IIM Notes
IIM Notes
Introduction
1. Define Organization
An organization is a group of individuals working together in a structured
and coordinated way to achieve common objectives. It involves allocating
tasks, defining roles, and establishing hierarchies to ensure efficient
operations and goal achievement.
Here are the answers to the CPM and PERT questions in detail and
short format:
1. Which type of organization is temporary by nature?
Detailed: A project is a temporary endeavor undertaken to create a unique
product, service, or result. It has a defined start and end date, 1 and
resources are allocated specifically for its duration.
Short: A project.
2. What is the symbol for activity in a network diagram?
Detailed: In a network diagram, activities are typically represented by
arrows. The length of the arrow may sometimes indicate the duration of the
activity.
Short: Arrows.
3. What is PERT Analysis?
Detailed: Program Evaluation and Review Technique (PERT) is a project
management tool used to analyze the task durations, dependencies, and
uncertainties in a project schedule. It helps identify the critical path and
estimate the project's completion time and potential delays.
Short: PERT is a project management tool for analyzing task durations,
dependencies, and uncertainties.
4. What is Master Scheduling?
Detailed: Master scheduling is a detailed plan that outlines the production
schedule for finished goods. It takes into account factors like demand
forecasts, available resources, and order commitments to ensure timely
production and efficient resource utilization.
Short: Master scheduling is a detailed production plan.
5. The expected time (Te) of a PERT activity in terms of optimistic
time (To), pessimistic time (Tp), and most likely time (Tm) is given 2
by
Detailed: The formula for calculating the expected time (Te) in PERT is:
Te = (To + 4Tm + Tp) / 6
Short: Te = (To + 4Tm + Tp) / 6
6. Define critical path in a network diagram.
Detailed: The critical path is the longest sequence of activities in a project
network. Any delay in these critical activities will directly impact the overall
project completion time.
Short: The critical path is the longest sequence of activities in a project
network.
Certainly, let's break down the answers and explanations for the remaining
questions on the page:
7. Which of the following is referred to as crash time?
Answer: (b) Time beyond which cost reduction is not possible.
Explanation: Crash time in project management refers to the minimum
possible time to complete an activity. It is the shortest duration achievable
through the application of additional resources or by expediting the work
process. Beyond the crash time, further reductions in activity duration are
not possible without incurring significant costs or compromising quality.
8. The proportion of profit to be retained for growth and to be
distributed among shareholders is decided through
Answer: (c) Dividend Decision.
Explanation: The dividend decision is a crucial aspect of financial
management for companies. It involves determining the portion of profits
that will be distributed to shareholders as dividends and the portion that will
be retained for reinvestment in the business for future growth.
9. PERT method of project scheduling is suitable for
Answer: (c) A spacecraft development project based on research.
Explanation: PERT (Program Evaluation and Review Technique) is
particularly well-suited for projects with high uncertainty and where activity
durations are estimated probabilistically. Spacecraft development projects
often involve complex research and development activities with inherent
uncertainties, making PERT a suitable tool for managing such projects.
10. Planning is
Answer: (a) Looking ahead.
Explanation: Planning is the process of defining goals, objectives, and
strategies for the future. It involves anticipating future events and
developing courses of action to achieve desired outcomes.
11. "Slack" refers to the difference between
Answer: (c) Early start time and late finish time.
Explanation: In project management, slack represents the amount of time
that an activity can be delayed without affecting the overall project
schedule. It is calculated as the difference between the late start time and
the early start time of an activity.
12. Difference between PERT and CPM
Answer: (b) PERT is probabilistic but CPM is not.
Explanation: The key difference between PERT and CPM (Critical Path
Method) lies in their approach to estimating activity durations. PERT
considers activity durations to be probabilistic, using optimistic, pessimistic,
and most likely estimates to calculate the expected duration. In contrast,
CPM assumes deterministic activity durations with known values.
13. Dummy activity in a project network diagram represents -
a) logical relationship
b) necessary delay
c) allocation of resources
3. Definitions
a) Events:
Definition: Points in a project network that represent the start or
completion of an activity.
Example: Beginning of a task or completion of a milestone.
b) Activity:
Definition: A task or operation that consumes time and resources in a
project.
Example: Designing, coding, or testing in a software development
project.
c) Critical Activity:
Definition: An activity that lies on the critical path, directly affecting
the project's completion time.
Importance: Delay in a critical activity delays the entire project.
d) Dummy Activity:
Definition: A placeholder activity that shows dependencies but
consumes no time or resources.
Purpose: Used to maintain logical sequencing in the network diagram.
Representation: Dashed line in network diagrams.
e) Non-Critical Activity:
Definition: An activity that does not lie on the critical path and has
slack (flexible start or finish time).
Significance: Delaying a non-critical activity won't delay the overall
project, as long as it stays within its slack.