Rate Analysis
Rate Analysis
Rate Analysis
The process of determining rate per unit of any work in Civil Engineering project like
earthwork, concrete work, brickwork, plastering, painting etc. is known as Analysis of
Rates or simply Rate Analysis. The rates of materials and labour vary from place to place
and hence the rates of different items of works also vary from place to place. The rates of
these works further help in determining cost of particular work and in turn cost of the
project.
The various factors that are involved in determining rate of any item, process or work are
mentioned below:
The analysis of rates is worked out for the unit payment of the particular item of work
under two heads: Materials and Labour.
Material cost
The rate of various materials as per specifications for the items under consideration can
be chalked out from market survey. The costs of materials are taken as delivered at site of
work. This is inclusive of:
The distance between the source of availability of material and construction site is known
as "Lead” and is expressed in Km. The cost of conveyance of material depends on lead.
This statement is required when a material is transported from a distant place, more than
8kms (5 miles). The lead statement will give the total cost of materials per unit item
including first cost, conveyance loading-unloading, stacking charges etc.
To obtain labour cost the number and wages of different categories of labourers, skilled
(Skilled 1st Class), semi-skilled (Skilled 2nd Class) and unskilled, required for each unit of
work should be known and this number is multiplied by the respective wage per day. The
labour charges can be obtained from the standard schedule of rates. 30% of the skilled
labour provided in the data may be taken as 1st class, remaining 70% as 2nd class.
The length of time required to do a certain piece of the work may vary according to the
skill and mental development of the workmen and working conditions to the particular
job.
This is the quantity of work which can be done by an artisan or skilled labour (with the
help of semiskilled and unskilled labours) of the trade working for 8 hours a day. The out-
turn of work per artisan varies according to the nature, size, height, situation, location etc.
Out-turn is more in larger cities, as the more specialized and experienced labours are
available, than the small cities and country sides.
The recommendation of All India Standard Schedule of Rates and various other govt.
reports are used to work out approximate quantity of labour required to prepare the
analysis of rates. IS: 7272 (part 1)-1974, provides recommendations for labour output
constants for building work which can be used to fix up the labour cost.
A typical labour output constant issued by National Building Organization is provided
bellow:
Miscellaneous cost
The cost of equipment and ordinary tools and plats and miscellaneous petty items
(sundries) are added to the specific item rate as lump-sum. A provision of 2.5 to 3 % of
the labour cost is made for such items. In certain tools and plants if it is difficult to
allocate their use for a particular item of rate; then the cost of such tools or plants may be
allocated to the over-head expenditure.
For big works and projects where it becomes necessary to use special types of equipment
like batching plants or WMM plant or dumpers or cranes for transportation of concrete
mix, provisions of an amount 1% to 1.5% of the estimated cost is provided in the estimate
under the head “special tools and plants”.
b) Water charges
For drinking purpose of the workers and for the work, arrangement of water is made
sinking tube well; bore well or from temporary connection from municipality. For this
purpose a provision of 1.5 to 2 % of total cost (Material + Labour+ Sundries) is made in
the estimate.
Overhead charges include general office expanses, rents, taxes, supervision and other cost
which are indirect expanses on the job. Expanses for small tools such as planks, ladders,
ropes and other hand tools are also included in the over-head charges. A provision of
2.5% to 5% is made in the rate analysis as overhead charge. Overhead charges can be
divided under two categories: General Overhead and job overhead.
General overhead:
These are the expanses made throughout the year irrespective to running works in hand.
These include:
These are the expanses indirectly incurred for the job or the project. These include:
o Salaries of personnel engaged for the work (Site engineers, Surveyors or site
office staff)
o Rent of temporary site office space, electricity, telephone and water bills
o Handling of materials
o Repairs, carriage and depreciation of T & P.
o Labour welfare, safety measures and insurance etc.
o Interest on investment
o Thept and other losses.
c) Contractor’s profit
Generally a provision of 10% is made in the rate analysis as contractor’s profit for
ordinary contracts. For small jobs 15% profit and for large jobs 8% profit may be
considered as reasonable. Contractors profit is not included in rate analysis if material is
supplied by the department.
a) Estimation of Materials
The remaining space is filled by mortar, hence the volume of mortar required for 10 cum
Additional mortar required for frog filling, brick bonding and wastages @ 15%.
But, 1.25 cu m of dry volume of mortar materials produces 1.0 cu m set mortar.
a) Estimation of Materials
Add 30 % more to the above volume for filling of joints, for making an uniform surface and for
wastages
Thus total set volume of mortar including wastages and joint filling etc.
As, 1.25 cu m of dry volume of mortar materials produces 1.0 cu m set mortar;
b) Rate Analysis
4) Cement Concrete (1:2:4) for RC work excluding reinforcement and form work
a) Estimation of Materials
1.54 cum dry volume of concrete making materials produces 1.0 cu m set concrete
b) Rate Analysis
Note: If concrete mixture is employed for mixing of concrete, hiring and running charges
may add @ Rs. 100.00 per cu m of concrete; but the labour may be reduced by 2 beldars
per 10 cu m of concrete.
5) Providing cold twisted steel reinforcement in R.C.C. slab including bending, binding and
placing in position complete.
a) Estimation of Materials
If bar bending schedule is available, then reinforcement quantity may be estimated from
the schedule. Alternatively, reinforcement steel for beams and slabs may be taken as @
1% of volume of concrete and for columns @ 2% of volume of concrete. The weight of 1
cum of steel is 78.5 quintals.
Thus the volume of reinforcement required = 7.85 + 7.85 × 5/100 = 8.25 qu.
Black iron wire (Binding Wire) @ 1kg per quintal = 8.25 kg.
b) Rate Analysis
a) Estimation of Materials
b) Rate Analysis
a) Estimation of Materials
11.7 cu m of undressed stone and 0.80 cu m of through stone (header) is required for 10
cu m of RR masonry. Further, 4.2 cum of dry mortar materials (cement and sand) are
required for same volume of RR masonry work.
b) Rate Analysis
a) Estimation of Materials
An empirical quantity of 0.63 cum (dry) mortar is required for 100 sq. m of Rule and Tuck
pointing. In case of Flush pointing 75% of above quantity is required.
b) Rate Analysis