0% found this document useful (0 votes)
35 views13 pages

Method Statement For Monitoring of Adjacent Structures and Utilities in The Vicinity of Diaphragm Wall

Uploaded by

S Sahil
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
35 views13 pages

Method Statement For Monitoring of Adjacent Structures and Utilities in The Vicinity of Diaphragm Wall

Uploaded by

S Sahil
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 13

ENABLING WORKS FOR CENTRAL HUB PHASE 3 BLOCK E

METHOD STATEMENT FOR MONITORING OF


ADJACENT STRUCTURES AND UTILITIES IN THE VICINITY OF
DIAPHRAGM WALL

Rev: 00

Date: 30.06.2024

00 Sanjay Sahil Ashreet VM Iyad Al Khatab

Site Engineer Project Manager Project Director

Page 1 of 13
TABLE OF CONTENT

1. DESCRIPTION OF WORK 03

2. RESOURCES 04

3. MONITORING PROCEDURE 09

4. HSE ASPECTS 12

5. COMMUNICATION 13

Page 2 of 13
1. DESCRIPTION OF WORK

1.1. Purpose

This Method statement has been developed to describe the procedure for Monitoring of

adjacent structures and utilities in the vicinity of diaphragm wall.

1.2. Scope and Location

This monitoring procedure has been developed to carry the monitoring of adjacent

structures and utilities in the vicinity of diaphragm wall in accordance with project

specifications applicable codes and standards referred in the project specification.

1.3. Definitions and Abbreviations

Client ARADA
Consultant DAR AL- HANDASAH CONSULTANTS
Contractor AL ANQAA ROAD CONTRACTING LLC
HSE Health, Safety and Environment
PPE Personal Protective Equipment
SSSP Site Specific Safety Plan

1.4 Work Duration

This task is planned to be done till the completion of diaphragm wall

Page 3 of 13
2. RESOURCES:

2.1. Man Power

a) PROJECT DIRECTOR
b) PROJECT MANAGER
c) SITE ENGINEER
d) HSE ENGINEER
e) ELECTRICIANS
f) WELDERS
g) CRANE OPERATOR
h) SKILLED LABOURS
i) RIGGERS
j) MASONS
k) DRIVERS

2.2. SITE & EQUIPMENTS

All mechanical equipment mentioned herewith shall be inspected by Al Anqaa Road


Maintanance Contracting LLC SP and APCC and an inspection sticker shall be provided.
The Machinery/ plant shall be inspected by an HSE Engineer.

Will ensure machine and hand tools are used correctly and worn tools and equipment shall
be decommissioned and replaced.

a) Service Crawler Crane

b) BC30 Cutter

c) Decanter

d) Generators

e) High Shear Turbulence Bentonite Mixer

f) Noise Monitoring Device

g) Vibration Monitor

h) Trimie Pipes

i) Bentonite Tanks

j) Welding Sets

k) Excavator, bob cat or equivalent

Page 4 of 13
l) Electrical Switch Boxes

m) Workshop Containers

2.3. Supervision & Responsibilities

3.1 Roles, Responsibilities, Authorities


Project Director
- Ensure that the Contractor’s Quality Management System is effectively implemented in the contract.
- Coordinate with the General Manager / Heads of Departments to obtain the necessary resources for the project and
deploy as required.
- Submit progress reports as per contractual requirements.
- Perform initial post award and periodical contract review as and when required during the execution of the
Contract.
- Overall coordination and liaison with subcontractors (if any)
- Responsible for ensuring that the work is performed in accordance with the specifications and within the time and
cost constraints.
- Approve all QA/QC procedures / plans / work instructions for implementation at site
- Obtain subcontractors procedures plans and ensure their review and approval by the QC dept.
- Identify training needs, inform the department heads, and coordinate with the appropriate functions for fulfilling
the training requirements.
- Review and approve subcontract agreements
- Approve material requisitions or authorize other personnel to approve the same.
- Arrange required manpower resources for the project
- Ensure compliance with Contract requirements by subcontractors.
Project & Quality Manager
- Review and approve the Project Quality Plans for adequacy and correctness.
- Review and approve the Subcontractor’s Quality System Plans and Procedures.
- Review project specific procedures, work instructions and QA/QC plans.
- Ensure QA/QC compliance with quality plans and procedures
- Ensure through the Site Quality Representative that work execution is as per the PQP, contract requirements, and

