Cme Module 3
Cme Module 3
Presentation on
CONSTRUCTION
MANAGEMENT&
ENTREPRENEURSHIP(BCV501)
by
Prof. K V Mahesh Chandra
Assistant Professor
Department of Civil Engineering
Bangalore Institute of Technology
Bengaluru-560 004
MODULE 3- PROCUREMENT
& CONTRACT MANAGEMENT
CONTENTS
Procurement Management
1. Definition.
2. Procurement Stages.
3. Procurement Types.
4. Sustainable Procurement Management.
Procurement in construction is the process of sourcing the
products, services, and equipment required to complete a
project successfully.
Suitability
Demerits
Before the contract is awarded, the project has to be studied
thoroughly and the complete contract document has lo be
prepared in advance.
In this type of contract, unforeseen details of work are not
specified in the contract document. Many additional items may
have to be undertaken as the work progresses, giving opportunity
to the contractor for claiming higher rates for the extra items
not included in the contract agreement.
Types of Contracts
2. Item Rate Contracts
Suitability
The item rate contract is most commonly used for all types
of engineering works financed by public or government
bodies. This type of contract is suitable for works which
can be split into various items and quantities under each
item can be estimated with accuracy.
Types of Contracts
2. Item Rate Contracts
Merits
• In this type of contract, there is no need for detailed drawings at
the time of allotting contract as ¡n the case of lump sum contract. The
detailed drawings can be prepared after the contract is awarded.
• Changes in drawings and quantities of individual items can be made as
per requirement within agreed limits. •
The payment to the contractor is made on the actual work done by him
at the agreed rates.
Demerits
• The total cost of work can only be known upon completion. As such,
the owner may incur financial difficulty if the final cost increases
substantially.
• Additional staff is required to take detailed measurements of work
done for releasing payments to the contractor.
• The scope for additional saving with the use of inferior quality
materials may prompt the contractor to use such materials in the work.
Types of Contracts
3. Lump Sum and Scheduled Contracts
This is similar to the lump sum contract except the schedule
of rates is also included in the contract agreement. In this
type of contract, the contractor offers to do a particular
work at a fixed sum within a specified time as per plans and
detailed specifications. The schedule of rates for various
items is provided which regulates the extra amount to be paid
or deducted for any additions or deletions made during the
progress of work. Measurements of different items of
original work are not required but extra items are required to
be measured for payment. The original work shall however be
checked and compared with the drawings and specifications.
Types of Contracts
3. Lump Sum and Scheduled Contracts
Suitability
This type of contract is more suitable for construction
works for which contractors have prior work experience
and can consequently estimate the project cost more
realistically.
Merits
• In this type of contract, additional staff for recording
detailed measurement of original item of work is not
required for making payment to the contractor.
Types of Contracts
3. Lump Sum and Scheduled Contracts
Merits
• The owner can know from tenders as to what the project will
cost him. Knowing the financial implications, the owner can
decide to start or defer the project.
Demerits
• Before the contract is awarded the project has to be studied
thoroughly and all the contract documents are required to be
completed in every respect.
• The non-scheduled extra items arising out of changes made in
the drawings and specifications are often a source of dispute
because the contractor presses for rates higher than the
prevailing market rates.
Types of Contracts
4. Cost Plus Fixed Fee Contract
Cost plus fixed fee contract is desirable when the scope
and nature of the work can atleast be broadly defined. The
amount of fee is determined as a lump sum from a
consideration of the scope of work, its approximate cost,
nature of work, estimated time of construction, manpower
and equipment requirements etc. In order to negotiate such
a type of contract, it is essential that the scope and some
general details of the work are defined. The contractor in
this type of contract is selected on the basis of merit
rather than the fee alone.
Types of Contracts
4. Cost Plus Fixed Fee Contract
In case of cost-plus percentage contract, the contractor
has a tendency to increase his profit by increasing the cost
of work.
But this drawback is overcome in cost plus fixed fee
contract because here the contractor‘s fee is fixed and
does not fluctuate with actual cost of work. Once this fee
is fixed, the contractor cannot increase the cost of work.
Types of Contracts
4. Cost Plus Fixed Fee Contract
Suitability
• This type of contract is suitable for works required to
be completed expeditiously and where it is difficult to
foretell what difficulties are likely to be encountered.
• This contract is also suitable for important structures
where the cost of construction is immaterial.
Merits
• In this type of contract, actual cost is to be borne by
the owner. Therefore, the contractor performs the work
in the best interest of the owner resulting in good
quality work.
Types of Contracts
4. Cost Plus Fixed Fee Contract
Merits
• The work can be taken in band even before the detailed
drawings and specifications are finalized.
• Changes in design and method of construction if needed
can be easily carried out without disputes.
• The work can be executed speedily.
Demerits
• This form of contract cannot bc adopted normally in case of
public bodies and Government departments.
• The final cost of the work is no known in advance and this may
subject the owner to financial difficulties.
Types of Contracts
5. Cost Plus Percentage of Cost Contract
In this type of contract, instead of awarding the work on lump sum or
item rate basis, it is given on certain percentage over the actual cost
of construction. The actual cost of construction is reported by the
contractor and paid to him by the owner together with a certain
percentage as agreed earlier.
