E) Course Outcomes :
CO-1 Prepare estimate of R.C.C. structures i.e. slab, beam, column and column footing, staircase.
CO-2 Prepare estimate of steel structures i.e. beam, column and column footing, and roof
trusses.
CO-3 Prepare estimates of culvert and bridges.
CO-4 Prepare estimates of water supply and sanitary engineering works.
CO-5 a. Do the valuation and rent fixation of different type of buildings.
b. Prepare estimates for repairing works for dismantling, demolishing and repair works in
buildings.
F) Scheme of Studies:
Board of Course Scheme of Studies Credit
Course
Study Code (Hours/Week) L+T+P/2
L T P
Civil 2020671 Quantity Surveying and 3 - 2 4
Engineering (020) Costing-II
L- Lecture, T- Tutorial, P- Practical,
Legend: Lecture (L) CI: Classroom Instruction (Includes different instructional strategies i.e. Lecture and
others).
Practical (P) LI: Laboratory Instruction (Includes Practical performances in laboratory workshop, field or
other locations using different instructional strategies).
Tutorial (T) SL: Self Learning
G) Scheme of Assessment:
Scheme of Examinations
Board of Course
Course Title Theory Practical Total
Study Code
ESE CT TA ESE TA Marks
Civil 2020671 Quantity Surveying
Engineering (020) and Costing-II 70 20 30 40 60 220
ESE: End Semester Exam, CT: Class Test, TA: Teachers Assessment
Legend - PRA : Process Assessment, PDA : Product Assessment
H) Course-Curriculum Detailing:
This course curriculum detailing depicts learning outcomes at course level and session level and their attainment
by the students through Classroom Instruction (CI), Laboratory Instruction (LI), Sessional Work (SW) and Self
Learning (SL). Students are expected to demonstrate the attainment of Session Outcomes (SOs) and finally
Course Outcomes (COs) upon the completion of course.
Convert unit of the given physical quantity from one unit system to other.
CO-1 Prepare estimate of R.C.C. structures i.e. slab, beam, column and column footing, staircase.
(Approx. Hrs: CI+LI = 9+10)
Session Outcomes Laboratory Instruction (LI) Class room Instruction (CI) Self Learning (SL)
(SOs)
SO1.1 Identify items of
LI 1.1 Estimate the quantities Unit-1 Estimate of R.C.C. SL1.1 Study
work in RCC structure and prepare abstract of cost structures description of
and prepare schedule for RCC slab from given 1.1 Items of work in RCC PCC and RCC
of bars. working drawing. structures, bar bending work from CG
SO1.2 Prepare LI 1.2 Estimate the quantities schedule. PWD SOR for
estimate of RCC slab and prepare abstract of cost 1.2 Estimate of slab buildings.
and beam. for RCC beam from given 1.3 Estimate of beam
SO1.3 Prepare working drawing. 1.4 Estimate of T-beam
estimate of RCC stair LI 1.3 Estimate the quantities 1.5 Estimate of RCC column
case. and prepare abstract of cost with footing.
SO1.4 Prepare for RCC staircase from given 1.6 Preparation of abstract of
estimate of RCC working drawing. cost above estimates.
column and footing. LI 1.4 Estimate the quantities
and prepare abstract of cost
for RCC column and footing
from given working drawing.
SW-1 Suggested Sessional Work (SW):
a. Assignments:
1. Explain the method of estimation of RCC work.
2. Explain bar bending schedule and calculation of quantity of steel reinforcement.
3. Numerical problems on estimate of RCC structure.
b. Mini Project
1. Prepare the estimate of RCC framed building (one BHK) from given working drawing using suitable
software for estimation.
SO2.1 Identify items of LI 2.1 Estimate the quantities Unit-2 Estimate of Steel SL2.1 Study
work in steel structure and prepare abstract of cost Structures description of steel
and prepare schedule of for steel beam and column 2.1 Items of work in steel work from CG PWD
bars. with base from given working structure. SOR for building.
SO2.2 Prepare estimate drawing. 2.1Estimate of steel beam and
of steel beam and LI 2.2 Estimate the quantities column (Stanchion) with base.
column. and prepare abstract of cost 2.2 Estimate of steel truss.
