Capacity Planning
Capacity Planning
Capacity Planning
Capacity Planning
• Capacity is the upper limit or ceiling on the
load that an operating unit can handle.
• Capacity is the maximum rate of output of a process or
a system
1
20/1/2022
Importance of Capacity
Decisions
CAPACITY DECISIONS ARE STRATEGIC
2
20/1/2022
Actual output
Efficiency =
Effective capacity
Actual output
Utilization =
Design capacity
Both measures expressed as percentages
Efficiency/Utilization Example
Design capacity = 50 units/day
Effective capacity = 40 units/day
Actual output = 36 units/day
3
20/1/2022
Determinants of Effective
Capacity
Strategy
• Strategies plans for achieving
organizational goals
– Vision
– Mission
– Goal
– Strategy (It provides focus for decision
making)
– Tactics (the methods and actions used to
accomplish strategies)
– Operations
191
4
20/1/2022
Strategy Formulation
• Capacity strategy for long-term demand
• Demand patterns
• Growth rate and variability
• Facilities
– Cost of building and operating
• Technological changes
– Rate and direction of technology changes
• Behavior of competitors
• Availability of capital and other inputs
193
5
20/1/2022
Make or Buy
Make - Produce good or provide service itself
Buy – Outsource from another organizations
Factors:
• Available capacity
• Expertise
• Quality considerations
• Nature of demand
• Cost
• Risk
6
20/1/2022
Developing Capacity
Alternatives
1.Design flexibility into systems
2.Take stage of life cycle into account
3.Take a “big picture” approach to capacity
changes
4.Prepare to deal with capacity “chunks”
(mass/large)
5.Attempt to smooth out capacity
requirements
6.Identify the optimal operating level ( in
terms of cost of unit cost of output)
196
197
7
20/1/2022
Evaluating Alternatives
Production units have an optimal rate of output for minimal cost.
Minimum cost
0 Optimal
Rate Rate of output
198
Economies of Scale
• Economies of scale
– If the output rate is less than the optimal
level, increasing output rate results in
decreasing average unit costs
• Diseconomies of scale
– If the output rate is more than the optimal
level, increasing the output rate results in
increasing average unit costs
199
8
20/1/2022
Evaluating Alternatives
Minimum cost & optimal operating rate are
functions of size of production unit.
Small
plant Medium
plant Large
plant
0 Output rate
200
201
9
20/1/2022
Cost-Volume Relationships
Amount ($)
0
Q (volume in units)
202
Cost-Volume Relationships
B. Total revenue increases linearly with output
Amount ($)
0
Q (volume in units)
203
10
20/1/2022
Cost-Volume Relationships
C. Profit = TR – TC
(At BEP, TR = TC)
Amount ($)
0 BEP units
Q (volume in units) 204
Break-even Analysis
205
11
20/1/2022
Break-even Analysis
• Profit = TR – TC
= (Q X r) - [FC + VC]
= (Q X r) - [FC + (Q X v)]
= Qr - FC – Qv
= Qr - Qv - FC
= (r-v)Q – FC
𝑷𝒓𝒐𝒇𝒊𝒕 𝑭𝑪
Q=
𝒓 𝒗
206
Break-even Analysis
• Break-even point (BEP) is the point at which total
cost and total revenue are equal. That means profit
is equal to zero. There no profit, no loss at this
point.
• TR = TC
=> Q X r = FC + VC
Q X r = FC + (Q X v)
Qr – Qv = FC
=> Q( r – v) = FC
=> Q =
BEPx = BEP$ = Xr
207
12
20/1/2022
Break-even Analysis
208
Figure: Break-even Chart
13
20/1/2022
Break-even Analysis
Problem-1
Normal production level of a company is 60 per
month, but due to significantly improved economic
conditions, now the production is increased at 72
per month. Fixed cost is $2400 per month,
Variable cost per unit is $35 and Revenue per unit
is $75.
(a) Calculate the breakeven point.
(b) What is the current profit level per month for
the facility?
