Low Rise Pow
Low Rise Pow
( GAA 2024 )
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
QUEZON 2ND DISTRICT ENGINEERING OFFICE
Lucena City, Quezon, Region IV-A
Date:
EXECUTIVE SUMMARY
Project ID :
Project Name :
LOCAL PROGRAM, National Building Program, Buildings and Other
Structures, Multipurpose / Facilities, Construction (Completion) of 3
Storey Camp Nakar Station Hospital Building, Southern Luzon
Command, Lucena City
PREPARED BY:
KENNY S. AVELLANO
Engineer II
SUBMITTED BY:
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
PART A Facilities for the Engineer 0.000% 110,816.44 0.00% 110,816.44
PART B Other General Requirements 3.000% 2,000,567.15 3.00% 2,000,567.15
DIVISION I GENERAL
PART C EARTHWORKS 1.000% 355,575.91 1.00% 355,575.91
PART D REINFORCED CONCRETE (PLS. SEE FORM POW-2015-01C-00) 2.000% 1,407,453.50 2.00% 1,407,453.50
DIVISION II BUILDINGS
PART E FINISHING AND OTHER CIVIL WORKS 53.000% 32,947,302.55 53.00% 32,947,302.55
PART F ELECTRICAL WORKS 29.000% 18,372,643.45 29.00% 18,372,643.45
PART G MECHANICAL WORKS 12.000% 7,187,415.96 12.00% 7,187,415.96
Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:
KENNY S. AVELLANO FAUSTINO MARK ANTHONY S. DE LA CRUZ CHARLOTTE KAYE A. CONSTANTINO RAMONITO S.M. PAZ DEL ROSARIO C. NACA
Engineer II Chief, Planning & Design Section OIC, Construction Section Assistant District Engineer District Engineer
Planning & Design Section
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
PART A FACILITIES FOR THE ENGINEER
As Submitted 0.15% 1.00 L.s. 63,156.64 31,884.80 - 95,041.44 95,041.44 18% 17,107.46 5,607.45 117,756.35
A.1.1(3) Construction of Field Office for the Engineer
As Evaluated 0.15% 1.00 L.s. 63,156.64 31,884.80 - 95,041.44 95,041.44 18% 17,107.46 5,607.45 117,756.35
Provision of Furnitures/Fixtures, Equipment & Appliances for the Field Office for As Submitted 0.02% 1.00 L.s. 10,375.00 - - 10,375.00 10,375.00 8% 830.00 560.25 11,765.25
A.1.1(11)
the Engineer As Evaluated 0.02% 1.00 L.s. 10,375.00 - - 10,375.00 10,375.00 8% 830.00 560.25 11,765.25
As Submitted 0.01% 12.00 Mo. 5,400.00 - - 450.00 5,400.00 8% 432.00 291.60 6,123.60
A.1.4(1) Provision of Progress Photographs
As Evaluated 0.01% 12.00 Mo. 5,400.00 - - 450.00 5,400.00 8% 432.00 291.60 6,123.60
As Submitted 0.18% 78,931.64 31,884.80 - 110,816.44 18,369.46 6,459.30 135,645.20
TOTAL OF PART A
As Evaluated 0.18% 78,931.64 31,884.80 110,816.44 18,369.46 6,459.30 135,645.20
PART B OTHER GENERAL REQUIREMENTS
As Submitted 0.04% 1.00 L.s. 32,250.00 - - 32,250.00 32,250.00 0% - 1,612.50 33,862.50
B.3 (1) Permits and Clearances
As Evaluated 0.04% 1.00 L.s. 32,250.00 - - 32,250.00 32,250.00 0% - 1,612.50 33,862.50
As Submitted 0.00% 1.00 Ea 2,562.80 305.26 - 2,868.06 2,868.06 18% 516.25 169.22 3,553.53
B.5 (1) Project Billboard/ Sign Board
As Evaluated 0.00% 1.00 Ea 2,562.80 305.26 - 2,868.06 2,868.06 18% 516.25 169.22 3,553.53
As Submitted 0.74% 1.00 L.s. 102,718.74 402,305.92 - 505,024.66 505,024.66 8% 40,401.97 27,271.33 572,697.96
B.7(1) Occupational Safety and Health
As Evaluated 0.74% 1.00 L.s. 102,718.74 402,305.92 - 505,024.66 505,024.66 8% 40,401.97 27,271.33 572,697.96
As Submitted 0.22% 1.00 L.s. - - 160,000.00 160,000.00 160,000.00 0% - 8,000.00 168,000.00
B.9 (1) Mobilization/Demobilization
As Evaluated 0.22% 1.00 L.s. - - 160,000.00 160,000.00 160,000.00 0% - 8,000.00 168,000.00
As Submitted 2.09% 1.00 l.s. - 217,400.13 1,083,024.30 1,300,424.43 1,300,424.43 18% 234,076.40 76,725.04 1,611,225.87
B.24(1) General scaffolding and shoring and Netting
As Evaluated 2.09% 1.00 l.s. - 217,400.13 1,083,024.30 1,300,424.43 1,300,424.43 18% 234,076.40 76,725.04 1,611,225.87
As Submitted 3.09% 137,531.54 620,011.31 1,243,024.30 2,000,567.15 274,994.62 113,778.09 2,389,339.86
TOTAL OF PART B
As Evaluated 3.09% 137,531.54 620,011.31 1,243,024.30 2,000,567.15 274,994.62 113,778.09 2,389,339.86
DIVISION I GENERAL
PART C EARTHWORKS
As Submitted 0.55% 1.00 L.s. - 312,885.00 31,288.50 344,173.50 344,173.50 18% 61,951.23 20,306.24 426,430.97
801(1) Removal of Structure and Obstruction
As Evaluated 0.55% 1.00 L.s. - 312,885.00 31,288.50 344,173.50 344,173.50 18% 61,951.23 20,306.24 426,430.97
As Submitted 0.01% 17.94 m³ - 320.81 4,459.67 266.47 4,780.48 18% 860.49 282.05 5,923.02
803(1)a Structure Excavation (Common Soil)
As Evaluated 0.01% 17.94 m³ - 320.81 4,459.67 266.47 4,780.48 18% 860.49 282.05 5,923.02
As Submitted 0.01% 20.24 m³ - 735.65 3,496.78 209.11 4,232.43 18% 761.84 249.71 5,243.98
804(1)a Embankment from Structure Excavation (Common Soil)
As Evaluated 0.01% 20.24 m³ - 735.65 3,496.78 209.11 4,232.43 18% 761.84 249.71 5,243.98
As Submitted 0.00% 2.07 m³ 1,604.77 616.95 167.78 1,154.35 2,389.50 18% 430.11 140.98 2,960.59
804(7) Gravel Fill
As Evaluated 0.00% 2.07 m³ 1,604.77 616.95 167.78 1,154.35 2,389.50 18% 430.11 140.98 2,960.59
As Submitted 0.57% 1,604.77 314,558.41 39,412.73 355,575.91 64,003.67 20,978.98 440,558.56
TOTAL OF PART C
As Evaluated 0.57% 1,604.77 314,558.41 39,412.73 355,575.91 64,003.67 20,978.98 440,558.56
PART D REINFORCED CONCRETE
As Submitted 0.55% 42.73 m³ 325,147.53 8,901.28 8,641.95 8,019.91 342,690.76 18% 61,684.34 20,218.76 424,593.86
900(1)d Structural Concrete (4000 psi Class A @ 28 days)
As Evaluated 0.55% 42.73 m³ 325,147.53 8,901.28 8,641.95 8,019.91 342,690.76 18% 61,684.34 20,218.76 424,593.86
As Submitted 0.36% 29.48 m³ 211,261.05 6,141.11 5,962.20 7,576.81 223,364.36 18% 40,205.58 13,178.50 276,748.44
900(1)c Structural Concrete (3000 psi Class A @ 28 days)
As Evaluated 0.36% 29.48 m³ 211,261.05 6,141.11 5,962.20 7,576.81 223,364.36 18% 40,205.58 13,178.50 276,748.44
As Submitted 0.46% 4,545.11 Kg 227,975.90 46,445.37 9,471.87 62.46 283,893.14 18% 51,100.77 16,749.70 351,743.61
902(1)a1 Reinforcing Steel (Deformed), Grade 40
As Evaluated 0.46% 4,545.11 Kg 227,975.90 46,445.37 9,471.87 62.46 283,893.14 18% 51,100.77 16,749.70 351,743.61
As Submitted 0.48% 4,745.68 Kg 242,969.32 48,494.94 9,889.85 63.50 301,354.11 18% 54,243.74 17,779.89 373,377.74
902(1)a2 Reinforcing Steel (Deformed), Grade 60
As Evaluated 0.48% 4,745.68 Kg 242,969.32 48,494.94 9,889.85 63.50 301,354.11 18% 54,243.74 17,779.89 373,377.74
As Submitted 0.41% 574.87 m² 90,578.04 165,312.87 260.22 445.58 256,151.13 18% 46,107.20 15,112.92 317,371.25
903(2) Formworks & Falseworks
As Evaluated 0.41% 574.87 m² 90,578.04 165,312.87 260.22 445.58 256,151.13 18% 46,107.20 15,112.92 317,371.25
As Submitted 2.26% 1,097,931.84 275,295.57 34,226.09 1,407,453.50 253,341.63 83,039.77 1,743,834.90
TOTAL OF PART D
As Evaluated 2.26% 1,097,931.84 275,295.57 34,226.09 1,407,453.50 253,341.63 83,039.77 1,743,834.90
LOCAL PROGRAM, National Building Program, Buildings and Other Structures, Multipurpose / Facilities, Construction (Completion) of 3 Storey Camp Nakar Station Hospital Building, Southern Luzon Command, Lucena City
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
DIVISION II BUILDINGS
PART E FINISHING AND OTHER CIVIL WORKS
As Submitted 0.00% 2.45 L 624.75 172.33 17.23 332.37 814.31 18% 146.58 48.04 1,008.93
1000(1) Soil Poisoning
As Evaluated 0.00% 2.45 L 624.75 172.33 17.23 332.37 814.31 18% 146.58 48.04 1,008.93
As Submitted 5.33% 3,214.08 m² 2,535,009.61 557,097.09 229,553.03 1,033.47 3,321,659.73 18% 597,898.75 195,977.92 4,115,536.40
1046(2)a2 CHB Non Load Bearing (including Reinforcing Steel), 150mm
As Evaluated 5.33% 3,214.08 m² 2,535,009.61 557,097.09 229,553.03 1,033.47 3,321,659.73 18% 597,898.75 195,977.92 4,115,536.40
As Submitted 0.60% 1.00 l.s. 208,210.18 151,936.00 15,193.60 375,339.78 375,339.78 18% 67,561.16 22,145.05 465,045.99
1003(2)e Wall
As Evaluated 0.60% 1.00 l.s. 208,210.18 151,936.00 15,193.60 375,339.78 375,339.78 18% 67,561.16 22,145.05 465,045.99
As Submitted 3.44% 1.00 L.s. 1,810,000.00 300,369.60 30,036.96 2,140,406.56 2,140,406.56 18% 385,273.18 126,283.99 2,651,963.73
1003(17) Carpentry and Joinery Works
As Evaluated 3.44% 1.00 L.s. 1,810,000.00 300,369.60 30,036.96 2,140,406.56 2,140,406.56 18% 385,273.18 126,283.99 2,651,963.73
As Submitted 0.39% 147.45 m2 103,215.00 140,658.08 - 1,653.94 243,873.08 18% 43,897.15 14,388.51 302,158.74
1010 (2)a Doors (Flush)
As Evaluated 0.39% 147.45 m2 103,215.00 140,658.08 - 1,653.94 243,873.08 18% 43,897.15 14,388.51 302,158.74
