Microsoft Project Exercises
Microsoft Project Exercises
You have been assigned as the project manager for a new software application development
project, "HealthTrackApp," which is intended to help users monitor and manage their health
data. The application must be delivered in 6 months, and the project team includes software
developers, testers, a UI/UX designer, and project resources for equipment and software tools.
Your task is to set up, organize, and manage this project in Microsoft Project 2010, following the
steps below:
Tasks
Scenario: You are the project manager for a software development project aimed at creating an
online learning platform. Your team is expected to complete the project within a specified
timeframe and budget. Use Microsoft Project 2010 to set up, manage, and track this project.
Exercise Instructions:
You are the project manager for a new project to develop a Customer Relationship
Management (CRM) System. The project involves setting up and managing tasks, resources,
budgets, and progress tracking in Microsoft Project 2010. Use the provided task, resource, and
task-resource tables to configure the project and answer questions based on best practices in
project management.
Project Overview
Resource ID Resource Name Type Standard Rate Overtime Rate Max Units (%)
R1 Project Manager Work $65/hr $95/hr 100%
R2 Business Analyst Work $55/hr $85/hr 100%
Resource ID Resource Name Type Standard Rate Overtime Rate Max Units (%)
R3 System Architect Work $60/hr $90/hr 100%
R4 Database Developer Work $50/hr $75/hr 100%
R5 Backend Developer Work $45/hr $70/hr 100%
R6 Frontend Developer Work $45/hr $70/hr 100%
R7 Tester Work $40/hr $60/hr 100%
R8 Training Specialist Work $55/hr $80/hr 100%
R9 Technical Writer Work $40/hr $60/hr 100%
Task
Task Name Assigned Resources
ID
1 Project Planning Project Manager
2 Requirements Analysis Project Manager, Business Analyst
3 System Architecture Design System Architect, Project Manager
4 Database Development Database Developer
5 Backend Development Backend Developer
6 Frontend Development Frontend Developer
System Architect, Backend Developer, Frontend
7 System Integration
Developer
8 User Acceptance Testing Tester
Training and
9 Training Specialist, Technical Writer
Documentation
10 Go Live Project Manager
Exercise Questions
You are assigned as the project manager for developing an Inventory Management Software.
Your task is to set up and manage this project in Microsoft Project 2010, including task
schedules, resource allocations, and budgets. This exercise will use pre-defined tables for tasks,
resources, and task-resource allocations to test your ability to manage and track projects
efficiently.
Project Overview
Define resources for the project using the following table in Resource Sheet:
Resource ID Resource Name Type Standard Rate Overtime Rate Max Units (%)
R1 Project Manager Work $60/hr $90/hr 100%
R2 Business Analyst Work $50/hr $75/hr 100%
R3 System Designer Work $55/hr $80/hr 100%
R4 Database Administrator Work $45/hr $65/hr 100%
Resource ID Resource Name Type Standard Rate Overtime Rate Max Units (%)
R5 Frontend Developer Work $40/hr $60/hr 100%
R6 Backend Developer Work $40/hr $60/hr 100%
R7 Tester Work $35/hr $50/hr 100%
R8 Deployment Engineer Work $50/hr $75/hr 100%
Exercise Questions
You are assigned as the project manager for an E-Commerce Website Development project.
This project involves planning, resource allocation, scheduling, and tracking progress using
Microsoft Project 2010. Use the information in the task, resource, and task-resource allocation
tables provided to set up and manage this project.
Project Overview
Resource ID Resource Name Type Standard Rate Overtime Rate Max Units (%)
R1 Project Manager Work $65/hr $95/hr 100%
R2 Business Analyst Work $50/hr $75/hr 100%
R3 UI/UX Designer Work $55/hr $85/hr 100%
R4 Database Engineer Work $50/hr $75/hr 100%
Resource ID Resource Name Type Standard Rate Overtime Rate Max Units (%)
R5 Backend Developer Work $45/hr $70/hr 100%
R6 Frontend Developer Work $45/hr $70/hr 100%
R7 QA Tester Work $40/hr $60/hr 100%
R8 Training Specialist Work $50/hr $75/hr 100%
Exercise Questions
As a project manager, you are tasked with overseeing the development of a Mobile Application
for a healthcare company. This project involves breaking down tasks into a work breakdown
structure (WBS) with subtasks, assigning resources, tracking progress, and reporting in
Microsoft Project 2010. Use the provided task, resource, and task-resource tables to manage the
project and answer questions based on your project setup.