SO2.3 Prepare estimate for steel truss from given 2.3 Estimate of roof covering
of steel truss. working drawing. materials
SO2.4 Prepare estimate LI 2.3 Estimate the quantities 2.4 Estimate of GIC roof and
of GIC roof and AC roof. and prepare abstract of cost AC roof.
for GIC roof and AC roof from 2.5 Estimate of steel frames
given working drawing. for doors and windows.
2.6 Preparation of abstract of
cost above estimates
SW-2 Suggested Sessional Work (SW) :
a. Assignments:
1. Explain the method of estimation of steel work.
2. Numerical problems on estimate of steel structure.
b. Mini Project
1. Prepare the estimate of GIC roof of workshop with steel truss from given working drawing using
suitable software for estimation.
a. Assignments:
1. State the items of work in culverts.
2. Numerical problems on estimate of bridge and culverts.
b. Mini Project
1. Visit a bridge construction site and study the estimate of the project.
CO-4 Prepare estimates of water supply and sanitary engineering works for building.
(Approx. Hrs: CI+LI = 10+10)
Session Outcomes Laboratory Instruction (LI) Class room Instruction (CI) Self Learning (SL)
(SOs)
SO 4.1 Identify items LI 4.1 Estimate the UNIT-4 Estimates of Water SL4.1 Study CG
of water supply work quantities and prepare Supply and Sanitary Engineering PWD SOR for
for a building. abstract of cost for water Works for Buildings Water Supply and
SO4.2 Identify items s u p p ly w o r k s in b u ild in gs 4 .1 Ite m s o f wo rk in W at e r Su p ply Sanitary
of sanitary work for a fr o m giv e n w o rk in g dr aw ing. an d S anit ary E ng in e erin g W o rks E ngineering
building. LI 4.2 Estimate the for Buildings. Works for
quantities and prepare 4.2 Detailed estimate of water Buildings
SO4.3Prepare abstract of cost for sanitary supply for building work.
estimate of water works in buildings from
supply works in 4.3Detailed estimate of sanitary
given working drawing. works for building work.
buildings. LI 4.3 Estimate the
4.4Estimate of S.W., R.C.C. and
SO 4.4 Prepare quantities and prepare
H.D.P.E pipe line.
estimate of sanitary in abstract of cost for septic
buildings. tank with soak pit from 4.5Estimate of septic tank
SO4.5 Prepare given working drawing. 4.6Estimate of manhole.
estimate of septic L I 4 .4 E st im a t e t h e 4.7 Preparation of abstract of cost
tank. quantities and prepare above estimates.
abstract of cost for manhole
SO4.6Prepare
from given working drawing.
estimate of drainage
LI 4.5 Estimate the
pipe.
quantities and prepare
abstract of cost for HDPE
drainage pipe from given
working drawing.
a. Assignments:
1. State the items of work in Water Supply and Sanitary Engineering Works for Buildings..
2. Numerical problems on estimate of Water Supply and Sanitary Engineering Works for Buildings..
b. Mini Project
1. Prepare the detailed estimate of sanitary and water supply works of building from given plan.
Legend: CI: Classroom Instruction (Includes different instructional strategies i.e. Lecture (L) and Tutorial (T) and
others), LI : Laboratory Instruction (Includes Practical performances in Laboratory, Workshop, field or
other locations using different instructional strategies) SL: Self Learning
a. Assignments:
1. Define Gross income, Net income, Out goings.
2. Explain obsolescence.
3. Differentiate annuity and sinking fund.
4. What is depreciation? State the methods of calculating depreciation.
5. Describe rent fixation of building.
6. Solve numerical problems on valuation and rent fixation.
7. Solve numerical problems on dismantling, demolishing and repair works in buildings.
b. Project:
1. Visit a old building and prepare estimate for dismantling, demolition and repair for addition,
alternation and maintenance.
c. Mini Project: Visit nearby godowns/plants/factories and observe the types of trusses used and prepare a
report regarding selection of type of truss.