(c) What will be the revenue if monthly production
level reduced to 45 units and others remain
constant? 210
Break-even Analysis
Here, Fixed cost, FC = $2400
Variable cost per unit, v = $35
Revenue per unit, r = $75
(a)BEPx = = = 60 units
(b) Current profit, p = Q × (r - v) - FC
= 72 × ($75 - $35) - $2400
= $480
(c) We know, p = Q × (r - v) – FC
For Q = 45 units,
$480 = 45 × (r - $35) - $2400
=> $480 + $2400= 45 × (r - $35)
=>$2880/45 = r - $35
⸫ revenue, r = $99 211
14
20/1/2022
Break-even Analysis
Problem-2
A firm produces radios with a fixed cost of $7000
per month and a variable cost of $5 per radio. If
radio sell for $8 each:
a) What is the break even point?
b) What output is needed to produce a profit of
$2000/month?
c) What is the profit or loss if 500 radios are
produced each week?
212
Break-even Analysis
213
15
20/1/2022
Break-even Analysis
Problem-3
214
Break-even Analysis
For any Q: TR = 8Q
For Q<=3000/month: TC = 7000 + 5Q
For Q>3000/month: TC = 7000 + 5(3000) + 10 (Q-3000)
= -8000 + 10Q
For Q<=3000/month: 7000 + 5Q = 8Q => Q= 2333/month
This is Q<=3000/month. So, it is a valid break-even point.
For Q>3000/month: -8000 + 10Q = 8Q => Q =4000/month
This is Q>3000/month. So, it is a valid break-even point.
215
16
20/1/2022
Resource Planning ,
Budgeting &
Cost Estimation
When you do not have enough capacity, basically you have two
alternatives:
Get more capacity
Change the MPS
217
17
20/1/2022
Capacity Planning
Capacity
Planning
Material
Requirement
Planning
218
18
20/1/2022
220
MRP Evolution
ERP
19
20/1/2022
ERP Systems
20
20/1/2022
Dependent demand
Quantity required varies with the production plans of other items
Component
Parent
21
20/1/2022
MRP Inputs
Authorized Other
master production sources
schedule of demand
Engineering
Inventory Inventory MRP Bills of
and process
transactions records explosion materials
designs
Material
requirements
plan
Bill of Materials
• A record of all components of an item
• Shows the parent-component relationship
• The usage quantities are derived from engineering and
process design
22
20/1/2022
LT = 1
B (3) C (1)
LT = 2 LT = 3
LT = 3 LT = 6 LT = 1 LT = 3
G (1)
LT = 3
Figure 15.19 – BOM for Product A
Copyright © 2010 Pearson Education, Inc.
Publishing as Prentice Hall.
23
20/1/2022
CRP MRP
• Deals with Workcenter • Deals with Part Number
• How much capacity need? • What is needed?
• When the capacity needed? • When the material is needed?
• Objective: • Objective:
Sufficient capacity Provide ‘right
availability materials/parts
‘where’ and ‘when’ ‘right time to right place’
needed to meet schedules for
to accomplish planned complete products
production
230
Budget &
Cost Estimation
A plan for allocating resources, especially, allocates
the scarce resources to various endeavors of
organization
After plan, First priority is to obtain resources to do work
Need to forecast
• resources required
• quantity and time required
• cost including price inflation
231
24
20/1/2022
• Top-Down
• Bottom-Up
Top-Down budget
• Managers estimate overall project cost as well as cost of major subprojects
• Lower levels breakdown the estimates for the specific tasks
• Mainly prepared based on “considerable past experience”
Bottom-Up budget
• Elemental tasks, schedules and individual budgets are constructed following WBS
• People related to work are consulted regarding times and budgets for accuracy
• Start with estimating in terms of resources, e.g., labor hr, material
232
Iterative budget
25
20/1/2022
Estimating cost
• Direct cost
• Overhead cost
• General & Administrative (G&A) cost
234
Time-phased budget
Committed
Costs
Scheduled
Actual
Project duration
235
26
20/1/2022
236
27