Inhouse Production Time in Work Scheduling View

Uploaded by

Khadeer Ahamed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
151 views21 pages

Inhouse Production Time in Work Scheduling View

Uploaded by

Khadeer Ahamed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 21

11/22/24, 9:36 PM Inhouse Production time in work scheduling view is...

- SAP Community
m
m
Products and Technology Groups Partners Topics Events What's New Get Started Explore SAP
u
ni
t
y
SAP Community  Products and Technology  Enterprise Resource Planning  ERP Q&A  Inhouse Production time in work scheduling view is...

Q&A  What are you looking for today?

Options

Inhouse Production time in work scheduling view is not getting Ask A Question
assigned in Production order
Type your question here...


former_member220469 Participant
on ‎2013 Oct 24
Continue

 0 Kudos  2,164

SAP Managed Tags: MAN Production Planning (PP)


Recommendations

Dear all,  work schedulling view 


 ‎2023 Feb 20

I have maintained the Setup time , Inter operation time , Processing  External procure,
inhouse produce and
time in the work scheduling view in the material master for a material, I am not  subcontract ... 
using Schedule margin key for the production order scheduling. I have not updated ‎2023 Jun 03
any setup / wait / queue time in the routing also. Scheduling type for the Production
https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 1/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community

order control key is "Backwards" . When I create the Production order the dates  Minimum Viable
are getting scheduled in todays date ie it is not getting with the number of days  product 
‎2023 Aug 04
given in the Material master. Am I proceeding in the correct manner or should I
check for any configuration?  Production Overhead
 to assign to product 
‎2016 Jun 11
Please solve the issue
 Define and assign
status profile in
J.Balakrishnan  production ord... 
‎2012 Sep 13

Know the answer? Need more details?


Help others by sharing your Request clarification before
knowledge. answering. Related Content
Discrepancy between PO and SO
Answer Comment
items while adding / change in
Quantities not reflecting in SO. 
in Enterprise Resource Planning Q&A an
 Replies (0) hour ago

Damaged label in warehouse and


Accepted Solutions (0) need to print one single product
label 
in Enterprise Resource Planning Q&A 3
 Answers (3) hours ago

Use product group fields in a pricing


access sequence for service orders 
Anupam1143  in Enterprise Resource Planning Blogs by
‎2013 Oct 24 SAP 9 hours ago
Active Contributor

https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 2/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community

Work Order creation using Migration


Cockpit 
 0 Kudos in Enterprise Resource Planning Blogs by
SAP 10 hours ago

Hi,
Recommendation-Assisted Sales
Order Creation - Part 3: Auto

When you create Production order manually through CO01 it will always take routing
Training with Turnkey 
in Enterprise Resource Planning Blogs by
time which you have defined in Routing. SAP yesterday

Check this link:


Top Q&A Solution Author
http://help.sap.com/saphelp_46c/helpdata/en/f4/7d297144af11d182b40000e829fbfe/
content.htm SAPSupport  107

Regards, Harish_Vatsa  19

Anupam Sharma
DominikTylczyn  7

 You must be a registered user to add a comment. If you've already


registered, sign in. Otherwise, register and sign in.
Edrilan_Berisha  7
Comment

 Replies (3) Enda  6


former_member220469 
Participant ‎2013 Oct 25

https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 3/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community

matjazmoser  5
 0 Kudos

Vivek_Savant  4
Dear shyam,

Thank you, but what is the purpose of the In house production time in AndreasMuno  3
the work scheduling view and when system will consider this settings.

2. Which lead time will system consider if I have maintained the Inhouse
HenrikeGrötecke  3
production time in MRP 2 view and if I have maintained setup, processing time in
work scheduling view. What is the difference between these times and which will
be preferred by MRP run and also what is the Purpose of T-Code - CA97N
Kangkana  3

Kindly solve the query View all

J.Balakrishnan

Latest Posts
Re: Finite Scheduling not
working during productio... 

Former Member
‎2013 Oct 25
Authorization for repl. model
&1 and outbound impl... 

 0 Kudos Re: Sec 603 automatically


move catch-up contributi... 

https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 4/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community

Hi Balakrishnan, Re: how to Change default


browser in SAP Business ... 

The In-House Production time in MRP2 / Workscheduling view is used just for Re: how to Change default
browser in SAP Business ... 
planning purpose."

