IIM Notes
IIM Notes
Introduction
1. Define Organization
An organization is a group of individuals working together in a structured and coordinated way to achieve common
objectives. It involves allocating tasks, defining roles, and establishing hierarchies to ensure efficient operations
and goal achievement.
Here are the answers to the CPM and PERT questions in detail and short format:
1. Which type of organization is temporary by nature?
Detailed: A project is a temporary endeavor undertaken to create a unique product, service, or result. It has a
defined start and end date,1 and resources are allocated specifically for its duration.
Short: A project.
2. What is the symbol for activity in a network diagram?
Detailed: In a network diagram, activities are typically represented by arrows. The length of the arrow may
sometimes indicate the duration of the activity.
Short: Arrows.
3. What is PERT Analysis?
Detailed: Program Evaluation and Review Technique (PERT) is a project management tool used to analyze the task
durations, dependencies, and uncertainties in a project schedule. It helps identify the critical path and estimate the
project's completion time and potential delays.
Short: PERT is a project management tool for analyzing task durations, dependencies, and uncertainties.
4. What is Master Scheduling?
Detailed: Master scheduling is a detailed plan that outlines the production schedule for finished goods. It takes into
account factors like demand forecasts, available resources, and order commitments to ensure timely production
and efficient resource utilization.
Short: Master scheduling is a detailed production plan.
5. The expected time (Te) of a PERT activity in terms of optimistic time (To), pessimistic time (Tp), and most likely
time (Tm) is given2 by
Detailed: The formula for calculating the expected time (Te) in PERT is:
Te = (To + 4Tm + Tp) / 6
Short: Te = (To + 4Tm + Tp) / 6
6. Define critical path in a network diagram.
Detailed: The critical path is the longest sequence of activities in a project network. Any delay in these critical
activities will directly impact the overall project completion time.
Short: The critical path is the longest sequence of activities in a project network.
Certainly, let's break down the answers and explanations for the remaining questions on the page:
7. Which of the following is referred to as crash time?
Answer: (b) Time beyond which cost reduction is not possible.
Explanation: Crash time in project management refers to the minimum possible time to complete an activity. It is the
shortest duration achievable through the application of additional resources or by expediting the work process.
Beyond the crash time, further reductions in activity duration are not possible without incurring significant costs or
compromising quality.
8. The proportion of profit to be retained for growth and to be distributed among shareholders is decided through
Answer: (c) Dividend Decision.
Explanation: The dividend decision is a crucial aspect of financial management for companies. It involves
determining the portion of profits that will be distributed to shareholders as dividends and the portion that will be
retained for reinvestment in the business for future growth.
9. PERT method of project scheduling is suitable for
Answer: (c) A spacecraft development project based on research.
Explanation: PERT (Program Evaluation and Review Technique) is particularly well-suited for projects with high
uncertainty and where activity durations are estimated probabilistically. Spacecraft development projects often
involve complex research and development activities with inherent uncertainties, making PERT a suitable tool for
managing such projects.
10. Planning is
Answer: (a) Looking ahead.
Explanation: Planning is the process of defining goals, objectives, and strategies for the future. It involves
anticipating future events and developing courses of action to achieve desired outcomes.
11. "Slack" refers to the difference between
Answer: (c) Early start time and late finish time.
Explanation: In project management, slack represents the amount of time that an activity can be delayed without
affecting the overall project schedule. It is calculated as the difference between the late start time and the early
start time of an activity.
12. Difference between PERT and CPM
Answer: (b) PERT is probabilistic but CPM is not.
Explanation: The key difference between PERT and CPM (Critical Path Method) lies in their approach to estimating
activity durations. PERT considers activity durations to be probabilistic, using optimistic, pessimistic, and most likely
estimates to calculate the expected duration. In contrast, CPM assumes deterministic activity durations with known
values.
13. Dummy activity in a project network diagram represents -
a) logical relationship
b) necessary delay
c) allocation of resources
3. Definitions
a) Events:
• Definition: Points in a project network that represent the start or completion of an activity.
• Example: Beginning of a task or completion of a milestone.
b) Activity:
• Definition: A task or operation that consumes time and resources in a project.
• Example: Designing, coding, or testing in a software development project.
c) Critical Activity:
• Definition: An activity that lies on the critical path, directly affecting the project's completion time.
• Importance: Delay in a critical activity delays the entire project.
d) Dummy Activity:
• Definition: A placeholder activity that shows dependencies but consumes no time or resources.
• Purpose: Used to maintain logical sequencing in the network diagram.
• Representation: Dashed line in network diagrams.
e) Non-Critical Activity:
• Definition: An activity that does not lie on the critical path and has slack (flexible start or finish time).
• Significance: Delaying a non-critical activity won't delay the overall project, as long as it stays within its
slack.