to


each other and tied with the tread supporting on the 50x50mm
MS "L" section frame which will be welded with the main metal
0
structure as per given detail. other required services to be
considered in final cost. Finished price to be inclusive of all
necessary scaffolding, Cutting work, lead and lift as directed.

FF & SF - Metal structure Roof SFT 1150.00 140 161,000


0
6 Coffered Ceiling Panelling 0
Providing and fixing to be made with 12 or 19mm thk. ply
backing with required ply framework which will be anchored on
true ceiling, cladded with 1mm approved brust brass finish ss
sheet sample as per given detail in the drawing. Exposed edges
0
to be also finished with brust brass finish as per detail. Finished
price to be inclusive of all necessary hardware's will be of
approved make,scaffolding, Cutting work, lead and lift as
directed.
FF SFT 600.00 600 360,000
0
7 Stepped Ceiling 0

Providing and fixing POP false ceiling with required make mesh
on standard India Gypsum perimeter channels, intermediate
channels, hangers and accessories( 80x26x0.5mm of GYPROC
heavy duty suspended from true ceiling spaced at every 450mm
c/c, perimeter channels of Gypsteel Ultra 20x28x30x0.5m,
45x15x15x0.9mm intermediate channels at 1200mm c/c).
12.5mm tapered edge Gypsum board panels to be fixed to
channels using 25mm self tapping fasteners at 250mm centres.
Hangers and suspenders to be fixed using 2nos. anchor
fasteners each at anchorage ends. The rate is inclusive of 0
coves, cornice & steps wherever shown in Drawing, Upstands
upto 600mm to be considered with necessary supports,
necessary Cut-outs for the speakers,lights,smoke detectors,
sprinklers, trap doors, A/C grills and other services to be
considered in final cost. Additionally, 12x 12mm groove to be
provided at periphery as indicated in drawings , to be assumed
in final cost. Finished rate to be inclusive of all necessary
scaffolding at all levels. Mode of measurement will be on actual
laid area.

SF - Open Bar & Live Kitchen Area SFT 400.00 170 68,000
0
8 Royal Emulsion Paint 0

Providing and applying three coats of pre-approved Royal paint


to walls using roller brush. Including surface preparation with
one coats of white cement based putty (ready made), primer
and sanding all complete. With the necessary drying periods for
each coat. The final finish should be of a uniform and neat finish 0
to the satisfaction of the Designer. Cost to include all scaffolding
and staging.(Low VOC content paint). The mode of
measurement for certification of payment will be on actual laid
area which includes necessary wastages.

Basic Price: 0
FF- Washroom Passage Area SFT 165.00 33 5,445
SF - Washroom Passage Area SFT 60.00 33 1,980
FF- Kitchen (Only one coat) SFT 900.00 33 29,700
FF - Ceiling SFT 2200.00 33 72,600
SF - Ceiling SFT 1900.00 33 62,700
0
TOTAL OF CEILING WORKS 1,245,925
0
F CARPENTRY WORKS 0
1 Wall shelves Wall Panelling 0
Providing and Cladding as per designer's detail using 18mm
thick approved bwp ply, finished with 1mm thk. brass plate
pasting to be done with all complete in all levels. Finished price 0
to be inclusive of all necessary Cutting work, lead and lift as
directed.
FF- Niches SFT 55.00 450 24,750
0
2 Wood cladding / Lipping Work 0
Providing and Fixing approved size wooden block/lipping
cladded on the metal columns as per designer's detail and 3D
using approved screw or adhesive, All wood surfaces shall be
stained to approved colour and finished with 2 coats of matt 0
clear polish (Exterior Grade) as approved with all complete in all
levels.Finished price to be inclusive of all necessary Cutting
work, lead and lift as directed.
Size : As per 3D 0
FF & SF - Metal Columns (75 x75 1200 - 30No.) Nos 30.00 5500 165,000
0
3 Wood cladding / Lipping Work & High ledge 0
Providing and Fixing approved 6mm thk. wooden block/lipping
cladded on 12mm thk. ply backing as per designer's detail using
approved screw or adhesive, High Ledge counter to be made
with required aluminium box section, cladded with 8mm thk. ply
backing, finished with approved veneer as per given detail.
50mm dia brass rod for the foot rest to be fixed as per detail. All
wood and veneer surfaces shall be stained to approved colour 0
and finished with 2 coats of matt clear polish as approved with
all complete in all levels.Finished price to be inclusive of all
necessary Cutting work, lead and lift as directed.