As Submitted 0.78% 73.29 m² 403,095.00 77,329.09 7,732.91 6,660.62 488,157.00 18% 87,868.26 28,801.26 604,826.52
1010(2)b Door (Wood Panel)
As Evaluated 0.78% 73.29 m² 403,095.00 77,329.09 7,732.91 6,660.62 488,157.00 18% 87,868.26 28,801.26 604,826.52
As Submitted 0.23% 1.00 Ls 92,946.00 45,580.80 4,558.08 143,084.88 143,084.88 18% 25,755.28 8,442.01 177,282.17
1006(6) Steel Doors and Frames
As Evaluated 0.23% 1.00 Ls 92,946.00 45,580.80 4,558.08 143,084.88 143,084.88 18% 25,755.28 8,442.01 177,282.17
Wooden Doors and Windows As Submitted 0.22% 1.00 L.s. 50,951.25 76,257.60 7,625.76 134,834.61 134,834.61 18% 24,270.23 7,955.24 167,060.08
1010(4)
As Evaluated 0.22% 1.00 L.s. 50,951.25 76,257.60 7,625.76 134,834.61 134,834.61 18% 24,270.23 7,955.24 167,060.08
Aluminum Glass Windows (Casement Type) As Submitted 0.70% 122.13 m2 321,232.43 103,559.46 10,355.95 3,562.99 435,147.84 18% 78,326.61 25,673.72 539,148.17
1008(1)b
As Evaluated 0.70% 122.13 m2 321,232.43 103,559.46 10,355.95 3,562.99 435,147.84 18% 78,326.61 25,673.72 539,148.17
Aluminum Glass WIndow (Awning Type) As Submitted 0.01% 2.52 m² 6,501.98 2,136.82 213.68 3,512.89 8,852.48 18% 1,593.45 522.30 10,968.23
1008(1)c
As Evaluated 0.01% 2.52 m² 6,501.98 2,136.82 213.68 3,512.89 8,852.48 18% 1,593.45 522.30 10,968.23
Aluminum Glass Windows - Sliding As Submitted 0.47% 75.83 m² 223,338.31 64,299.63 6,429.96 3,877.99 294,067.90 18% 52,932.22 17,350.01 364,350.13
1008(1)a
As Evaluated 0.47% 75.83 m² 223,338.31 64,299.63 6,429.96 3,877.99 294,067.90 18% 52,932.22 17,350.01 364,350.13
As Submitted 0.14% 1.00 L.s. 85,440.00 - - 85,440.00 85,440.00 18% 15,379.20 5,040.96 105,860.16
1004(2) Finishing Hardware
As Evaluated 0.14% 1.00 L.s. 85,440.00 - - 85,440.00 85,440.00 18% 15,379.20 5,040.96 105,860.16
As Submitted 0.82% 1.00 L.s. 278,046.13 114,386.40 116,186.64 508,619.17 508,619.17 18% 91,551.45 30,008.53 630,179.15
1051(1)a Railing
As Evaluated 0.82% 1.00 L.s. 278,046.13 114,386.40 116,186.64 508,619.17 508,619.17 18% 91,551.45 30,008.53 630,179.15
As Submitted 2.57% 6,428.16 m² 697,616.06 564,568.38 336,138.19 248.64 1,598,322.63 18% 287,698.07 94,301.04 1,980,321.74
1027(1) Cement Plaster Finish
As Evaluated 2.57% 6,428.16 m² 697,616.06 564,568.38 336,138.19 248.64 1,598,322.63 18% 287,698.07 94,301.04 1,980,321.74
As Submitted 1.19% 1,994.45 m² 470,407.65 152,322.35 119,144.76 371.97 741,874.76 18% 133,537.46 43,770.61 919,182.83
1021(1)a Cement Floor Finish (Plain)
As Evaluated 1.19% 1,994.45 m² 470,407.65 152,322.35 119,144.76 371.97 741,874.76 18% 133,537.46 43,770.61 919,182.83
As Submitted 0.47% 1.00 L.s. 175,386.95 107,632.44 10,763.24 293,782.63 293,782.63 18% 52,880.87 17,333.18 363,996.68
1021(12) Floor Finishes
As Evaluated 0.47% 1.00 L.s. 175,386.95 107,632.44 10,763.24 293,782.63 293,782.63 18% 52,880.87 17,333.18 363,996.68
As Submitted 4.05% 1,795.00 m² 1,922,839.90 548,521.96 54,852.20 1,407.36 2,526,214.06 18% 454,718.53 149,046.63 3,129,979.22
1003(1)a1 Ceiling (4.5mm, Metal Frame, Fiber Cement Board)
As Evaluated 4.05% 1,795.00 m² 1,922,839.90 548,521.96 54,852.20 1,407.36 2,526,214.06 18% 454,718.53 149,046.63 3,129,979.22
LOCAL PROGRAM, National Building Program, Buildings and Other Structures, Multipurpose / Facilities, Construction (Completion) of 3 Storey Camp Nakar Station Hospital Building, Southern Luzon Command, Lucena City
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
As Submitted 0.25% 715.50 m² 101,422.13 48,880.49 4,888.05 216.90 155,190.67 18% 27,934.32 9,156.25 192,281.24
1038(1) Reflective Insulation
As Evaluated 0.25% 715.50 m² 101,422.13 48,880.49 4,888.05 216.90 155,190.67 18% 27,934.32 9,156.25 192,281.24
As Submitted 2.77% 970.14 m² 953,765.27 704,087.10 70,408.71 1,781.46 1,728,261.08 18% 311,086.99 101,967.40 2,141,315.47
1018(1) Glazed Tiles and Trims
As Evaluated 2.77% 970.14 m² 953,765.27 704,087.10 70,408.71 1,781.46 1,728,261.08 18% 311,086.99 101,967.40 2,141,315.47
As Submitted 0.59% 362.90 m² 164,112.91 184,364.37 18,436.44 1,011.06 366,913.72 18% 66,044.47 21,647.91 454,606.10
1018(2) Unlglazed Tiles
As Evaluated 0.59% 362.90 m² 164,112.91 184,364.37 18,436.44 1,011.06 366,913.72 18% 66,044.47 21,647.91 454,606.10
As Submitted 7.57% 1.00 l.s. 4,038,303.78 616,308.00 61,630.80 4,716,242.58 4,716,242.58 18% 848,923.66 278,258.31 5,843,424.55
1020(2) Vinyl Floor Tile
As Evaluated 7.57% 1.00 l.s. 4,038,303.78 616,308.00 61,630.80 4,716,242.58 4,716,242.58 18% 848,923.66 278,258.31 5,843,424.55
As Submitted 0.03% 79.20 m² 4,573.80 12,894.18 1,289.42 236.84 18,757.40 18% 3,376.33 1,106.69 23,240.42
1016(1)a Water Proofing (Cement Base)
As Evaluated 0.03% 79.20 m² 4,573.80 12,894.18 1,289.42 236.84 18,757.40 18% 3,376.33 1,106.69 23,240.42
As Submitted 3.38% 6,428.16 m² 752,441.84 1,230,625.32 123,062.53 327.64 2,106,129.69 18% 379,103.34 124,261.65 2,609,494.68
1032(1)a Painting Works (Masonry/Concrete)
As Evaluated 3.38% 6,428.16 m² 752,441.84 1,230,625.32 123,062.53 327.64 2,106,129.69 18% 379,103.34 124,261.65 2,609,494.68
As Submitted 0.21% 294.04 m² 66,549.34 59,106.45 5,910.65 447.44 131,566.44 18% 23,681.96 7,762.42 163,010.82
1032(1)c Painting Works (Steel)
As Evaluated 0.21% 294.04 m² 66,549.34 59,106.45 5,910.65 447.44 131,566.44 18% 23,681.96 7,762.42 163,010.82
As Submitted 0.95% 934.57 m² 402,369.77 170,995.70 17,099.57 631.80 590,465.04 18% 106,283.71 34,837.44 731,586.19
1014(1)b2 Prepainted Metal Sheets Above 0.427mm, rib type long span
As Evaluated 0.95% 934.57 m² 402,369.77 170,995.70 17,099.57 631.80 590,465.04 18% 106,283.71 34,837.44 731,586.19
As Submitted 2.34% 15,607.11 Kg 1,029,061.52 133,761.06 293,125.45 93.29 1,455,948.03 18% 262,070.65 85,900.93 1,803,919.61
1047(8)a Structural Steel (Trusses)
As Evaluated 2.34% 15,607.11 Kg 1,029,061.52 133,761.06 293,125.45 93.29 1,455,948.03 18% 262,070.65 85,900.93 1,803,919.61
As Submitted 1.47% 10,668.11 Kg 743,276.21 73,806.30 99,613.45 85.93 916,695.96 18% 165,005.27 54,085.06 1,135,786.29
1047(8)b Structural Steel (Purlins)
As Evaluated 1.47% 10,668.11 Kg 743,276.21 73,806.30 99,613.45 85.93 916,695.96 18% 165,005.27 54,085.06 1,135,786.29
As Submitted 0.01% 72.53 Kg 4,706.73 1,703.87 170.39 90.73 6,580.99 18% 1,184.58 388.28 8,153.85
1047(5)d Metal Structure Accessories (Steel Plates)
As Evaluated 0.01% 72.53 Kg 4,706.73 1,703.87 170.39 90.73 6,580.99 18% 1,184.58 388.28 8,153.85
As Submitted 0.03% 314.28 Kgs 12,539.77 7,379.78 737.98 65.73 20,657.53 18% 3,718.36 1,218.79 25,594.68
1047(5)b Metal Structure Accessories (Sagrods)
As Evaluated 0.03% 314.28 Kgs 12,539.77 7,379.78 737.98 65.73 20,657.53 18% 3,718.36 1,218.79 25,594.68
As Submitted 0.05% 440.55 Kgs 17,577.95 10,344.79 1,034.48 65.73 28,957.22 18% 5,212.30 1,708.48 35,878.00
1047(5)c Metal Structure Accessories (Crossbracing)
As Evaluated 0.05% 440.55 Kgs 17,577.95 10,344.79 1,034.48 65.73 28,957.22 18% 5,212.30 1,708.48 35,878.00
As Submitted 0.03% 68.00 Ea 13,600.00 3,113.65 311.37 250.37 17,025.02 18% 3,064.50 1,004.48 21,094.00
1047(4)b Metal Structure Accessories (Turnbuckle)
As Evaluated 0.03% 68.00 Ea 13,600.00 3,113.65 311.37 250.37 17,025.02 18% 3,064.50 1,004.48 21,094.00
As Submitted 0.01% 88.00 Ea 2,904.00 2,686.29 268.63 66.58 5,858.92 18% 1,054.61 345.68 7,259.21
1047(4)a Metal Structure Accessories (Bolts and Rods)
As Evaluated 0.01% 88.00 Ea 2,904.00 2,686.29 268.63 66.58 5,858.92 18% 1,054.61 345.68 7,259.21
As Submitted 9.13% 1.00 L.s. 4,159,887.02 849,398.80 679,259.88 5,688,545.70 5,688,545.70 18% 1,023,938.23 335,624.20 7,048,108.13
1047(3) Metal Structure Accessories
As Evaluated 9.13% 1.00 L.s. 4,159,887.02 849,398.80 679,259.88 5,688,545.70 5,688,545.70 18% 1,023,938.23 335,624.20 7,048,108.13
As Submitted 0.05% 127.49 L.m. 26,768.50 3,891.76 389.18 243.54 31,049.44 18% 5,588.90 1,831.92 38,470.26
1013(2)b Fabricated Metal Roofing Accessory, (Ga. 26 (0.551mm), Flashing)
As Evaluated 0.05% 127.49 L.m. 26,768.50 3,891.76 389.18 243.54 31,049.44 18% 5,588.90 1,831.92 38,470.26
Sewer Line Works As Submitted 0.18% 1.00 L.s. 72,005.85 36,353.60 3,635.36 111,994.81 111,994.81 18% 20,159.07 6,607.69 138,761.57
1001(8)
As Evaluated 0.18% 1.00 L.s. 72,005.85 36,353.60 3,635.36 111,994.81 111,994.81 18% 20,159.07 6,607.69 138,761.57
Cold Water lines As Submitted 0.29% 1.00 L.s. 130,205.17 45,580.80 4,558.08 180,344.05 180,344.05 18% 32,461.93 10,640.30 223,446.28