View all
"Use

The system requires the in-house production time to determine the planned
dates for planned orders in materials planning."

It shall determine you the planned dates but not the actual dates.

If you want to determine the actual dates then the system checks for the values
maintained in the Standard Value Key Values from Routing.

CA97N tcode is for calculating the In-House Production time and update the field
In-House production Time automatically into the Material Master from Routing. By
executing this transaction your In-house production time in Material master and
Routing are one and the same.

Hope this answer your question.

Regards,

Shyam

https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 5/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community

Caetano 
‎2013 Oct 26
Product and Topic Expert

 0 Kudos

Hello Balakrishnan

As already mentioned on this thread, on transaction CO01 the routing will always be exploded and the in-

house production time is not considered.

Running CA97N will only make the in-house production time match the routing.

BR

Caetano


Former Member
‎2013 Oct 24

https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 6/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community

 0 Kudos

There are 4 dates in Production Order header screen.

Basic start/ Basic Finish , Scheduled start/Scheduled finish.

You cannot prevent system from reading routing while production order creation.
Routing will be used to calculate Schedule start & Schedule finish.

This is how system works.

1: it will determine date on which production order must be finished after deducting
SD lead times.

2: that date is copied to Basic finish date & Scheduled Finish date(Note System has
hrs for scheduled finish , while basic finish donot have any hrs)

3:System will determine work center of last operation & copy end time of workcenter
on that day next to schedule finish date.

4: Last operation times are deducted from that date & start time of set up is
calculated.

https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 7/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community

5: Process repetes for all operation till it reaches first operation Set up time. It is
copied to schedule start date/time.

6: System will deduct material master lead time ( there is qty in Work scheduling
view, so it will calculate prorated lead time) from Basic finish time & calculate Basic
start time.

7: System will switch to forward scheduling , if start time calculated are in past+
allowed days in past setting.

8: Whole process of calculating timing will be repeted in forward schedule manner.

If you want to use only material master time, you can use Basic start & Basic Finish
date for all your reporting & ignore Schedule start & schedule finish dates.

Hope it helps,

Jatin

 You must be a registered user to add a comment. If you've already


registered, sign in. Otherwise, register and sign in.

Comment

 Replies (2)
https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 8/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community

former_member220469 
‎2013 Oct 25
Participant

 0 Kudos

Sir,

Thank you. Can you please explain with simple example


Former Member
‎2013 Oct 25

 0 Kudos

Hi Balakrishna,

There are two types of scheduling. They are

1) Basic Scheduling

2) Lead Time scheduling.

https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 9/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community

Basic Scheduling: When you run the MRP and when you select Basic Scheduling,
the system will consider the In-House production days and will calculate your
basic start and finish dates. Basic scheduling doesn't need your Routing to
calculate the basic start and finish date as it completely depends on the Material
master settings.

Lead Time Scheduling: When you run the MRP with Lead Time scheduling, the
system calculates the dates based on the values (Setup , Run , Break times etc)
assigned to standard value keys in routing for the corresponding Work center.

As a result of MRP run and scheduling type the planned order dates are
calculated and when you convert your Planned orders to Production orders the
same dates shall be updated.

If you create the Production Orders manually then based on the scheduling type
(forward,backward,current date) it calculates the dates based on the values
maintained in the routing for each operations

Regards,

Shyam

https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 10/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community


Former Member
‎2013 Oct 24

 0 Kudos

Hi,

Setup, machine and other times to be maintained in routing only. After that, use tcode
CA97/ CA97N to update these values in material master work scheduling view. This
step is required to minimise the issue raised during scheduling when you compare
basic date scheduling and lead time scheduling.

Regards,

Dharma

 You must be a registered user to add a comment. If you've already


registered, sign in. Otherwise, register and sign in.

Comment

 Replies (9)
former_member220469 
Participant ‎2013 Oct 25

 0 Kudos

https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 11/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community

Sir,

As you suggested, I have updated the Machine and setup time in the
routing and I have not updated the queue time and wait time in the routing. When
I executed the material in CA97N with indicator "Direct update" and output is
appearing with 0. It is not getting updated

Please resolve this issue


Former Member
‎2013 Oct 25

 0 Kudos

Hi,

Kindly check with tcode CA97 and activate Update material master directly.