FF - Central Ledge Seating RFT 130.00 1200 156,000


FF - High Ledge Counter SFT 40.00 1600 64,000
0
4 Panneling Work 0

Providing and Fixing 4mm thk. approved veneer, cladded on 12


- 18mm thk. ply backing as per designer's detail using approved
adhesive, All veneer surfaces shall be stained to approved
colour and finished with 2 coats of matt clear polish (Exterior 0
Grade) as approved with all complete in all levels. Finished
price to be inclusive of all necessary Cutting work, lead and lift
as directed.

FF - Below the Courtyard Glazing SFT 75.00 650 48,750


Veneer taken as ----- Rs sqft 0
5 Panneling Work 0

Providing and Cladding as per designer's detail using 18mm


thick approved bwp ply, finished with 1mm thk. brass plate
pasting to be done. (Panelling to be flushed with the finished 0
wall lvl.) with all complete in all levels.Finished price to be
inclusive of all necessary Cutting work, lead and lift as directed.

FF - Above the Lift door (size : 900 x 750) NO. 1.00 8000 8,000
Need a reference image or Drawing for costing 0
6 Bar Front Counter 0

Providing & fixing Main Bar Counter as per drawing using brick
masonry in cement mortar 1:4 using table mould bricks of
standard size with minimum crushing strength of 35 Kg/sq. cm
including of raking of joints, scaffolding, etc. all complete as
directed at all levels. Masonry to be fixed with 20mm thick pre
polished approved marble cladding for the higher and lower
both counter top as detailed in drawing. Vertical Support below
the counter to be cladded with approved granite / tile with paper
joint + storage to be made in 18mm thk. pvc ply with approved 0
laminate of approved shade & make for internal and external
surface. Front of the counter to be made with required ply
backing, cladded with 1mm thk. brass plate as shown in the
detail drawing to be pasted with required adhesive. All
necessary hardware will be hafele make. handles customised
as per Architect's design to be provided.Finished price to be
inclusive of all necessary scaffolding, Cutting work, lead and lift
as directed.

100mm thk. Brick work to be considered in the price - 150 sqft


0
quantity
Marble Quantity :----- sqft (Note: Marble to be provided by the
0
client)
Note : Tile Under the counter to be considered in the quote
0
(Basic Price : 60/sqft)

FF (Size : As per Drawing) Rft 166.50 250 41,625


0
7 Bar Back Counter 0

Providing & fixing Bar back Counter as per drawing using


required size of aluminium box section framing cladded with
18mm thk. ply backing on all side with 20mm thick pre
polished approved marble cladding for the shelves and counter
top as detailed in drawing. Horizontal shelves to be made with
18mm thk. ply backing with aluminium box section framing if
required, finished with 1mm thk. brass plate as per detail shown
in drawing. Vertical Support below the counter to be cladded
with approved granite / tile with paper joint + storage and 0
shutters to be made in 18mm thk. pvc ply with approved
laminate of approved shade & make for internal and external
surface. Unit to have openable shutters with fingerskip details.
All necessary hardware like hinges/floor spring, door stoppers,
door locks, door closers etc will be hafele make. handles
customised as per Architect's design to be provided.Finished
price to be inclusive of all necessary scaffolding, Cutting work,
lead and lift as directed.

Note : Marble to be provided by the client 0


FF (11100 x 1250 x 1000) Rft 166.50 250 41,625
0
8 Bar Counter Door 0

Providing & fixing Bar Counter door as per drawing using 18mm
thk ply backing, internally finished with the approved 1mm thk.
laminate of approved shade and externally finished with 1mm
thk. brass plate cladding or approved brass paint finish in
stepped design as per given drawing. All necessary hardware 0
like hinges, door stoppers, door locks etc will be hafele make.
handles customised as per Architect's design to be
provided.Finished price to be inclusive of all necessary
scaffolding, Cutting work, lead and lift as directed.

