Homework 8
Homework 8
1
Hint: Try the binding constraints in the following order, checking if the choices are
feasible
3. Generator 1 is binding at its upper bound and generator 4 is bounding at its lower
bound.
Each generator can be tuned on or off. They should satisfy a load of 500 MW. Find the
optimal (least cost) combination of the unit status and the generation of each unit.