AS9100 - Project Managers Guide
AS9100 - Project Managers Guide
Manager’s
Guide
AS9100 Implementation
©2019 AS9100 Store
Table of Contents
Introduction.........................................................................................3
Project Plan.........................................................................................4
This Project Manager’s Guide is designed to help you plan and manage AS9100 Project
using the AS9100 Store Documented Quality Management System. The Documented
QMS includes a Quality Manual, Procedures and related Forms.
If you purchase the complete All-in-One Documentation and Training Package, you
also receive the Gap Analysis Checklist, Online Employee Training, Training Materials
Package, and Internal Auditor Training.
All of the documents in the Documented Quality System are in Microsoft Word or Excel,
and are very easy to edit. You will make this system your own by reviewing and editing
the procedures, manual and forms. You will also be making changes to your existing
processes so you meet the requirements of the AS9100 Standard. This project plan will
help you manage these changes.
This guide outlines these steps in more detail, and provides forms and templates to help
you. This is a recommended plan, and you may change it to suit your organization.
2. When does your company want to have the AS9100 certificate in hand?
The answer to this question will determine your timeline.
a. The shorter time frame allowed for the project, the more resources the
project will demand during implementation.
b. It is important to know what your goal is because other dates will
be determined by this information.
c. Find out if there are company goals, are there clients that are requesting
certification or other circumstances that will determine the date?
d. Your date may be revised later. You will use this as a target date, and as
we move along to the gap analysis and creating the task list you will be
able to determine if the date is realistic. It will depend on what you
currently have in place for your quality system, and how many resources
you have available for the project.
1. When will you conduct your Gap Analysis and how long will it take to complete?
a. A Gap Analysis can typically take anywhere from 2 days to 5 days to
perform. It will depend on the size of your organization, the number of
auditors, the state of your current quality system and the experience of
your auditors.
2. Assign responsibilities
a. This will take one or two meetings. The project manager and top
management should be involved. Choose a date after the task list has
been completed. You will use this information to assign responsibility.
(See section 2 “Planning and Holding the Planning Meetings”)
1. Follow the schedule that you have prepared. Go into each area of the
facility to evaluate the current quality system. Focus on what is in place,
and what is not in place. Remind auditors that you are not focusing on
compliance or non compliance to the current system, but on the design of
the current system, and how it matches the AS9100 requirements.
2. Take notes on what is in place, and what will need to be developed and
changed. Take complete notes, reference documents and examples.
1. Summarize the audit findings in the form of a task list. You will usually
identify several categories of tasks.
For each requirement (or set of requirements) of the standard you will
want to identify the status of the current system. The AS9100 Steering
Team will use this information as they assign responsibility and timelines
to Teams. Teams will be assigned responsibility for development of a
procedure.
Project goals:
Start Date:
Responsibilities:
Project Manager:
Management Representative:
Top Management:
Steering Team
Project timeline:
Agenda:
*Keep minutes of all of the AS9100 Planning and Steering Team meetings. This helps demonstrate top management
involvement in the development of the AS9100 Quality Management System. Record attendees.
Implementation Steps
1. The team of people assigned responsibility will use the Procedures, Quality Manual and Forms provided in the All
in One Package as a foundation for the process to address the requirements of the standard. The team will use the
task list to identify what areas need changes to processes.
2. Each responsible team will evaluate the process presented in the procedure, determine if any changes are
necessary for your organization, and make edits to the procedure and forms.
3. The team will finalize the procedure and send it to the Steering Team for review and approval.
4. The team will train employees that are affected by or have responsibility for the procedure.
5. The employees will start following the documented process and maintaining records.
Quality Manual
Document Control
Management Responsibility
Configuration Management
Infrastructure
Risk Management
Key Characteristics
Purchasing
Customer Property
Preservation of Product
Internal Audits
Monitoring, Measuring and
Analysis of Product and
Realization Processes
Control of Nonconforming Product
Statistical Techniques
Task Group Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9
Document Control
Management Responsibility
Infrastructure
Risk Management
Key Characteristics
Purchasing
Customer Property
Preservation of Product
Task Group Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9
Statistical Techniques
Implementation Steps
1. The team assigned responsibility for each procedure will use the
procedures provided as a foundation for the process to address the
requirements of the standard. The team will use the task list to identify
what areas need changes to processes.
3. The team will finalize the procedure and send it to the Steering Team for
review and approval.
4. The team will train employees that are affected by or have responsibility
for the procedure.