DCM Learning - Project Management - Formulas To Know
DCM Learning - Project Management - Formulas To Know
Formulas
Project Management Formulas
________________________________________________________________________________________
Variance of an Activity
1
Project Management Formulas
________________________________________________________________________________________
In order to calculate Float (Slack) of an activity, Late Start (LS) and Early Start (ES) or
Late Finish (LF) and Early Finish (EF) values of the activity are determined first.
● Earned Value = EV
● Planned Value = PV
● Actual Cost = AC
● Cost Variance = CV
● Schedule Variance = SV
● Cost Performance Index = CPI
● Schedule Performance Index = SPI
● Budget at Completion = BAC
● Estimate to Complete = ETC
● Estimate at Completion = EAC
● Variance at Completion = VAC
● To-Complete Performance Index = TCPI
2
Project Management Formulas
________________________________________________________________________________________
EAC value can be found by 3 different approaches using EV, SPI and CPI values.
Approach #1: assumes that all future ETC work will be accomplished at the budgeted
rate.
3
Project Management Formulas
________________________________________________________________________________________
Approach #2: assumes that cost performance achieved till now is expected to continue
in the future.
Approach #3: assumes that ETC work will be performed at an efficiency rate that
considers both the cost and schedule performance indices.
Approach #1:
Approach #2:
4
Project Management Formulas
________________________________________________________________________________________
● Present Value = PV
● Future Value = FV
● Interest rate = r
● Number of periods = n
5
Project Management Formulas
________________________________________________________________________________________
6
Project Management Formulas
________________________________________________________________________________________