FF (900 x 1050) SFT 10.50 800 8,400


0
9 DJ Cabin Door 0

Providing & fixing 30mm thk. DJ Counter door as per drawing


using 18mm thk ply backing, internally and externally finished
with the approved 1mm thk. laminate of approved shade All
necessary hardware like hinges, door stoppers, door locks etc 0
will be hafele make. handles customised as per Architect's
design to be provided.Finished price to be inclusive of all
necessary scaffolding, Cutting work, lead and lift as directed.

FF (900 x 940) SFT 9.60 550 5,280


0
10 Pick-Up & Pizza Oven Counter 0

Providing & fixing Panelling to be done in 18mm thk. ply backing


with 1mm thk. brass sheet or approved brass paint as per given
detail in drawing. Providing and laying marble counter top with
paper joints as per designer's detail with matching grout/joint
filling chemical to match shade of marble, finished with 3
cutting/levelling courses, application of pore sealing, resin filling
0
& necessary curing, washing, 7 coats of polishing and finishing
with all chemicals hardeners of HI TEK / equivalent make,
curing, balance 4 courses of polishing till a perfect matt finish is
obtained. Including 3mm thick vinyl sheet protection cleaning
etc. , all complete in all levels. Finished price to be inclusive of
all necessary Cutting work, lead and lift as directed.

100mm thk. Brick work to be considered in the price - 50 sqft


0
area
Marble Quantity :------ sqft (Note: Marble to be provided by the
0
client)
Size : As per drawing 0
FF - Pick-Up Counter (2100 x 825 x 1250) SQFT 21.00 1200 25,200
FF - Pizza Oven Counter (2850 x 400 x 1250) SQFT 38.00 1200 45,600
0
11 Pizza Oven Service Counter 0

Providing and laying Black Granite counter top as per


designer's detail with matching grout/joint filling chemical to
match shade of granite, finished with glossy finish with all
chemicals hardeners of HI TEK / equivalent make, curing,
0
balance 4 courses of polishing till a perfect glossy finish is
obtained. Including 3mm thick vinyl sheet protection cleaning
etc. , all complete in all levels. Finished price to be inclusive of
all necessary Cutting work, lead and lift as directed.

Marble Quantity : ------ sqft (Note: Granite to be provided by the


0
client)
Size : As per drawing 0
FF (2860 x 600 x 900) SFT 27.70 180 4,985
0
12 Metal Staircase 0

Providing, fabricating and erecting Structural steel members in


position at all levels and at all heights as specified in the
drawings made out of standard MS sections conforming to IS
226/2062/800. Cost to include fabricating necessary Gusset
Plates, Stiffener plates, Brackets, Bolts, anchor bolts, anchor
fasteners, Cleats, L and Tee angles, Chequered plate, MS
plates etc., to the required size, shape, alignment etc., as per
the drawings. Cost to include welding of members using
0
structural steel welding electrodes as per IS 814/816/817, a
coat of anti corrosive primer (non flammable) to the exposed
surfaces, testing as per IS 7307 (PART 1), necessary
equipment's, tools and tackles, staging, scaffolding required
etc., complete. for all floors & staircases, including a coat of zinc
chromate primer and two coats of Synthetic enamel painting for
the steps and duco paint for the railing of approved shade &
make.

SF- Internal Staircase LMS 1.00 150000 150,000


0
13 Metal Railing 0
Providing, fabricating Ms railing with given different sizes of Ms
box section and ms plate with required thickness as per
detail. .Finished price to be inclusive of all necessary 0
Cutting,welding & metal paste filling work, lead and lift as
directed.
FF- Entrance Area RFT 175.00 225 39,375
FF- Balcony RFT 100.00 225 22,500
0
14 Ply Boxing (for the hanging lights) 0
Providing and fixing in place, Ply boxing using 50x25mm
aluminum framework anchored true ceiling as detailed fixed with
18mm thick approved ply wood above the false ceiling as 0
detailed in drawing. (Height to be considered : 600mm)

500 X 500 X 600 NO. 10.00 2500 25,000


1000 X 1000 X 600 NO. 1.00 4000 4,000
0
15 Vanity Counter 0

Providing, fabricating and fixing Vanity unit as per drawing using


12mm, 19mm thick approved PVC ply fixed with 20mm thick
approved Granite with sandwiched & polished edges &
supported using necessary MS L angle supports as detailed.
0
Under counter Basin also will be made with approved same
granite as counter as per the detail. Rate inclusive of making
necessary cut-outs for fixing wash basin. Exposed edges to be
fixed with wooden beading as approved.

