Inhouse Production Time in Work Scheduling View
Inhouse Production Time in Work Scheduling View
- SAP Community
m
m
Products and Technology Groups Partners Topics Events What's New Get Started Explore SAP
u
ni
t
y
SAP Community Products and Technology Enterprise Resource Planning ERP Q&A Inhouse Production time in work scheduling view is...
Options
Inhouse Production time in work scheduling view is not getting Ask A Question
assigned in Production order
Type your question here...
former_member220469 Participant
on 2013 Oct 24
Continue
0 Kudos 2,164
I have maintained the Setup time , Inter operation time , Processing External procure,
inhouse produce and
time in the work scheduling view in the material master for a material, I am not subcontract ...
using Schedule margin key for the production order scheduling. I have not updated 2023 Jun 03
any setup / wait / queue time in the routing also. Scheduling type for the Production
https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 1/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community
order control key is "Backwards" . When I create the Production order the dates Minimum Viable
are getting scheduled in todays date ie it is not getting with the number of days product
2023 Aug 04
given in the Material master. Am I proceeding in the correct manner or should I
check for any configuration? Production Overhead
to assign to product
2016 Jun 11
Please solve the issue
Define and assign
status profile in
J.Balakrishnan production ord...
2012 Sep 13
https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 2/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community
Hi,
Recommendation-Assisted Sales
Order Creation - Part 3: Auto
When you create Production order manually through CO01 it will always take routing
Training with Turnkey
in Enterprise Resource Planning Blogs by
time which you have defined in Routing. SAP yesterday
Regards, Harish_Vatsa 19
Anupam Sharma
DominikTylczyn 7
https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 3/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community
matjazmoser 5
0 Kudos
Vivek_Savant 4
Dear shyam,
Thank you, but what is the purpose of the In house production time in AndreasMuno 3
the work scheduling view and when system will consider this settings.
2. Which lead time will system consider if I have maintained the Inhouse
HenrikeGrötecke 3
production time in MRP 2 view and if I have maintained setup, processing time in
work scheduling view. What is the difference between these times and which will
be preferred by MRP run and also what is the Purpose of T-Code - CA97N
Kangkana 3
J.Balakrishnan
Latest Posts
Re: Finite Scheduling not
working during productio...
Former Member
2013 Oct 25
Authorization for repl. model
&1 and outbound impl...
https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 4/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community
The In-House Production time in MRP2 / Workscheduling view is used just for Re: how to Change default
browser in SAP Business ...
planning purpose."
View all
"Use
The system requires the in-house production time to determine the planned
dates for planned orders in materials planning."
It shall determine you the planned dates but not the actual dates.
If you want to determine the actual dates then the system checks for the values
maintained in the Standard Value Key Values from Routing.
CA97N tcode is for calculating the In-House Production time and update the field
In-House production Time automatically into the Material Master from Routing. By
executing this transaction your In-house production time in Material master and
Routing are one and the same.
Regards,
Shyam
https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 5/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community
Caetano
2013 Oct 26
Product and Topic Expert
0 Kudos
Hello Balakrishnan
As already mentioned on this thread, on transaction CO01 the routing will always be exploded and the in-
Running CA97N will only make the in-house production time match the routing.
BR
Caetano
Former Member
2013 Oct 24
https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 6/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community
0 Kudos
You cannot prevent system from reading routing while production order creation.
Routing will be used to calculate Schedule start & Schedule finish.
1: it will determine date on which production order must be finished after deducting
SD lead times.
2: that date is copied to Basic finish date & Scheduled Finish date(Note System has
hrs for scheduled finish , while basic finish donot have any hrs)
3:System will determine work center of last operation & copy end time of workcenter
on that day next to schedule finish date.
4: Last operation times are deducted from that date & start time of set up is
calculated.
https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 7/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community
5: Process repetes for all operation till it reaches first operation Set up time. It is
copied to schedule start date/time.
6: System will deduct material master lead time ( there is qty in Work scheduling
view, so it will calculate prorated lead time) from Basic finish time & calculate Basic
start time.
7: System will switch to forward scheduling , if start time calculated are in past+
allowed days in past setting.
If you want to use only material master time, you can use Basic start & Basic Finish
date for all your reporting & ignore Schedule start & schedule finish dates.
Hope it helps,
Jatin
Comment
Replies (2)
https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 8/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community
former_member220469
2013 Oct 25
Participant
0 Kudos
Sir,
Former Member
2013 Oct 25
0 Kudos
Hi Balakrishna,
1) Basic Scheduling
https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 9/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community
Basic Scheduling: When you run the MRP and when you select Basic Scheduling,
the system will consider the In-House production days and will calculate your
basic start and finish dates. Basic scheduling doesn't need your Routing to
calculate the basic start and finish date as it completely depends on the Material
master settings.