Project Overview
Enter tasks and subtasks in Gantt Chart View using the following structure:
Task
WBS Task Name Duration Start Date Predecessor Milestone
ID
1 1 Project Initiation 2 days 03/01/2025 - Yes
1.1 1.1 Project Charter 1 day 03/01/2025 -
1.2 1.2 Stakeholder Meeting 1 day 03/02/2025 1.1
2 2 Requirements Gathering 7 days 03/03/2025 1
2.1 2.1 Functional Requirements 4 days 03/03/2025 -
2.2 2.2 Technical Requirements 3 days 03/07/2025 2.1
3 3 Design Phase 10 days 03/10/2025 2
3.1 3.1 UI/UX Design 6 days 03/10/2025 -
3.2 3.2 Architecture Design 4 days 03/16/2025 3.1
4 4 Development 20 days 03/20/2025 3
4.1 4.1 Frontend Development 10 days 03/20/2025 -
4.2 4.2 Backend Development 10 days 03/20/2025 -
4.3 4.3 API Integration 5 days 04/03/2025 4.1, 4.2
5 5 Testing 15 days 04/10/2025 4
5.1 5.1 Unit Testing 5 days 04/10/2025 -
5.2 5.2 System Testing 5 days 04/15/2025 5.1
5.3 5.3 User Acceptance Testing 5 days 04/20/2025 5.2
6 6 Deployment 3 days 04/28/2025 5
6.1 6.1 Production Setup 2 days 04/28/2025 -
Task
WBS Task Name Duration Start Date Predecessor Milestone
ID
6.2 6.2 Go Live 1 day 04/30/2025 6.1 Yes
7 7 Project Closeout 2 days 05/01/2025 6 Yes
7.1 7.1 Final Review and Approval 1 day 05/01/2025 -
Lessons Learned and
7.2 7.2 1 day 05/02/2025 7.1
Documentation
Resource ID Resource Name Type Standard Rate Overtime Rate Max Units (%)
R1 Project Manager Work $70/hr $100/hr 100%
R2 Business Analyst Work $55/hr $80/hr 100%
R3 UI/UX Designer Work $50/hr $75/hr 100%
R4 System Architect Work $65/hr $90/hr 100%
R5 Frontend Developer Work $45/hr $70/hr 100%
R6 Backend Developer Work $45/hr $70/hr 100%
R7 QA Tester Work $40/hr $60/hr 100%
R8 DevOps Engineer Work $55/hr $85/hr 100%
Exercise Questions
You are assigned as the project manager for a Cloud Data Migration project. This project
involves planning, resource allocation, scheduling, and tracking the migration of company data
from on-premises servers to a cloud-based solution. In this exercise, each main task in the work
breakdown structure (WBS) will serve as a milestone, representing key project phases.
Project Overview
Enter tasks and subtasks in Gantt Chart View based on the following structure. Ensure each main
task (phase) is marked as a milestone.