Note : Granite to be provided by the client 0


FF- Male Washroom (455 x 1935 x 175) NO. 1.00 9000 9,000
FF- Female Washroom (455 x 1920 x 175) NO. 1.00 9000 9,000
SF- Male Washroom (1500 x 450 x 175) NO. 1.00 8000 8,000
SF- Female Washroom (600 x 450 x 175) NO. 1.00 6000 6,000
0
16 Washroom Cubicles 0

Providing, fabricating and fixing partition made with aluminium


box section framing, cladded with approved colour, finish and
make ACP sheet. Rate inclusive of All necessary hardware will
be hafele make. handles customised as per Architect's design 0
to be provided.Finished price to be inclusive of all necessary
scaffolding, Cutting work, lead and lift as directed. (Note : Doors
to be included)

FF- Male & Female Washroom SFT 180.00 550 99,000


FF- Male & Female Washroom Doors (700 x 3050) NO. 4.00 10000 40,000
( Rate as actual to be taken from Glass vendor ) 0
17 Janitor Closet 0

Providing & fixing Storage as per drawing using 12mm, 18mm


thick approved pvc ply finished with laminate of approved shade
& make for all internal & external areas.Unit to have openable
shutters with fingerskip details. Exposed edges to be fixed with
wooden beadings stained & finished in polish as approved. All 0
necessary hardware like hinges, door stoppers, door locks etc
will be hafele make. handles customised as per Architect's
design to be provided.Finished price to be inclusive of all
necessary scaffolding, Cutting work, lead and lift as directed.

FF- Female Washroom (1290 x 3050 x 365) NO. 1.00 51000 51,000
FF- Female Washroom ( 410 x 3050 x 365) NO. 1.00 16000 16,000
0
18 Mirrors 0
Providing & fixing mirror as per drawing using approved ply
framework fixed with 19mm thick approved ply fixed with 6mm
thick approved mirror as detailed in drawing. All exposed edges 0
to be fixed with wooden beading stained & finished in polish as
detailed in drawing.
FF- Male Washroom (1935 x 1200) NO. 1.00 10500 10,500
FF- Female Washroom (1925 x 1200) NO. 1.00 10500 10,500
SF- Male Washroom (1500 x 1200) NO. 1.00 8000 8,000
SF- Female Washroom (620 x 1200) NO. 1.00 3200 3,200
( Rate as actual to be taken from Glass vendor ) 0
19 Community Seating 0

Providing & laying 20mm thk approved marble on block work for
the community table. Vertical support to be made with block
work as per given size and top will be cast in concrete, cladded
with approved marble as per given detail. 75mm dia SS pipe to
be fixed for the foor rest, finished in brass finish as per detail. All
0
exposed edges of the marble to be machine polished. Table to
be protected using 3mm thick vinyl sheet. Required water
proffing etc to be considered for the intigrated planters in the
table.Finished price to be inclusive of all necessary Cutting
work, lead and lift as directed.

SF - (7220 x 900 x 750) NO. 1.00 60000 60,000


0
20 Open Bar & Live Kitchen Counter 0

Providing & fixing Open Bar Counter as per drawing using brick
masonry in cement mortar 1:4 using table mould bricks of
standard size with minimum crushing strength of 35 Kg/sq. cm
including of raking of joints, scaffolding, etc. all complete as
directed at all levels. Masonry to be fixed with 20mm thick pre
polished approved marble cladding with paper joint for the
higher and lower both counter top and bottom step design as
detailed in drawing. Vertical Support below the counter inner
0
side to be cladded with approved granite / tile with paper joint +
storage to be made in 18mm thk. pvc ply with approved
laminate of approved shade & make for internal and external
surface. Unit to have openable shutters with fingerskip details.
All necessary hardware will be hafele make. handles
customised as per Architect's design to be provided.Finished
price to be inclusive of all necessary scaffolding, Cutting work,
lead and lift as directed.

