KGG-SOP-020, Material Handling - Storage & Logistics Procedure
KGG-SOP-020, Material Handling - Storage & Logistics Procedure
Rev DATE:
PREPARED BY REVIEWED BY APPROVED BY
00 15-01-21 VICTORY
KENNETH ODIA
ONOFUA
STATEMENT OF AUTHORITY
This Materials Control Procedure has been prepared to comply with KGG operations to
satisfy customer requirements. The procedure is the key working document that links all
materials control issues pertaining to yard and site construction and management of all
operations.
The Materials Control Procedure is issued with my authority and approval. Responsibility
for compliance with its provisions rests with all personnel assigned whose work are
defined therein, with managers and supervisors playing the leading role.
The responsibility for maintenance of the procedure, and for monitoring compliance with
it, rests with the Quality Assurance & Quality Control Manager, while the Materials
Manager is the document owner.
COUNTRY MANAGER
2
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 3 of 39
TABLE OF CONTENTS
Description Page
Policy 5
Purpose 5
Definitions 5
Responsibilities 7
Implementation 7
Policy ................................................................................................ 8
Purpose............................................................................................. 8
Affects ............................................................................................... 8
Responsibilities ................................................................................. 9
Implementation ................................................................................. 9
Attachments ...................................................................................... 9
Policy ................................................................................................ 11
Purpose............................................................................................. 11
Affects ............................................................................................... 11
Responsibilities ................................................................................. 12
Implementation ................................................................................. 12
Attachments ...................................................................................... 17
Policy ................................................................................................ 19
Purpose............................................................................................. 19
Affects ............................................................................................... 20
Responsibilities ................................................................................. 20
3
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 4 of 39
Implementation 20
Attachments 21
Policy ................................................................................................ 21
Purpose............................................................................................. 21
Affects ............................................................................................... 21
Responsibilities ................................................................................. 22
Constraints ........................................................................................ 22
Implementation ................................................................................. 22
Warehouse Safety Guidelines........................................................... 23
Policy ................................................................................................ 35
Purpose............................................................................................. 35
Affects ............................................................................................... 35
Responsibilities ................................................................................. 36
Implementation ................................................................................. 36
Attachments ...................................................................................... 37
Policy ................................................................................................ 38
Purpose............................................................................................. 38
Responsibilities ................................................................................. 38
Implementation ................................................................................. 38
Attachment ........................................................................................ 40
4
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 5 of 39
INTRODUCTION
Policy
The policy for Material Control is to develop and implement the systems required
for the efficient and effective receipt, inspection, preservation and disbursement of
material, maintenance of required and auditable historical data and to advise
Construction and Operations management of potential problem areas.
Purpose
Definitions
Report
A record of the visible damage detected upon receipt from the carrier or concealed
damage determined upon inspection following unpacking.
Documentation
Inspection
5
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 6 of 39
The basic document of materials receiving It records all pertinent information from
vendor shipping and purchase order documents about what was received.
Material Exception
Physical defects
Tests failures
Incorrect or inadequate documentation
Deviation from prescribed processing
Inspection
Test procedures
Overage
Any excess over and above that stated on carrier’s freight note or supplier’s
delivery receipt. It can also be excess material over and above what is listed in
the purchase order.
Shortage
A record of quantity deviations from the freight bill, delivery receipt and purchase
order as determined during material receiving.
Physical Inventory
6
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 7 of 39
Store Requisition
Responsibilities
Materials Manager
The Materials Manager has the authority and responsibility for ensuring the
implementation of Material Control Procedures and reports directly to the
Administration and Finance Manager.
He shall be the focal point for all matters relating to scope of material supply.
Implementation
Warehouse safety program to ensure efficient and safe working conditions for
warehouse employees.
7
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 8 of 39
Control of field engineering material changes to any project surplus and final
reconciliation of KGG scope of material supply.
MATERIAL COORDINATION/CONTROL
The following reports will be provided to the Materials Manager prior to receipt of materials:
Policy
Purpose
To ensure that transfer of material into custody is handled expeditiously and that
records are complete and accurate.
Affects
Procurement Department
8
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 9 of 39
Responsibilities
Materials Manager
The Materials Manager shall have overall responsibility for establishing and
ensuring compliance with materials control documentation procedures.