1002(24)
As Evaluated 0.29% 1.00 L.s. 130,205.17 45,580.80 4,558.08 180,344.05 180,344.05 18% 32,461.93 10,640.30 223,446.28
Storm Drainage and Downspout As Submitted 0.25% 1.00 L.s. 115,380.30 36,464.64 3,646.46 155,491.40 155,491.40 18% 27,988.45 9,173.99 192,653.84
1001(9)
As Evaluated 0.25% 1.00 L.s. 115,380.30 36,464.64 3,646.46 155,491.40 155,491.40 18% 27,988.45 9,173.99 192,653.84
Plumbing FIxtures As Submitted 1.81% 1.00 L.s. 790,763.90 304,704.00 30,470.40 1,125,938.30 1,125,938.30 18% 202,668.89 66,430.36 1,395,037.55
1002(4)
As Evaluated 1.81% 1.00 L.s. 790,763.90 304,704.00 30,470.40 1,125,938.30 1,125,938.30 18% 202,668.89 66,430.36 1,395,037.55
Catch Basin (CHB) As Submitted 0.08% 5.00 Ea 37,751.54 9,496.00 949.60 9,639.43 48,197.14 18% 8,675.49 2,843.63 59,716.26
1001(5)b
As Evaluated 0.08% 5.00 Ea 37,751.54 9,496.00 949.60 9,639.43 48,197.14 18% 8,675.49 2,843.63 59,716.26
As Submitted 52.88% 23,024,828.50 7,552,774.98 2,369,699.07 32,947,302.55 5,930,514.46 1,943,890.85 40,821,707.87
TOTAL OF PART E
As Evaluated 52.88% 23,024,828.50 7,552,774.98 2,369,699.07 32,947,302.55 5,930,514.46 1,943,890.85 40,821,707.87
LOCAL PROGRAM, National Building Program, Buildings and Other Structures, Multipurpose / Facilities, Construction (Completion) of 3 Storey Camp Nakar Station Hospital Building, Southern Luzon Command, Lucena City
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
PART F ELECTRICAL WORKS
As Submitted 11.62% 1.00 Set 6,962,000.00 250,308.00 25,030.80 7,237,338.80 7,237,338.80 18% 1,302,720.98 427,002.99 8,967,062.77
1110(4) Patient Bed Station
As Evaluated 11.62% 1.00 Set 6,962,000.00 250,308.00 25,030.80 7,237,338.80 7,237,338.80 18% 1,302,720.98 427,002.99 8,967,062.77
As Submitted 1.89% 1.00 L.s. 840,297.00 303,872.00 30,387.20 1,174,556.20 1,174,556.20 18% 211,420.12 69,298.82 1,455,275.14
1100(10) Conduits, Boxes & Fittings (Conduit Works/Conduit Rough-in)
As Evaluated 1.89% 1.00 L.s. 840,297.00 303,872.00 30,387.20 1,174,556.20 1,174,556.20 18% 211,420.12 69,298.82 1,455,275.14
As Submitted 11.10% 1.00 L.s. 5,572,951.51 1,220,121.60 122,012.16 6,915,085.27 6,915,085.27 18% 1,244,715.35 407,990.03 8,567,790.65
1101(33) Wires and Wiring Devices
As Evaluated 11.10% 1.00 L.s. 5,572,951.51 1,220,121.60 122,012.16 6,915,085.27 6,915,085.27 18% 1,244,715.35 407,990.03 8,567,790.65
As Submitted 3.39% 1.00 L.s. 1,512,923.42 545,304.00 54,530.40 2,112,757.82 2,112,757.82 18% 380,296.41 124,652.71 2,617,706.94
1102(1) Panel Board with Main and Branch Breaker
As Evaluated 3.39% 1.00 L.s. 1,512,923.42 545,304.00 54,530.40 2,112,757.82 2,112,757.82 18% 380,296.41 124,652.71 2,617,706.94
As Submitted 1.50% 1.00 L.s. 665,498.00 243,097.60 24,309.76 932,905.36 932,905.36 18% 167,922.96 55,041.42 1,155,869.74
1103(1) Lighting Fixtures & Lamps
As Evaluated 1.50% 1.00 L.s. 665,498.00 243,097.60 24,309.76 932,905.36 932,905.36 18% 167,922.96 55,041.42 1,155,869.74
As Submitted 29.49% 15,553,669.93 2,562,703.20 256,270.32 18,372,643.45 3,307,075.82 1,083,985.97 22,763,705.24
TOTAL OF PART F
As Evaluated 29.49% 15,553,669.93 2,562,703.20 256,270.32 18,372,643.45 3,307,075.82 1,083,985.97 22,763,705.24
PART G MECHANICAL WORKS
Airconditioning / Package / Split Type As Submitted 5.98% 1.00 L.s. 3,444,100.00 256,176.00 25,617.60 3,725,893.60 3,725,893.60 18% 670,660.85 219,827.72 4,616,382.17
1200(13)a
As Evaluated 5.98% 1.00 L.s. 3,444,100.00 256,176.00 25,617.60 3,725,893.60 3,725,893.60 18% 670,660.85 219,827.72 4,616,382.17
1201(7)a Water Tank - Stainless As Submitted 1.48% 1.00 Set 683,265.06 145,178.64 93,792.00 922,235.70 922,235.70 18% 166,002.43 54,411.91 1,142,650.03
As Evaluated 1.48% 1.00 Set 683,265.06 145,178.64 93,792.00 922,235.70 922,235.70 18% 166,002.43 54,411.91 1,142,650.03
1202(1) Automatic Water Sprinkler As Submitted 3.66% 1.00 L.s. 1,506,724.80 700,862.40 70,086.24 2,277,673.44 2,277,673.44 18% 409,981.22 134,382.73 2,822,037.39
As Evaluated 3.66% 1.00 L.s. 1,506,724.80 700,862.40 70,086.24 2,277,673.44 2,277,673.44 18% 409,981.22 134,382.73 2,822,037.39
1208(1) Fire Alarm System As Submitted 0.42% 1.00 L.s. 99,214.50 147,635.20 14,763.52 261,613.22 261,613.22 18% 47,090.38 15,435.18 324,138.78
As Evaluated 0.42% 1.00 L.s. 99,214.50 147,635.20 14,763.52 261,613.22 261,613.22 18% 47,090.38 15,435.18 324,138.78
As Submitted 11.54% 5,733,304.36 1,249,852.24 204,259.36 7,187,415.96 1,293,734.87 424,057.54 8,905,208.37
TOTAL OF PART G
As Evaluated 11.54% 5,733,304.36 1,249,852.24 204,259.36 7,187,415.96 1,293,734.87 424,057.54 8,905,208.37
As Submitted 96.73% 45,411,339.40 11,955,184.40 2,903,867.57 60,270,391.37 10,848,670.46 3,555,953.11 74,675,014.94
TOTAL OF DIVISION I & II
As Evaluated 96.73% 45,411,339.40 11,955,184.40 2,903,867.57 60,270,391.37 10,848,670.46 3,555,953.11 74,675,014.94
As Submitted 100.00% 45,627,802.58 12,607,080.51 4,146,891.87 62,381,774.96 11,142,034.53 3,676,190.50 77,200,000.00
GRAND TOTAL
As Evaluated 100.00% 45,627,802.58 12,607,080.51 4,146,891.87 62,381,774.96 11,142,034.53 3,676,190.50 77,200,000.00
LOCAL PROGRAM, National Building Program, Buildings and Other Structures, Multipurpose / Facilities, Construction (Completion) of 3 Storey Camp Nakar Station Hospital Building, Southern Luzon Command, Lucena City
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
TOTAL UNIT COST (DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALAUTED AS SUBMITTED AS EVALAUTED
A.1.1(3) Construction of Field Office for the Engineer 1.00 1.00 L.s. 95,041.44 95,041.44 95,041.44 95,041.44 117,756.35 117,756.35 0.15% 0.15%
Provision of Furnitures/Fixtures, Equipment & Appliances for the Field Office for the
A.1.1(11) 1.00 1.00 L.s. 10,375.00 10,375.00 10,375.00 10,375.00 11,765.25 11,765.25 0.02% 0.02%
Engineer
A.1.4(1) Provision of Progress Photographs 12.00 12.00 Mo. 5,400.00 5,400.00 450.00 450.00 510.30 510.30 0.01% 0.01%
B.3 (1) Permits and Clearances 1.00 1.00 L.s. 32,250.00 32,250.00 32,250.00 32,250.00 33,862.50 33,862.50 0.05% 0.05%
B.5 (1) Project Billboard/ Sign Board 1.00 1.00 Ea 2,868.06 2,868.06 2,868.06 2,868.06 3,553.53 3,553.53 0.00% 0.00%
B.7(1) Occupational Safety and Health 1.00 1.00 L.s. 505,024.66 505,024.66 505,024.66 505,024.66 572,697.96 572,697.96 0.81% 0.81%
B.9 (1) Mobilization/Demobilization 1.00 1.00 L.s. 160,000.00 160,000.00 160,000.00 160,000.00 168,000.00 168,000.00 0.26% 0.26%
B.24(1) General scaffolding and shoring and Netting 1.00 1.00 l.s. 1,300,424.43 1,300,424.43 1,300,424.43 1,300,424.43 1,611,225.87 1,611,225.87 2.08% 2.08%
DIVISION I - GENERAL
PART C EARTHWORKS
801(1) Removal of Structure and Obstruction 1.00 1.00 L.s. 344,173.50 344,173.50 344,173.50 344,173.50 426,430.97 426,430.97 0.55% 0.55%
803(1)a Structure Excavation (Common Soil) 17.94 17.94 m³ 4,780.48 4,780.48 266.47 266.47 330.16 330.16 0.01% 0.01%
804(1)a Embankment from Structure Excavation (Common Soil) 20.24 20.24 m³ 4,232.43 4,232.43 209.11 209.11 259.09 259.09 0.01% 0.01%
804(7) Gravel Fill 2.07 2.07 m³ 2,389.50 2,389.50 1,154.35 1,154.35 1,430.24 1,430.24 0.00% 0.00%
TOTAL OF PART C 355,575.91
900(1)d Structural Concrete (4000 psi Class A @ 28 days) 42.73 42.73 m³ 342,690.76 342,690.76 8,019.91 8,019.91 9,936.67 9,936.67 0.55% 0.55%
900(1)c Structural Concrete (3000 psi Class A @ 28 days) 29.48 29.48 m³ 223,364.36 223,364.36 7,576.81 7,576.81 9,387.67 9,387.67 0.36% 0.36%
902(1)a1 Reinforcing Steel (Deformed), Grade 40 4,545.11 4,545.11 Kg 283,893.14 283,893.14 62.46 62.46 77.39 77.39 0.46% 0.46%
902(1)a2 Reinforcing Steel (Deformed), Grade 60 4,745.68 4,745.68 Kg 301,354.11 301,354.11 63.50 63.50 78.68 78.68 0.48% 0.48%
903(2) Formworks & Falseworks 574.87 574.87 m² 256,151.13 256,151.13 445.58 445.58 552.08 552.08 0.41% 0.41%
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
TOTAL UNIT COST (DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALAUTED AS SUBMITTED AS EVALAUTED
DIVISION II - BUILDINGS
PART E FINISHING AND OTHER CIVIL WORKS
1000(1) Soil Poisoning 2.45 2.45 L 814.31 814.31 332.37 332.37 1,008.93 1,008.93 0.00% 0.00%
1046(2)a2 CHB Non Load Bearing (including Reinforcing Steel), 150mm 3,214.08 3,214.08 m² 3,321,659.73 3,321,659.73 1,033.47 1,033.47 1,280.47 1,280.47 5.32% 5.32%
1003(2)e Wall 1.00 1.00 l.s. 375,339.78 375,339.78 375,339.78 375,339.78 465,045.99 465,045.99 0.60% 0.60%