SF - Open Bar Counter (3080 x 1050 x 1200) NO. 1.00 65000 65,000
SF - Live Kitchen Counter (3080 x 1050 x 1200) NO. 1.00 60000 60,000
0
21 Open Bar & Live Kitchen Back Counter 0

Providing & fixing Bar back Counter as per drawing using 20mm
thick pre polished approved marble cladding for the counter top
as detailed in drawing. Vertical Support below the counter to be
cladded with approved granite / tile with paper joint + storage
and shutters to be made in 18mm thk. pvc ply with approved
shade and make 4mm thk. veneer external surface and 1mm
thk. approved shade and make 1mm thk. laminate for internal 0
surface. Unit to have openable shutters with fingerskip details.
All necessary hardware like hinges/floor spring, door stoppers,
door locks, door closers etc will be hafele make. handles
customised as per Architect's design to be provided.Finished
price to be inclusive of all necessary scaffolding, Cutting work,
lead and lift as directed.

FF - Open Bar Back Counter (4380 x 900 x 900) NO. 1.00 63000 63,000
FF - Live Kitchen Back Counter (4380 x 900 x 900) NO. 1.00 63000 63,000
0
22 Open Bar & Live Kitchen Wall Shelves 0

Providing & Fixing 50mm thk shelves made out of required


aluminium framing cladded with 8mm th. ply all side, finished
with approved shade and make 4mm thk. veneer with required
achorfastner to fixe the shelves on the wall + 1mm thk. brass
0
plate cladding on 12mm thk. ply backing or approved make
brass paint finish to be done between the two shelves as per
given detail. Finished price to be inclusive of all necessary
Cutting work, lead and lift as directed.

SF - Open Bar Wall Shelves (4380 x 450 x 50) NO. 2.00 45000 90,000
SF - Live Kitchen Wall Shelves (4380 x 450 x 50) NO. 2.00 45000 90,000
0
23 Mosaic Artwork Frame 0

Providing & Fixing wooden/HDF frame to be fixed on the wall as


per given detail in drawing for the mosaic artwork to be finished
in the same as wall finish.12mm thk. ply backing to be 0
considered for to fix the mosaic. Finished price to be inclusive of
all necessary Cutting work, lead and lift as directed.

SF - (2610 x 2485 x 50) NO. 1.00 70000 70,000


0
24 Inlay work (In the wall) 0
Providing & Fixing wooden lipping inlay have to be done with
0
required ply backing as per details.
SF - As per 3d LMS 1.00 50000 50,000
0
25 Beam Covering 0

Providing & Fixing 18mm thk. ply boxing to cover the metal
beam with required aluminium box section framing to give
0
support, to finished with pop. Finished price to be inclusive of all
necessary Cutting work, lead and lift as directed.

FF - Double Height Cut-out SFT 275.00 350 96,250


0
26 Ply Boxing 0

Providing & Fixing 6" thk. boxing to be done above the stepped
ceiling using required aluminium box section framing, cladded
0
with 12mm thk. ply as required. Finished price to be inclusive of
all necessary Cutting work, lead and lift as directed.

SF - Open Bar & Live Kitchen Counter SFT 150.00 400 60,000
0
TOTAL OF CARPENTRY WORKS 1,917,540
0
G DOORS & GLAZING & SKYLIGHTS 0
1 Fixed Glazing 0
Providing and fixing in place Glazed Partitions in Approved
brand Aluminium Frame as per designer's detail. 10mm thk
toughened glass is to be fitted in standard Matt Black aluminium
frame using clips. All aluminium sections to be powder coated to
0
approved shade. Rate to include providing & fixing approved
film as directed.Finished price to be inclusive of all necessary
Harware, Cutting work, lead and lift as directed. (consider thin
section)
Basic Price: 0
FF- Open Courtyard SFT 275.00 650 178,750
FF- Sofa Seating Area SFT 120.00 650 78,000
FF- Private Dining SFT 190.00 650 123,500
FF - Outdoor Seating Area SFT 60.00 650 39,000
FF - Balcony(Smoking Area) SFT 68.00 650 44,200
0
SF - Outdoor Seating & Smoking Area SFT 320.00 650 208,000
SF - Cabana SFT 860.00 650 559,000
SF - Multifunction Area SFT 300.00 650 195,000
SF - Front Façade (Above the Entrance) SFT 270.00 650 175,500
1600950
2 Top Hung Openable Glazing 0