Warehouse Supervisor
Implementation
Receipt from carrier and transfer to storage shall be accomplished with care to
ensure complete and accurate records are maintained and exposure to damage
eliminated. This work shall be carried out under warehouse staff supervision.
9
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 10 of 39
Identification of Materials
A completely filled out Material Receiving Report shall be issued for each material
shipment received by referencing the relative purchase order number within one
week of receipt at the yard or site.
The MRR complete with purchase order data is then confirmed by checking this
data against delivery dockets. Any difference is then documented on the
appropriate form, i.e. over and short damage report, and/or material exception
report.
All MRR’s shall be filled out completely and shall be distributed as indicated below:
10
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 11 of 39
Copy : Procurement
Copy : Project Control
3.6 Attachments
Policy
All materials and equipment received shall be checked to determine any overage
or shortage against quantity purchased.
All material and equipment received shall be checked to detect any shipping or
transportation damage.
Purpose
To ensure the quality of the material received meets the job specifications.
Affects
11
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 12 of 39
QA/QC Department
Procurement Department
Site Engineer
Responsibilities
Materials Manager
The Materials Manager shall have overall responsibility for establishing and
maintaining effective material inspection instructions.
Warehouse Supervisor
Implementation
Shortages and visible damage detected at time of delivery from the carrier shall be
assumed to have occurred in transit. The carrier agent’s acknowledgement of the
delivery condition shall be obtained to permit recovery of costs by the insurer
and/or carrier. Field material control will issue the applicable over/short, damage
report and make required distribution.
12
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 13 of 39
These items shall remain in quarantine until the “Action” requirements of the site
engineer listed on the damage report and material exception report are completed
and signed accepted by QA/QC inspection staff. Items are then released from
quarantine.
Use a rubber receiving stamp of the following type to stamp the original freight
note:
Received in apparent good order except as noted, but subject to inspection for
concealed damage. (Note any apparent loss or damage here).
The receiving stamp and any applicable loss or damage notations are to be
applied to the original freight note, plus one copy; the original goes back to the
carrier; a copy is retained for use in preparing the MRR.
After uncrating or unpacking goods, during inspection, verifying actual count and
comparing purchase order quantities and descriptions with packing lists, various
discrepancies (over, short, concealed damage, or material exceptions) can occur
13
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 14 of 39
which will prevent the writing of a clean material receiving report. Any time that
equipment or materials which vary in quantity from that claimed by the vendor do
not meet purchasing document description or specification requirements, or are
received in a damaged condition, supplemental reports must be initiated to assure
rectification and to expedite the receipt of items which may be critical to the
construction schedule. The supplemental reports are:
Two simple rules govern warehousing and project account handling of over and
short materials and equipment situations:
14
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 15 of 39
A material over/short report log shall be kept listing the report number and the
status.
This log will serve as the basis for expediting the procurement department for a
resolution
This log will be distributed to Procurement “on a weekly basis” showing what items
still require action.
Damage Report
Warehouse Officer shall then contact the QA representative who will fill out the
damage report in detail per his inspection and attach any data, reports and
pertinent evidence deemed required to support the claim.
15
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 16 of 39
Each damage report will advise required corrective action by the Site Engineer.
Settlement of all carrier damage claims is the responsibility of the Logistics Officer.
The Material Manager shall transmit copies of all carrier damage reports (including
concealed damage), along with photographs, if any, inspection reports and any
other reports or pertinent information/instructions to the Logistics Officer for
processing of insurance claims and/or back-charges to carriers.
If the carrier wishes to inspect the damage after approval by the Logistics Officer,
the warehouse shall accommodate them and as a courtesy, be provided with a
copy of the damage report with all supporting evidence.
If the representative of the QA/QC Manager deems jobsite repair costs will exceed
minimum amounts a back-charge work order (BWO) will be initiated by the QA/QC
department. It will advise required repairs, replacement of material, estimated
cost, etc. This BWO number will be identified on the transit damage report and all
repair costs will be accumulated for an eventual back-charge, or insurance claim.
The formal MRR for the material received shall have a note against the item(s)
damaged:
The damaged material is not to be listed as “in stock” until a revision to the MRR is
issued after repair or replacement.