1003(17) Carpentry and Joinery Works 1.00 1.00 L.s. 2,140,406.56 2,140,406.56 2,140,406.56 2,140,406.56 2,651,963.73 2,651,963.73 3.43% 3.43%
1010 (2)a Doors (Flush) 147.45 147.45 m2 243,873.08 243,873.08 1,653.94 1,653.94 2,049.23 2,049.23 0.39% 0.39%
1010(2)b Door (Wood Panel) 73.29 73.29 m² 488,157.00 488,157.00 6,660.62 6,660.62 604,826.52 604,826.52 0.78% 0.78%
1006(6) Steel Doors and Frames 1.00 1.00 Ls 143,084.88 143,084.88 143,084.88 143,084.88 177,282.17 177,282.17 0.23% 0.23%
1010(4) Wooden Doors and Windows 1.00 1.00 L.s. 134,834.61 134,834.61 134,834.61 134,834.61 167,060.08 167,060.08 0.22% 0.22%
1008(1)b Aluminum Glass Windows (Casement Type) 122.13 122.13 m2 435,147.84 435,147.84 3,562.99 3,562.99 539,148.17 539,148.17 0.70% 0.70%
1008(1)c Aluminum Glass WIndow (Awning Type) 2.52 2.52 m² 8,852.48 8,852.48 3,512.89 3,512.89 10,968.23 10,968.23 0.01% 0.01%
1004(2) Finishing Hardware 1.00 1.00 L.s. 85,440.00 85,440.00 85,440.00 85,440.00 105,860.16 105,860.16 0.14% 0.14%
1008(1)a Aluminum Glass Windows - Sliding 75.83 75.83 m² 294,067.90 294,067.90 3,877.99 3,877.99 4,804.83 4,804.83 0.47% 0.47%
1051(1)a Railing 1.00 1.00 L.s. 508,619.17 508,619.17 508,619.17 508,619.17 630,179.15 630,179.15 0.82% 0.82%
1027(1) Cement Plaster Finish 6,428.16 6,428.16 m² 1,598,322.63 1,598,322.63 248.64 248.64 308.07 308.07 2.56% 2.56%
1021(1)a Cement Floor Finish (Plain) 1,994.45 1,994.45 m² 741,874.76 741,874.76 371.97 371.97 460.87 460.87 1.19% 1.19%
1021(12) Floor Finishes 1.00 1.00 L.s. 293,782.63 293,782.63 293,782.63 293,782.63 363,996.68 363,996.68 0.47% 0.47%
1003(1)a1 Ceiling (4.5mm, Metal Frame, Fiber Cement Board) 1,795.00 1,795.00 m² 2,526,214.06 2,526,214.06 1,407.36 1,407.36 1,743.72 1,743.72 4.05% 4.05%
1038(1) Reflective Insulation 715.50 715.50 m² 155,190.67 155,190.67 216.90 216.90 268.74 268.74 0.25% 0.25%
1018(1) Glazed Tiles and Trims 970.14 970.14 m² 1,728,261.08 1,728,261.08 1,781.46 1,781.46 2,207.22 2,207.22 2.77% 2.77%
1018(2) Unlglazed Tiles 362.90 362.90 m² 366,913.72 366,913.72 1,011.06 1,011.06 1,252.70 1,252.70 0.59% 0.59%
1020(2) Vinyl Floor Tile 1.00 1.00 l.s. 4,716,242.58 4,716,242.58 4,716,242.58 4,716,242.58 5,843,424.55 5,843,424.55 7.56% 7.56%
1016(1)a Water Proofing (Cement Base) 79.20 79.20 m² 18,757.40 18,757.40 236.84 236.84 293.44 293.44 0.03% 0.03%
1032(1)a Painting Works (Masonry/Concrete) 6,428.16 6,428.16 m² 2,106,129.69 2,106,129.69 327.64 327.64 405.95 405.95 3.38% 3.38%
1032(1)c Painting Works (Steel) 294.04 294.04 m² 131,566.44 131,566.44 447.44 447.44 554.38 554.38 0.21% 0.21%
LOCAL PROGRAM, National Building Program, Buildings and Other Structures, Multipurpose / Facilities, Construction (Completion) of 3 Storey Camp Nakar Station Hospital Building, Southern Luzon Command, Lucena City
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
TOTAL UNIT COST (DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALAUTED AS SUBMITTED AS EVALAUTED
1014(1)b2 Prepainted Metal Sheets Above 0.427mm, rib type long span 934.57 934.57 m² 590,465.04 590,465.04 631.80 631.80 782.81 782.81 0.95% 0.95%
1047(8)a Structural Steel (Trusses) 15,607.11 15,607.11 Kg 1,455,948.03 1,455,948.03 93.29 93.29 115.58 115.58 2.33% 2.33%
1047(8)b Structural Steel (Purlins) 10,668.11 10,668.11 Kg 916,695.96 916,695.96 85.93 85.93 106.47 106.47 1.47% 1.47%
1047(5)d Metal Structure Accessories (Steel Plates) 72.53 72.53 Kg 6,580.99 6,580.99 90.73 90.73 112.41 112.41 0.01% 0.01%
1047(5)b Metal Structure Accessories (Sagrods) 314.28 314.28 Kgs 20,657.53 20,657.53 65.73 65.73 81.44 81.44 0.03% 0.03%
1047(5)c Metal Structure Accessories (Crossbracing) 440.55 440.55 Kgs 28,957.22 28,957.22 65.73 65.73 81.44 81.44 0.05% 0.05%
1047(4)b Metal Structure Accessories (Turnbuckle) 68.00 68.00 Ea 17,025.02 17,025.02 250.37 250.37 310.21 310.21 0.03% 0.03%
1047(4)a Metal Structure Accessories (Bolts and Rods) 88.00 88.00 Ea 5,858.92 5,858.92 66.58 66.58 7,259.21 7,259.21 0.01% 0.01%
1047(3) Metal Structure Accessories 1.00 1.00 L.s. 5,688,545.70 5,688,545.70 5,688,545.70 5,688,545.70 7,048,108.13 7,048,108.13 9.12% 9.12%
1013(2)b Fabricated Metal Roofing Accessory, (Ga. 26 (0.551mm), Flashing) 127.49 127.49 L.m. 31,049.44 31,049.44 243.54 243.54 38,470.26 38,470.26 0.05% 0.05%
1001(8) Sewer Line Works 1.00 1.00 L.s. 111,994.81 111,994.81 111,994.81 111,994.81 138,761.57 138,761.57 0.18% 0.18%
1002(24) Cold Water lines 1.00 1.00 L.s. 180,344.05 180,344.05 180,344.05 180,344.05 223,446.28 223,446.28 0.29% 0.29%
1001(9) Storm Drainage and Downspout 1.00 1.00 L.s. 155,491.40 155,491.40 155,491.40 155,491.40 192,653.84 192,653.84 0.25% 0.25%
1002(4) Plumbing FIxtures 1.00 1.00 L.s. 1,125,938.30 1,125,938.30 1,125,938.30 1,125,938.30 1,395,037.55 1,395,037.55 1.80% 1.80%
1001(5)b Catch Basin (CHB) 5.00 5.00 Ea 48,197.14 48,197.14 9,639.43 9,639.43 11,943.25 11,943.25 0.08% 0.08%
TOTAL OF PART E 32,947,302.55
PART F ELECTRICAL WORKS
1110(4) Patient Bed Station 1.00 1.00 Set 7,237,338.80 7,237,338.80 7,237,338.80 7,237,338.80 8,967,062.77 8,967,062.77 11.60% 11.60%
1100(10) Conduits, Boxes & Fittings (Conduit Works/Conduit Rough-in) 1.00 1.00 L.s. 1,174,556.20 1,174,556.20 1,174,556.20 1,174,556.20 1,455,275.14 1,455,275.14 1.88% 1.88%
1101(33) Wires and Wiring Devices 1.00 1.00 L.s. 6,915,085.27 6,915,085.27 6,915,085.27 6,915,085.27 8,567,790.65 8,567,790.65 11.09% 11.09%
1102(1) Panel Board with Main and Branch Breaker 1.00 1.00 L.s. 2,112,757.82 2,112,757.82 2,112,757.82 2,112,757.82 2,617,706.94 2,617,706.94 3.39% 3.39%
1103(1) Lighting Fixtures & Lamps 1.00 1.00 L.s. 932,905.36 932,905.36 932,905.36 932,905.36 1,155,869.74 1,155,869.74 1.50% 1.50%
TOTAL OF PART F 18,372,643.45
PART G MECHANICAL WORKS
1200(13)a Airconditioning / Package / Split Type 1.00 1.00 L.s. 3,725,893.60 3,725,893.60 3,725,893.60 3,725,893.60 4,616,382.17 4,616,382.17 5.97% 5.97%
1201(7)a Water Tank - Stainless 1.00 1.00 Set 922,235.70 922,235.70 922,235.70 922,235.70 1,142,650.03 1,142,650.03 1.48% 1.48%
1202(1) Automatic Water Sprinkler 1.00 1.00 L.s. 2,277,673.44 2,277,673.44 2,277,673.44 2,277,673.44 2,822,037.39 2,822,037.39 3.65% 3.65%
1208(1) Fire Alarm System 1.00 1.00 L.s. 261,613.22 261,613.22 261,613.22 261,613.22 324,138.78 324,138.78 0.42% 0.42%
TOTAL OF PART G 7,187,415.96
TOTAL OF DIVISION I & II 60,270,391.37
GRAND TOTAL 62,381,774.96 100.00% 100.00%
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City
FORM ABC-2015-02A-00
LOCAL PROGRAM, National Building Program, Buildings and Other Structures, Multipurpose / Facilities, Construction (Completion) of 3 Storey Camp Nakar Station Hospital Building, Southern Luzon Command, Lucena City
FORM ABC-2015-02A-00
LOCAL PROGRAM, National Building Program, Buildings and Other Structures, Multipurpose / Facilities, Construction (Completion) of 3 Storey Camp Nakar Station Hospital Building, Southern Luzon Command, Lucena City
FORM ABC-2015-02A-00
LOCAL PROGRAM, National Building Program, Buildings and Other Structures, Multipurpose / Facilities, Construction (Completion) of 3 Storey Camp Nakar Station Hospital Building, Southern Luzon Command, Lucena City
FORM ABC-2015-02A-00
LOCAL PROGRAM, National Building Program, Buildings and Other Structures, Multipurpose / Facilities, Construction (Completion) of 3 Storey Camp Nakar Station Hospital Building, Southern Luzon Command, Lucena City
ANNA RIELLA MARGARITA B. PERICAS ILONAH JANE M. LOTERTE JESSA M. CONTRERAS RAMONITO S.M. PAZ DEL ROSARIO C. NACA
Engineer II Engineer II Engineer II Assistant District Engineer District Engineer
Power Throwel 1
11 34
12 Truck Mounted Crane, 21-25 mt, 200 hp 1 35
13 Boom Truck (2-5 mt) 1 36
14 37
15 38
16 39
17 40
18 41
19 43
20 44
21 45
22 46
SUB-TOTAL 16 SUB-TOTAL 0
TOTAL
COMPUTATION OF NET WORKING DAYS
DESCRIPTION Mar-24 Apr-24 May-24 Jun-24 Jul-24 Aug-24 Sep-24 Oct-24 Nov-24 Dec-24 Jan-25 Feb-25 TOTAL
SUNDAYS 4 4 4 4 4 4 5 4 4 5 4 4 50
NATIONAL
0 3 1 2 0 2 2 0 3 5 2 1 21
HOLIDAYS
RAINY DAYS 6 6 6 6 6 5 7 7 6 6 6 4 71
TOTAL NON-
10 13 11 12 10 11 14 11 13 16 12 9 142
WORKING DAYS
Net Working Days 21 17 20 18 21 20 16 15 17 15 19 19 218
COMPUTATION OF ESTIMATED PROJECT DURATION AS PER DO 159 SERIES OF 2015
LOCAL PROGRAM, National Building Program, Buildings and Other Structures, Multipurpose /
