Method Statement For Monitoring of Adjacent Structures and Utilities in The Vicinity of Diaphragm Wall
Method Statement For Monitoring of Adjacent Structures and Utilities in The Vicinity of Diaphragm Wall
Rev: 00
Date: 30.06.2024
Page 1 of 13
TABLE OF CONTENT
1. DESCRIPTION OF WORK 03
2. RESOURCES 04
3. MONITORING PROCEDURE 09
4. HSE ASPECTS 12
5. COMMUNICATION 13
Page 2 of 13
1. DESCRIPTION OF WORK
1.1. Purpose
This Method statement has been developed to describe the procedure for Monitoring of
This monitoring procedure has been developed to carry the monitoring of adjacent
structures and utilities in the vicinity of diaphragm wall in accordance with project
Client ARADA
Consultant DAR AL- HANDASAH CONSULTANTS
Contractor AL ANQAA ROAD CONTRACTING LLC
HSE Health, Safety and Environment
PPE Personal Protective Equipment
SSSP Site Specific Safety Plan
Page 3 of 13
2. RESOURCES:
a) PROJECT DIRECTOR
b) PROJECT MANAGER
c) SITE ENGINEER
d) HSE ENGINEER
e) ELECTRICIANS
f) WELDERS
g) CRANE OPERATOR
h) SKILLED LABOURS
i) RIGGERS
j) MASONS
k) DRIVERS
Will ensure machine and hand tools are used correctly and worn tools and equipment shall
be decommissioned and replaced.
b) BC30 Cutter
c) Decanter
d) Generators
g) Vibration Monitor
h) Trimie Pipes
i) Bentonite Tanks
j) Welding Sets
Page 4 of 13
l) Electrical Switch Boxes
m) Workshop Containers
Page 5 of 13
the Contractor’s quality management system.
- Initiate internal quality audits ensuring proper audit standards are maintained.
- Verify corrective and preventive action.
- Provide guidance and assistance to fulfill the Quality System requirements.
- Ensure a comprehensive pre-award and post-award contract review
- Execution and administration of the project as per the contract requirements, specifications,& PQP.
Reports to the Project Director
Site Engineer
- Understand fully the specifications and drawings related to the works.
- Achieve targets as shown in project schedule by
A) Setting out priorities, and obtaining necessary approvals from Client before commencement of work.
B) Preparing the requirement schedule of resources
- Obtain necessary permits from the Client for day-to-day activities and technical issues
- Prepare and submit RFA/Inspection Request to the consultant.
- Provide leadership and organizational support to team members.
- Encourage, promote, and maintain safe site working conditions.
- Ensure compliance with QA/QC procedures, plans, and work instructions.
- Liaise with site QA/QC team for preparation and maintenance of applicable quality records.
- Liaise with site QA/QC team to attend to non-conformities and ensure that corrective actions are taken as
appropriate.
- Liaise with site QA/QC team to carry out relevant inspections and tests.
- Manage subcontractor activities and ensure timely completion as per project schedule.
- Obtain resources as required as per Contractor procedure.
Reports to the Project Manager
Office Engineer
- Prepare and submit project-required technical documentation such as shop drawings, RFI’s, method statements,
daily, weekly, and monthly reports.
- Control of all project documentation such as project contracts, drawings, plans, minutes of project meetings,
submittals, and approvals.
Reports to the Project Manager
Quantity Surveyor
- Preparing take off quantities of the project.
- Prepare and submit monthly billing statement to consultant after the review and approval from PM.
- Monitor the cost/revenue and activity profitability
- Managing the finances for any kind of construction project
- Working to keep the project within the budget
- Measure and value the work done on site
Page 6 of 13
- Preparation of new rates
Reports to the Project Manager
Draughtsman
- Preparing all necessary project drawings, shop and as build
- Prepare and submit the same to consultant for approval
- In charge for internal distribution and drawing control
- Preparing and updating the drawing submittal/ status log sheet base on the project requirement
Reports to Site Engineer
Surveyor
- Responsible for all survey activities in the Contract
- Coordinate with surveyors to meet the survey requirements of the contract as per drawings and specifications.