When only part of the material received is damaged, the acceptable material is put
in stock and only the damaged quantity placed in quarantine.
16
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 17 of 39
A damage log shall be kept listing the damage report number and resolution. This
log will be distributed, as needed to project and operation management. This log
shall be used to expedite the procurement department for a resolution to the
problem.
In all cases, this representative shall sign the material exception report stating
acceptance or rejection of material.
If acceptable, an MRR is written receiving the material with a copy of the signed
off material exception report attached.
The warehousing group shall formally transmit a copy of the material exception
report along with photographs, acknowledgements and other supporting evidence
to the procurement department.
17
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 18 of 39
A material exception log shall be maintained listing the report number and the
resolution. This log shall be distributed, as required, to construction and operations
management and Procurement Officer showing what items still require action.
After the material exception problem has been settled, a material receiving report
is written for the acceptable material.
4.6 Attachments
Policy
Purpose
18
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 19 of 39
Affects
Engineering Group
QA/QC Department
Responsibilities
Materials Manager
The Materials Manager shall be responsible for specific material protection and
storage requirements applicable to the jobsite. These requirements shall be
based on published industry standards and determined in consultation with
responsible engineering staff or statutory bodies. These shall include any special
vendor and/or specification requirements. Failure to comply with vendor
storage/maintenance requirements may jeopardize vendor extended warranties.
QA/QC Manager
19
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 20 of 39
Implementation
Attachments
WAREHOUSING SAFETY
Policy
A safety program is required for warehousing operations that provide, as priority, a healthy
and safe working environment for warehousing personnel and conforms to the overall safety
program.
Because of the high probability of fire and accident in a warehouse, a detailed program for
safety and training is required.
6.2 Purpose
20
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 21 of 39
To provide guidelines and establish accountability for ensuring safe and healthy
working areas and methods, and security for material control records.
Affects
Safety Department
QA/QC Department
Advise, as required.
Responsibilities
Materials Manager
The Materials Manager has direct responsibility to ensure that an effective safety
program is in effect in the warehouse.
HSES Manager
The HSES Manager has overall responsibility for safety regulations and assuring
they are used and enforced.
Constraints
Not applicable.
Implementation
It is the Material Manager’s duty to make changes, additions and revisions to the warehouse
safety guidelines.
All personnel in the warehouse shall be given a copy of the warehouse safety guidelines.
The HSES Manager shall establish more specific safe practices required.
21
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 22 of 39
Risk of fire is great at the warehouse vis-à-vis packing materials, chemicals, etc.
The use of fire and safety equipment by warehouse staff is important to the
general safety program.
The warehouse safety guidelines and project safety procedures shall be used as a basis to
formulate safety training and awareness.
The Materials Manager shall establish a safety program for warehouse operations
in accordance with the requirements of this procedure, which shall be in
compliance with the safety procedures established in the KGG yard or any jobsite.
The main characteristics of a good safety program are proper work assignments,
good housekeeping, use of proper protective devices, safe practices, the
correction of unsafe conditions and effective communications.
Work Assignments
A) Job Appraisal
Before a job is assigned, the warehouse representative shall appraise the safety factors.
How many and what kinds of personnel are needed? Do they know the applicable safe
practices? What equipment should be used? Which safe practices apply? Are the personnel
trained in the safe use of the equipment?
22
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 23 of 39
B) Selection of Personnel
The Warehouse representative shall exercise good judgment in assigning work to make
certain that it is within the capabilities of the personnel. At least one person in each crew
should be qualified and experienced in the particular work.
C) Instructions
The Warehouse representative shall first decide what he wants done and
how he wants it done, and then clearly convey this to those receiving the
assignment. If equipment is to be used, it should be in a safe operating
condition and the operators must know how to use it safely. If protective
gear is necessary, each employee must have it, know its purpose, and use
it.
D) Reporting
A basic rule of safety is that any accident must be immediately reported to the Material
Manager. The Material Manager shall direct all injuries to the company first aid station no
matter how trivial and take corrective action to prevent a recurrence of the accident. In case
of serious accidents, the Company Construction and Operations Procedure shall be followed
for obtaining professional care. The first aid station will maintain the required records.