Page 5 of 13
the Contractor’s quality management system.
- Initiate internal quality audits ensuring proper audit standards are maintained.
- Verify corrective and preventive action.
- Provide guidance and assistance to fulfill the Quality System requirements.
- Ensure a comprehensive pre-award and post-award contract review
- Execution and administration of the project as per the contract requirements, specifications,& PQP.
Reports to the Project Director
Site Engineer
- Understand fully the specifications and drawings related to the works.
- Achieve targets as shown in project schedule by
A) Setting out priorities, and obtaining necessary approvals from Client before commencement of work.
B) Preparing the requirement schedule of resources
- Obtain necessary permits from the Client for day-to-day activities and technical issues
- Prepare and submit RFA/Inspection Request to the consultant.
- Provide leadership and organizational support to team members.
- Encourage, promote, and maintain safe site working conditions.
- Ensure compliance with QA/QC procedures, plans, and work instructions.
- Liaise with site QA/QC team for preparation and maintenance of applicable quality records.
- Liaise with site QA/QC team to attend to non-conformities and ensure that corrective actions are taken as
appropriate.
- Liaise with site QA/QC team to carry out relevant inspections and tests.
- Manage subcontractor activities and ensure timely completion as per project schedule.
- Obtain resources as required as per Contractor procedure.
Reports to the Project Manager

Office Engineer
- Prepare and submit project-required technical documentation such as shop drawings, RFI’s, method statements,
daily, weekly, and monthly reports.
- Control of all project documentation such as project contracts, drawings, plans, minutes of project meetings,
submittals, and approvals.
Reports to the Project Manager
Quantity Surveyor
- Preparing take off quantities of the project.
- Prepare and submit monthly billing statement to consultant after the review and approval from PM.
- Monitor the cost/revenue and activity profitability
- Managing the finances for any kind of construction project
- Working to keep the project within the budget
- Measure and value the work done on site

Page 6 of 13
- Preparation of new rates
Reports to the Project Manager

Draughtsman
- Preparing all necessary project drawings, shop and as build
- Prepare and submit the same to consultant for approval
- In charge for internal distribution and drawing control
- Preparing and updating the drawing submittal/ status log sheet base on the project requirement
Reports to Site Engineer
Surveyor
- Responsible for all survey activities in the Contract
- Coordinate with surveyors to meet the survey requirements of the contract as per drawings and specifications.
- Ensure that survey equipment is calibrated and the calibration status identified as per the QA/QC procedures.
- Coordinate with Project Engineer / Draughtsman for preparation of setting out / survey drawings and submit for
Client’s approval
- Conduct periodic in-house calibration tests to verify accuracy of survey equipment and maintain suitable records.
- Maintain proper records of all survey data.
- Responsible for collection of all information required for the preparation of As-Built drawings.
Reports to the Site Engineer

Site Laboratory Technician


- Coordinate the activities of subcontracted testing activities as well as the site laboratory.
- Conduct process testing and analysis to ensure that construction activities are in conformance with the Project
Quality requirements.
- Inform the Project Manager and the Site QA/QC engineer in the event of test failure for corrective action.
- Ensure that all testing equipment used in the laboratory are calibrated periodically and maintained in a good
condition
- Responsible for forwarding test results to the Client and act on their comments / approvals in consultation with the
site QA/QC engineer.
- Maintain up to date test records as per the PQP.
Reports to the Project Manager and Site Engineer

Foreman
- Lead the workforce to execute work as per project requirements.
- Inform Section Engineer on completion of all operations for checking and Client’s approval
- Distribute work force according to the program agreed with the Section engineer in advance.
- Check output and quality of planned work activities on a day-to-day basis.
- Coordinate with Engineer for preparation of a weekly concrete requirement program.
- Inform Project Manager of weekly material requirement schedule.

Page 7 of 13
- Ensure safe working conditions. Inspect site daily to ensure quality and safety requirements are met.
Reports to the Site Engineer

Store Keeper
- Maintain proper inventory records and control all materials at site including assets.
- Ensure availability of all Client supplied material for the Contract at the right time. Comply with procedures
relating to control of Client supplied products
- Keep track of materials ordered, received and pending receipt.
- Liaise with QA/QC engineer for receiving inspection as required
- Ensure proper storage, handling and accounting requirements of all stored materials.
- Assess periodically the condition of items stored.
- Maintain records of all materials received and delivered to site
- Comply with the requirements of the relevant procedures relating to stores.
Reports to the Office Engineer and Project Manager

Timekeeper
- Responsible for checking the attendance of all site manpower and site office personnel.
- Prepare and submit timesheets of manpower and plant external & internal to main office after approving from
Project manager.
- Allocate manpower, transportation, and equipment required in the site as per instruction from PM or DPM.
Reports to Site Engineer.