Providing and fixing Top Hung Openable glazing in approved


brand Aluminium Frame as per designer's detail. 12mm thk
toughened laminated glass is to be fitted in standard Matt Black
aluminium frame using clips and rubber gaskit to prevent from
the water. All aluminium sections to be powder coated to 0
approved shade. Rate to include providing & fixing approved
film as directed.Finished price to be inclusive of all necessary
Harware, Cutting work, lead and lift as directed. (consider thin
section)

Basic Price: 0
SF - Cabana (Size : 750 x 1200) - 16 no SFT 160.00 800 128,000
0
3 Skylight 0

Providing and fixing Skylight in approved brand Aluminium


Frame as per designer's detail. 12mm thk toughened laminated
glass is to be fitted in standard Matt Black aluminium frame
using clips and rubber gaskit to prevent from the water. All
0
aluminium sections to be powder coated to approved shade.
Rate to include providing & fixing approved film as
directed.Finished price to be inclusive of all necessary Harware,
Cutting work, lead and lift as directed. (consider thin section)
Basic Price: 0
FF & SF - Metal Frame Roof SFT 1250.00 650 812,500
FF- Entrance SFT 100.00 650 65,000
FF - Common Area (6 cut-out) SFT 400.00 650 260,000
650 0
SF - Open Bar & Live Kitchen Counter SFT 132.00 650 85,800
SF - Community Seating + Multifunction Area SFT 660.00 650 429,000
SF - Cabana SFT 1025.00 650 666,250
2318550
4 Glass Doors (Openable) 0

Providing and fixing in place Glass Door in Aluminium Frame as


per designer's detail. 10mm thk toughened glass is to be fitted
in standard Matt Black aluminium frame using clips. All
aluminium sections to be powder coated to approved shade.
0
Necessary hardware like butt hinges, locks, tower bolts, mortise
lock, stopper and door closer are to be provided. Rate to
include providing & fixing approved film as directed.Finished
price to be inclusive of all necessary lead and lift as directed.

Basic Price: 0
FF- Outdoor Area Opening size is 1000 (500x3250) Nos. 2.00 35000 70,000
FF- Internal Staircase Area (775x3250) Nos. 1.00 32000 32,000
FF- Washroom Passage (940x3050) Nos. 2.00 28000 56,000
SF- Cabana (1300 x 3660) Nos. 2.00 38000 76,000
0
5 Glass Doors (Sliding) 0

Providing and fixing in place Glass Sliding Door in Aluminium


Frame as per designer's detail. 10mm thk toughened glass is to
be fitted in standard Matt Black aluminium frame using clips. All
aluminium sections to be powder coated to approved shade.
0
Necessary hardware like butt hinges, locks, tower bolts, mortise
lock, stopper and door closer are to be provided. Rate to
include providing & fixing approved film as directed. Finished
price to be inclusive of all necessary lead and lift as directed.

Basic Price: 0
FF- Outdoor Seating Area (synchronised sliding) (1425 x 3090)
Nos. 2.00 145000 290,000
These are Sensor door
SF- Outdoor Seating Area (1200 x 3660) Nos. 1.00 135000 135,000
SF- Outdoor Smoking Area (1200 x 3660) Nos. 1.00 135000 135,000
0
6 Main Door (Openable) 0
Providing, fabricating & fixing using Approved floor spring
double leaf door using bloack board with 4mm the approved
veneer + wooden beading/lipping as per given sizes and detail
on both sides. The exposed edges of shutter shall be fitted with
12mm the TW Lipping. All wood and veneer surfaces shall be
stained to approved colour and finished with 2 coats of matt
clear polish as approved. All necessary hardware like
hinges/floor spring, door stoppers, door locks, door closers etc 0
will be hafele make. Door will be on approved make floor spring.
handles customised as per Architect's design to be
provided.Finished price to be inclusive of all necessary
scaffolding, Cutting work, lead and lift as directed.