Housekeeping
Clean, orderly, and properly laid out warehouse and storage areas are essential to
the person's health and safety. The warehouse superintendent is responsible for
maintaining these conditions.
i) Proper Layout
The warehouse and storage areas shall be laid out for safe and efficient handling and storage
of materials. Specific areas shall be designated for receiving, shipping, storage and other
warehousing functions. Straight lines, providing maximum clear vision, shall be used
throughout the layout plan.
23
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 24 of 39
Materials shall be stored according to safe and efficient standards. Storage shall be neat,
tight and squared off. Aisles and working areas shall be kept free of storage materials.
Leaning storage shall be corrected immediately. Tools shall have a fixed safe storage place,
and should be promptly returned after use.
iii) Cleanliness
The warehouse shall have a sufficient number of refuse containers located at strategic places
to provide for systematic waste containment, removal and disposal. Scrap packaging, wire
straps, etc., which are common to most warehousing, shall be immediately put into the
approved containers by the person first encountering them.
Materials that are received in damaged condition and those damaged in the process of
handling shall be segregated from the usable inventories. Damaged materials are
characteristically more hazardous than usable materials. For this reason, they shall be
handled with special care and stored in an area away from the regular storage.
The type and amount of lighting will depend on the nature of the
warehousing. Adequate lighting is essential to safe warehouse operation.
Posts and other obstructions in areas that are frequently traveled should be striped with
diagonal lines. Access to electric panels, fire extinguishers and other such important areas
should be designated with proper markings and signs.
24
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 25 of 39
i) Handrail Guards
Protective guards shall be maintained on the parts of moving equipment that are inherently
hazardous.
Much can be done to prevent accidents and injuries, i.e., proper use of protective clothing.
The use of gloves, hard hats and safety glasses shall be established as standard practice.
The following color codes are generally accepted for warehouse operations:
25
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 26 of 39
Caution Signs
Hand and Guardrails
Hooks and Blocks on Hoists
Material Handling Equipment such as Lift Trucks,
Tractors, Conveyors and Carts
Aisle Lines and Striping
Edge of Docks
Corner Board Marking for Storage Stacks
Pillars, Posts and Columns near highly traveled areas
Danger Signs
Fire Equipment and its location
Containers for flammable liquids (contents must be
indicated)
Lights used to bring attention to open pits, barricades and
temporary obstructions
Stop buttons on equipment
* Green : This is the basic color for denoting "Safety". It is commonly used
with white to form a stronger contrast than either color will
give used alone. A green cross on a white background is a
specific marking to designate first aid. Green or green and
white should be used for:
Safety Signs
Safety Equipment other than Fire Equipment, which is
Red
Start buttons on equipment
26
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 27 of 39
Housekeeping Signs
Directions Sign
Dead Ends of Aisles or Passageways
Debris Containers
Warehouse Management shall establish standard safe practices for all routine
handling and storing functions pertinent to the operation. Safety consciousness in
employees is important for the safe operation of a warehouse, but this is not
enough.
In addition to the specific project construction safety regulations, the following are
a series of standard safe practices that cover some of the main functions of
warehousing. These must, of necessity, be general in nature. The project safety
supervisor shall establish further specific safe practices that are necessary.
ii. Only qualified mechanics shall perform maintenance, inspections and make
repairs. Records must be kept of inspections and repairs.
iii. Regular maintenance checks shall include, but not be limited to the
following:
Brakes
Steering and control mechanisms
Horns and other warning devices
Lights
Stressed parts of lift and truck mechanisms
Hydraulic systems
27
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 28 of 39
v. Only authorized persons shall drive lift trucks. All operators must be trained
in safe operations.
vi. Drivers shall operate at safe speeds and keep safe distances from other
vehicles.
viii. Loads shall be picked up and placed down squarely without quick jerky
starts and stops.
ix. At start of shifts, drivers shall check horn, water, brakes, steering and
battery power of fuel and oil.
xii. Fuel and oil spillage shall be immediately washed away or absorbed by
compounds approved for this purpose.
xv. Lift trucks shall be driven upgrade with load first, downgrade with load last.
xvi. Drivers shall not put arms, legs or head outside the perimeter of the lift truck
while moving.
xvii. Lift truck wheels shall be securely blocked when unit is left on an incline.