PROJECT : Facilities, Construction (Completion) of 3 Storey Camp Nakar Station Hospital Building,
Southern Luzon Command, Lucena City
LOCATION : Lucena City, Quezon
AMOUNT: P 80,000,000.00
X = 203 CD
Prepared by:
KENNY S. AVELLANO
Engineer II
HAULING DISTANCE
Project Name : LOCAL PROGRAM, National Building Program, Buildings and Other Structures, Multipurpose /
Facilities, Construction (Completion) of 3 Storey Camp Nakar Station Hospital Building,
Southern Luzon Command, Lucena City
MAP SHOWING THE SOURCE OF MATERIAL TO THE POINT OF REFERENCE (PROJECT SITE) L= 12.50 KM
MAP SHOWING FROM POINT OF PROJECT SITE TO LOCATION OF STEEL ASIA L = 106.00 KM
MAP SHOWING DPWH QUEZON 2ND TO PROJECT SITE L = 4.10 KM
Prepared by:
KENNY S. AVELLANO
Engineer II
UNIT COST ANALYSIS FOR AGGREGATES (SAND and GRAVEL)
LOCAL PROGRAM, National Building Program, Buildings and Other Structures, Multipurpose / Facilities,
Project : Construction (Completion) of 3 Storey Camp Nakar Station Hospital Building, Southern Luzon Command,
Lucena City
Prevailing
Liter/ hr Cost/Hr
Fuel Adjustment due to Energy Crisis Cost/L
Fuel Consumption 14.0427 60.75 ₱853.09
OIL/LUBRICANTS 0.0211 220.00 ₱4.64
Cargotruck Operated Dry / hr ₱598.00
₱1,455.74
Revised Rate per day ₱6,264.00
Project : LOCAL PROGRAM, National Building Program, Buildings and Other Structures, Multipurpose / Facilities, Construction (Completion)
of 3 Storey Camp Nakar Station Hospital Building, Southern Luzon Command, Lucena City
A.1.1(11) Provision of Furnitures/Fixtures, Equipment & Appliances for the Field Office for the Engineer
AREA
3.3 X 26
35
L = 2.45
70.65
COLUMN
ID B D L SET AREA
C-1 0.25 0.25 12.75 5 63.75
63.75
COLUMN
ID B D L SET AREA
B-1 0.20 0.40 3.20 2 7.68
B-2 0.20 0.25 3.20 2 5.76
B-2 0.20 0.25 3.28 1 2.95
B-2 0.20 0.25 1.50 1 1.35
B-1 0.20 0.40 5.63 1 6.75
B-1 0.20 0.40 5.75 2 13.80
B-1 0.20 0.40 2.75 1 3.30
B-2 0.20 0.25 1.60 2 2.88
44.47
ROOF BEAMS
ID B D L SET AREA
RB-1 0.35 0.20 6.00 30 198.00
RB-1 0.35 0.20 6.00 30 198.00
60 396.00
TOTAL 574.87 m2
803(1)a STRUCTURE EXCAVATION (Common Soil)
FOOTING TIE BEAMS / WALL FOOTING FOUNDATION
ID B D L SET TOTAL ID L W D SET TOTAL
FTB 300 450 3300 1 0.45 CF-1 1200 1200 1200.0 5 8.64
FTB 300 450 5876 1 0.79
FTB 300 450 6000 3 2.43
FTB 300 450 1100 1 0.15
WF 400 600 2750 1 0.66
WF 400 600 3025 1 0.73
WF 400 600 9325 1 2.24
WF 400 600 1250 2 0.60
WF 400 600 5200 1 1.25
12 9.30 8.64
FOUNDATION
CF-1 1200 1200 200 5 1.44
SLAB ON FILL
SOG 3.47 0.100 1 0.347
SOG 2.81 0.100 1 0.281
0.000 2.07
3.984
38 9.289
SECOND FLOOR
B-1 0.2 0.4 3.2 2.00 0.512
B-2 0.2 0.25 3.2 2.00 0.320
B-2 0.2 0.25 3.3 1.00 0.164
B-2 0.2 0.25 1.5 1.00 0.075
B-1 0.2 0.4 5.6 1.00 0.450
B-1 0.2 0.4 5.8 2.00 0.920
B-1 0.2 0.4 2.8 1.00 0.220
B-2 0.2 0.25 1.6 2.00 0.160
12.00 2.82
ROOF BEAMS
RB-1 0.35 0.20 6.00 30 12.600
RB-1 0.35 0.20 6.00 30 12.600
25.20
OTHER CONCRETING
CONCRETE GUTTER 0.20 m² 30 2 11.730
CONCRETE GUTTER 0.20 m² 6 1 1.173
CONCRETE RAMP-1 0.21 m² 27.6334 1 5.872
CONCRETE RAMP-2 0.36 m² 20.75 1 7.522
CONCRETE RAMP-3 0.43 m² 3.75 2 3.188
29.484
TOTAL 29.48
902(1)a SUSPENDED SLAB
SUMMARY OF BARS:
T1
SIZE
DESCRIPTION LENGTH (m) WIDTH 1 (mm) WIDTH 2 (mm) THICKNESS (mm) ANGLE QTY. NO. OF TRUSS WEIGHT/METER TOTAL WEIGHT
KING POST 1.00 100 50 6.35 2 2 10 7.477 299.09
BOTTOM CHORD 14.26 100 50 6.35 2 2 10 7.477 4265.55
TOP CHORD 14.24 100 50 6.35 2 2 10 7.477 4258.97
MEMBERS-VERTICAL 6.28 50 50 6.35 2 2 10 4.985 1252.97
MEMBERS-DIAGONAL 12.83 50 50 6.35 2 2 10 4.985 2558.17
SUBTOTAL 12634.75
T2
SIZE
DESCRIPTION LENGTH (m) WIDTH 1 (mm) WIDTH 2 (mm) THICKNESS (mm) ANGLE QTY. NO. OF TRUSS WEIGHT/METER TOTAL WEIGHT
KING POST 1.00 100 50 6.35 2 2 1 7.477 29.91
BOTTOM CHORD 16.88 100 50 6.35 2 1 1 7.477 252.35
TOP CHORD 16.89 100 50 6.35 2 1 1 7.477 252.59
MEMBERS-VERTICAL 8.06 50 50 6.35 2 1 1 4.985 80.35
MEMBERS-DIAGONAL 15.73 50 50 6.35 2 1 1 4.985 156.83
SUBTOTAL 772.04
Ramp Framing
SIZE
DESCRIPTION LENGTH (m) WIDTH 1 (mm) WIDTH 2 (mm) THICKNESS (mm) ANGLE QTY. NO. OF TRUSS WEIGHT/METER TOTAL WEIGHT
HOLLOW STEEL GIRDER 20.88 150 75 3 1 1 1 10.598 221.22
HOLLOW STEEL GIRDER 26.20 150 75 3 1 2 1 10.598 555.31
HOLLOW STEEL RAFTER 6.51 100 50 3 1 10 1 7.065 459.93
HOLLOW STEEL RAFTER 3.30 100 50 3 1 3 1 7.065 69.94
SUBTOTAL 1306.41
SUBTOTAL 150.72
PURLINS
SIZE WEIGHT/METE
DESCRIPTION LENGTH QTY. NO. OF PANEL TOTAL WEIGHT
L1 (mm) W1 (mm) W2 (mm) THICKNESS (mm) R
TRUSS
PURLINS 30 0.1016 0.0508 0.0508 0.0047625 24 1 7850 5469.67
PURLINS 6 0.1016 0.0508 0.0508 0.0047625 20 1 7850 911.61
PURLINS 15 0.1016 0.0508 0.0508 0.0047625 10 1 7850 1139.51
PURLINS 18 0.1016 0.0508 0.0508 0.0047625 10 1 7850 1367.42
PURLINS 20.875 0.1016 0.0508 0.0508 0.0047625 7 1 7850 1110.08
PURLINS 5.325 0.1016 0.0508 0.0508 0.0047625 4 1 7850 161.81
SUBTOTAL 10,160.10
STEEL PLATE
SIZE
DESCRIPTION WIDTH 1 (mm) WIDTH 2 (mm) THICKNESS (mm) QTY. WEIGHT/M³ TOTAL WEIGHT
STEEL BASE PLATE 200 200 10 4 4 7850 50.24
STEEL BASE PLATE 200 200 10 3 2 7850 18.84
SUBTOTAL 69.08
Prepainted Metal Sheets Above 0.427mm, rib type long span
QUANTITY: 934.57 m²
STEEL PLATE
AREA
DESCRIPTION L W
METAL ROOFING 18 27.8 500.4
METAL ROOFING 6 17.208 103.248
METAL ROOFING 6 27.8 166.8
METAL ROOFING 20.875 6.51 135.89625
METAL ROOFING 5.325 5.3 28.2225
SUBTOTAL 934.56675
314.28
440.55
QUANTITY: 68.00 Ea
QUANTITY: 88.00 Ea
GRADE 40
GRADE 60 151.52
902 REINFORCING DEFORMED BARS
FROM FDN UP TO NGL
BAR L / col
QTY (pcs) QTY (pcs) QTY (pcs) BAR PER COLUMN
BAR L
BAR L
ID B L Set Bar Ø Wt (Kgs)
Length
FOR 30% For 70% FOR 30% Pcs
(m)
651.85 Kgs
253.33 Kgs
1959.110 4594.161
Total Gr.40 1,959.11 Total Grade 60 4,594.16
WINDOWS
DESCRIPTION W H Set Area Total Jamb (Lm)
W-1 0.60 1.75 79 1.05 82.95 371.30 casement
W-3 1.80 1.95 6 3.51 21.06 45.00 casement
W-4 0.60 1.90 2 1.14 2.28 10.00 casement
W-5 1.80 1.20 6 2.16 12.96 36.00 sliding
W-6 1.20 1.20 10 1.44 14.4 48.00 sliding
W-7 1.20 0.60 22 0.72 15.84 79.20 casement
W-8 0.60 1.20 2 0.72 1.44 7.20 awning
W-9 0.60 0.60 3 0.36 1.08 7.20 awning
W-11 1.40 2.85 1 3.99 3.99 8.50 sliding
W-12 2.25 5.75 2 12.94 25.88 32.00 sliding
W-16 3.00 3.10 2 9.3 18.6 24.40 sliding
79.200
INSULATION
DESCRIPTION W L Set Area (m2)
Roof 427.50 1 427.50
Roof 72 1 72.00
Roof 216 1 216.00
715.50
0 150 150 MM CHB with REINFORCING STEEL BARS
OPENING (AREA)
Grid Name L,m H,m SET,pc TOTAL AREA
AREA
W-1 0.6 1.75 1.05
W-2 0.70 1.50 1.05
W-3 1.80 1.95 3.51
W-4 0.60 1.90 1.14
W-5 1.80 1.20 2.16
W-6 1.20 1.20 1.44
W-7 1.20 0.60 0.72
W-8 0.60 1.20 0.72
W-9 0.60 0.60 0.36
W-10 0.60 0.60 0.36
W-11 1.40 2.85 3.99
W-12 2.25 5.75 12.94
W-13 3.10 5.75 17.83
W-14 3.10 5.63 17.44
W-15 2.95 3.10 9.15
W-16 3.00 3.10 9.30
W-17 2.70 3.10 8.37
D-1 1.20 2.10 2.52
D-2 1.20 2.10 2.52
D-3 0.90 2.10 1.89
D-4 1.20 2.10 2.52
D-5 0.90 2.10 1.89
D-6 1.20 2.10 2.52
D-7 0.80 2.10 1.68
D-8 0.90 2.10 1.89
D-9 0.70 2.10 1.47
D-10 1.60 2.10 3.36
D-11 1.60 2.10 3.36
D-12 3.40 2.10 7.14
D-13 1.60 2.10 3.36
D-14 2.70 2.10 5.67
D-15 2.15 2.10 4.52
D-16 1.80 2.41 4.33
D-17 1.00 2.10 2.10
1027(1) Cement Plaster Finish 1027(1) Painting Works (Masonry/Concrete)
GROUND FLOOR / SECOND FLOOR/THIRD FLOOR
No. of No. of Area of
Area of Net Area,
CHB NAME Net Area, m2 Plastered NAME Painte Painted
Plaster,m2 m2
Face d Face Face,m2
1 GROUND FLOOR 188.76 2 377.52 1 GROUND FLOOR 188.76 2 377.52
2 SECOND FLOOR 1862.51 2 3725.02 2 SECOND FLOOR 1862.51 2 3725.02
3 THIRD FLOOR 881.63 2 1763.26 3 THIRD FLOOR 881.63 2 1763.26
4 ROOF DECK 281.18 2 562.36 4 ROOF DECK 281.18 2 562.36
TOTAL 294.040 m2
970.14
1018(2) Flr Unlglazed Tiles
DESCRIPTION Finish Area, (frm Cadd) TYPICAL Net Area, m2
2ND FLOOR TILES 162.9 1 162.9
3RD FLOOR TILES 200 1 200
362.90
1020(2) Flr Vinyl Floor Tile
DESCRIPTION Finish Area, (frm Cadd) TYPICAL Net Area, m2
2ND FLOOR TILES 677.12 1 677.12
3RD FLOOR TILES 260 1 260
937.12
LOCAL PROGRAM, National Building Program, Buildings and Other Structures, Multipurpose / Facilities, Construction
(Completion) of 3 Storey Camp Nakar Station Hospital Building, Southern Luzon Command, Lucena City
No. of No. of
Designation Hourly Rate Amount (PhP)
A1. Person/s Hr/s
Labor
a. Construction Foreman 1 40.00 133.91 5,356.40
b. Skilled Laborer 3 40.00 96.77 11,612.40
c. Unskilled Laborer 5 40.00 74.58 14,916.00
Item no./Description : A.1.1(11) Provision of Furnitures/Fixtures, Equipment & Appliances for the Field Office for the
Engineer
Unit of Measurement : l.s.