FF- Main Entry (2370 x 3165) Nos. 1.00 75000 75,000


0
7 Toilet Doors (Openable) 0

Providing & fixing openable door as per drawings using 32-


35mm thk. block board and clad with 1mm the approved
Laminate on both sides as per detail. The edges to be fixed with
wooden beading as approved. All wooden surface to be stained
0
& finished polished as approved. Necessary hardware like
Hinges, Concealed locks & handles, signage etc will be hafele
make. Finished price to be inclusive of all necessary
scaffolding, Cutting work, lead and lift as directed.

FF- Male Washroom (760 x 3050) Nos. 1.00 22000 22,000


FF- Female Washroom (835 x 3050) Nos. 1.00 22000 22,000 Consider 2400 mm Height
SF- Male Washroom (800 x 3050) Nos. 1.00 22000 22,000
SF- Female Washroom (800 x 3050) Nos. 1.00 22000 22,000
0
8 Back Entry Door (Openable) 0
Providing & fixing openable using 32-35mm thk. block board,
clad with 18mm thk. mdf on front side with scooping detail as
per drawing cladding with 1mm thk. brass plate cladding in the
scooping area and 4mm approved veneer on both sides with
brass handle as per detail drawing. The edges to be fixed with
wooden beading as approved. All wooden surface to be stained 0
& finished polished as approved. Door to be fixed on the floor
spring.Necessary hardware like Hinges, Concealed locks &
handles, signage etc will be hafele make.

FF (1500 x 3050) Nos. 1.00 35000 35,000


0
9 Back Entry Door (Openable) 0

Providing & fixing openable using 32-35mm thk. block board,


clad with 8mm thk. mdf on both side with approved paint finish
same as the wall on both side with approved handle detail as
per drawing.The edges to be fixed with wooden beading as
0
approved. All wooden surface to be stained & finished polished
as approved. Door will be on exposed door closer fixture.
Necessary hardware like Hinges, Concealed locks & handles,
signage etc will be hafele make.

SF (1285 x 3250) Nos. 1.00 32000 32,000


0
10 Kitchen Door (Openable) 0

Providing & fixing openable door as per drawings using 32-


35mm thk. block board and clad with 1mm the approved
Laminate and SS plate for the handle on both sides and look
out window as per detail. The edges to be fixed with wooden
beading as approved. All wooden surface to be stained &
0
finished polished as approved. Double side openable hinge to
be use for the shutters. Necessary hardware like Hinges,
Concealed locks & handles, signage etc will be hafele make.
Finished price to be inclusive of all necessary scaffolding,
Cutting work, lead and lift as directed.

FF (1120 x 3250) Nos. 1.00 35000 35,000


0
11 Preparation Storage & Live Kitchen Area Door (Sliding) 0

Providing & fixing Sliding door using 32-35mm thk. block board,
clad with 12mm thk. mdf on both side with approved paint finish
same as the wall on both side with approved handle detail as
per drawing.The edges to be fixed with wooden beading as 0
approved. All wooden surface to be stained & finished polished
as approved. Necessary Sliding hardware, Concealed locks &
handles, signage etc will be hafele make.

SF (1150 x 3050) Nos. 2.00 35000 70,000


0
12 L4 Doors (Openable) 0

Providing & fixing openable door as per drawings using 32-


35mm thk. block board and clad with 1mm the approved
Laminate on both sides as per detail. The edges to be fixed with
wooden beading as approved. All wooden surface to be stained
& finished polished as approved. Normal Butt hinge will be use 0
for this door. Necessary hardware like Hinges, Concealed locks
& handles, signage etc will be hafele make. Finished price to be
inclusive of all necessary scaffolding, Cutting work, lead and lift
as directed.

SF (980 x 2500) Nos. 1.00 22000 22,000


0
13 Glass Railing 0

Providing and fixing glass railing in 50x25mm MS box section


frame as per designer's detail. 10mm thk toughened glass is to
be fitted in standard MS frame using clips. All sections to be
powder coated to approved shade. Rate to include providing & 0
fixing approved film as directed and inclusive of all necessary
silicon grouting, scaffolding, Cutting work, lead and lift as
directed.