The contractor agrees to do the work in accordance with the drawings,
specifications, other conditions of contract. In this type of contract
proper control has been exercised by the owner in purchase of
materials and in arranging labour.
The suitability, merits and demerits of these type of contract are
similar to cost plus fixed fee contract. An addition to demerit, the
tendency of the contractor to increase the cost of work to earn more
profit by way of percentage of enhanced actual cost.
Special Contracts
1. Turnkey contract
A turnkey contract is an integrated contract in which all
works pertaining to various disciplines such as civil, electrical,
mechanical etc. are in a single contract called the main
contract. The main contractor can sublet the contract to sub-
contractors who are specialist in their respective fields.
In this contract, the main advantage of the owner is that he
need not to coordinate the work of different contractors.
The main contractor is responsible for all kinds of jobs,
starting from planning to commissioning stage.
The owner takes over the entire work which is fully
operational and of proven performance from the main
contractor.
Special Contracts
2. Package contract
In a package contract, two or more related jobs, each of which
could form a separate contract are combined in a single contract.
In the field of civil engineering, generally design and
development are combined with construction and supplying or
maintenance.
In this type of contract, plan of work and standards are
established and the work is carried out accordingly by the
contractor. The main contractor is responsible for safe guarding
the owner‘s interest, clear approval of design and technical
aspect have to be taken from the owner. The responsibility for
the correctness of design lays with the main contractor.
Special Contracts
3. Negotiated contract
In this type of contract, negotiation across the table takes
place between the representatives of the owner and the
main contractor for the project cost and other conditions
of contract. In this type of contract, detailed project
specifications, are arrived at by discussions between the
owner and the main contractor.
A negotiated contract involves extended discussions for
finalization as a competitive contract. Most of the
consultancy works of World Bank are negotiated contract.
Special Contracts
4. Continuing contract
In this type of contract new or additional work is awarded
to the contractor on the basis of the agreed terms and
conditions of an existing contract. Such contract do not
require retendering and hence can save time and money.
5. Running contract
Such contracts provide goods and services at specified
intervals or as on when required by the owner. The
contract price is not fixed and the payment is based on
actual goods supplied and services rendered as specified in
the contract document.
Special Contracts
7. BOT (Build - Operate – Transfer) contract
A third-party contract to build, then operate an assets( for
e.g dam , bridge, road) for a specific amount of time for a fee
and then transfer the asset back to contracting company or
entity ( usually a government entity). This is commonly used
by public sector for large capital projects. The system of
contracting is useful when client does not want to invest
directly in the project and wants to encourage development
projects through external funding and investment. It is also a
method of attracting and involving the private sector which
typically involve very heavy capital investment.
Special Contracts
8. BOOT - Build – Own –Operate –Transfer contract
It is similar to BOT except that rather than receiving a
fee for operating it. It receives the net income from the
asset as if it owned it. This asset is a revenue generating
asset ( e.g: toll bridges, powerstations)
Important Conditions of Contracts
The members of the construction team should be fully aware of their
rights and obligations under the contract. Following are the important
conditions of contract.
1. Time of completion.
2. Delay and extension of time.
3. Penalty.
4. Compensation of delay in completion of work.
5. Liquidated damages.
6. Debitable agency.
7. Valuation of variations.
8. Settlement of disputes.
9. Force majeure and natural disaster.
10. Price escalation.
11. Termination of contract.
Contract Document
The contract document consist of contract agreement on
non-judicial stamp paper of prescribed value and the
following sets of document each page of it is signed both
by the owner and the contractor.
1. Cover or Title Page
It contains the name of the work, name of the owner, name
of the contractor, contract agreement number, contents
etc.
2. Contents page
It contains the contents of the agreement with page
references
Contract Document
3. Notice Inviting Tender(NIT)
It contains a brief description of work estimated cost of work
date and time for receiving the tender, amount of earnest money
(EMD), security deposit(SD), time of completion etc.
4. Tender form
It comprises of bill of quantities, contractor‘s rate, total cost of
work, time for completion, security money to be deposited and
penalty process etc.
5. Schedule of issue of materials
It contains the list of materials to be issued by the department
or owner to the contractor with rates or place of issue.
Contract Document
6. Drawings
These comprise a complete set of fully dimensioned
drawings including plans, elevations, sections, detailed
drawings and site plan.
7. Specifications
It is not practicable to include the detailed information of
each item of work in the limited space of description in the
bill of quantities. As such detailed agreement forms a part
of the contract agreement.
Contract Document
7. Specifications
Specification should be clear and precise covering all items of
bill of quantities (BOQ).
Following specifications are normally included in the contract
document
a. General specification - These specify the class and type of
work, quality of materials etc, in general for the work as a
whole.
b. In detailed specification – These views detailed
description of each item of work including material and
method to be used along with quality of workmanship
required
Contract Document
8. Conditions of Contract
The terms and conditions of the contract specify the
following.
a. Rates of each item of work inclusive of materials, labour ,
transport, plant and equipment and other arrangements
required for the completion of work.
b. Amount and form of earnest and security money to be
deposited.