Chapter 6. (Answare)
Chapter 6. (Answare)
- On a construction project, to erect the superstructure only after the foundation has been
built
- The work to be accomplished in the near term is planned in detail, whereas the work in
the future is planned at a higher level.
- 10.0 weeks.
6. Consider the following schedule network that shows the activities in your
project and their associated durations in days:
- 12
7. The critical path is established by calculating the following dates:
8. Consider the following schedule network that shows the activities in your project and
their associated durations in days:
- A-B-D.
- 11.0 weeks.
- A technique in which activities are represented by nodes and are graphically linked by
one or more logical relationships to show the sequence in which the activities are to be
performed.
11.Consider the following schedule network that shows the activities in your
project and their associated durations in days:
- Is the process of monitoring the status of the project to update the project schedule and
managing changes to the schedule baseline.
12.All of the following are true about resource levelling EXCEPT:
13. The duration of the activity is affected by all of the following EXCEPT:
- Using the precedence diagramming method (PDM) for scheduling activities instead of
using the critical path method (CPM).
- A schedule compression technique used to shorten the schedule duration for the
least incremental cost by adding resources.
16.As one of the tools and techniques of the Sequence Activities process, a lead:
- Is the amount of time whereby a successor activity can be started before the previous
activity is completed.
- Frequently used to estimate project duration when there is a limited amount of detailed
information about the project.
- 4.5 weeks.
19. A schedule compression technique used to shorten the schedule duration for the least
incremental cost by adding resources is called:
- Crashing
20. An activity in a project network has the following characteristics: ES = 5, EF = 10, and
LF = 14. Therefore, LS = ____.
- 9.0 weeks
- Performing in parallel for at least a portion of their duration activities or phases that are
normally done in sequence, which may result in rework and increased risk.
23. Consider the following three estimates for the duration of an activity:
Using the beta distribution and the three-point estimating approach, the calculated
Expected activity duration (tE) is:
- 5.5 weeks.
1. How many days can activity D be delayed without affecting the final project
duration?
- 4
- 31
- 33
Interactive content
- 600/20(5)=6
- (8-3)/6=0.83
- 33
6. What are the activity in critical path? نفس الصورة الي فوق
- BCEF
7. what is the total float of activity A?
= Lf-Ef
=6-5=1
8. how many days can activities D be delayed without affecting the final
project duration?
= 29 - 25 = 4
- 33
- 33
- 31