SF - Double Height cut-outs SFT 275.00 500 137,500


0
TOTAL OF DOORS & GLAZING & SKYLIGHTS WORKS 5,336,000
0
G ELECTRICAL WORKS 0
Electrical Works
(Tendered to quote a rate per sft. of the entire floor plate as per
the parameters mentioned herein and the drawings / design
shared by architect).
Whats includes -
Labour charge for all wiring, conduiting, cheiseling of walls,
Fixing modular boxes, Data Points, CAT6, Curtain points.
Rate also includes data points such as cabling works for data
/ voice face plates, i.o's of dlink or equivalent make, jack panels,
patch panels, ferruling, numbering, cable dressing, data cabling 0
for fire alarm, cctv & access control, etc.
Rate also includes wiring for communication points such as
telephone points, Wiring for AC's, Bells, Camera Points and
Cabelings, TV wires, 2 core speaker wires unless a specialized
cabling is required.

ITEMS NOT INCLUDED ARE :


1. Designer FacePlates
2. All kind of lights, Decorative or Ambiant, Chandeliers etc
3. EPBAX machines.
4. DVR Or Racks
5. DISH OR DTH dish for TV
6. ANY EQUIPMENTS - Server Rack, Online UPS, all 0
Electronic equipments are in scope of the Clients.
7. EQUIPMENTS LIKE High load Electrical Panel, Servo and
other related equipments. If those are required has to be bought
by the clients directly.
8. Main line / Armored cable work, Transformer work is not
included in the price. That needs to be provided by the Electrical
Authorities.
First Floor SFT 4850.00 230 1,115,500 all Wiring included
Second Floor SFT 4100.00 230 943,000
0
ELECTRICAL WORKS 2,058,500
0
I PLUMBING WORKS 0
Labour Charges for Internal plumbing work.
All fittings to be bought by clients directly and given to us. 0
1 Labour Charges for all Internal pipes for Toilets Nos 4.00 12000 48,000
2 Labour Charges for Plumbing lines and drain lines for Water bode Nos 3.00 5000 15,000
SEEWAGE LINES Nos 2.00 4000 8,000
1 4 Inch and 6 Inch Pipe line Approximate area, Rft 615.00 50
Actual to be counted later on. 30,750
only laying pipe
2 Chamber / Manholes Nos 5.00 4500 22,500
3 Shaft Drain, and Rain wate Pipeline Stacks Rft 1050.00 50 52,500 only laying pipe
All quantities are given in approximation, areas to be checked
and updated post completion of work. 0
4 Waterproofing for the Toilets and Waterbody LMS 1.00 20000 20,000
0
PLUMBING WORKS 196,750

NOTE
MATERIAL MAKE LIST
CONSIDER ALL COMM PLYWOOD ISI BRANDED MR GRADE , TOILET & PANTRY AREA USE WP
1
PLYWOOD.
CONSIDER INTERNAL SURFACE 0.8MM LAMINET & OUTSIDE 1MM LAMINETES. MERRINO, GREEN ,
2
CENTURY, IDEAL.
3 CONSIDER ALL HARDWARE MAKE HATTICH, EBCO, ENOX OR EQUALANCE. (SOFT CLOSING)
4 CONSIDER ALL PAINT & POLISHING METARIAL MAKE BY ASIAN PAINTS.
CONSIDER GLASS & MIRRORS MAKE SAINT GOBIN
5
BRAND.
CONSIDER GYPSUM & CALCIUM SILICATE BOARD SAINT
6
GOBIN MAKE
CONSIDER ALLUMINIUM SECTION FRAME DOORLINE
7
MAKE
CONSIDER PLUMBING INTERNAL PIPE CPVC ASHIRWAD,
8
SUPRIME MAKE
CONSIDER PVC PIPE FOR DRANAGE AND EXTRANAL
9
SUPERIME MAKE

10 CONSIDER ELECTRICAL WIRES POLYCAB, HAVELS MAKE


CONSIDER ELECTRICAL SOCKETS & SWITACHES LEGRAND
11
MAKE BLACK MATT