After material master update, system shows timings in 'Days' in work scheduling
view.

https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 12/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community

Regards,

Dharma

 Capture1.PNG 
 Capture2.PNG 

former_member220469 
‎2013 Oct 25
Participant

https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 13/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community

 0 Kudos

Sir,

I tried the same thing , for a material I have maintained the setup, machine
time and also with queue, wait time in routing. I executed for the material in
CA97N. But it is not getting updated in the material master. Please check whether
am I correct

former_member184737 
Active Contributor ‎2013 Oct 25

 0 Kudos

Hi Balakrishnan,

After run the CA97N, system give you a log information how many
materials are ran in which is how many with errors like that. Please check the log
information where you can check the setup and processing time also. If your
value too low against your routing base qty value system will display with zero
value only (like .0003 Hr/Min). In this case you have to create/change your routing
base qty with more value.kindly check the value you have maintained in routing

https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 14/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community

with the base qty value. The another main reason is "Direct Update" indicator, as
you said that you have already activated that indicator. So, please check the
values you have maintain in your routing against the material.

As per our expert Mr.Anupam suggestion, system will consider only "in-house
production days" in MRP2 view when your are creating production order
manually. System will consider the values which you have updated in "Work
scheduling" view will be considered only if you create/generate production order
through MRP.

Thanks.

 CA97N-log.png 

former_member220469 
‎2013 Oct 26
Participant

https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 15/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community

 0 Kudos

Dear sir,

Thank you I understood, but I have an issue in CA97N,

For a material, I have created routing with only Machine time as 2 hrs for the base
quantity of 1 Ea, when I executed the T-Code - CA97N, Processing time has been
calculated as 0.8 hrs. In my routing I have not maintained any setup / queue time.
Can any one tell me how Processing time has been calculated ???

J.Balakrishnan

former_member220469 
‎2013 Oct 26
Participant

 0 Kudos

Sorry, the Processing time has been calculated as 0.08 days

https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 16/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community

former_member184737 
‎2013 Oct 26
Active Contributor

 0 Kudos

Hi Balakrishnan,

As per your above value, system calculate the processing time based on
your machine time and assembly's base qty. You have also consider your work
center capacity, utilization rate, break time, operating time and No. of individual
capacities.

1 day = 24 Hrs, Machine time = 2 Hrs, Processing time = (1/24)*2*1( Assembly


base qty in routing, in your case it's 1 EA ) So, processing time as 0.083333 days.

The processing time depends on the order quantity. Please check this value with
different base qty, it will help to understand the calculation in better.

Please refer http://scn.sap.com/thread/3443034

Thanks

https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 17/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community

former_member220469 
‎2013 Oct 27
Participant

 0 Kudos

Dear sir,

Thank you, I understood the concept and I have created the routing
and updated the In house production time in master by CA97N as given below,

Operating time in scheduling tab in Work center = 16 hrs

The below details are given in routing,

Machine time = 2 hrs

Labor time = 2 hrs

Setup time = 5 hrs

Base quantity = 1 Each

As a result of executing in CA97N, the below results where shown,

Setup time = ( 1 / 16 * 5 * 1 ) = 0.31 days

https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 18/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community

Processing time = ( 1 / 16 * 2 * 1) = 0.125 = 0.135

Interoperation time = 2 days ???????????????????????????

My issue is , how the system has calculated Interoperation time and why
the system has not considered the Labor time in this calculation.????

Will the system consider the routing formula anywhere ???

Is my understanding is correct ???

Please resolve the issue

J.Balakrishnan

former_member184737 
‎2013 Oct 28
Active Contributor

 0 Kudos

Hi Balakrishnan,

https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 19/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community

Please Check the formula in scheduling tab for your work center. I hope
you used the standard formula "SAP002" for processing formula. If you want to
calculate processing time as per your requirement, you can create your own
formula and will assign it to work center scheduling tab formula fields.

standard formula

SAP002 = Machine Time * Operation quantity / Base quantity / Operation


splits

Please refer http://scn.sap.com/thread/1665431

http://help.sap.com/saphelp_erp60_sp/helpdata/en/55/67049b95d711d3b6fb000
0e8359890/content.htm

It will give you some idea.Please check it and test with your data.

Thanks

Privacy Terms of Use

https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 20/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community