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00
No. of
Designation No. of Hour/s Hourly Rate Amount
Person
A.1 Labor
No. of No. of
Designation Hourly Rate Amount (PhP)
A1. Person/s Hr/s
Labor
a. -
b. -
c. -
a. Labor -
b. Skilled Laborer -
c. Unskilled Laborer -
. -
Sub - Total for A1 (As Submitted) -
A2. Labor
a. Construction Foreman -
b. Skilled Laborer -
c. Unskilled Laborer -
801(1) Construction Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1.00 1.00 Skilled Laborer 2 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
Removal of Structure and Obstruction
Unskilled Laborer 4 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
803(1)a Construction Foreman 1 0.11 0.11 0.11 0.11 0.11 0.11 0.11
17.94 20.00
Structure Excavation (Common Soil) Unskilled Laborer 3 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11
804(1)a Construction Foreman 1 0.26 0.26 0.26 0.26 0.26 0.26 0.26
20.24 9.84
Embankment from Structure Excavation Unskilled Laborer 3 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26
804(7) Construction Foreman 1 0.22 0.22 0.22 0.22 0.22 0.22 0.22
2.07 1.20
Gravel Fill Unskilled Laborer 3 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22
900(1)d Construction Foreman 1 1.44 1.44 1.44 1.44 1.44 1.44 1.44
42.73 3.72 Skilled Laborer 2 1.44 1.44 1.44 1.44 1.44 1.44 1.44 1.44 1.44
Structural Concrete (4000 psi Class A @ 28 days)
Unskilled Laborer 6 1.44 1.44 1.44 1.44 1.44 1.44 1.44 1.44 1.44
900(1)c Construction Foreman 1 0.99 0.99 0.99 0.99 0.99 0.99 0.99
29.48 3.72 Skilled Laborer 2 0.99 0.99 0.99 0.99 0.99 0.99 0.99 0.99 0.99
Structural Concrete (3000 psi Class A @ 28 days)
Unskilled Laborer 6 0.99 0.99 0.99 0.99 0.99 0.99 0.99 0.99 0.99
902(1)a1 Construction Foreman 1 4.4 4.4 4.4 4.4 4.4 4.4 4.4
4,545.11 129.094 Skilled Laborer 3 4.4 4.4 4.4 4.4 4.4 4.4 4.4 4.4 4.4
Reinforcing Steel (Deformed), Grade 40
Unskilled Laborer 12 4.4 4.4 4.4 4.4 4.4 4.4 4.4 4.4 4.4
902(1)a2 Construction Foreman 1 4.6 4.6 4.6 4.6 4.6 4.6 4.6
4,745.68 129.094 Skilled Laborer 3 4.6 4.6 4.6 4.6 4.6 4.6 4.6 4.6 4.6
Reinforcing Steel (Deformed), Grade 60
Unskilled Laborer 12 4.6 4.6 4.6 4.6 4.6 4.6 4.6 4.6 4.6
903(2) Construction Foreman 1 15.97 15.97 15.97 15.97 15.97 15.97 15.97
574.87 4.5 Skilled Laborer 4 15.97 15.97 15.97 15.97 15.97 15.97 15.97 15.97 15.97
Formworks & Falseworks
Unskilled Laborer 6 15.97 15.97 15.97 15.97 15.97 15.97 15.97 15.97 15.97
1000(1) Construction Foreman 1 0.06 0.06 0.06 0.06 0.06 0.06 0.06
2.45 5.4 Skilled Laborer 1 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06
Soil Poisoning
Unskilled Laborer 2 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06
1046(2)a2 Construction Foreman 1 126.34 126.34 126.34 126.34 126.34 126.34 126.34
3,214.08 3.18 Skilled Laborer 2 126.34 126.34 126.34 126.34 126.34 126.34 126.34 126.34 126.34
CHB Non Load Bearing (including Reinforcing Steel), 150mm
Unskilled Laborer 3 126.34 126.34 126.34 126.34 126.34 126.34 126.34 126.34 126.34
1003(2)e Construction Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1.00 1.00 Skilled Laborer 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
Wall
Unskilled Laborer 2 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1003(17) Construction Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1.00 1.00 Skilled Laborer 2 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
Carpentry and Joinery Works
Unskilled Laborer 4 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1010 (2)a Construction Foreman 1 57.6 57.6 57.6 57.6 57.6 57.6 57.6
147.45 0.32 Skilled Laborer 1 57.6 57.6 57.6 57.6 57.6 57.6 57.6 57.6 57.6
Doors (Flush)
Unskilled Laborer 1 57.6 57.6 57.6 57.6 57.6 57.6 57.6 57.6 57.6
1010(2)b Construction Foreman 1 25.45 25.45 25.45 25.45 25.45 25.45 25.45
73.29 0.36 Skilled Laborer 1 25.45 25.45 25.45 25.45 25.45 25.45 25.45 25.45 25.45
Door (Wood Panel)
Unskilled Laborer 2 25.45 25.45 25.45 25.45 25.45 25.45 25.45 25.45 25.45
1006(6) Construction Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1.00 1.00 Skilled Laborer 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
Steel Doors and Frames
Unskilled Laborer 2 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1010(4) Construction Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1.00 1.00 Skilled Laborer 2 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
Wooden Doors and Windows
Unskilled Laborer 2 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1008(1)b Construction Foreman 1 42.41 42.41 42.41 42.41 42.41 42.41 42.41
122.13 0.36 Skilled Laborer 1 42.41 42.41 42.41 42.41 42.41 42.41 42.41 42.41 42.41
Aluminum Glass Windows (Casement Type)
Unskilled Laborer 1 42.41 42.41 42.41 42.41 42.41 42.41 42.41 42.41 42.41
1008(1)c Construction Foreman 1 0.88 0.88 0.88 0.88 0.88 0.88 0.88
2.52 0.36 Skilled Laborer 1 0.88 0.88 0.88 0.88 0.88 0.88 0.88 0.88 0.88
Aluminum Glass WIndow (Awning Type)
Unskilled Laborer 1 0.88 0.88 0.88 0.88 0.88 0.88 0.88 0.88 0.88
1008(1)a Construction Foreman 1 26.33 26.33 26.33 26.33 26.33 26.33 26.33
75.83 0.36 Skilled Laborer 1 26.33 26.33 26.33 26.33 26.33 26.33 26.33 26.33 26.33
Aluminum Glass Windows - Sliding
Unskilled Laborer 1 26.33 26.33 26.33 26.33 26.33 26.33 26.33 26.33 26.33
1004(2) Construction Foreman 0 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1.00 1.00 Skilled Laborer 0 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
Finishing Hardware
Unskilled Laborer 0 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1051(1)a Construction Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1.00 1.00 Skilled Laborer 2 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
Railing
Unskilled Laborer 2 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1027(1) Construction Foreman 1 112.77 112.77 112.77 112.77 112.77 112.77 112.77
6,428.16 7.13 Skilled Laborer 2 112.77 112.77 112.77 112.77 112.77 112.77 112.77 112.77 112.77
Cement Plaster Finish
Unskilled Laborer 4 112.77 112.77 112.77 112.77 112.77 112.77 112.77 112.77 112.77
1021(1)a Construction Foreman 1 41.9 41.9 41.9 41.9 41.9 41.9 41.9
1,994.45 5.95 Skilled Laborer 1 41.9 41.9 41.9 41.9 41.9 41.9 41.9 41.9 41.9
Cement Floor Finish (Plain)
Unskilled Laborer 13 41.9 41.9 41.9 41.9 41.9 41.9 41.9 41.9 41.9
1021(12) Construction Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1.00 1.00 Skilled Laborer 2 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
Floor Finishes
Unskilled Laborer 4 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1003(1)a1 Construction Foreman 1 180.51 180.51 180.51 180.51 180.51 180.51 180.51
1,795.00 1.24 Skilled Laborer 1 180.51 180.51 180.51 180.51 180.51 180.51 180.51 180.51 180.51
Ceiling (4.5mm, Metal Frame, Fiber Cement Board)
Unskilled Laborer 2 180.51 180.51 180.51 180.51 180.51 180.51 180.51 180.51 180.51
1038(1) Construction Foreman 1 16.09 16.09 16.09 16.09 16.09 16.09 16.09
715.50 5.56 Skilled Laborer 1 16.09 16.09 16.09 16.09 16.09 16.09 16.09 16.09 16.09
Reflective Insulation
Unskilled Laborer 2 16.09 16.09 16.09 16.09 16.09 16.09 16.09 16.09 16.09
1018(1) Construction Foreman 1 88.84 88.84 88.84 88.84 88.84 88.84 88.84
970.14 1.37 Skilled Laborer 5 88.84 88.84 88.84 88.84 88.84 88.84 88.84 88.84 88.84
Glazed Tiles and Trims
Unskilled Laborer 5 88.84 88.84 88.84 88.84 88.84 88.84 88.84 88.84 88.84
1018(2) Construction Foreman 1 23.26 23.26 23.26 23.26 23.26 23.26 23.26
362.90 1.95 Skilled Laborer 5 23.26 23.26 23.26 23.26 23.26 23.26 23.26 23.26 23.26
Unlglazed Tiles
Unskilled Laborer 5 23.26 23.26 23.26 23.26 23.26 23.26 23.26 23.26 23.26
1020(2) Construction Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1.00 1.00 Skilled Laborer 2 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
Vinyl Floor Tile
Unskilled Laborer 5 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1016(1)a Construction Foreman 1 5.28 5.28 5.28 5.28 5.28 5.28 5.28
79.20 1.88 Skilled Laborer 1 5.28 5.28 5.28 5.28 5.28 5.28 5.28 5.28 5.28
Water Proofing (Cement Base)
Unskilled Laborer 1 5.28 5.28 5.28 5.28 5.28 5.28 5.28 5.28 5.28
1032(1)a Construction Foreman 1 382.63 382.63 382.63 382.63 382.63 382.63 382.63
6,428.16 2.10
6,428.16 2.10 Skilled Laborer 2 382.63 382.63 382.63 382.63 382.63 382.63 382.63 382.63 382.63
Painting Works (Masonry/Concrete)
Unskilled Laborer 1 382.63 382.63 382.63 382.63 382.63 382.63 382.63 382.63 382.63
1032(1)c Construction Foreman 1 18.38 18.38 18.38 18.38 18.38 18.38 18.38
294.04 2.00 Skilled Laborer 2 18.38 18.38 18.38 18.38 18.38 18.38 18.38 18.38 18.38
Painting Works (Steel)
Unskilled Laborer 1 18.38 18.38 18.38 18.38 18.38 18.38 18.38 18.38 18.38
1014(1)b2 Construction Foreman 1 56.27 56.27 56.27 56.27 56.27 56.27 56.27
934.57 2.08 Skilled Laborer 1 56.27 56.27 56.27 56.27 56.27 56.27 56.27 56.27 56.27
Prepainted Metal Sheets Above 0.427mm, rib type long span
Unskilled Laborer 2 56.27 56.27 56.27 56.27 56.27 56.27 56.27 56.27 56.27