Page 8 of 13
3.0 Work Sequence:

Preliminary Activities:

 Prior to commencement Al Anqaa Road Maintanance Contracting LLC personnel

shall be inducted by HSE Engineer.

 Tool Box Talks shall be conducted prior to commencement of work each day.

 HSE Engineer shall be present at all times during the site activity.

 Ensure all the required documentation has been obtained like permits, civil

clearance.

 Arrange all necessary personnel, plant and equipment as required for the works.

 Ensure adequate PPE’s for all workers.

 Ensure welfare facilities are provided (Rest area, drinking water).

 Housekeeping should be done before commencing and after completing the work

Survey & Marking:

 Avoid Marking out near plant/vehicle movement areas, or isolate the area by

physical barriers and sign posted

 Underground utilities shall be marked and avoid using sharp tools or steel pins as

marker to avoid striking on live cables, or other utilities.

Access and Egress:

 Provide proper access to the equipment’s as applicable to reach all work areas for

any work.

 Do not allow persons to jump down from any height.

 Proper Access and Egress signs shall be provided.

Page 9 of 13
Installation of Electrical appliances from Office cabins:

 Only authorized personal should carry out the task.

 Ensure all electrical connections are disconnected from the services

 Provide adequate working platform to carry out the task.

 Use proper PPE for the task.

 Keep assistance while removing Air conditioners and other fixtures.

Installation of Generators:

 Lifting activity shall be carried as per the project SSSP.

 Ensure the Crane inspected and passed by the P&M and HSE Dept.

 Monthly inspection shall be done and color coded for the all the equipment’s.

 Ensure the Competent crane operator, lifting supervisor, rigger shall be deployed

for the task.

 Operator and rigger should ensure the ground condition, underground utilities

before execute the task.

 Ensure the, Generators is completely free from the external sources and concrete

supports.

3.1 Monitoring Procedure :

1. A thorough survey will be conducted and assessment of the surrounding area is done as
per the drawings and survey team.

2. Precise mechanical equipment and technique to be followed:


 tremie pipes with male and female connections

 rubber O-Rings for a water tightness of pipe connections


 tremie locking ropes
 1 x lifting cap
 1 x tremie support fork to rest the string on the guide wall
 1 x 1.2-meter diameter conical shape hopper with lifting rope tremie hopper at the top.

3. Monitoring systems like vibration monitors and crack gauges will be installed as per the
requirement

4. Consider underpinning or shoring techniques for additional support to be provided if


construction is to be done near building areas

Page 10 of 13
5. Temporary support systems are provided along with temporary guide walls to restrict any
kind of flow or vibration to to area under vicinity of diaphragm wall

 Construction logs of equipment and approximate time frames are to be maintained


during the construction of construction
 Vibration monitoring is done during the entire process
Prior to construction activity, it can be desirable to establish a benchmark,
Prior to the commencement of the concrete pouring process, proper quality checks for the
workability of concrete will be made. The installed tremie pipe(s) shall be plugged with a
temporary plug (concreting ball or polystyrene pieces in a bag, etc.) in order to avoid
contamination of the concrete by the slurry contained in the tremie pipe during the priming (first
pouring of the concrete).
The poured concrete through the hopper will force the temporary plug in the tremie pipe ahead
of the concrete and prevent any contamination of the concrete by the slurry contained in the
tremie pipe.
To ensure this requirement until the completion of the panel pouring procedure, the concrete
supply shall be continuous and interruptions should not exceed 15 min.
To ensure an approximate horizontal level of the poured concrete in the panel at all times, two
tremie pipe sets in large panels will be placed and charged with equal distribution.
In order to get non-contaminated concrete approx. 0.50 to 1.0 m over-placement on top of the
designed cut-off level will be performed.
Earliest Time of Excavating Secondary Panels
Excavation of the secondary panels will be done after the poured concrete in the adjacent panel
has gained sufficient strength to be freestanding and avoid any kind of shear failures in
surrounding areas.
The required curing period shall be determined on-site for the particular properties of the
concrete produced under mass production on-site.
Generally, the time for overcutting of primary panels will be a matter of several days. However,
from experience with similar concrete mix designs used on other sites, a minimum of 24 hrs
shall elapse before secondary panels are excavated in-between previously cast primary panels.
Disposal of Excavated Spoil
Spoil removed from the excavation shall be separated from the slurry employed in the
excavation process with the help of desanding unit BE 500. It shall be disposed of at the site
after the water in it is evaporated sufficiently and as quickly as possible to an approved dump
site by using dumpers and shovel loaders in such a manner that spillage and annoyance are
minimized and as described in the waste disposal plan. Please refer to Construction
Environmental Management.