Task
WBS Task Name Duration Start Date Predecessor Milestone
ID
1 1 Project Planning 1 day 01/15/2025 - Yes
1.1 1.1 Define Scope and Objectives 2 days 01/15/2025 -
1.2 1.2 Identify Stakeholders 1 day 01/17/2025 1.1
1.3 1.3 Develop Project Charter 2 days 01/18/2025 1.2
2 2 Requirement Analysis 1 day 01/21/2025 1 Yes
2.1 2.1 Data Inventory 5 days 01/21/2025 -
Define Data Structure and
2.2 2.2 5 days 01/28/2025 2.1
Mapping
Compliance and Security
2.3 2.3 3 days 02/04/2025 2.2
Requirements
3 3 System Design 1 day 02/07/2025 2 Yes
3.1 3.1 Cloud Infrastructure Design 7 days 02/07/2025 -
3.2 3.2 Network and Storage Setup 5 days 02/17/2025 3.1
3.3 3.3 Security and Access Control Setup 4 days 02/24/2025 3.2
4 4 Data Migration and Validation 1 day 03/01/2025 3 Yes
4.1 4.1 Initial Data Migration 5 days 03/01/2025 -
Data Validation and Quality
4.2 4.2 4 days 03/07/2025 4.1
Checks
4.3 4.3 Incremental Data Migration 7 days 03/11/2025 4.2
Task
WBS Task Name Duration Start Date Predecessor Milestone
ID
5 5 Testing and User Training 1 day 03/20/2025 4 Yes
5.1 5.1 System Testing 4 days 03/20/2025 -
5.2 5.2 User Acceptance Testing (UAT) 5 days 03/26/2025 5.1
5.3 5.3 User Training 3 days 04/02/2025 5.2
6 6 Project Closure 1 day 04/10/2025 5 Yes
6.1 6.1 Final Review and Sign-off 2 days 04/10/2025 -
Project Documentation and
6.2 6.2 2 days 04/12/2025 6.1
Handover
Resource ID Resource Name Type Standard Rate Overtime Rate Max Units (%)
R1 Project Manager Work $70/hr $100/hr 100%
R2 Business Analyst Work $60/hr $85/hr 100%
R3 Data Engineer Work $55/hr $80/hr 100%
R4 Cloud Architect Work $65/hr $90/hr 100%
R5 Security Specialist Work $60/hr $90/hr 100%
R6 QA Tester Work $50/hr $75/hr 100%
R7 Trainer Work $45/hr $70/hr 100%
Exercise Questions
You are assigned as the project manager for the development of an E-Commerce Website. This
project will require defining tasks, allocating resources, setting milestones, and tracking project
progress to ensure timely delivery and quality. Each main task in the WBS represents a major
phase of the project and should be set as a milestone.
Project Overview
Enter tasks and subtasks in Gantt Chart View based on the following structure. Set each main
task as a milestone to signify a critical phase of the project.
Task
WBS Task Name Duration Start Date Predecessor Milestone
ID
1 1 Project Planning 1 day 02/01/2025 - Yes
1.1 1.1 Define Project Goals and Scope 2 days 02/01/2025 -
1.2 1.2 Develop Project Charter 2 days 02/03/2025 1.1
1.3 1.3 Identify Key Stakeholders 1 day 02/05/2025 1.2
2 2 Requirements Gathering 1 day 02/06/2025 1 Yes
2.1 2.1 Gather Functional Requirements 4 days 02/06/2025 -
2.2 2.2 Gather Technical Requirements 3 days 02/10/2025 2.1
Security and Compliance
2.3 2.3 2 days 02/13/2025 2.2
Requirements
3 3 Design Phase 1 day 02/15/2025 2 Yes
3.1 3.1 UI/UX Design 5 days 02/15/2025 -
Database and Backend
3.2 3.2 4 days 02/21/2025 3.1
Architecture Design
3.3 3.3 Security Design 3 days 02/25/2025 3.2
4 4 Development 1 day 02/28/2025 3 Yes
4.1 4.1 Frontend Development 10 days 02/28/2025 -
4.2 4.2 Backend Development 10 days 02/28/2025 -
4.3 4.3 API and Payment Integration 5 days 03/12/2025 4.1, 4.2
5 5 Testing and Quality Assurance 1 day 03/17/2025 4 Yes
Task
WBS Task Name Duration Start Date Predecessor Milestone
ID
5.1 5.1 Functional Testing 5 days 03/17/2025 -
5.2 5.2 User Acceptance Testing 5 days 03/24/2025 5.1
5.3 5.3 Security Testing 4 days 03/31/2025 5.2
6 6 Deployment 1 day 04/04/2025 5 Yes
6.1 6.1 Deployment to Production 2 days 04/04/2025 -
6.2 6.2 Post-Deployment Verification 2 days 04/06/2025 6.1
7 7 Project Closure 1 day 04/10/2025 6 Yes
7.1 7.1 Final Review and Project Sign-off 1 day 04/10/2025 -
Lessons Learned and
7.2 7.2 2 days 04/11/2025 7.1
Documentation
Resource ID Resource Name Type Standard Rate Overtime Rate Max Units (%)
R1 Project Manager Work $70/hr $100/hr 100%
R2 Business Analyst Work $60/hr $90/hr 100%
R3 UI/UX Designer Work $50/hr $75/hr 100%
R4 Backend Developer Work $55/hr $80/hr 100%
R5 Frontend Developer Work $55/hr $80/hr 100%
R6 QA Tester Work $45/hr $70/hr 100%
R7 Security Specialist Work $60/hr $90/hr 100%
R8 DevOps Engineer Work $55/hr $85/hr 100%
Exercise Questions
You are tasked with managing the development of a Mobile Fitness Tracking App. This project
involves setting up tasks and resources, defining milestones, and tracking progress to ensure the
app is launched on time. Each main task in the WBS will represent a critical project phase and
should be set as a milestone.