1047(8)a Construction Foreman 1 22.95 22.95 22.95 22.95 22.95 22.95 22.95
15,607.11 85.00 Skilled Laborer 2 22.95 22.95 22.95 22.95 22.95 22.95 22.95 22.95 22.95
Structural Steel (Trusses)
Unskilled Laborer 2 22.95 22.95 22.95 22.95 22.95 22.95 22.95 22.95 22.95
1047(8)b Construction Foreman 1 14.74 14.74 14.74 14.74 14.74 14.74 14.74
10,668.11 90.45 Skilled Laborer 2 14.74 14.74 14.74 14.74 14.74 14.74 14.74 14.74 14.74
Structural Steel (Purlins)
Unskilled Laborer 4 14.74 14.74 14.74 14.74 14.74 14.74 14.74 14.74 14.74
1047(5)d Construction Foreman 1 0.7 0.7 0.7 0.7 0.7 0.7 0.7
72.53 13.00 Skilled Laborer 1 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7
Metal Structure Accessories (Steel Plates)
Unskilled Laborer 1 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7 0.7
1047(5)b Construction Foreman 1 3.02 3.02 3.02 3.02 3.02 3.02 3.02
314.28 13.00 Skilled Laborer 1 3.02 3.02 3.02 3.02 3.02 3.02 3.02 3.02 3.02
Metal Structure Accessories (Sagrods)
Unskilled Laborer 1 3.02 3.02 3.02 3.02 3.02 3.02 3.02 3.02 3.02
1047(5)c Construction Foreman 1 4.24 4.24 4.24 4.24 4.24 4.24 4.24
440.55 13.00 Skilled Laborer 1 4.24 4.24 4.24 4.24 4.24 4.24 4.24 4.24 4.24
Metal Structure Accessories (Crossbracing)
Unskilled Laborer 1 4.24 4.24 4.24 4.24 4.24 4.24 4.24 4.24 4.24
1047(4)b Construction Foreman 1 8.5 8.5 8.5 8.5 8.5 8.5 8.5
68.00 1.00 Skilled Laborer 1 8.5 8.5 8.5 8.5 8.5 8.5 8.5 8.5 8.5
Metal Structure Accessories (Turnbuckle)
Unskilled Laborer 1 8.5 8.5 8.5 8.5 8.5 8.5 8.5 8.5 8.5
1047(4)a Construction Foreman 1 11 11 11 11 11 11 11
88.00 1.00 Skilled Laborer 1 11 11 11 11 11 11 11 11 11
Metal Structure Accessories (Bolts and Rods)
Unskilled Laborer 1 11 11 11 11 11 11 11 11 11
1047(3) Construction Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1.00 1.00 Skilled Laborer 4 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
Metal Structure Accessories
Unskilled Laborer 8 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1013(2)b Construction Foreman 1 1.59 1.59 1.59 1.59 1.59 1.59 1.59
127.49 10.00 Skilled Laborer 1 1.59 1.59 1.59 1.59 1.59 1.59 1.59 1.59 1.59
Fabricated Metal Roofing Accessory, (Ga. 26 (0.551mm), Flashing)
Unskilled Laborer 1 1.59 1.59 1.59 1.59 1.59 1.59 1.59 1.59 1.59
1001(8) Construction Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1.00 1.00 Skilled Laborer 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
Sewer Line Works
Unskilled Laborer 3 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1002(24) Construction Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1.00 1.00 Skilled Laborer 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
Cold Water lines
Unskilled Laborer 2 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1001(9) Construction Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1.00 1.00 Skilled Laborer 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
Storm Drainage and Downspout
Unskilled Laborer 2 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1002(4) Construction Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1.00 1.00 Skilled Laborer 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
Plumbing FIxtures
Unskilled Laborer 4 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1001(5)b Construction Foreman 1 0.63 0.63 0.63 0.63 0.63 0.63 0.63
5.00 1.00 Skilled Laborer 1 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63
Catch Basin (CHB)
5.00 1.00
Catch Basin (CHB)
Unskilled Laborer 2 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63
1100(10) Construction Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1.00 1.00 Skilled Laborer 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
Conduits, Boxes & Fittings (Conduit Works/Conduit Rough-in)
Unskilled Laborer 2 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1101(33) Construction Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1.00 1.00 Skilled Laborer 2 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
Wires and Wiring Devices
Unskilled Laborer 2 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1102(1) Construction Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1.00 1.00 Skilled Laborer 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
Panel Board with Main and Branch Breaker
Unskilled Laborer 3 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1103(1) Construction Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1.00 1.00 Skilled Laborer 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
Lighting Fixtures & Lamps
Unskilled Laborer 2 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1200(13)a Construction Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1.00 1.00 Skilled Laborer 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
Airconditioning / Package / Split Type
Unskilled Laborer 2 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1201(7)a Construction Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1.00 1.00 Skilled Laborer 2 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
Water Tank - Stainless
Unskilled Laborer 4 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1202(1) Construction Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1.00 1.00 Skilled Laborer 2 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
Automatic Water Sprinkler
Unskilled Laborer 4 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1208(1) Construction Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13
1.00 1.00 Skilled Laborer 1 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
Fire Alarm System
Unskilled Laborer 0 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
A. TOTAL PERSONNEL/MAN-DAYS 321.00 3,909.07 3,909.07 3,909.07 3,909.07 2,605.85 3,909.07 3,909.07 2,605.85 -
B. SERVICE LIFE, DAYS 730.00 365.00 180.00 3.00 730.00 365.00 60.00 60.00
C. PURCHASE COST, PPh 200.00 1,200.00 150.00 80.00 245.00 500.00 109.05 109.05
D. UNIT COST/MAN-DAY(C/B) 0.27 3.29 0.83 26.67 0.34 1.37 1.82 1.82
E. DIRECT COST FOR PPE's (D*A(Man-days)) 1,070.98 12,851.74 3,257.56 69,489.33 1,311.95 5,354.89 4,736.13 - 98,072.58
F. SAFETY OFFICER/PRACTITIONER(PART TIME) @ P15,000.00/MONTH (AS PER D.O. 56,S2005, consider at least 4hours per week) -
G. HEALTH PERSONNEL ( FULL TIME) @ P8,400.00/MONTH (AS PER D.O. 56,s2005) -
H. TOTAL DIRECT COSTM(E+F+G) 98,072.58
I. OCM (0% of E) -
J. PROFIT (8% of H) 7,845.81
K. VAT (5% of (H+I+J)) 5,295.92
L. TOTAL COST (H+I+J+K) 111,214.31
LOCAL PROGRAM, National Building Program, Buildings and Other Structures, Multipurpose / Facilities, Construction (Completion) of
3 Storey Camp Nakar Station Hospital Building, Southern Luzon Command, Lucena City
a. Use 1% of E.D.C. as per D.O. 197 Series of 2016 1 8.00 20,000.00 160,000.00
(Service Truck, Low Bed Trailer)
- Mini Backhoe, Crawler Type.
a. Use 1% of E.D.C. as per D.O. 197 Series of 2016 1 8.00 20,000.00 160,000.00
(Service Truck, Low Bed Trailer)
- Mini Backhoe, Crawler Type.
F2. Materials
- - - -
- - - -
- - - -
- - - -
a. Bar Cutter, 25 mm Maximum Rebar Ø (Grade 40), Single Phase 1 0.50 105.47 52.74
b. Bar Bender, 25 mm Maximum Rebar Ø, Three Phase 1 0.50 168.75 84.38
c. Minor Tools (10% of Labor Cost) 131.92
a. Bar Cutter, 25 mm Maximum Rebar Ø (Grade 40), Single Phase 1 0.50 105.47 52.74
b. Bar Bender, 25 mm Maximum Rebar Ø, Three Phase 1 0.50 168.75 84.38
c. Minor Tools (10% of Labor Cost) 131.92
a. Bar Cutter, 25 mm Maximum Rebar Ø (Grade 40), Single Phase 1 0.50 105.47 52.74
b. Bar Bender, 25 mm Maximum Rebar Ø, Three Phase 1 0.50 168.75 84.38
c. Minor Tools (10% of Labor Cost) 131.92
a. Bar Cutter, 25 mm Maximum Rebar Ø (Grade 40), Single Phase 1 0.50 105.47 52.74
b. Bar Bender, 25 mm Maximum Rebar Ø, Three Phase 1 0.50 168.75 84.38
c. Minor Tools (10% of Labor Cost) 131.92
63/114
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials
a. Lead Sheeting, Sheet Lead Rolls 12"x"12"x1/16" pcs 73.00 2,500.00 182,500.00
b. Marine Plywood 1/2" pcs 15.08 920.00 13,875.41
c. 50x50x3mm metal furring pcs 12.00 160.00 1,920.00
d. Consumables (5% of Material Cost) 9,914.77
a. Lead Sheeting, Sheet Lead Rolls 12"x"12"x1/16" pcs 73.00 2,500.00 182,500.00
b. Marine Plywood 1/2" pcs 15.08 920.00 13,875.41
c. 50x50x3mm metal furring pcs 12.00 160.00 1,920.00
d. Consumables (5% of Material Cost) 9,914.77
64/114
LOCAL PROGRAM, National Building Program, Buildings and Other Structures, Multipurpose / Facilities, Construction (Completion) of
3 Storey Camp Nakar Station Hospital Building, Southern Luzon Command, Lucena City
65/114
LOCAL PROGRAM, National Building Program, Buildings and Other Structures, Multipurpose / Facilities, Construction (Completion) of 3
Storey Camp Nakar Station Hospital Building, Southern Luzon Command, Lucena City
a. Labor Cost for this items are to be considered/included in the installation of doors,windows, and other fab. Materials.