Lead Time Scheduling: When you run the MRP with Lead Time scheduling, the
system calculates the dates based on the values (Setup , Run , Break times etc)
assigned to standard value keys in routing for the corresponding Work center.
As a result of MRP run and scheduling type the planned order dates are
calculated and when you convert your Planned orders to Production orders the
same dates shall be updated.
If you create the Production Orders manually then based on the scheduling type
(forward,backward,current date) it calculates the dates based on the values
maintained in the routing for each operations
Regards,
Shyam
https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 10/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community
Former Member
2013 Oct 24
0 Kudos
Hi,
Setup, machine and other times to be maintained in routing only. After that, use tcode
CA97/ CA97N to update these values in material master work scheduling view. This
step is required to minimise the issue raised during scheduling when you compare
basic date scheduling and lead time scheduling.
Regards,
Dharma
Comment
Replies (9)
former_member220469
Participant 2013 Oct 25
0 Kudos
https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 11/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community
Sir,
As you suggested, I have updated the Machine and setup time in the
routing and I have not updated the queue time and wait time in the routing. When
I executed the material in CA97N with indicator "Direct update" and output is
appearing with 0. It is not getting updated
Former Member
2013 Oct 25
0 Kudos
Hi,
Kindly check with tcode CA97 and activate Update material master directly.
After material master update, system shows timings in 'Days' in work scheduling
view.
https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 12/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community
Regards,
Dharma
Capture1.PNG
Capture2.PNG
former_member220469
2013 Oct 25
Participant
https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 13/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community
0 Kudos
Sir,
I tried the same thing , for a material I have maintained the setup, machine
time and also with queue, wait time in routing. I executed for the material in
CA97N. But it is not getting updated in the material master. Please check whether
am I correct
former_member184737
Active Contributor 2013 Oct 25
0 Kudos
Hi Balakrishnan,
After run the CA97N, system give you a log information how many
materials are ran in which is how many with errors like that. Please check the log
information where you can check the setup and processing time also. If your
value too low against your routing base qty value system will display with zero
value only (like .0003 Hr/Min). In this case you have to create/change your routing
base qty with more value.kindly check the value you have maintained in routing
https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 14/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community
with the base qty value. The another main reason is "Direct Update" indicator, as
you said that you have already activated that indicator. So, please check the
values you have maintain in your routing against the material.
As per our expert Mr.Anupam suggestion, system will consider only "in-house
production days" in MRP2 view when your are creating production order
manually. System will consider the values which you have updated in "Work
scheduling" view will be considered only if you create/generate production order
through MRP.
Thanks.
CA97N-log.png
former_member220469
2013 Oct 26
Participant
https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 15/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community
0 Kudos
Dear sir,
For a material, I have created routing with only Machine time as 2 hrs for the base
quantity of 1 Ea, when I executed the T-Code - CA97N, Processing time has been
calculated as 0.8 hrs. In my routing I have not maintained any setup / queue time.
Can any one tell me how Processing time has been calculated ???
J.Balakrishnan
former_member220469
2013 Oct 26
Participant
0 Kudos
https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 16/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community
former_member184737
2013 Oct 26
Active Contributor
0 Kudos
Hi Balakrishnan,
As per your above value, system calculate the processing time based on
your machine time and assembly's base qty. You have also consider your work
center capacity, utilization rate, break time, operating time and No. of individual
capacities.
The processing time depends on the order quantity. Please check this value with
different base qty, it will help to understand the calculation in better.
Thanks
https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 17/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community
former_member220469
2013 Oct 27
Participant
0 Kudos
Dear sir,
Thank you, I understood the concept and I have created the routing
and updated the In house production time in master by CA97N as given below,
https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 18/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community
My issue is , how the system has calculated Interoperation time and why
the system has not considered the Labor time in this calculation.????
J.Balakrishnan
former_member184737
2013 Oct 28
Active Contributor
0 Kudos
Hi Balakrishnan,
https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 19/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community
Please Check the formula in scheduling tab for your work center. I hope
you used the standard formula "SAP002" for processing formula. If you want to
calculate processing time as per your requirement, you can create your own
formula and will assign it to work center scheduling tab formula fields.
standard formula
http://help.sap.com/saphelp_erp60_sp/helpdata/en/55/67049b95d711d3b6fb000
0e8359890/content.htm
It will give you some idea.Please check it and test with your data.
Thanks
https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 20/21
11/22/24, 9:36 PM Inhouse Production time in work scheduling view is... - SAP Community
Trademark Support
Cookie Preferences
Follow
https://community.sap.com/t5/enterprise-resource-planning-q-a/inhouse-production-time-in-work-scheduling-view-is-not-getting-assigned-in/qaq-p/9778518 21/21