Project Overview
Enter tasks and subtasks in Gantt Chart View based on the following structure. Set each main
task as a milestone to indicate a key project phase.
Task
WBS Task Name Duration Start Date Predecessor Milestone
ID
1 1 Project Initiation 1 day 03/01/2025 - Yes
1.1 1.1 Define Project Scope and Goals 2 days 03/01/2025 -
1.2 1.2 Develop Project Charter 2 days 03/03/2025 1.1
1.3 1.3 Identify Key Stakeholders 1 day 03/05/2025 1.2
2 2 Requirement Analysis 1 day 03/06/2025 1 Yes
2.1 2.1 Gather Functional Requirements 3 days 03/06/2025 -
2.2 2.2 Define Technical Requirements 3 days 03/09/2025 2.1
Define Security and Compliance
2.3 2.3 2 days 03/12/2025 2.2
Needs
3 3 Design Phase 1 day 03/14/2025 2 Yes
3.1 3.1 UI/UX Design 6 days 03/14/2025 -
3.2 3.2 Database and Backend Design 5 days 03/22/2025 3.1
3.3 3.3 Security Design 4 days 03/29/2025 3.2
4 4 Development 1 day 04/03/2025 3 Yes
4.1 4.1 Frontend Development 12 days 04/03/2025 -
4.2 4.2 Backend Development 10 days 04/03/2025 -
API and Fitness Tracker
4.3 4.3 6 days 04/20/2025 4.1, 4.2
Integration
5 5 Testing and Quality Assurance 1 day 04/28/2025 4 Yes
Task
WBS Task Name Duration Start Date Predecessor Milestone
ID
5.1 5.1 Functional Testing 5 days 04/28/2025 -
5.2 5.2 User Acceptance Testing (UAT) 4 days 05/05/2025 5.1
5.3 5.3 Security Testing 4 days 05/09/2025 5.2
6 6 Deployment 1 day 05/14/2025 5 Yes
6.1 6.1 App Store Submission 3 days 05/14/2025 -
6.2 6.2 Post-Deployment Testing 2 days 05/17/2025 6.1
7 7 Project Closure 1 day 05/20/2025 6 Yes
7.1 7.1 Final Review and Sign-off 1 day 05/20/2025 -
Lessons Learned and
7.2 7.2 2 days 05/21/2025 7.1
Documentation
Resource ID Resource Name Type Standard Rate Overtime Rate Max Units (%)
R1 Project Manager Work $75/hr $110/hr 100%
R2 Business Analyst Work $65/hr $95/hr 100%
R3 UI/UX Designer Work $50/hr $80/hr 100%
R4 Backend Developer Work $60/hr $90/hr 100%
R5 Frontend Developer Work $60/hr $90/hr 100%
R6 Security Specialist Work $65/hr $95/hr 100%
R7 QA Tester Work $55/hr $85/hr 100%
R8 DevOps Engineer Work $55/hr $85/hr 100%
Exercise Questions