a. Labor Cost for this items are to be considered/included in the installation of doors,windows, and other fab. Materials.
a. Welding Machine, Electric Driven/DC Output, 500 Amp 1 240.00 391.00 93,840.00
b. Cutting Outfit 1 240.00 45.45 10,908.00
c. Minor Tools (10% of Labor Cost) 11,438.64
a. Welding Machine, Electric Driven/DC Output, 500 Amp 1 240.00 391.00 93,840.00
b. Cutting Outfit 1 240.00 45.45 10,908.00
c. Minor Tools (10% of Labor Cost) 11,438.64
Item No./Description : 1003(1)a1 Ceiling (4.5mm, Metal Frame, Fiber Cement Board)
Unit of Measurement : m²
Output per Hour - As Evaluated : 1.243
Output per Hour - As Submitted 1.243
82/114
LOCAL PROGRAM, National Building Program, Buildings and Other Structures, Multipurpose / Facilities, Construction (Completion) of 3
Storey Camp Nakar Station Hospital Building, Southern Luzon Command, Lucena City
Item No./Description : 1014(1)b2 Prepainted Metal Sheets Above 0.427mm, rib type long span
Unit of Measurement : m²
Output per Hour - As Evaluated : 2.076
Output per Hour - As Submitted 2.076
0
Sub - Total for A1 (As Submitted) 379.84
A2. Labor
37.98
Minor Tools (10% of Labor Cost)
a. pre-painted metal roofing sheet ga. 26 long span m² 1.05 360.00 378.00
b. J-bolt with washers pcs. 10.00 4.00 40.00
c. Consumables (3% of Matl Cost) 12.54
a. pre-painted metal roofing sheet ga. 26 long span m² 1.05 360.00 378.00
b. J-bolt with washers pcs. 10.00 4.00 40.00
c. Consumables (3% of Matl Cost) 12.54
a. Welding Machine, Electric Driven/DC Output, 500 Amp 1 0.75 391.00 293.25
b. Cutting Outfit 1 0.25 45.45 11.36
c. Truck Mounted Crane, 21-25 mt, 200 hp 1 0.49 2,340.18 1,146.69
d. Minor Tools (10 % of Labor Cost) 145.13
a. Welding Machine, Electric Driven/DC Output, 500 Amp 1 0.75 391 293.25
b. Cutting Outfit 1 0.25 45.45 11.36
c. Truck Mounted Crane, 21-25 mt, 200 hp 1 0.49 2340.18 1,146.69
d. Minor Tools (10 % of Labor Cost) 145.13
a. Welding Machine, Electric Driven/DC Output, 500 Amp 2 1.00 391.00 782.00
a. Welding Machine, Electric Driven/DC Output, 500 Amp 2 1.00 391.00 782.00
a Composite frame 50 x 50 mm x 4mm single angle bar kgs. 971.17 80.00 77,693.65
b Aluminum Composite panel price pcs. 70.00 2,500.00 175,000.00
c Tubular Aluminum (50x100mmx3mm) per 2.5 mts lm 170.70 2,883.00 492,128.10
d Tubular Aluminum (50x50mmx4mm) per 2.5 mts lm 1,062.09 2,548.00 2,706,210.42
e SOLCOM AFP HEALTH SERVICES SIGNAGE l.s. 1.00 350,000.00 350,000.00
f Signages and way Finders l.s. 1.00 150,000.00 150,000.00
g Welding rod kgs. 78.00 110.00 8,580.00
h Acetylene kgs. 19.00 65.00 1,235.00
i Oxygen kgs. 19.00 50.00 950.00
j Consumable Materials (5% Material Cost) 198,089.86 198,089.86
94/114
LOCAL PROGRAM, National Building Program, Buildings and Other Structures, Multipurpose / Facilities, Construction (Completion) of 3
Storey Camp Nakar Station Hospital Building, Southern Luzon Command, Lucena City
Item No./Description : 1013(2)b Fabricated Metal Roofing Accessory, (Ga. 26 (0.551mm), Flashing)
Unit of Measurement : L.m.
Output per Hour - As Evaluated : 10
Output per Hour - As Submitted 10
0 - -
Sub - Total for A1 (As Submitted) 305.26
A2. Labor
a. ICU Bed inc. Accessories w/ uratex foam set 30.000 28,000.00 840,000.00
b. Heavy Duty Suction Machine 45L/m set 6.000 199,500.00 1,197,000.00
c. NC3 Vital Sign Monitor, 6 in. Led Disp. set 30.000 99,500.00 2,985,000.00
d. Patient Monitors (Touch Screen) Complete Acc. set 9.000 215,000.00 1,935,000.00
e. Consumables l.s. 1.000 5,000.00 5,000.00
a. ICU Bed inc. Accessories w/ uratex foam set 30.000 28,000.00 840,000.00
b. Heavy Duty Suction Machine 45L/m set 6.000 199,500.00 1,197,000.00
c. NC3 Vital Sign Monitor, 6 in. Led Disp. set 30.000 99,500.00 2,985,000.00
d. Patient Monitors (Touch Screen) Complete Acc. set 9.000 215,000.00 1,935,000.00
e. Consumables l.s. 1.000 5,000.00 5,000.00
Item No./Description : 1100(10) Conduits, Boxes & Fittings (Conduit Works/Conduit Rough-in)
Unit of Measurement : L.S
Output per Hour - As Evaluated : 1
Output per Hour - As Submitted 1
No. of
Designation No. of Hour/s Hourly Rate Amount (PhP)
A1. Person/s
Labor
Item No./Description : 1102(1) Panel Board with Main and Branch Breaker
Unit of Measurement : L.s.
Output per Hour - As Evaluated : 1
Output per Hour - As Submitted 1
No. of
Designation No. of Hour/s Hourly Rate Amount (PhP)
A1. Person/s
Labor
a. Construction Foreman 1 1200.00 133.91 160,692.00
b. Electrician 1 1200.00 96.77 116,124.00
c. Unskilled Laborer 3 1200.00 74.58 268,488.00
Sub - Total for A1 (As Submitted) 545,304.00
A2. Labor
a. Construction Foreman 1 1200.00 133.91 160,692.00
b. Electrician 1 1200.00 96.77 116,124.00
c. Unskilled Laborer 3 1200.00 74.58 268,488.00
Sub - Total for A2 (As Evaluated) 545,304.00
Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment
Minor Tools (10% of Labor Cost) 54,530.40
Sub - Total for B1 (As Submitted) 54,530.40
B2. Equipment
Minor Tools (10% of Labor Cost) 54,530.40
Sub - Total for B2 (As Evaluated) 54,530.40
C1. Total (A1 + B1) 599,834.40
C2. Total (A2 + B2) 599,834.40
D1. Output per our - As Submitted = 1 Ls
D2. Output per our - As Evaluated = 1 Ls
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 599,834.40
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 599,834.40
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials
1 PANEL BOARD
a. Surface Mounted nema 3r enclosure SET 1.00 160,000.00 160,000.00
Main:1-175at, 200af, 3p, 240VAC MCCB
Branches: 3 - 60at, 100af, 3p, 240VAC,3Ø 18KAIC PC. 19.00
1-75at,100AF,3p,240VAC
Enclose circuit breaker, Nema 3R for 2nd and 3rd Floor ACCU
n. 20AT,60AF, 2 pole, 240 VAC SET 2.00 281.71 563.42
o. 40AT,100AF, 2 pole, 240 VAC SET 2.00 817.50 1,635.00
p. 30AT, 60AF, 2 pole, 240 VAC SET 35.00 735.00 25,725.00
1,512,923.42
F2. Materials
1 PANEL BOARD
a. Surface Mounted nema 3r enclosure SET 1.00 160,000.00 160,000.00
Main:1-175at, 200af, 3p, 240VAC MCCB
Branches: 3 - 60at, 100af, 3p, 240VAC,3Ø 18KAIC
1-75at,100AF,3p,240VAC
Enclose circuit breaker, Nema 3R for 2nd and 3rd Floor ACCU
n. 20AT,60AF, 2 pole, 240 VAC SET 2.00 281.71 563.42
o. 40AT,100AF, 2 pole, 240 VAC SET 2.00 817.50 1,635.00
p. 30AT, 60AF, 2 pole, 240 VAC SET 35.00 735.00 25,725.00
No. of
Designation No. of Hour/s Hourly Rate Amount (PhP)
A1. Person/s
Labor
a. 18 Watts surface mounted Led Square Panel set 247.00 1,100.00 271,700.00
b. for indoor use
1-Heavy duty 10 watts circular lamp set 83.00 500.00 41,500.00
for outdoor use
1-Heavy duty 10 watts circular lamp set 50.00 500.00 25,000.00
c. 18 watts recessed led lighting square panel set 23.00 288.00 6,624.00
d. Heavy duty 98 watts recessed mount led panel light set 28.00 3,158.00 88,424.00
e. 2-20 watts emergency light set 11.00 1,600.00 17,600.00
f. 20 watts ceiling mounted emergency light set 97.00 700.00 67,900.00
g. ceiling mounted exhaust fan set 31.00 1,000.00 31,000.00
h. recessed led stair step light fixture set 10.00 550.00 5,500.00
i. concealed led strip light set 5.00 1,050.00 5,250.00
j. decorative light fixture set 1.00 50,000.00 50,000.00
k. ceiling mounted fan with speed control set 11.00 5,000.00 55,000.00
a. 18 Watts surface mounted Led Square Panel set 247.00 1,100.00 271,700.00
b. for indoor use
1-Heavy duty 10 watts circular lamp set 83.00 500.00 41,500.00
for outdoor use
1-Heavy duty 10 watts circular lamp set 50.00 500.00 25,000.00
c. 18 watts recessed led lighting square panel set 23.00 288.00 6,624.00
d. Heavy duty 98 watts recessed mount led panel light set 28.00 3,158.00 88,424.00
e. 2-20 watts emergency light set 11.00 1,600.00 17,600.00
f. 20 watts ceiling mounted emergency light set 97.00 700.00 67,900.00
g. ceiling mounted exhaust fan set 31.00 1,000.00 31,000.00
h. recessed led stair step light fixture set 10.00 550.00 5,500.00
i. concealed led strip light set 5.00 1,050.00 5,250.00
j. decorative light fixture set 1.00 50,000.00 50,000.00
k. ceiling mounted fan with speed control set 11.00 5,000.00 55,000.00
No. of
Designation No. of Hour/s Hourly Rate Amount (PhP)
A1. Person/s
Labor
a. Equipment For Fire Alarm, Control Panel set 1.00 1,850.00 1,850.00
b. Manual Pull Switch set 9.00 1,610.00 14,490.00
c. Bell, Vibrating Type set 9.00 1,400.00 12,600.00
d. Equipment For Fire Alarm, Smoke Detector Pcs 69.00 950.00 65,550.00
e. Consumables (5% of Materials) 4,724.50
a. Equipment For Fire Alarm, Control Panel set 1.00 1,850.00 1,850.00
b. Manual Pull Switch set 9.00 1,610.00 14,490.00
c. Bell, Vibrating Type set 9.00 1,400.00 12,600.00
d. Equipment For Fire Alarm, Smoke Detector Pcs 69.00 950.00 65,550.00
e. Consumables (5% of Materials) 4,724.50