- Ensure that survey equipment is calibrated and the calibration status identified as per the QA/QC procedures.
- Coordinate with Project Engineer / Draughtsman for preparation of setting out / survey drawings and submit for
Client’s approval
- Conduct periodic in-house calibration tests to verify accuracy of survey equipment and maintain suitable records.
- Maintain proper records of all survey data.
- Responsible for collection of all information required for the preparation of As-Built drawings.
Reports to the Site Engineer
Foreman
- Lead the workforce to execute work as per project requirements.
- Inform Section Engineer on completion of all operations for checking and Client’s approval
- Distribute work force according to the program agreed with the Section engineer in advance.
- Check output and quality of planned work activities on a day-to-day basis.
- Coordinate with Engineer for preparation of a weekly concrete requirement program.
- Inform Project Manager of weekly material requirement schedule.
Page 7 of 13
- Ensure safe working conditions. Inspect site daily to ensure quality and safety requirements are met.
Reports to the Site Engineer
Store Keeper
- Maintain proper inventory records and control all materials at site including assets.
- Ensure availability of all Client supplied material for the Contract at the right time. Comply with procedures
relating to control of Client supplied products
- Keep track of materials ordered, received and pending receipt.
- Liaise with QA/QC engineer for receiving inspection as required
- Ensure proper storage, handling and accounting requirements of all stored materials.
- Assess periodically the condition of items stored.
- Maintain records of all materials received and delivered to site
- Comply with the requirements of the relevant procedures relating to stores.
Reports to the Office Engineer and Project Manager
Timekeeper
- Responsible for checking the attendance of all site manpower and site office personnel.
- Prepare and submit timesheets of manpower and plant external & internal to main office after approving from
Project manager.
- Allocate manpower, transportation, and equipment required in the site as per instruction from PM or DPM.
Reports to Site Engineer.
Page 8 of 13
3.0 Work Sequence:
Preliminary Activities:
Tool Box Talks shall be conducted prior to commencement of work each day.
HSE Engineer shall be present at all times during the site activity.
Ensure all the required documentation has been obtained like permits, civil
clearance.
Arrange all necessary personnel, plant and equipment as required for the works.
Housekeeping should be done before commencing and after completing the work
Avoid Marking out near plant/vehicle movement areas, or isolate the area by
Underground utilities shall be marked and avoid using sharp tools or steel pins as
Provide proper access to the equipment’s as applicable to reach all work areas for
any work.
Page 9 of 13
Installation of Electrical appliances from Office cabins:
Installation of Generators:
Ensure the Crane inspected and passed by the P&M and HSE Dept.
Monthly inspection shall be done and color coded for the all the equipment’s.
Ensure the Competent crane operator, lifting supervisor, rigger shall be deployed
Operator and rigger should ensure the ground condition, underground utilities
Ensure the, Generators is completely free from the external sources and concrete
supports.
1. A thorough survey will be conducted and assessment of the surrounding area is done as
per the drawings and survey team.
3. Monitoring systems like vibration monitors and crack gauges will be installed as per the
requirement
Page 10 of 13
5. Temporary support systems are provided along with temporary guide walls to restrict any
kind of flow or vibration to to area under vicinity of diaphragm wall
Page 11 of 13
Necessary HSE Arrangement will be done to check any kind of unwanted flow of slurry water to
the surrounding areas
Vibration Monitoring
Vibrations will be monitored in every 3 hours on daily basis to avoid any kind of damage.
Necessary HSE Arrangement will be done to check any kind of unwanted flow of slurry water to
the surrounding areas
Before casting of Diaphragm wall Inclinometer Casing in Diaphragm wall will be done to avoid
vibrations and damage to adjacent surrounding areas.
Page 12 of 13
b) Access to elevated platform will be properly secured and inspected before use.
c) Assembly point shall be allocated at all work areas.
d) Proper exclusion zone will be provided. Man-Machine interface will be maintained
with proper use of safety appliances and trained Banksman.
e) Required trainings and mock up drills to be conducted as per approved HSE plan.
5.0 COMMUNICATION
Team Communication
Page 13 of 13