28
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 29 of 39
xviii. Drivers shall carry loads as low as possible, consistent with safe operations.
xix. Drivers shall move empty lift trucks with forks in lowered positions.
xx. Forks shall be in a fully lowered position when lift truck is parked.
xxi. Only loads that are secure and within the capacity of the vehicle shall be
moved.
xxiii. Drivers shall move over buckboards cautiously and only when boards have
been secured.
xxiv. Wheels of highway trucks or trailers shall be secured with proper choking
before lift truck enters.
xxv. A lift truck shall not be used as elevator for personnel except with an
approved safe platform with handrails to protect raised person from falling
and when such a platform has been approved by the appropriate
government body.
xxvi. The lift trucks shall be equipped with fire extinguishers and drivers shall be
trained to use them.
To provide standard instructions for safe operation of two and four-wheeled hand
trucks.
i. Operators shall keep trucks clean, oiled and in safe operating condition,
reporting any malfunction to their supervisors for corrective action.
ii. Operators shall load heaviest objects at the bottom to keep center of
gravity as low as possible.
29
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 30 of 39
iii. Loads shall be securely stacked to prevent objects from slipping or falling
off.
iv. Trucks shall bear loads with operators providing power and guidance.
vi. With two wheel trucks, operators shall keep truck ahead when moving
down an incline, behind when moving up an incline and shall not walk
backwards.
vii. With four-wheel trucks, operators shall push load. If trucks are equipped
with handle and fifth wheel, they should be pulled for the most effective
steering.
To provide standard instructions for safe manual lifting and carrying of materials.
General
30
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 31 of 39
iii Object shall be inspected for nails, slivers, rough edges and slippery
surfaces, which shall be eliminated before lifting object.
Purpose
i Loading docks, inside of car or truck and adjacent working areas shall be
well lighted.
ii Carrier doors shall first be opened slightly to inspect for objects that may
fall out.
iii Contents of carrier shall be checked for insecure load conditions before
starting unloading operations.
iv Shoring and bracing shall be removed and floors and sides cleared of nails
and other protruding objects.
v Lumber and other debris removed from carrier shall be immediately put in
designated containers.
31
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 32 of 39
ii Broken and weakened skids and pallets shall be immediately taken from
use.
iii Empty skids and pallets shall be stored on flat side in neat stable stacks.
iv Skids and pallets shall be standard in design, size, grade and construction.
v Loading of skids and pallets shall be uniform, with the same stacking
pattern used for all of the same product. Alternating tier patterns shall be
used for cartoned products to attain locking effect.
vi Stacking, height of pallet loads, one pallet on another shall be limited to the
height at which the next pallet loaded has a reasonable chance of topping.
Purpose
iii Tools, rope and similar equipment shall be inspected before use and all
defective items shall be reported to the supervisor.
vii Moving parts and points of contact of all tools shall be protective shielded
as far as is practical.
32
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 33 of 39
viii Electrical power tools are not to be used without earth leakage circuit
breaker protection.
ix Warehouse tools that are not in use shall be stored in designated area with
a specific place for each tool.
Purpose
i Platform ladders used to pick or stock shelves shall have safety handrails
on sides of steps and around front and sides of top platform.
iii Ladder shall be set on solid foundation. It shall be lashed at top with rope
or its equivalent unless a person is designated to hold the ladder.
iv If ladder must be used in front of doorway, the door shall be locked from
ladder side or a second person shall be used to guard ladder security.
v Person using ladder shall face steps when climbing up and down.
vi Extended reaches shall not be made from ladder. Persons shall climb
down and move ladder close to object to avoid reaching from ladder.
vii Stepladder shall be fully opened and brace secured before use, and
personnel shall not use the top of the ladder as a work platform.
The Project Safety Procedure will outline the requirements for the following:
33
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 34 of 39
Policy
Purpose
To establish the means for initiating and recording the transfers of material from
warehouse inventory to subcontractors.
Affects
Subcontractor
Documentation required.
Construction Manager
Information and historical data as to what material the subcontractor has received.
Responsibilities
Materials Manager
Warehouse Supervisor
34
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 35 of 39
Warehouse Supervisor checks for accuracy, verifies approval and executes issue
documents.
