Pipe Culvert 22503
Pipe Culvert 22503
A
Micro Project Report
On
“Pipe Culvert ”
Under Course
Estimating and costing(22503)
Submitted by,
1.Darshan Gaikwad
2.Aditya Mhaske
3.Vedant Kakad
4.Vaibhav Vispute
Guided by
Mr. S.S.Sonawane
CERTIFICATE
This is to Certify that this Micro project report
“Pipe Culvert ”
Under Course
Estimating and costing (22503)
Submitted by,
1.Darshan Gaikwad
2.Aditya Mhaske
3.Vedant Kakad
4.Vaibhav Vispute
Title of Micro-Project
Pipe Culvert
The aim of this micro-project is to study the design, construction, and applications of pipe
culverts, focusing on their role in drainage systems, and evaluate their performance in
real-world scenarios.
3.0 Action Plan
**************
Annexure –II
PART B (Outcomes after Execution and)
Title of Micro-Project
Pipe Culvert
1. Research: Gathering information about pipe culverts, their designs, and materials.
2. Field Visit: Observing pipe culverts in existing infrastructure (if possible).
INDEX
6.1) INTRODUCTION
6.4) CONCLUSION
6.1 INTRODUCTION
CULVERT : Culverts are structures used to convey runoff from one side of the road to another
and are usually covered with embankment and composed of structural material around the entire
perimeter, although some are supported on spread footings with the streambed serving as the
bottom of the culvert. For economy and hydraulic efficiency, culvert should be designed to
operate with the inlet submerged during the flood flows, if conditions permit. Cross-drain are
those culverts and pipes that are used to convey runoff from one side of highway to another
ESTIMATION: For all engineering works it is required to know beforehand the probable cost
of construction know as the estimated cost. If the estimated cost is grater than the money
available, then attempts are made to reduced the cost by reducing the work or changing the
specification. From this the importance of estimate for engineers may be understood. In
preparing in estimate, the quantities of different items of work are calculated by simple
mensuration method and from these quantities the cost is calculated. The subject of estimating is
simple, nothing much to understand, but knowledge of drawing is essential. One who understand
and can read drawing may find out the dimension- length, breath, & height etc.
In preparing an estimate one has to go in to details of each items, big or small, nothing can be left
or missed.
Inaccuracy in preparing estimate, omission of items, change in designs improper rates etc.
• Box Culvert
• Arch Culvert
• Slab Culvert
• Hume Pipe Culvert
Hume Pipe Culverts provide low clearance, openings suitable for large waterways, and are more
aesthetic. They may also provide a greater hydraulic advantage to fishes at low flows and require
less road fill.
• Box Culvert
Box culverts are used to transmit water during brief runoff periods. These are usually used by
wildlife because they remain dry most of the year. They can have an artificial floor such as
concrete. Box culverts generally provide more room for wildlife passage than large pipe culverts.
Box culverts are usually made up of Reinforced Concrete (RCC).
• Arch Culvert
A pipe arch culvert is a round culvert reshaped to allow a lower profile while maintaining flow
characteristics. It is good for installations with shallow cover.
Materials used for arch culverts are RCC, Corrugated Metal or Stone Masonry.
•Slab Culvert
Slab culvert are used where the total load acting on it very large. In this case a slab culvert is
used.
It has a very large load carrying capacity as compared to pipe and box culvert
6.3 ESTIMATION & COSTING
Detailed Estimation:
Detailed estimate is an accurate estimate and consists of working out the quantities of each item
of works, and working the cost. The dimensions, length, breadth and height of each item are
taken out correctly from drawing and quantities of each item are calculated, and abstracting and
billing are done.
The details of measurements of each item of work are taken out correctly from plan and drawing
and quantities under each item are calculated in a tabular form named as details of measurement
form.
The cost of each item of work is calculated in a tabular form the quantities already computed and
total cost is worked out in abstract estimate form. The rates of different items of work are taken
as per schedule of rates or current workable rates for finished item of work.
7.0 CONCLUSION
Use culverts as wide as stream width Use same gradient as stream channel • Use same
alignment as stream channel • Single large culvert is better for debris passage than several
small ones • Flared ends improve efficiency
This micro-project facilitated the development of the following skills and learning outcomes: