0% found this document useful (0 votes)
275 views4 pages

Corrigendum MSOP Change

Uploaded by

Dillip Sahoo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
275 views4 pages

Corrigendum MSOP Change

Uploaded by

Dillip Sahoo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

7{lr,',,',,,,.*.',t;,',,,.,,- tTT{d q{iDTT Government of India .ll' .

::#

:" t-ryffi ta qaraq Ministryof Railways : Tff'


*1:**]:-'** (tad eld Railway Board) ;.'; _". .; r.4,. :
:

No.2018/CE-ACT/36-EPC Contract Policy Pt-I New Delhi, Dated 11.10.2023

To,
As per list attached.

Sub:- Corrigendum Slip to Model SOP 2018

Ministry of Railways (Railway Board) has decided to introduce new Para 9(I) in Part A:
'Works Matter of Model SOP' as shown in enclosed Corrigendum Slip.

2. This issues with the concurrence of the Finance Directorate of Ministry of Railways.

Encl: As above.
-._-
*o
zW4,p
\_./- \ GrtG)
frtqrn frtuilifr.tilnsisE
[Rly No. 030-47598, MTNL No. 011-230475981
e-mail address : dce [email protected]. gov. in

No.2018/CE-VCT/36-EPC Contract Policy Pt-I New Delhi, Dated 11.10.2023

Copy forwarded for information to:

(i) The PFAs, All Indian Railways.


(ii) Dy. Comptroller and Auditor General of India (Railways), Room No. 224, Rail
Bhawan, New Delhi.

For Member Finance


LIST FOR DISTRIBUTION (No. 2018ICE-IICT/36-EPC Contract Policy Pt I New Delhi, Dated 11.10.2023)

1. General Managers, All lndian Railways & Production Units


2. General Manager (Con), N.F. Railway, Guwahati
3. General Manager ICORE, Allahabad
4. Chief Administrative officers (con), All Indian Railways (Except N.F. Railway)
5. Principal Chief Engineers, All Indian Railways
(A)
l. CAO, COFMOW, Tilak Bridge, New Delhi
2. Principal CAO, Diesel Loco Modernization Works, Patiala (Punjab)
3. CAO (Workshop Projects), Charnber Bhawan, Judge's Court Road,.Anta Ghat, Patna-800001, Bihar
(B)
l. Director General, RDSO. Manak Nagar, Lucknorv
2. Director General, NAIR, Vaclodara
3. Director, IRICEN, Pune - 41 1 00 I (Maharashtra)
4. Director,lzuEEN, PB No.-233. Nasik Road-422101 (Maharashtra)
5. Director, IRISET, Taa Naka Road, Lalla Guda, Secunderabad-500017
6. Director, IRIMEE, Jamalpur Disff-Jamalpur, PIN-811214 (Bihar)
7. Director, IRITM, Sarswati Residential Estate, IRITM Campus, Manak Nagar, Lucknow
(c)
1. MD, CONCOR, Concor Bhawan, C-3, Mathura Road, Opp. Apollo lJospital, New Delhi- I10076
2. IRCON International Limited, C-4, District Centre, Saket, Nelv DelhLi- 110017
3. MD, RITES Ltd., RITES Bhawan, Plot No.l, Sector-29, Gurgaon
4. CMD, RVNL, August Kranti Bhawan,Plot No.25, 1" Floor, Bhikaji tSama Place, New Delhi
5. MD, MRVC Ltd., Churchgate Station Bldg, Munrbai- 400020
6. CMD, KONKAN Raihvay Corporation Ltd, Rail Bhawan, New Deltri-110001
7. MD, DFCCIL, 5'h Floor, Pragati Maidan Metro Station Building Cornplex, New Dclhi-110001
8. MD, RLDA, Near Safdarjune Railway Station, MotiBagh, Phase-I, .Nerv Delhi- I10021
9. MD. CRIS, Chanakyapur, New Delhi
10. CMD. RailTel Corporation of India Ltd. Plot No. 143, Institutional Area, Sector-44, Gurgaon '122003
I 1. CME, IROAF, l2'h Floor, Core-1, Scope Minar, Distt. Centre, Laxmi Nagar, Delhi- 110092
12. Managing Director, IRFC Lirnited, UG Floor, EastTower, NBCC Place, Bhisham Pitamah Marg,
LodhiRoad, Pragati Vihar, Ner.r Delhi
13. CMD. IRCTC l-td., B-i48, I lth Floor, Statesman House, Barakharnba Road, New Delhi 110001
14. CMD, Braithrvaite & Co. limited, 5 Hide Road Kolkata 700043
Copy to:
(4l
1. General IRCA, DRM Office, Nerv Delhi
Secretary,
2. General AIRF, Rail Bhawan, New Delhi
Secretary,
3. Ceneral NFIR, Rail Bhawan, Nerv Delhi
Secretary,
4. General IRPOF, Rail Bhawan, New Delhi
Secretary,
5. General FROA, Rail Bhawan, Nerv Delhi
Secretary,
6. General AIRPA, Rail Bhawan, New Delhi
Secretary,
7. General Secretary, AISC & STREA, Rail Bhawan, Nerv Delhi
8. The Secretary, IIBSS, Croup (A) Offices Association, Rail Bhawan
9. The Secretary, RBSS, Group (B) Offices Association, Rail Bhawan
10. General Secretary, RBSSS Association, Rail Bharvan
1 l. fne Secretary, IIBMSA, Rail Bharvan

12. fne Secretarv, Railway', GroLrp (D) Employees Association, Rail Bhawan
(B)
1. Concerned PSO for kind information of Chairman cunr CEO, M/lnfra, M/T&RS M'O&BD, IvVFinance,
Railway Board
2. Adv^/MR, EDPG/MR, OSDiMR, OSR(Co-ord)/MR
3. Chief Vigilance Officers, All Indian Railways
4. DG(RHS), DG(RPF), AM(CE), AM(Works), AM(B), AM(EIec.), AM(RS), AM(ME), AIWTele,
AM/C&lS, AM/Sig., AM(Plg.), PED(B&S), PED(Vigilance), PEDCE(P), PED/Safety, PED/Gati Shakti,
EDCE(G), EDTK(M&MC), EDCE(B&S), EDF(X), ED/GS(Civil-I), ED/GS(Civil-Il), ED/GS(Elect.),
ED/GS(S&T), ED/GS/SD, EDw(Plg.), ED(L&A), ED(PSU), EDVE, ED(Safety), ED(Sig. Dev.), ED(
Tele), EDRS(G), EDEE(G), EDFE, EDE(N), ED(Accounts), ED/T&MPP, EDME(Chg.), EDME(Frt.),
ED/Plg., JS(conf), JS(P), JS(G), JS(D), Vigilance-Ill, Vig(Conf) of Railway Board.

i .rt 4

\t'lu
Corrigendum Slip to Model SOP 2018

Chanse of Scope In EPC Contracts


Nature of Powers PIIOD DRM Divisional REMARKS
Officers,
Extra
Divisional
Officers &
Officers in
Headquarters
e(r) A. Change in Scope due to As define in EPC Document, The
change in specifications of any 'Authority' has Full Powers upto the
item of Works in accordance threshold limit specified in clause
with provision of Clause 13.1.2 13.4.2. of Article- 13 of the EPC
of Article-l3 of the EPC Agreement
Agreement.
B. Omission of any work from
the Scope of the Project in
accordance with provisions of
Clause 13.1.2 of Article-l3 of
the EPC Agreement.
C. any additional work, Plant,
Materials or services which are
not included in the Scope of the
Project, including any associated
Tests on completion of
construction.
D. Variation in the quantities of
certain items (positive or
negative) necessitated due to any
change(s) in the L-
Section/Alignment/ESPs of the
Project with respect to those
attached with this document

Note for item No. 9(I)

Authority shall not be below the rank of SA Grade.


Finance concuffence shall be obtained for any change in scope of the contract. These
powers shall apply for both positive and negative change in the scope.
Change in scope shall be restricted in accordance with provisions of Clause 13.4 of
Article-13 of the EPC Agreement.
The ratelcost for the Change of Scope shall be determined in accordance with provisions
of Clause 13.2.3 of Article-13 of the EPC Agreement.