7.5 Implementation
The material control system engineer shall ensure all available Engineering MTO's
are pre-loaded into the warehouse inventory system in hard copy and
electronically if possible for cross checking of actual requirements versus material
requisitions.
Any quantity of material requisitioned by the subcontractor in excess of the designated MTO
quantity must be indicated on the material requisition substantiated by a type of formal
documentation.
The Materials Manager or his designated representative will determine if requested excess
material is within the pre-determined allowance and will not require re-purchasing. Maintenance
of available spare material inventory will differ by individual systems to meet each requirement.
Example –revised drawings.
The Materials Manager will designate large and/or bulk commodities to be offloaded and
formally accepted by the subcontractor upon arrival. The formal acceptance is in lieu of the
standard requisitioning procedure.
Subcontractors may initiate inquiries for availability and issuance of material by preparation of a
material requisition and obtaining the planning engineer's signature that the material request is
valid with respect to the agreed subcontract schedule. Material requests shall be submitted not
less than 30 days prior to the proposed collection date.
A separate area shall be reserved for the consolidation, packing and dispatch of material.
The material requisition is checked to ensure that all required information and signatures are
included.
The material requisition is issued to the warehousemen who shall arrange for the material
required to be removed from the nominated storage areas and placed in dispatch consolidation
areas (excluding pipe, equipment and other items not requiring packaging).
35
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 36 of 39
Parts, fittings, valves, etc., shall be crated, palletized or bundled for dispatch and the
packages marked with the material requisition number.
Crated items, equipment, pipe and any other material not requiring to be packaged, shall be
clearly marked with the material requisition number, but left in their storage locations.
The material located, packaged and assigned to a material requisition number shall be
checked by the Warehouse Supervisor.
Actual quantity issued shall be clearly marked and from what location. Where
material is not available or is insufficient to meet requirements, this information
shall be recorded. The warehouseman shall sign and print name on requisition.
The Subcontractor shall sign the warehouse issue ticket when he receives the material.
The name of the person shall be printed and his signature under the printed name.
The date shall be clearly printed below the name.
This copy shall then be retained on warehouse file as a receipt for the material.
Warehousemen are responsible for observing the loading of all subcontractor vehicles for
which material transfers are being made to ensure no damage is incurred during loading of
material.
No material shall leave the warehouse or storage areas without a signed warehouse issue.
7.6 Attachments
Material Requisition
36
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 37 of 39
Policy
Active records on warehoused materials shall be maintained for each item until
disposed of through issue for installation, transfer to client, return to vendor or
sale.
Purpose
To provide guidelines for accounting of material from receipt until final disposition.
Responsibilities
Material Manager
Implementation
Data from the following documentation shall be maintained by Materials Controls: Material
Receiving Reports
Material Shipping Reports
Over/Short Reports
Damage Reports
Material Exception Reports
Material Requisitions
Material Exports
37
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 38 of 39
The quarantine area is a restricted area with no material movement into or out of this area
taking place unless under the direct supervision of the material control systems engineer who
shall ensure all necessary paperwork is in order before movements take place.
The reject area is for material waiting to be returned to vendor, this is subject to evaluation
with vendors for cost of re-export. This area shall also be restricted and no movement of
materials in or out of it shall take place unless under the direct supervision of the Material
Control Systems Engineer who shall ensure all necessary paperwork is in order before
movements take place.
The export area is for storage of items awaiting export, for example, items of returnable tools
and equipment off rental, etc. Traffic department shall be notified immediately of items requiring
export, for preparation of the necessary documentation.
When material has been returned to the warehouse, due to completion of a subcontract or
for whatever reason, the material shall be checked to establish exactly what it is and whether it
complies with specifications.
Once material is received into the warehouse, it shall be shown on the stock records as
being located in the warehouse by type of material.
When material is placed into storage, the location shall be entered into the inventory.
38
REV NO: 1
DOC NO:
KGG/MHLP/001/21
KGG DOC TITLE: MATERIAL HANDLING, STORAGE &
LOGISTICS PROCEDURE
PAGE 39 of 39
Any movement of materials internally within the different warehouse areas shall be entered
into the stock records.
Access to storage areas shall be controlled and limited only to Warehouse personnel.
After physical inventory is complete, the items on which problems were noted are
to be resolved.
8.5 Attachment