Disposal of Waste Slurry


After a certain number of cycles, the working slurry will not be recyclable anymore due to
contamination of cement & fines. The physical properties of the slurry will be monitored to
decide when to dispose of the slurry. The slurry will be disposed of at designated locations as
described in Environmental Management.

Page 11 of 13
Necessary HSE Arrangement will be done to check any kind of unwanted flow of slurry water to
the surrounding areas

Vibration Monitoring
Vibrations will be monitored in every 3 hours on daily basis to avoid any kind of damage.
Necessary HSE Arrangement will be done to check any kind of unwanted flow of slurry water to
the surrounding areas

Before casting of Diaphragm wall Inclinometer Casing in Diaphragm wall will be done to avoid
vibrations and damage to adjacent surrounding areas.

 Direct installation of an inclinometer casing in the diaphragm is not recommended.


The inclinometer casing will get distorted and stressed when firmly tied to a steel
structure from bottom to top.
 It is also no good to directly expose the casing to the heat of hydration and stresses
generated during the concreting process. The casing may distort and even get cracked.
Note: It is recommended that an auxiliary guide pipe be installed adjacent to the main guide pipe
at 1.25 m approx. center to the center distance at critical monitoring locations.
This auxiliary pipe can be used in case the main pipe gets choked and becomes useless due to
any reason.
 Weld guides the pipe firmly to the cage. Ensure that it remains vertical and is least
distorted during the lowering of the cage.
 Concrete cage after covering the mouth of guide pipe.
 Flush the guide pipe clean with water and verify depth with the help of a suitable depth
measuring device (e.g. a sounding chain) that it is fully open up to the bottom.
Note: Ensure that the heat of hydration of mass concrete has dissipated before installing the
access casing in the guide pipe. Use a temperature probe for this purpose. The temperature
should not exceed 40°C. The heat of hydration, if present may warp the access casing and
render installation useless.
 Lower casing with bottom cap into guide pipe gripping it with the safety clamp secured
around 500 mm from the top.
Note: Maintain one pair of casing grooves parallel to the direction in which lateral movement is
to be measured i.e. perpendicular to the diaphragm wall.
 Take a casing pre-assembled with a fixed coupling, having a safety clamp secured
around 500 mm from its top end, and mate it with the pipe already lowered through the
coupling end. Pop-rivet the fixed coupling to the lowered casing at four places.
 Seal the joint with mastic waterproof tape and BOPP tape. Remove the safety clamp
from the first casing and lower jointed casings into the guide pipe.

4.0 HSE ASPECTS:

4.1 Access and Egress


a) All the Accesses shall be clear from obstructions.

Page 12 of 13
b) Access to elevated platform will be properly secured and inspected before use.
c) Assembly point shall be allocated at all work areas.
d) Proper exclusion zone will be provided. Man-Machine interface will be maintained
with proper use of safety appliances and trained Banksman.
e) Required trainings and mock up drills to be conducted as per approved HSE plan.

4.2 Environmental Risk


a) The work area shall be maintained clean, tidy and safe on daily basis. Waste should
be collected and segregated.
b) All environment incidents arising out of equipment failure or fuel spillage shall be
reported to the engineer and the approved emergency response plan shall be
followed. Proper dip trays will be provided in all generators & static equipment’s to
reduce the oil spillage.
c) Tool box talks shall be given regularly to reiterate the environmental hazards of an
existing work activity or to highlight the risks of a new activity.
d) All briefing shall be given to the workers in a manner and language so the
information is fully understood.

4.3 First Aid


a) First-aid box and First aider shall be available during working hours.
b) In case of any emergency, necessary emergency protocol shall be followed.

4.4 Night Work


Night Permits will be issued on regular basis as per ARADA permit system through
Project Manager.

5.0 COMMUNICATION

Team Communication

METHOD STATEMENT RELATED TOOLBOX TALKS


It is the intention of Al Anqaa Road Maintanance Contracting LLC to hold tool box talks
related to the approved Method Statement for the project before commencement of the
activity. All workforce shall attend tool box talk.

Page 13 of 13

You might also like